RECOMMENDATIONS:
That Council receive the RBRC – 64 Avenue Rail Overpass at Highway 10 Project (“the
Project”) report; and
That Council authorize staff to enter into agreements with the Government of Canada,
Contribution Agreement (“GOC Agreement”) and the Project Agreement, Roberts Bank Rail
Corridor Program (“RBRC Agreement”) on behalf of the Township of Langley, subject to such
modifications as may be deemed necessary by legal counsel.
EXECUTIVE SUMMARY:
Public Consultation Process
The Project has recently completed a public consultation process which involved three separate
components:
1. Public Open Houses were held on January 31 and February 2 with 389 people attending.
Based on the questionnaire the general comments are as follows:
• The attendees were generally supportive of a road/rail overpass in the approximate
location of the intersection at Highway 10 / 64 Avenue / Mufford;
• The attendees were generally supportive of “Option J” however this option has technical
and financial challenges and was found by the other Project partners to be inconsistent
with the original project principles; and,
• Of all the remaining options the Open House attendees found the preliminary design to
be the next most acceptable alignment option.
2. Special Meeting of Township Council for the purpose of Public Input as to Mufford/64th
Avenue Road / Rail Overpass. A total of 41 people spoke at the Public Input Meeting. From
that 38 were opposed and 3 were in favour of the preliminary design. The meeting minutes are
attached to this report.
3. Community Survey
An independent research company, named Synovate, which were previously retained by the
Township for Community Surveys, conducted a telephone survey from February 4 to 7, 2009 of
residents living within the Township of Langley. From the 401 respondents the Community
Survey (which, from the sample size of 401 has a minimum margin of error of +/- 5%, 19 times
out of 20) provided the following results:
RBRC – 64 AVENUE RAIL OVERPASS AT HIGHWAY 10 PROJECT
Page 2 . . .
• Two-thirds of residents are aware of the proposal to build an overpass project in the
Township of Langley;
• Support for the overpass project outweighs the opposition by 49% to 11% with 38%
having no opinion either way; and,
• After reflecting on some of the positives and negatives of the overpass project support
rose to 69% leaving 15% still opposed and 16% undecided.
As a result of the feedback heard from the community members at the Open Houses the
preliminary design is being enhanced to account for several of the salient issues that were
brought forward, including:
Funding Agreements
The $51M Project is funded through two agreements, one with the Government of Canada,
valued at $3.1M and the second with the Roberts Bank Railway Corridor Program, valued at
$38.6M. Both agreements have been thoroughly reviewed by staff and the Township’s lawyers.
PURPOSE:
To provide Council with a briefing on the outcome of the recent public questionnaires and
community survey and to seek authority to enter into the Project funding agreements.
BACKGROUND/HISTORY:
Two Open Houses were held by the Township in order to present the latest project preliminary
design and have available project staff to answer questions, issues and concerns. The Open
Houses were held on Saturday, January 31, 2009, 10am to 2pm at the Milner Community Hall
and, Monday, February 2, 2009, 5:30pm to 8:30pm at the Township of Langley Civic Facility.
In attendance with Township staff at the Open Houses were representatives from Ministry of
Transportation and Infrastructure, TransLink, Roberts Bank Railway Corridor Program, Port
Metro Vancouver, Environmental, Agricultural and Planning consultants
In total 389 members of the public attended the Open Houses. A questionnaire was provided to
each of the attendees and the results have been tabulated and summarized in the following
tables:
RBRC – 64 AVENUE RAIL OVERPASS AT HIGHWAY 10 PROJECT
Page 3 . . .
If you said yes to question 2, which option best meets the needs of the Township of
Langley?
No. of 39 9 9 78 11 22 27 195
Responses
Results 20% 5% 5% 40% 5% 11% 14% 100%
A Public Meeting was held on Monday, February 9, 2009 from 7pm to 11:05 PM in a format
similar to a Public Hearing. Staff provided a brief presentation that generally responded to
questions that were raised at the Open Houses. Subsequently, 41 delegates approached
Council and spoke to the Project.
No. of Speakers 3 38 0 41
Based on the public consultation process the general results are as follows:
• Two-thirds of residents are aware of the proposal to build an overpass project in the
Township of Langley;
• The public is generally supportive of a road/rail overpass in the approximate location of
the intersection at Highway 10/64 Avenue/Mufford;
• Support for the overpass project outweighs the opposition by 49% to 11% with 38%
having no opinion either way;
• After reflecting on some of the positives and negatives of the overpass project support
rose to 69% leaving 15% still opposed and 16% undecided;
• The attendees were generally supportive of “Option J” however this option has technical
and financial challenges and was found by the other Project partners to be inconsistent
with the original project principles; and,
• Of all the remaining options the Open House attendees found the preliminary design to
be the next most acceptable alignment option.
Based on the comments received from the Open Houses the Project learned from the residents
of their issues and concerns. As such, the Project is working to enhance the preliminary design
to reflect the key issues, such as:
RBRC – 64 AVENUE RAIL OVERPASS AT HIGHWAY 10 PROJECT
Page 4 . . .
As mentioned previously a large number of attendees were supportive of the “Option J”,
however this Option is not recommended for the following reasons:
• Fails to meet the transportation objectives (not an integrated solution, lacks
network connectivity and redundancy, lacks added capacity);
• Unacceptable to the Funding Partners;
• Impact to the environmentally sensitive area; and,
• Unacceptable to the City of Langley, as stated in Mayor Fassbender’s letter,
dated February 3, 2009.
Funding Agreements:
The $51 million Project is funded through two Agreements, one with the Government of
Canada, through Transport Canada, for $3.1 million, and the other through a partnership
agreement with the Project funding partners, for the additional $38.6 million. The Township’s
share is $9.3 million.
The Agreements are the result of a thorough analysis by the Township and its Funding Partners
of the technical and financial aspects of several alignment options which resulted in consensus
on a preferred alignment option which is represented by the preliminary design.
The GOC Agreement is a general purpose, standard template agreement that is used for
infrastructure projects across Canada where GOC contributes funds to another level of
government agency. The contribution is at $3.1 million with no flexibility for change and no
exception. The Township, under the GOC Agreement, is obligated to deliver the Project to
completion based on the subject terms and conditions. Contributions are available based on
actual costs and on a quarterly basis up to the $3.1 million limit.
RBRC – 64 AVENUE RAIL OVERPASS AT HIGHWAY 10 PROJECT
Page 5 . . .
Eligible costs include all aspects of Project delivery including project management, professional
services, engineering, design, materials, construction and approvals. The most significant
exception is the cost of property acquisition that is covered under the partnership agreement.
The Township’s ability to invoice under the GOC Agreement is conditional on the Project
receiving the Canadian Environmental Assessment Authority approval, which we have been
advised is imminent.
In the RBRC Agreement the Township, as the Project delivery agent, is responsible to the
project partners to delivery the Project in manner that complies with the stated terms, conditions
and requirements. In kind, the partners are responsible to proportionately share on the risks and
liabilities associated with cost, schedule, scope changes, regulatory approvals and any other
unforeseen items associated with the Project. This is a significant shift from the GOC
Contribution Agreement where cost risk is capped.
The Township will invoice TransLink on a quarterly basis and subsequently TransLink receives
payment from the other agencies through a separate program agreement.
