You are on page 1of 14

3/7/2011

CABLE FAULTS
INTRODUCTION
Cable fault is referring to something that occurs current cant flow smoothly. It is because open circuit or short circuit that means the current flow is high value. Most faults are caused by dampness in the paper insulation of the cable due to porous or otherwise damaged lead sheath. The causes of damage to the lead sheath are: crystallization of the lead through vibration; chemical action on the lead when buried in the earth and insufficiently protected; and mechanical damage.

Main equipment to determine cable fault is ohmmeter. Beside that, a few test can be done to determine cable faults such as: 1. Continuity Test 2. Insulation Resistance Test

3/7/2011

TYPES OF CABLE FAULTS The faults which are most likely to occur in the cables are:1. Ground or Earth Faults (Break-down of cable insulation) When the insulation of the cable gets damaged, the current starts flowing from core to earth or to cable sheath. Short Circuit Faults When the insulation between two cables or between two cores of a multicore cable gets damaged, the current starts flowing from one cable to another cable or from one core to another core of a multi-core cable directly (without passing through load) Open Circuit Faults When the conductor of a cable is broken or joint is pulled out there is no current in the cable.

2.

3.

PROCEDURE TO FIND CABLE FAULT To find the cable faults, it has four steps, that is:1. Testing a. Continuity Test open circuit faults b. Insulation Test short circuit faults 2. Locating cable fault test from terminal cables To find length of faults from testing station 3. Confirmation fault point test To find actual location faults 4. Repair the fault

3/7/2011

CABLE FAULTS TEST Continuity Test Continuity test is to checking open circuit of cable faults. Usually, this test uses a bell and battery or multimeter. This test is dividing to two types, that is: 1. Short alignment 2. Long alignment

Short Alignment Using a bell and battery. This test is used for conduit types. For testing CC 1 cables, a connection is jointed between C and C1 through a bell and battery. If a bell ringing, the cable in continues condition, and the cable is marked with C1, if the bell not ringing, the cable is not in continues condition. For A and B cable, the same method is used to test cable condition.

Figure 7.1: Short alignment for Continuity Test

3/7/2011

Long Alignment

Figure 7.2: Long alignment for Continuity Test

Figure 7.2, the method is suitable to use for long cable. For cable A, B and C, choose a pair of cable, for example cable A and B will be connected with tester while the end of the same cable with short circuit. If the test shows an open circuit, the end of the cable will change with another pair and the circuit will test again. If a low reading is detected, so the cables are label with A1 or B1. Then, connect one of the cables with another cable for example cable A and B, and test with the same method. If reading is low, so cable A and C will detect and right. Thus, the cable will label clearly. The same method can be done for another cable in the same alignment.

3/7/2011

Insulation Resistance Test Insulation resistance is resistance that measured in ohm units between live part of equipment and earth for installation. Resistance will measured through insulation that covered conductor. Insulation Resistance Test Used to test short circuit and thickness of insulator. One of the equipment to short circuit test is insulator resistance tester. In this test, a few tests on installation must be made before connect to supply.

Voltage test Need to test the voltage that used for Insulation resistance test. If the used voltage is DC voltage, it must less than two times normally DC voltage and if the used voltage is AC voltage, it must less than two times normal Vrms; but not more than 500v for medium voltage circuit. Earth Installation test The test is made with all fuses stay at their place. The main switch must be switch off. Switch off all lamps and test it by separately. Insulation that measured to the earth must less than 1M and range for the equipment made in difference must less than 0.5M to the earth and 0.5M between polar and phase.

3/7/2011

Figure 7.3 shown connections for insulation resistance to earth testing 2 wires installation that finish with other lamp and feel off other equipment. Both of the cable to main switch twist together and connected to line terminal at ohmmeter. Earth terminal for ohmmeter connect to user earthing. Figure 7.3: Insulation resistance test for finish installation The terminals for two way switches must be connected together for a few times.

Heating equipment shall be tested separately, and Figure 4 shows an example of tests made on the electric kettle.

