PM Workshop

Post-Project Evaluation

Post Project Evaluation


When:
Completion of Design and Construction Phases Minimum Required Project Fee is Greater than $50,000 or Includes IDC Construction Multiple Small Projects (Quarterly)

Why:
Avoid Future Errors or Problems
Create Historical Cost Database Create Feedback for Staff and Management
2
Slides\closeout\evaluation.ppt

Post Project Evaluation


LESSONS LEARNED PATH TOWARDS CONTINUOUS IMPROVEMENT
Does project meet criteria for a required Lessons Learned? PM schedules Lessons Learned and notifies Project Operations and PI/QA of date PI/QA monitors & requests schedule updates YES NO PM conducts Lessons Learned (IDC056 - large projects or IDC057 small projects templates available)

Submit relevant items to IQ

PM consolidates all lessons learned input

PI/QA monitors and reports status to management

PM forwards LL summary to Project Ops and PI/QA

PM identifies items relevant to IQ

Project Ops reviews for feedback to project delivery methods

PM assigns owners to ensure IQ items are entered

PI/QA monitors and reports status to management

Project Ops implements into training materials as needed

PI/QA monitors and reports status to management

PM confirms IQ items are entered

Project team reviews IQ at the start of each NEW project and as issues arise

3
Slides\closeout\evaluation.ppt

Post Project Evaluation


If Your Project has One or More of the Following Conditions, You Must Contact IDC Corporate Counsel Prior to Initiating Lessons Learned:
Injury to ANY Person on the Project Threatened or Pending Litigation Between Any Party on the Project Significant Property Damage Insurance Claims or Issues Individual Pending Claims >$25,000
4
Slides\closeout\evaluation.ppt

Design Phase Evaluations


Data Gathering:
PM Directs Design Leads to Meet With Their Staff PM Meets With Client and CM PM Evaluates Design Leads

PM Evaluates Subconsultants

5
Slides\closeout\evaluation.ppt

PM/Lead/Staff Issues
Project Team Organization Change Management Design Input and Reviews From Owner and CM Production of Drawings and Specifications

Project Schedule and Approach


Direction Received From the PM and Lead Staff Interdiscipline Communication and Coordination Communication Between the Design, Construction and Client Team
6
Slides\closeout\evaluation.ppt

PM/Client/CM Issues
Design Consistent With the Established Construction Budgets Execution Demonstrated Teamwork and Leadership Completeness of Design Consistent With Project Requirements Solutions Creative or Innovative IDC Team Responsive to the Project, Client, and Other Entities Suggested Improvements to Meet Project Goals Would the Client and CM be Recommended for Other Work

7
Slides\closeout\evaluation.ppt

Evaluation of Lead Staff


PM Evaluates Design and CM Leads Related to Project Roles and Responsibilities

PM Provides Input to Discipline Manager


Address Positive and Negative Performance Issues As They Occur Coordinate Discussions With Team Members and Discipline Manager

8
Slides\closeout\evaluation.ppt

Evaluation Of Subconsultants
Necessary for the Completion of the Project Met Budget and Schedule Information Provided Clear and Consistent Effective Communication and Coordination Recommend for Future Projects Areas Where a Subconsultant Should Have Been Used

9
Slides\closeout\evaluation.ppt

Meetings And Documentation


PM Meeting With All Lead Staff Summarize Results (Schedule, Ambiguities in Documents, Highlights, Lowlignts, Etc.) Encourage Input to IQ Database

Assign Responsibilities to Input IQ Items that Add Value to Future Projects

10
Slides\closeout\evaluation.ppt

Meetings And Documentation, Cont.


Develop Cost Summary vs. Budget Spreadsheet (Cost/Mandays Per Sheet, Percent of Construction, Expenses, Nonbillables, Construction Cost Metrics, Etc.) Contract Wording Benefits and Problems Copy Leads, DMs, Project Operations, PMs, and PI/QA

11
Slides\closeout\evaluation.ppt

Construction Phase Evaluation


Input From Client, CM or GC Concerning Design Input From Client, Design Team Concerning CM

Input From Construction Staff, CM Concerning Subcontractors

12
Slides\closeout\evaluation.ppt

Concerning Design
Completeness of Documents Ambiguities Encountered and Resolutions in the Field Number and Type of RFIs and Design Clarifications Evaluate and Categorize Field Orders and Change Orders by Discipline for E&O and Compare to Original Bids Responsiveness of Design Staff to SDC Responsibilities

13
Slides\closeout\evaluation.ppt

Concerning CM
Safety Program Effective Met Budget and Schedule Goals Managed to Construction Documents Submittal Tracking and Management

Cost, Progress and Schedule Tracking


Quality of VE Input Status Reports Beneficial Invoicing and Payments Closeout Documents
14

Claims Management
Slides\closeout\evaluation.ppt

Concerning Subcontractors
Quality of Construction Responsive to Contract Requirements for Schedules, Submittals Cooperative With the Team to Resolve Issues to Benefit the Client Met Budget and Schedule Reasonable Demands With Respect to Submittals, RFIs and Conflict Resolution

15
Slides\closeout\evaluation.ppt

Construction Phase Reporting


Summarize and Share With Leads, DMs, PMs, Project Operations and PI/QA

16
Slides\closeout\evaluation.ppt

Eleven-month Warranty Walk-through


PM to Schedule With Client At Least One Month Prior to Expiration of Warrantees Determine Clients Satisfaction With Facility

Identify Problems the Client Has Encountered


Consider Including Leads, and CM

17
Slides\closeout\evaluation.ppt