DISCUSSION/ANALYSIS:
The Township has undertaken the following measures to ensure both Agreements are
acceptable to the Township:
1. Project staff have fully vetted the Agreements to ensure that the obligations under these
Agreements are acceptable and achievable;
2. Further, Project staff have ensured technical accuracy and the Agreements conform with
best business practices;
3. Township solicitor (Bull Houser Tupper) have reviewed and edited the Agreements,
where appropriate; and
4. Agreements have been reviewed to ensure that they are consistent and compliant with
the Community Charter.
RBRC – 64 AVENUE RAIL OVERPASS AT HIGHWAY 10 PROJECT
Page 6 . . .
Respectfully submitted,
Colin Wright
GENERAL MANAGER
for
ENGINEERING DIVISION
© Synovate 2009 1
Executive
Summary
Executive Summary
Overall Awareness and Opinion
• Two-thirds of residents are aware of the proposal to build an overpass in the Township of
Langley.
• Support for the proposed overpass outweighs opposition by a margin of 49% to 11%, with the
remaining 38% not having an opinion either way.
• After hearing reasons for and against the overpass, support solidifies to 69%, leaving 15% still
opposed and 16% undecided.
© Synovate 2009 3
Objectives &
Methodology
Objectives and Methodology
• Synovate, an independent professional market • A total of 401 telephone interviews were
research company, was commissioned by the conducted from February 4th to 7th, 2009.
Township of Langley on behalf of the project to
conduct a poll on a proposed overpass. • Quotas were set by gender and age. Further, the
• Questions were developed independently by sample was weighted by age to match the actual
Synovate staff and project partner input was age distribution of household maintainers in the
sought for technical accuracy. Township of Langley.
• Township heads of households were asked • The maximum margin of error on the sample of
about a proposal to build a new overpass at 401 is +/-5%, 19 times out of 20. The margins on
64th Avenue/Mufford and Highway 10 to allow smaller subsamples are wider.
car traffic to be routed over the railway traffic.
© Synovate 2009 5
Findings
Overall Awareness
Q1. Are you aware of the proposal to build a new road and Q1b. If yes, where did you hear about the
overpass at 64th Avenue/Mufford and Highway 10 to allow plan to build the overpass?
car traffic to be routed over the railway traffic?
Community Newspaper 79
Word of Mouth/Family 17
No
36% Daily Newspaper 7
TV 4
Radio 2
Open House 1
Yes Internet 1
64%
Other 1
Don't Know/Refused 3
%
(n=401) (n=260)
© Synovate 2009 7
Initial Overall Opinion
Q2. Overall, do you support or oppose the plan to build the overpass or do you not have an opinion either way?
Do you strongly or somewhat [support/oppose] it?
• By more than four to one margin, residents • Of those who consider the overpass decision
support the proposed overpass. extremely or very important, support outweighs
opposition 67% to 14%. Furthermore, strong support
• 49% say they strongly or somewhat support
stands at 56% among this group.
the planned overpass, while 11% express
opposition, including 7% who are strongly
opposed. A large minority, 38%, have no
opinion either way.
© Synovate 2009 8
Reasons For Initial Overall Opinion
Q3. Why do you [support/oppose] it? What does it depend on?
© Synovate 2009 9
Reasons For the Proposed Overpass
Q4. Please tell me whether you agree or disagree with the following reasons for or against the overpass.
Positive Reasons
%
(n=401)
• More than eight in ten residents agree with • The reasons in favour of the overpass also
each of the three reasons, namely, that it will attract majority agreement from those who
alleviate congestion, improve traffic flow in the do not approve of it, at least when they
future, and improve safety. were first asked for their opinion.
© Synovate 2009 10
Reasons Against the Proposed Overpass
Q4. Please tell me whether you agree or disagree with the following reasons for or against the overpass.
Negative Reasons
The overpass will cause more traffic to use the local rural 32 53 15
roads
%
(n=401)
• Three in ten residents agree that the overpass • Those who live in the vicinity of the overpass (V2Y)
will cause more traffic to rural roads, use too express the most concern over the overpass causing
much farmland, and create more rail traffic. more traffic to use the local rural roads. Still, they
concur more with all of the reasons in favour of the
• Residents that oppose the overpass are the overpass than with any of the objections.
most inclined to believe that the overpass is too
large and uses too much farmland. • Residents that initially were not sure how they felt about
the overpass expressed the greatest concern with
respect to the overpass using up too much farmland.
© Synovate 2009 11
Informed Overall Opinion
Q5. Now that you’ve heard some of the reasons for and against the overpass, would you prefer to see the project go
ahead or be cancelled?
Don't Know
16% Initial Opinion
Cancelled 2 76 14
(n=401)
• After hearing reasons for and against the overpass, • 54% of those residents initially undecided on
the margin of support to opposition stood at 69% to the proposed overpass became supportive,
15%. while 14% became opposed and 32%
remained unsure.
• 16% remained undecided.
• Almost all of those initially supportive of the
• The majority of all demographic groups and all
overpass remained so (94%), and 76% of
regions of the Township support the proposed
those initially opposed remained opposed.
overpass, including those who live in the area (69%
of those living in V2Y are supportive).
*Caution small base size
© Synovate 2009 12
Overall Importance of the Overpass Decision
Q6. Overall, how important is the decision on the overpass to you?
6% 8%
10% 12% • Overall, 1/3 of residents believe the
Extremely Important
decision on the overpass is extremely
or very important.
Very Important
19%
• Among those in the vicinity of the
23% 20% 29% overpass (V2Y), 37% consider the
Somewhat Important decision to be extremely or very
important.
Not that Important
• Older residents view the overpass
decision as more important than do
Not at all Important younger residents.
56%
Don't Know
44% 47% 38%
15%
16% 11%
18%
8% 9%
6% 3% 1%
Total 18-34 35-54 55+
(n=401) (n=36)* (n=202) (n=162)
Total
401
Base
%
Gender
Male 47
Female 53
Age
18-34 13
35-54 48
55+ 38
Region
V1M 32
V2Y 15
V2Z 18
V3A 14
V4W 21
© Synovate 2009 14
Demographic Profile
Total
401
Base
%
Main Transportation
Car/Motor Vehicle 98
Transit 1
Walking 1
Home Ownership
Own 90
Rent 8
Other 1
Don’t Know/Refused 1
© Synovate 2009 15
Our curiosity is yours.
Thank you.