Figure 4: Insulation Resistance Testing of Electric Kettle

3/7/2011

Testing between two conductor. Connect to pole or phase supply and between conductors to other pole or phase supply. Insulation resistance must be less than 1M. Figure 7.5 is an example of insulation resistance test between conductors.

Figure 7.5: Testing between conductors for 2 cables of single installation

LOCALIZATION CABLE FAULT TEST Murray loop test, Varley loop test and Pulse Echo test are simple and basic method to localize cable fault testing. This method used basic equipment that obtained easily. These tests are performed for the location of either an earth fault or short circuit fault in underground cable. In these tests the resistance of fault does not affect the results obtained except when the resistance of fault is very high. There are two loop tests usually used and are known as Murray Loop and Varley Loop Test. These tests emply the principle of Wheatstone bridge.

3/7/2011

Murray Loop Test The connection diagrams to locate earth fault and short circuit fault by Murray loop test method are shown in Figure 7.6 respectively. As already said Wheatstone bridge principle is used in these tests. P and Q are two ratio arms consisting of step resistors or slide wire, G is a galvanometer, E is a battery and S1 is a battery key. In this method, a sound cable is connected to a faulty cable for find actual happen fault. Figure 7.6 is connection method of Murray Loop Test.

Figure 7.6: Murray Loop Test Circuit.

3/7/2011

Procedures:
End of the faulty cable (assume F is a location fault) was connected with a sound cable from F to b location test through D connector. At location test, end of cable a connected to b through a galvanometer and S1 switch. Bridge is balanced by adjusting the resistances of ratio arms P and Q until the galvanometer indicates zero. Assume the sound and faulty cable have same cross-section and lenght, thereby r /m is same.

In balanced condition of bridge:

If L be known, so Lx can be calculate, that is distance of cable fault from test station.

3/7/2011

If L and r of sound and faulty cable is not same, so the formula above will be change. Assume r = resistance/lenght unit of sound cable L = length of sound cable

Example: Murray loop is a variation of the Wheatstone bridge is used to determine the location of the shorted two wires between them. (i) Refer to the diagram below, show the following equation when equilibrium.

(ii) Calculate the distance of fault from a test station where the balance is found when L1 = 50km, L2 = 100km, R1 = 3.3 / m, R2 = 10 /m, A/B = 8/1

10

3/7/2011

Varley Loop Test In this test also a sound cable is required in addtion to the existing cable. The circuit diagrams to determine the location of ground fault and short circuit fault by method of Varley loop tests are shown Figure below,

11

3/7/2011

When the switch is in position (a), S is adjusted so that the bridge resistors in a balanced situation. Suppose that in a balanced situation is found S = S1.

When the switch is in position (b), S is adjusted so that the bridge resistors in a balanced situation. Suppose that in a balanced situation is found S = S2

Solve equation (1) and (2)

Example: For cable fault test using Varley loop, when the switch is placed in position 1, the variable resistance, S is adjusted to a value of 50 to achieve a balance bridge. When the switch is placed at 2, equilibrium occurs when S is 35. Find the distance fault location from the source if the cable is 25km long, given fault cable resistance is 15/km, P = Q = 150 and 200 .

12

3/7/2011

PULSE ECHO TEST


Cable line in underground has a coating act as absorption or moisture blocker into insulator cable or main cable conductor. This moisture or underground water will make problem because the water usually acided and grounded cable will be fault. Pulse Echo Test is to find fault cable in grounded coating cable with identified the location that directly detect with ground.

Procedure: Connect a battery at end to end faulty cable. (The current will flow along conductor to location fault, from location fault to earth and then from earth to other terminals battery. Current can be imaging like it flowing out from location fault to surround ways.) Put voltmeter probe at two points such as in Figure 7.10. Positive or negative value will be obtained, it depend on flowing current in ground that fault happen.

13

3/7/2011

Move the voltmeter along the cable until the value of current change ways. the point that the current changes the way shown actual location faulty happen.

14

You might also like