PMP Mock Questions

Subject: Project Execution No of Questions: 19 www.techfaq360.com 03 - Execution Question - 1 You are the Project Manager of a project and One of the functional managers wants to make a major scope change during the execution of the project. What is your action should be to : A.Detail the impact of the change for the functional manager. B.Refuse the change. C.Complain to the sponsor. D.Ignore the request Answer : A is the correct answer. If there is scope change by functional manager during the execution of the project then Project Manager send the detail the impact of the changes to functional manager.

Question - 2 As changes are brought forward, What is the job of project manager? A.Install the change immediately B.Consider the impact of the change C.Refuse to consider the change D.Ask to team members about the changes Answer : B is the correct answer. If there is any change, Project manager consider the impact of the changes.

Question - 3

As the Scope changes are approved, a new baseline emerges. What about the original baseline document? A.Update the changes into original baseline. B.You can't change the original baseline. C.Scrap original baseline and create new original baseline. D.Scrap original baseline Answer : B is the correct answer. You can't change the original baseline. Keep the original to show everyone involved what was starting plan looked like.

Question - 4 The person who is must be on the CCB(Change Control Board) is the _______? A.Project Manager B.Team Lead C.Sponsor D.Executive manager Answer : A is the correct answer. The first person on the CCB is always the project manager of the project.

Question - 5 If you are project manager , After a change request has been denied, you should: A.Record it and save it. B.Pass on to the project team. C.Forget it D.Ask your team to save it Answer : A is the correct answer. You have to keep track of all change requests.

Question - 6 Change requests are made against the ____________? A.Project baseline B.SOW

C.Charter D.Executive summary Answer : A is the correct answer. All change requests are made against a project plan that has the project baseline.

Question - 7 Change requests should be ______ ? A.Formal B.Interesting C.Short D.Long Answer : A is the correct answer. Record of changes request should be maintained.

Question - 8 The Change Control Board should be _______? A.flexible B.Include the project manager C.appropriate authority D.All of the above Answer : D is the correct answer. CCB should have all the mentioned characteristics.

Question - 9 The tools and techniques used to gather, integrate, and disseminate the outputs of project management processes are called _____ ? A.Project Management Information System (PMIS) B.WBS C.Scope Statement D.Management System

Answer : A is the correct answer. The tools and techniques used to gather, integrate, and disseminate the outputs of project management processes are called PMIS .

Question - 10 A formal procedure for sanctioning project work is called ______? A.Work Authorization B.Project charter C.SOW D.Scope statement Answer : A is the correct answer. A formal procedure for sanctioning project work is a Work Authorization.

Question - 11 "a narrative description of products, services, or results to be supplied" is called _______? A.Statement of work B.WBS C.Scope Statement D.Risk Plan Answer : A is the correct answer. Based on the PMBOK, the SOW is "a narrative description of products, services, or results to be supplied."

Question - 12 Procurement items are detailed in the _________? A.Statement of works B.WBS C.Scope statement D.Project Charter Answer : A is the correct answer.

This is the document that will give all the description of products, services, or results to be supplied.

Question - 13 Which statement is true about Earned Value? A.the value of the work on the project that is actually completed. B.what you have in your plan for the project. C.which is the amount actually spent during the period of the project. D.the value of the work on the project that is actually completed after commitment time is over Answer : A is the correct answer. EV(Earned Value) : the value of the work on the project that is actually completed.

Question - 14 Which statement is true about Planned Value? A.the value of the work on the project that is actually completed. B.what you have in your plan for the project. C.which is the amount actually spent during the period of the project. D.the value of the work on the project that is actually completed. Answer : B is the correct answer. Planned Value(PV) : what you have in your plan for the project.

Question - 15 Planned Value(PV) is same as : A.Budgeted Cost of Work Scheduled(BSWS) B.Budgeted Cost of Work Performed(BCWP) C.Work Breakdown Structure(WBS) D.Statement of work(SOW) Answer : A is the correct answer. Planned Value(PV) is same as Budgeted Cost of Work Scheduled(BCWS)

Question - 16 Earned Value(EV) is same as : A.Budgeted Cost of Work Scheduled(BSWS) B.Budgeted Cost of Work Performed(BCWP) C.WBS D.SOW Answer : B is the correct answer. Earned Value(EV) is same as Budgeted Cost of Work Performed(BCWP)

Question - 17 If your AC(Actual Cost) = $18,000 and your EV(Earned Value) = $12,000, are you over budget? A.You are over budget. B.You are doing good, under budget. C.Zero D.EV(Earned Value) is not related to budget Answer : A is the correct answer. If EV-AC value is negative, you are over budget(Not doing good). Here $12,000 $18,000 = -$6000 , So you are over budget.

Question - 18 What is the most important tasks of the project manager during the Execution and Control phase? A.Information management. B.Maintain scope statement. C.Maintain Charter D.Manage project closing document Answer : A is the correct answer. One of the most important tasks of the project manager during the Execution and Control phases of the project is the management of information.

Question - 19 You are the project manager of a project. If there is approved changes to the original scope, What you do with old original scope ? A.Save the old versions. B.No need to save old version. C.Scrap the old version. D.Ignore It Answer : A is the correct answer. All the version you should keep in version control system.