© Synovate 2009 16
ATTACHMENT B
Agreement for the 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Page 1 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
TABLE OF CONTENTS
1. Interpretation ........................................................................................................................ 6
1.1 Definitions ....................................................................................................................... 6
1.2 Entire Agreement ............................................................................................................ 8
1.3 Schedules ....................................................................................................................... 8
1.4 Counterpart Signature..................................................................................................... 8
1.5 Accounting Principles and Auditing Standards ............................................................... 8
1.6 Severability...................................................................................................................... 9
1.7 Amendments ................................................................................................................... 9
1.8 Survival ........................................................................................................................... 9
1.9 Computation of Time....................................................................................................... 9
2. Term of Agreement .............................................................................................................. 9
3. Purpose ................................................................................................................................. 9
3.1 Purpose of this Agreement.............................................................................................. 9
3.2 Project Overview ............................................................................................................. 9
4. Project Financing ............................................................................................................... 10
4.1 Contribution by Canada ................................................................................................ 10
4.2 Commitments by the Recipient ..................................................................................... 10
5. Recipient Obligations ........................................................................................................ 11
6. Compliance with Environmental Legislation................................................................... 12
6.1 Conditional Commitment............................................................................................... 12
7. Aboriginal Consultation..................................................................................................... 13
7.1 Conditional Commitment............................................................................................... 13
7.2 Aboriginal consultation information ............................................................................... 13
8. Management Committee.................................................................................................... 14
8.1 Establishment ............................................................................................................... 14
8.2 Co-chairs....................................................................................................................... 14
8.3 Meetings ....................................................................................................................... 14
8.4 Rules and Procedures .................................................................................................. 14
8.5 Recommendations and Decisions................................................................................. 14
8.6 Mandate ........................................................................................................................ 14
8.7 Changes During the Term of the Agreement ................................................................ 15
8.8 RBRC Partners Committee ........................................................................................... 16
9. Contract Procedures.......................................................................................................... 16
9.1 Awarding of Contracts................................................................................................... 16
9.2 Contract Provisions ....................................................................................................... 16
10. Claims and Payments ........................................................................................................ 17
10.1 Payment Conditions .................................................................................................. 17
10.2 Method of Payment ................................................................................................... 17
10.3 Claim Procedures ...................................................................................................... 17
10.4 HCoMS ...................................................................................................................... 18
10.5 Retention of Contribution........................................................................................... 18
10.6 Final Payment............................................................................................................ 18
10.7 Time Limits for Claims ............................................................................................... 19
11. Audit, Evaluation and Reporting....................................................................................... 19
11.1 Reporting – Audit Evaluation Guidelines ................................................................... 19
11.2 Record Keeping......................................................................................................... 19
Page 2 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Page 3 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Page 4 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
This Contribution Agreement made in duplicate entered into on the __[INSERT st/rd/th]__ day of
___________, 20__.
PREAMBLE
WHEREAS the Parties recognize that investments in public infrastructure are fundamental to the
quality of life of Canadians and necessary to ensure continued economic growth;
WHEREAS the Minister of Transport, Infrastructure and Communities is responsible for the
Program entitled the Asia Pacific Gateway Corridor Initiative Transportation Infrastructure Fund
(hereinafter “APGCITIF and/or “Program”);
WHEREAS the Roberts Bank Rail Corridor Road/Rail Interface Study findings were used to
develop nine new crossing locations to be constructed along a 70km stretch of Railway in the
Lower Mainland of British Columbia that connects to the Deltaport Container Terminal.
WHEREAS Canada and the Township of Langley, along with the other stakeholder organizations,
agree to complete the Roberts Bank Rail Corridor Program as described in the Agreement-In-
Principle, dated June 28 2007
AND WHEREAS the Township of Langley agrees to carry out the Project and Canada wishes to
provide financial support for the Project and its objectives;
Page 5 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
NOW THEREFORE, in accordance with the principles set out above, Canada and the Township of
Langley hereby agree as follows:
1. INTERPRETATION
1.1 DEFINITIONS
In addition to the terms defined in the recitals and elsewhere in this Agreement, a
capitalized term has the meaning given to it in this section.
“Agreement” means this contribution agreement and all schedules, as may be amended
from time to time.
“Contract” means an agreement between the Recipient and a Third Party whereby the
latter agrees to supply a product or service to the Project in return for financial
consideration.
“Disposed Asset” means the Fixed and/or Non-Fixed Asset as further described in
subsection 16.1 a) i) and/or ii).
“Effective Date” means the date this Agreement is signed by the last Party.
“Eligible Costs” means costs of the Project eligible for reimbursement by Canada as
defined in Schedule A of this Agreement.
“Final Project Component Claim Date” means the earlier of twelve (12) months after the
Project Component Completion Date or two (2) months before the Agreement End Date.
“Fiscal Year” means the period beginning April 1 of a year and ending March 31 of the
following year.
Page 6 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
“Fixed Asset Disposal Period” means a period of twenty-five (25) years commencing from
the Project Component Completion Date.
“Joint Communications Material” means all public information material prepared jointly by
Canada and the Recipient regarding the Project including, but not limited to, news releases,
backgrounders, publications, invitations, signage and media advisories, and as further
outlined in Schedule C of this Agreement.
“Non-Fixed Asset” means any movable asset, including but not limited to vehicles,
purchased, constructed, rehabilitated, or improved, in whole or in part, with funds
contributed by Canada under the terms of this Agreement.
“Non-Fixed Asset Disposal Period” means a period of ten (10) years commencing from
the Project Component Completion Date.
“Project” means the infrastructure project described in the Project Overview in subsection
3.2 and Schedule B of this Agreement;
“Project Component Completion Date” means the date shown on the Solemn Declaration
of Substantial Completion in Schedule F for that Project Component but no later than the
Project Completion Date.
Page 7 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
“Substantial Completion” means when the Project Component is available for service to
the general public.
“Third Party” means any person, other than a Party, who participates in the implementation
of the Project.
“Tolls” means the user fees, rates or other charges imposed by the Recipient, or by a Third
Party operator pursuant to an agreement between the Recipient and a Third Party operator,
for the use of, in whole or in part, an infrastructure constructed, rehabilitated or improved
under this Agreement. For the purposes hereof, weight-distance taxes or other
highway/road network-wide levies will not be deemed Tolls.
1.3 SCHEDULES
The following schedules are attached to, and form part of, this Agreement:
Schedule E – Information;
Page 8 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
1.6 SEVERABILITY
If for any reason a provision of this Agreement that is not a fundamental term of this
Agreement between the Parties is found to be or becomes invalid or unenforceable, in
whole or in part, and if both Parties agree, it will be deemed to be severable and will be
deleted from this Agreement, but all the other terms and conditions of this Agreement will
continue to be valid and enforceable.
1.7 AMENDMENTS
Subject to the amendments / changes that can be made by the committee under section 8,
this Agreement may be amended at any time upon the written agreement of the Parties and
any amendments shall be deemed to form part of this Agreement.
1.8 SURVIVAL
Despite section 2 (Term of this Agreement), the Parties’ rights and obligations, which by
their nature extend beyond the expiration or termination of this Agreement, shall survive any
expiration or termination of this Agreement.
In this subsection business day means a day that is not a Saturday, Sunday or a holiday.
2. TERM OF AGREEMENT
This Agreement will be effective as of the Effective Date and shall terminate on the
Agreement End Date, subject to early termination in accordance with this Agreement.
3. PURPOSE
3.1 PURPOSE OF THIS AGREEMENT
The purpose of this Agreement is to establish the terms and conditions by which Canada
will reimburse the Recipient a part of the Eligible Costs paid by the Recipient for the Project,
as described in section 4 (Project Financing) and Schedule B of this Agreement.
The Project will consist of the construction of approximately 2km of new four-lane municipal
roadway extending from 204 St. to 216 St. on the 64th Avenue alignment. A new structure
will be constructed to carry the roadway over the Roberts Bank Rail Corridor as well as
Provincial Highway 10. Another new structure will be built to carry the roadway over North
Creek. The new facility will be a multi-modal facility that includes dedicated bicycle lanes
and pedestrian facilities.
