Pre Commissioning Check List Of HVAC System Project : Jindal Air Conditioning work at G H 1 Pre Commissioning Check List

for Pump - Motor set Sl No. Check List 1 Electrical Check Check the IR value of motor winding Check the IR value of cable Proper termination of cable for both panel and motor side Check the termination are tight well for both panel and motor side Proper earthing arrangement Check the over set point of OLR and other seafty device 2 No Load Run Test Pump direction of rotation Amps should be in permissible limit Run the motor for an hour Check Heat Check Noise 3 Mechanical Check Flushing of Water pipes is carried out Alignment check 4 On Load Run Test Check Amps Check Heat Check Noise Check vibration Check minimum leakage of water from pump gland Check discharge pressure Remark

Pre Commissioning Check List for CT Mechanical Check Flushing of Water pipes is carried out Check leakage of basin Clean the basin Check fan motor alignment Electrical Check Check the IR value of motor winding Check the IR value of cable Proper termination of cable for both panel and motor side Check the termination are tight well for both panel and motor side Proper earthing arrangement Check the over set point of OLR and other seafty device On Load Run Test Check Amps Check Heat Check Noise Check vibration Pre Commissioning Check List for Chiller Mechanical Check Flushing of Water pipes is carried out Confirm adequate space for operation and maintenance Standing Pressure checked by Pressure Gauge Visible leaks or Damages on Chiller

Insulation Damaged Oil level in sight glass Strainer provided for both chiller and condenser line Power Provided by Customer MCCB switched on Incoming Voltage Heater Energised

You might also like