Q. No.

2) The owner of a chain of fast food restaurants is considering a new computer system for accounting and inventory control. A computer company sent the following information about the computer system installation: Activity Description Predecessors Expected Time(weeks) To A B C D E F G H I Select the computer model Design input/output system Design monitoring system Assemble computer hardware Develop the main program Develop input/output routine Create database Install the system Test and implement A A B B C E D,F G,H 4 5 4 15 10 8 4 1 6 Tm 6 7 8 20 18 9 8 2 7 Tp 8 15 12 25 26 16 12 3 8

Using Ms- Project Software: 1) Draw the network Diagram 2) Draw the Gantt chart 3) Draw the Critical path and Critical activities 4) Report the following: i) Project Summary ii) Critical Tasks iii) Tasks starting soon iv) Top levels tasks.