Page 9 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
4. PROJECT FINANCING
4.1 CONTRIBUTION BY CANADA
a) Contribution
i) Canada agrees, subject to the terms and conditions of this Agreement, to pay a
contribution to the Recipient of not more than 50% of the total Eligible Costs of
the Project, as of the Effective Date, but only up to a total of $3.1M, in
accordance with the breakdown by Fiscal Year in Schedule B.
ii) The Parties agree that, no matter what the circumstances and notwithstanding
any other provision of this Agreement, Canada will not be required to contribute
more than fifteen (15) percent of Canada’s Contribution to those Eligible Costs
described in subsection A.1 c) d) f) and g) of Schedule A.
b) No involvement
The Parties agree that Canada’s role in the Project is limited to making a financial
contribution to the Project and that Canada will have no involvement in the Project
and/or the subsequent operation of the Project. Canada is neither a decision maker
nor an advisor to the Project, or any part thereof, except to the extent necessary to
enforce the provisions of this Agreement.
c) Appropriation and Funding
Any payment due by Canada under this Agreement is subject to there being an
appropriation by Parliament for the Fiscal Year in which the payment is to be made.
Funding under this Agreement may be reduced or terminated at Canada’s discretion in
response to the Government’s annual budget, a change in departmental funding levels
by Parliament or any other parliamentary spending decision that has an impact on the
Program under which this Agreement is made.
Canada will reimburse the Recipient only in accordance with the terms and conditions of
this Agreement. The Recipient shall fund all costs of the Project including cost overruns,
if any.
Page 10 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
b) Project implementation
The Recipient shall be solely responsible for the complete, diligent and timely
implementation of the Project, in accordance with the terms and conditions of this
Agreement.
The Recipient shall comply with, and ensure that any Third Party Contractor or
Concessionaire complies with all applicable laws, including environmental legislation of
Canada and British Columbia in the implementation of the Project under this Agreement.
c) Guidelines
The Recipient agrees to undertake, or cause to be undertaken, the engineering and
construction work, in accordance with the guidelines recognized by the Transportation
Association of Canada (TAC), or any other equivalent guidelines approved by the
Committee.
The Recipient shall inform Canada promptly of all financial and other assistance
received for the Project. If the federal government’s total financial assistance toward the
Project exceeds 50% of total Eligible Costs, or if the total financial assistance received
or due in respect of the Project’s total Eligible Costs exceeds 100% thereof, Canada
may recover the excess from the Recipient or reduce its contribution by an amount
equal to the excess.
e) Amounts Owing
The Recipient shall declare to Canada any amounts owing to the federal government,
under legislation or contribution agreements that constitute an overdue debt. The
Recipient recognizes that any amount owing is a debt and may be set off by Canada in
accordance with this Agreement.
f) Repayment
The Recipient shall repay to Canada any and all disallowed costs, surpluses, and
overpayments made under and according to the terms of this Agreement.
5. RECIPIENT OBLIGATIONS
Notwithstanding any other provision in this Agreement, the Recipient shall:
Page 11 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
managed for its duration and maintain that location until the Committee’s activities have
concluded;
b) retain at the location, and make available to the Parties, all documents relevant to this
Agreement and the work of the Committee;
c) prepare and make available to Canada, upon request, all documentation needed for the
proper administration of this Agreement, including but not limited to, payment claim
forms, approval documents, agendas and minutes of meetings of the Committee and its
subcommittees, Contracts, etc.;
d) ensure that any audit requested by Canada or the Federal Co-Chair under this
Agreement is performed and the results are reported to Canada;
e) promptly inform the Federal Co-chair of all proposed changes to any term of this
Agreement;
f) provide to Canada, as requested, accurate and timely financial forecasts for the Project
Components listed in Schedule B;
g) provide to Canada, as requested, status reports for the Project Components listed in
Schedule B to Canada’s satisfaction;
h) enter into bilateral agreements to support the terms of this Agreement where the
Recipient is not the deliverer of the Project; and
Page 12 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
7. ABORIGINAL CONSULTATION
a) Identification of all Aboriginal groups contacted by the Recipient for the Project;
Page 13 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
b) Summary of any and all communication to date with any and all Aboriginal groups;
c) Identification of any issues or concerns raised by Aboriginal groups for the Project and,
if applicable, how the Recipient intends to address those issues or concerns;
d) Written documentation of the Aboriginal groups contacted, and their identity, who are in
support of the Project or have no objection to the Project proceeding, and identification
of whether the positions are final, preliminary, or conditional in nature; and
e) Proposed plan for any further consultation through the Environmental Assessment and
Regulatory Phases of the Project, including federal involvement, if applicable.
8. MANAGEMENT COMMITTEE
8.1 ESTABLISHMENT
Within sixty (60) days of the Effective Date, the Parties agree to establish a Management
Committee (“Committee”) to administer and manage this Agreement. Each Party agrees to
appoint 1 member to the Committee and agrees to notify the other of the appointments
within the sixty (60) day period. The Committee will exist until its activities, including the
audits, reports and final adjustments, have been completed.
8.2 CO-CHAIRS
The Committee shall be chaired by the two (2) members (“Federal Co-chair” and “Recipient
Co-chair”). If a Co-chair is absent or otherwise unable to act, the representative duly
authorized to replace her/him will replace the Co-chair.
8.3 MEETINGS
The Committee shall meet regularly at the places and on the dates agreed to by the Co-
Chairs or at the written request of the Federal or Recipient Co-Chair.
8.6 MANDATE
The Committee shall:
Page 14 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
a) adhere to and comply with the terms and conditions of this Agreement, including but not
limited to policies, procedures and Schedules herein;
b) review the procedures described in subsection 9.1 (Awarding of Contracts) and ensure
that the principles in subsection 9.2 (Contract Provisions) are respected;
c) monitor the progress of the Project for the purpose of and to the extent necessary to
enforce the provisions of this Agreement;
d) subject to section 4 (Project Financing) and subsection 8.7 (Changes During the Term
of the Agreement), review and change the information in Schedule B by amending the
Schedule accordingly, to ensure that the work can be completed as described,
including but not limited to the Project descriptions, approved budgets, and cash flows,
prior to the beginning of each Fiscal Year and as may be required;
e) establish sub-committees, as needed, for carrying out this Agreement; and
f) attend to any other function required by this Agreement or as mutually directed by the
Parties.
i. any change to the Project Overview, as described in section 3.2, that Canada
deems significant;
iv. any change that may require a further environmental assessment decision under
subsection 6.1;
Page 15 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
b) A request for a change to the Project will be reviewed by the Committee, and
i. If the change is not significant, the Committee may approve or reject it unless
the change requires an amendment to any other part of this agreement
excluding Schedule B; or
ii. If the change is significant or could result in an amendment as contemplated
in Subsection 8.7 (b) (i), the Co-chairs shall present it to the Parties for a
decision.
9. CONTRACT PROCEDURES
9.1 AWARDING OF CONTRACTS
a) The Recipient shall ensure that all Contracts are awarded and managed in
accordance with its relevant policies and procedures, a copy of which will be
provided to the Committee, within thirty (30) days of the first Committee meeting,
and a copy of any amendment(s) will be provided to the Committee within thirty (30)
days of its effective date;
b) Notwithstanding the foregoing, the Recipient shall ensure that Contracts will be
awarded in a way that is:
i. transparent, competitive and consistent with value for money principles; and
ii. in accordance with the Agreement on Internal Trade;
c) Canada may require that a Contract for a Project Component be re-tendered if, in
Canada’s opinion, it was not awarded in compliance with the foregoing;
e) Within thirty (30) days of the first Committee meeting, the Recipient shall enter the
relevant Contract information into HCoMS for any existing Contracts for which the
Recipient will receive funding under this Agreement. For all Contracts awarded
thereafter, the Recipient shall, within thirty (30) days of awarding a Contract, enter
the relevant Contract information into HCoMS.
Page 16 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
The Recipient shall ensure that all Contracts are consistent with, and incorporate, the
relevant provisions of this Agreement. More specifically but without limiting the generality of
the foregoing, the Recipient agrees to include in the Contracts, provisions to ensure that:
a) proper and accurate accounts and records are maintained and that the Recipient has
the contractual right to audit them;
b) all applicable legislation is respected including labour, environmental and human rights
legislation; and
c) Canada and the Auditor General of Canada, to the extent permitted by law will at all
times, and upon reasonable notice, have free access to the Project sites and to any
documentation, for the purpose of ensuring compliance with this Agreement, including
access to all facilities and information required for inspection and audit.
b) Canada will under no circumstances be liable for the payment of interest for failing to
make a payment under this Agreement;
c) Subject to the exception of the claims related to those costs identified in A.1 (h),
Canada shall not be obliged to pay any claims submitted after the Final Project
Component Claim Date;
e) No payment shall be made by Canada until the Recipient has complied with its
obligations under section 7 (Aboriginal Consultation).
Page 17 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
ii. The amounts and the sources of all Project Component funding;
iv. The use made of the contribution under this Agreement and affirmation of all
Eligible Costs incurred and paid by the Recipient for the Project Component; and
v. All outstanding financial items, including any amount that may have been claimed
by the Recipient for ineligible costs or overpayments.
c) Confirmation from the Recipient Co-chair that the TDM Measures required under this
Agreement and the associated TDM Plan will be implemented and maintained for a
minimum of one (1) year after the Project Completion Date; and
Page 18 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Subject to the exception of the claims related to those costs identified in A.1 (h), Canada will
have no obligation to pay a claim submitted after the deadline specified in this provision.
Page 19 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
b) The Recipient will prepare a retrospective evaluation for each Project receiving a federal
contribution of $5 million or more, to the satisfaction of Canada, prepared from data
collected at one month after opening and 6 years after opening. The final report will be
submitted within 7 years of completion of the Project.
12. ACCESS
The Recipient shall provide free access to Canada, the Auditor General of Canada and /or
their designated representatives at all times, upon reasonable notice, to the Project sites
and any documentation for the purpose of ensuring compliance with this Agreement
including access to all facilities and information required for inspection and audit.
13. COMMUNICATIONS
The Parties shall comply with the Communications Protocol as established in Schedule C.
14. INDEMNIFICATION
a) The Recipient shall at all times indemnify and save harmless Canada, its officers,
servants, employees or agents (“Indemnified Party”), from and against all claims and
demands, losses, costs, damages, actions, suits or other proceedings by whomsoever
brought or prosecuted in any manner based upon, or occasioned by any injury to
persons, damage to or loss or destruction of property, economic loss or infringement of
rights caused by or arising directly or indirectly from:
Page 20 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
i. the Project;
ii. the performance of this Agreement or the breach of any term or condition of this
Agreement by the Recipient, its officers, servants, employees or agents, or by a
Third Party, its officers, servants, employees or agents;
iii. the design, construction, operation, maintenance and repair of any part of the
Project; and
iv. any omission, misrepresentation or other wilful or negligent act of the Recipient,
Third Party or any other outside party and their respective officers, servants,
employees or agents,
except to the extent to which such claims and demands, losses, costs, damages,
actions, suits, or other proceedings relate to the act or negligence of an Indemnified
Party in the performance of his or her duties.
b) An Indemnified Party shall give prompt notice to the Recipient of any action threatened
or commenced against it in respect of which indemnity may be sought under this
Agreement but failure to so notify the Recipient shall not relieve the Recipient from any
liability which it may have otherwise than on account of this indemnity. If requested by
Canada, the Recipient shall assume the defence of such action with legal advisors
chosen by the Recipient and approved by Canada. The Indemnified Party shall
cooperate with the Recipient in defending such claims, including providing the Recipient
with any necessary information and documentation. An Indemnified Party shall not
voluntarily admit any liability or settle any claim against them covered by this indemnity
without the Recipient prior written approval. The Recipient may not settle any action
commenced against an Indemnified Party without the written consent of Canada and
any other Indemnified Party.
15.2 REFERRAL
If an issue contemplated by section 15.1 (Dispute Resolution) arises, the Federal Co-Chair
and the Recipient Co-Chair shall examine it together as soon as possible and in any event
within 20 days within receipt of notice of such contentious matter. Where the Co-Chairs
cannot agree on a resolution, the matter will be referred to the Parties for resolution. A
decision will be provided within 90 days. Any payments related to the matter issue in
dispute will be suspended, together with the obligations related to such issue, pending
resolution.
Page 21 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
b) has not complied with any obligation, condition, undertaking or term in this
Agreement;
c) has neglected or failed to pay to Canada any amount due in accordance with this
Agreement;
f) is wound up or dissolved.
Canada will not suspend payment pursuant to this Agreement until it has provided the
Recipient with written notice specifying the nature of one of the events mentioned in section
16.1 of this Agreement and requesting the event to be remedied within thirty (30) days from
the date of notice, unless one of the events under subsection 16.1(e) or 16.1(f) of this
Agreement occurs wherein Canada may automatically suspend payment and advise the
Recipient, in writing, of the decision.
16.3 DEFAULT
(a) Canada shall suspend payment and may declare and advise the Recipient in writing that
it is in default if the Recipient fails to remedy any event of suspension mentioned in
subsection 16.1 (a) to 16.1(d) within the thirty (30) days pursuant to subsection 16.2; or
(b) Canada may consider the Recipient in default, if an event under subsections 16.1(e) or
16.1(f) occurs and advise the Recipient, in writing, of the decision.
Page 22 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
that amount shall be considered a debt due to Canada and shall be reimbursed forthwith on
demand to Canada. Any such debt remaining owing and unpaid shall carry interest
calculated in accordance with subsection 18.7 of this Agreement.
i) sells, leases, encumbers or otherwise disposes of, directly or indirectly, any Fixed
Asset or Non-Fixed Asset to a third party; or
ii) takes any action, directly or indirectly, that will leave the Fixed Asset and/or Non-
Fixed Asset no longer available for service to the general public;
the Recipient shall reimburse Canada, upon Canada’s demand, the greater of:
I) the proportion of proceeds received by the Recipient from the third party equal to the
percentage contributed by Canada for the Disposed Asset; or
ll) the proportion of Canada’s Contribution for the Disposed Asset, reduced in
accordance with the tables below-mentioned.
Notwithstanding the above, the total reimbursed by the Recipient shall not exceed the
amount paid by Canada towards said Disposed Asset.
Page 23 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Timeframe: Return of
contribution for
Fixed Asset
(in current dollars)
Up to 1 year after the Project Component Completion Date 100%
1 to 2 years after the Project Component Completion Date 96%
2 to 3 years after the Project Component Completion Date 92%
3 to 4 years after the Project Component Completion Date 88%
4 to 5 years after the Project Component Completion Date 84%
5 to 6 years after the Project Component Completion Date 80%
6 to 7 years after the Project Component Completion Date 76%
7 to 8 years after the Project Component Completion Date 72%
8 to 9 years after the Project Component Completion Date 68%
9 to 10 years after the Project Component Completion Date 64%
10 to 11 years after the Project Component Completion Date 60%
11 to 12 years after the Project Component Completion Date 56%
12 to 13 years after the Project Component Completion Date 52%
13 to 14 years after the Project Component Completion Date 48%
14 to 15 years after the Project Component Completion Date 44%
15 to 16 years after the Project Component Completion Date 40%
16 to 17 years after the Project Component Completion Date 36%
17 to 18 years after the Project Component Completion Date 32%
18 to 19 years after the Project Component Completion Date 28%
19 to 20 years after the Project Component Completion Date 24%
20 to 21 years after the Project Component Completion Date 20%
21 to 22 years after the Project Component Completion Date 16%
22 to 23 years after the Project Component Completion Date 12%
23 to 24 years after the Project Component Completion Date 8%
24 to 25 years after the Project Component Completion Date 4%
25 years after the Project Component Completion Date 0%
Page 24 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Timframe: Return of
contribution for
Non-Fixed Asset (in
current dollars)
Up to 1 year after the Project Component Completion Date 100%
1 to 2 years after the Project Component Completion Date 90%
2 to 3 years after the Project Component Completion Date 80%
3 to 4 years after the Project Component Completion Date 70%
4 to 5 years after the Project Component Completion Date 60%
5 to 6 years after the Project Component Completion Date 50%
6 to 7 years after the Project Component Completion Date 40%
7 to 8 years after the Project Component Completion Date 30%
8 to 9 years after the Project Component Completion Date 20%
9 to 10 years after the Project Component Completion Date 10%
10 years after the Project Component Completion Date 0%
b) Subject to subsection 19.13 (Assignment), if the Recipient takes any action described in
subsection 17.1 a) i) of this Agreement during the Fixed Asset Disposal Period or Non-
Fixed Asset Disposal Period, the Recipient shall assign its rights and obligations under
this Agreement to the outside party involved;
c) Notwithstanding the foregoing, if the Recipient takes any action described in subsection
16.1 a) i) of this Agreement during the Fixed Asset Disposal Period or Non-Fixed Asset
Disposal Period, based on technical or operational requirements of the Recipient, the
Recipient may, at Canada's discretion and with its written approval, in lieu of the
repayment set out above, reinvest the proceeds from the Disposed Asset into an asset
that replaces the Disposed Asset. If Canada deems the reinvestment inappropriate, the
Recipient shall be required to reimburse Canada, as per subsection 16.1 a); and
d) Notwithstanding the foregoing, if the Recipient takes any action described in subsection
16.1 a) i) of this Agreement during the Fixed Asset Disposal Period or Non-Fixed Asset
Disposal Period, for a nominal amount, and the Disposed Asset remains available for
service to the general public, Canada may, at its discretion, choose to waive the
remedies identified in subsections 16.1 a) I) and 16.1 a) II).
17.3 NOTICE
RDIMS No. 2370671 version 5
Page 25 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
The Recipient shall notify Canada in writing, one hundred eighty (180) days in advance if, at
any time during the Fixed Asset Disposal Period or Non-Fixed Asset Disposal Period, the
Recipient proposes, plans or anticipates to take any action as described in subsection 16.1
a) (Disposal of Fixed and Non-Fixed Assets).
The Recipient shall notify Canada in writing, one hundred eighty (180) days in advance if, at
any time during the Fixed Asset Disposal Period or Non-Fixed Asset Disposal Period, the
Recipient proposes to significantly reduce, abandon or essentially abandon a Fixed and/or
Non-Fixed Asset, as described in subsection 16.1 a) (Disposal of Fixed and Non-Fixed
Assets).
18.2 TOLLING
The Project, as described under this Agreement, will not be tolled at any time during a
period of twenty-five (25) years after the Project Completion Date, unless an agreement is
reached with Canada relative to the establishment of Tolls and the treatment of funds
contributed by Canada for the Project under this Agreement, and:
(i) A free and fully accessible alternate route is available, without significant
restrictions, unless the only alternate route is serviced by ferry, bridge, or through
tolled facilities already existing as at the Effective Date;
(ii) toll revenues are used exclusively to offset project costs for projects where toll
revenues, in whole or in part, flow to a private sector operator excluding Eligible
Costs covered under this Agreement; ongoing operating costs; capital maintenance
(e.g., resurfacing); a contingency reserve; rate of return on capital (excluding all
public contributions); and purchase of private land for the right-of-way, if any;
(iii) a tariff of Tolls be made available by the Recipient to any member of the public, on
request;
(iv) the tariff of Tolls, and exemptions, be applied without discrimination for the same
class of user, regardless of their place of origin; and
(v) Tolls are collected, where feasible, through the use of electronic tolling systems that
Page 26 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
The Recipient agrees not to permit the establishment of Tolls, at any time during a period of
twenty-five (20) years after the date of completion of a Project, for all or a portion of the
Project, unless an agreement is reached with Canada relative to the establishment of Tolls
and the treatment of funds contributed by Canada for the Project under this Agreement.
19. GENERAL
19.1 GOVERNING LAW
This Agreement is governed by the laws of British Columbia, subject always to any
paramount or applicable federal laws.
19.9 NO BENEFIT
Page 27 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
No member of the House of Commons or the Senate of Canada will be admitted to any
share or part of this Agreement or of any Contract made pursuant to this Agreement, or to
any benefit arising from them.
No provision of this Agreement and no action by the Parties will establish or be deemed to
establish a partnership, joint venture, principal-agent relationship, or employer-employee
relationship in any way or for any purpose whatsoever between Canada and the Recipient
or between Canada and a Third Party.
Without limiting the generality of the foregoing, the Recipient agrees not to represent itself,
including in any agreement with a Third Party, as a partner or agent of the Crown. Canada
shall have no responsibility for fulfilment of any obligation into which the Recipient enters in
relation to the Project, including, without limitation, any loan, capital lease or other long-term
obligation.
The Recipient represents that it is not subject to an obligation or prohibition which could
restrict or interfere with its performance of this Agreement, and further, that no actions or
legal proceedings have been brought and that it has not received any threat of actions or
proceedings that could or may restrict or interfere with its performance of this Agreement.
The Recipient agrees to inform Canada immediately if any such action or proceedings are
threatened or brought during the term of this Agreement.
19.13 ASSIGNMENT
The Recipient shall not transfer or assign its rights or obligations under this Agreement
without the prior written consent of Canada. Any attempt by the Recipient to assign any of
the rights, duties or obligations of this Agreement without Canada’s express written consent
shall be deemed invalid.
19.14 WAIVER
Any tolerance or indulgence demonstrated by a Party will not constitute a waiver. A Party
may only waive its rights under this Agreement in writing.
Page 28 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
No current or former public servant or public office holder or reporting public office holder to
whom the Conflict of Interest Act (2006, c. 9, s.2), the Values and Ethics Code for the Public
Service and/or the Conflict of Interest and Post-employment Code for Public Office Holders
apply, shall derive any direct benefit from this Agreement, unless said individual is in
compliance with the applicable provisions of the Act and/or Codes.
The Recipient shall inform Canada, in writing, should any real and/or apparent conflict of
interest exist or arise that could have a direct impact on Canada’s contribution to the
Project.
19.19 SUCCESSOR
This Agreement is binding upon the Parties and their respective administrators and
successors.
19.20 OFFICIAL LANGUAGES ACT
The Recipient is responsible, in consultation with Canada, for taking the necessary
measures to respect the spirit and intent of Official Languages Act, R.S.C. 1985 c. 31 (4th
Supp.) to communicate with the public in the official language of their choice.
Page 29 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Any notice, including but not limited to, certificates and declarations provided for under this
Agreement shall be delivered in person or sent by registered mail, or facsimile. Said notice
shall be deemed to have been delivered on the earlier of either receipt by the addressee or
ten (10) business days after mailing if sent by registered mail or the following business day
if delivered in person or sent by facsimile.
Subject to subsection 19.1 (Notice deemed given), any information and/or documentation
provided for under this Agreement may be delivered in person, or sent by mail, facsimile, or
by electronic transmission.
For Canada:
Page 30 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Page 31 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
SIGNATURES
This Agreement has been executed on behalf of Her Majesty in Right of Canada by the
Minister of Transport, Infrastructure and Communities, and on behalf of the Recipient by
[TITLE].
____________________
____________________ [NAME]
[NAME] [TITLE]
Minister of Transport, Infrastructure
and Communities
__________________ ____________________
Page 32 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Subject to subsection A.2, Eligible Costs will be all direct costs, which are in Canada’s opinion
properly and reasonably incurred and paid by an eligible Recipient for an eligible investment
under a contract for goods or services necessary for the implementation of a Project, and
includes:
c) The costs of joint communication activities (press releases, press conferences, translation,
etc.) and road signage recognition set out in the Communication Protocol that will form part
of the Agreement;
d) All planning (including plans and specifications) design and evaluation costs specified in the
Agreement such as the costs of environmental planning, surveying, engineering,
architectural supervision, testing and management consulting services, as limited by
subsection 4.1 a) ii) of this Agreement;
g) The costs of developing and implementing innovative techniques for carrying out the
Project;
i) Other costs that, in the opinion of Canada, are considered to be direct and necessary for the
successful implementation of the Project and have been approved in writing prior to being
incurred, with the exception of Ineligible Costs as noted below.
Page 33 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Certain costs are not eligible for funding and therefore will not be considered in the
calculation of the total Eligible Costs of the Project, including:
a) Costs incurred prior to the signature of the Agreement and after the Project Completion
Date.
b) The cost of purchasing land, associated real estate and other fees, financing charges and
interest payments on loans;
c) Provincial sales tax and the Goods and Services Tax for which the Recipient or a third party
is eligible for a tax rebate and all other costs eligible for rebates;
d) Costs which have been shared under other federal statutes or programs;
e) Legal fees;
f) General repairs and maintenance of a Project work and related structures unless they are
part of a larger capital expansion Project;
i) Employee wages and benefits, overhead costs as well as other direct or indirect operating,
maintenance and administrative costs incurred by the Recipient, and more specifically costs
relating to survey, engineering, design, architecture, supervision, management and other
services delivered directly by permanent employees of the Recipient, or of a Crown
corporation or corporation owned and controlled by the Recipient except in the case where
the Recipient can demonstrate value for money.
Page 34 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
$ $ $ % $ % $ $ $
th th
64 Avenue Extension from 204 St. to
th
216 St
Page 35 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
C.1 General
C.1.1 The Parties agree to carry out joint communications activities and products that
will promote opportunities to communicate project milestones with the public in
an open, transparent, effective and proactive manner, using appropriate,
ongoing, consistent public information material acknowledging the Parties’
contributions.
C.1.2 The Committee shall identify appropriate forms for these communications and
public information activities and products, and may strike a communications sub-
committee responsible for providing advice and support on these matters. If
necessary, the sub-committee will create a proposed rollout of communication
activities. The sub-committee shall be made up of at least one representative of
each Party.
C.1.3 All Joint Public Communication Material in relation to this Agreement shall be
prepared in both official languages in accordance with the Official Languages Act
(Canada), and shall equitably reflect the contributions of the Parties and, where
applicable, any Third Party Operators. This includes ensuring equal recognition
and prominence where words, logos, symbols and other types of identification
are incorporated into materials.
C.1.5 All Joint Public Communication Material concerning this Agreement shall be in a
form approved by the Committee.
C.1.6 In the event of an election call that affects the riding the project is located in,
whether federal, provincial or municipal, no public announcements will be
permitted.
C.1.7 Costs associated with the development and delivery of joint communications
products and activities are an Eligible Cost. All costs are to paid by the Recipient
and submitted to Canada for reimbursement in accordance with the funding ratio
established in Schedule B.
Page 36 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
C.3.2 All draft joint communications products shall be distributed to the partners in
sufficient time to allow for appropriate approvals. The lead-time should be, at a
minimum, twenty (20) business days prior to the event/publication of material.
Media releases
C.3.3 Unless agreed to in advance by the Parties, the Parties shall organize a signing
ceremony and a joint media release shall be issued when the Agreement is
signed. A release, in which each of the Parties is assigned equal importance,
shall be issued in respect of each Project or in combination with other Projects,
unless otherwise agreed by the parties. The releases will include quotations from
all Parties. The Parties shall agree upon and approve the content of the release.
C.3.5 Either Party may organize a joint media conference or public ceremony
pertaining to a Project. Unless agreed to in advance by the Parties, the Party that
does so shall give the other Party reasonable notice of twenty (20) business
days, and such notice shall also be given in respect of other joint events or public
announcements.
Signage
C.3.6 the Recipient further agrees to supply, erect and maintain, on the direction of
Canada:
b) upon completion of a project and where feasible, the Parties may provide and
install, a plaque or permanent sign bearing an appropriate inscription. The
Page 37 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Page 38 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
D.1 Purpose
The purpose of the audit framework is to provide independent and objective assurances
that:
a) systems and procedures are in place to ensure that the management process has
regard to the terms and conditions of the Agreement and ensures that the financial
assistance is granted for Projects that met the eligibility criteria and the applicable
obligations or requirements.
a) to determine whether funds have been disbursed for the agreed purposes, by
examining the payment approval process, including the nature and extent of the
supporting documents, the accuracy of the information supplied in respect of claims
for payment and the evidence of appropriate authorizations, and such other due
diligence reviews as appropriate; and
b) to ensure that prompt and timely corrective action is taken in response to audit
findings.
The criteria with which, the auditor will express an opinion as to the recipient’s financial
compliance are established by the following sections of Agreement:
Page 39 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
D.4.1 The auditor should provide an audit opinion as to the recipient’s compliance with
the criteria established by Section D3 – Audit Criteria of Schedule D – Audit
Framework.
D.4.2 The auditor should provide an audit opinion in accordance with Section 5815 –
Audit Reports on Compliance with Agreements, Statutes and Regulations of the
Canadian Institute of Chartered Accountant’s assurance handbook.
D.4.3 The auditor’s report should refer to the eligible criteria and to a Schedule of
Eligible Expenditures.
D.4.4 Notes attached to the Schedule of Eligible Expenditures should include a general
note outlining a general description of the project, a listing of significant
accounting policies used to prepare the Schedule of Eligible Expenditures and a
note describing what constitutes and eligible and ineligible expenditure.
D.5.1 The independent auditor will have an equal duty of care to both Canada and the
Recipient.
D.5.2 The Committee shall approve the annual audit plans and the report of the audit
findings, and shall ensure that prompt and timely corrective action is taken in
response to the audit findings, including the recovery of funds, where applicable
D.5.3 The Recipient will be responsible for ensuring that all audits required under the
Agreement are carried out and will pay all audit costs, except for those audits
specified in Section 11.8.
D.6.1 The Committee shall ensure that an annual audit plan is drawn up and includes
an overall strategy for the audit as well as a detailed audit plan.
The overall strategy would include but is not limited to the following:
Page 40 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
b) The overall audit strategy sets the scope, timing and approach to the audit, and
guides the development of more detailed audit plans;
c) Ascertaining the reporting objectives of the engagement to plan the timing of the
audit and the nature of the communications required, and key dates for expected
communications with management and those responsible for governance;
The detailed component of the audit plan would include but is not limited to the following:
D.6.2 The Committee shall ensure that all audit reports be available to the public on
request. In addition, pursuant to the Treasury Board of Canada’s audit policy,
the Federal Co-chair shall ensure that the results of any available audits are
provided to the public on request.
D.6.3 Any audit conducted within the framework of this Agreement shall be done in
accordance with accepted auditing standards such as the rules of the Canadian
Institute of Chartered Accountants.
Page 41 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
SCHEDULE E – INFORMATION
E1 General
The purpose of Schedule E is to identify the data and information that the
Recipient must collect and provide to Canada under this Agreement, as well as
the sharing and the use of this information by the Parties. The Parties agree that
the collection of accurate and timely data and information is essential to ensure
the sound management of this Agreement and to report to Canadians on results
and accomplishments.
E2 Annual Report
As per section 11.6 (Annual Report), Recipient will provide an Annual Report by
July 31st of each Fiscal Year. The report shall include the following:
E3 Retrospective Evaluation
Page 42 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Within 7 years following the Final Project Component Completion Date, the
Recipient agrees to prepare and submit a retrospective analysis in order to
evaluate whether the objectives of the prospective analysis have been met.
Page 43 of 44
Agreement for 64th Avenue Extension from 204 St. to 216 St, Township of Langley
2008/2009-2011/2012
Engineer’s SEAL
(name, title)
____________________________
(Witness name, title)
Page 44 of 44
ATTACHMENT C
PROJECT AGREEMENT
TransLink
BC Ministry of Transportation and Infrastructure
Port Metro Vancouver
Township of Langley
2904702.1
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
PROJECT AGREEMENT
64th Avenue Rail Overpass at Highway 10
Project
(the “Project”)
BETWEEN:
(“TransLink”)
AND:
(“BC MoT)”)
AND:
(the “Township”)
AND:
WHEREAS
A. The British Columbia Ministry of Transportation and Infrastructure (“BC MoT”), the
South Coast British Columbia Transportation Authority (“TransLink”), Vancouver Fraser Port
2904702.1 Page 1
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Authority (“Port Metro Vancouver”) and the Township of Langley (“Township”), herein called
the Parties, along with other agencies identified below, wish to promote international trade
through a program, funded in part by the Asia-Pacific Gateway and Corridor Initiative, that
provides a comprehensive program of road/rail grade separations on the Roberts Bank Rail
Corridor (the “RBRC Program”).
B. The RBRC Program is intended to facilitate and improve the movement of rail freight to
and from the Roberts Bank marine terminals through the communities of Delta, Surrey, Langley
City and the Township of Langley while providing relief for those communities and road users
affected by the rail transport and enhancing movement of people and goods in those
communities.
C. The RBRC Program Partners include Transport Canada, BC MoT, TransLink, Port Metro
Vancouver, the Township, the Corporation of Delta, the City of Surrey, the City of Langley, the
British Columbia Railway Company, the Canadian Pacific Railway Company, the Canadian
National Railway, and the BNSF Railway. The RBRC Program Partners have agreed to
participate in and to contribute to the RBRC Program as described in an “Agreement-in-
Principle” signed on June 28th, 2007 (the “AIP”) under which TransLink, on behalf of the
partners under the RBRC Program, has been appointed to develop, coordinate and implement,
administer and manage the overall delivery of the RBRC Program.
D. TransLink has appointed a program manager for the RBRC Program (the “RBRC
Program Manager”) who will undertake the day to day activities of the RBRC Program.
E. The 64th Avenue Highway 10 Road Rail Grade Separation Project (the “Project”) is part
of the RBRC Program, and will separate rail and vehicular traffic thereby facilitating and
improving the movement of people and goods on the road network and the movement of rail
freight to and from the Roberts Bank marine terminals through the communities of the City of
Langley and the Township of Langley.
F. TransLink wishes to improve the Major Road Network and promote the movement of
goods and people through participation in the Project.
G. BC MoT wishes to ensure it maintains a safe and efficient highway system through the
delivery of the Project.
H. Port Metro Vancouver wishes to participate in the Project in order to improve and
enhance the movement of imported and exported goods to and from the marine port facilities at
Roberts Bank along the Roberts Bank rail corridor.
I. The Township wishes to participate in the Project in order to provide relief for its citizens
through the grade separation of rail and vehicular traffic and to improve public safety,
emergency vehicle access and the movement of goods and people in the surrounding
communities.
2904702.1 Page 2
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
J. Accordingly, the Parties wish to meet the objectives of the RBRC Program through the
overpass and associated road improvements described in this Agreement by the cost-effective
planning, design, construction and funding of the Project. The Parties agree to cooperate in the
Project with a shared sense of purpose, mutual respect and trust.
K. The Parties agree that the Township will be responsible for the day to day delivery and
implementation of the Project in accordance with the terms and conditions of this Agreement
including land acquisition and consolidation, procurement, design and construction.
IN CONSIDERATION of the promises and covenants contained in this Agreement the Parties
hereby agree as follows:
1. DEFINITIONS
1.1 In this Agreement, the following terms will have the following meanings:
(a) “Approval Matrix” means the approval matrix attached as Schedule “A” to this
Agreement;
(b) “Agreement-in-Principle” means the agreement-in-principle dated for reference June
27, 2007, in which Transport Canada, BC MoT; TransLink, Port Metro Vancouver;
the Corporation of Delta; the City of Surrey; the City of Langley; the Township;
British Columbia Railway Company; Canadian Pacific Railway; Canadian National
Railway; and, BNSF Railway agreed to participate in and to contribute to the RBRC
Program, including this Project, and under which TransLink is appointed to manage
the overall delivery of, and to develop, coordinate and implement, the RBRC Program;
(c) “BC MoT” means Her Majesty the Queen in right of the Province of British Columbia
as represented by the Minister of Transportation and Infrastructure;
(d) “Communications” includes media releases, media updates, public responses, printed
materials, information sessions and staged events;
(e) “Communications Plan” means the plan which is approved as part of the Project
Implementation Plan and which shall be consistent with the RBRC Program
communications plan;
(f) “Commencement Date” means the date of reference of this Agreement;
(g) “Conceptual Plan” means the plan for the Project attached as Schedule “B” to this
Agreement as it may be amended in writing from time to time during the Term;
(h) “Contract” means the written agreement for the Design, Construction and completion
of the Project that will be made between the Township and the successful Proponent in
accordance with the terms of the RFP;
(i) “Contractor” means the person who enters into the Contract with the Township;
(j) “Contribution Amount” means, subject to amendment in accordance with this
Agreement, the contribution for each Party to the Project as identified and set out in
2904702.1 Page 3
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Schedule “C” to this Agreement for an aggregate total amount not to exceed $51
Million or such other amount or amounts as the Parties hereto may agree in writing;
(k) “Construction” means all things other than Design necessary to complete the Work;
(l) “Design” means the compendium of drawings, plans, specifications and other project
material produced by a professional engineer or other professional that is lawfully
authorized to provide design services in British Columbia, to calculate, determine and
define the items of Work to be constructed together with the labour required to prepare
such materials;
(m) “District Transportation Manager” means the District Transportation Manager of the
Lower Mainland District of the Ministry of Transportation and Infrastructure;
(n) “Document of Requirements” means the document described in Subsection 6.1(b) as
may be amended in writing from time to time during the Term;
(o) “Engineer” means a person who is authorized, registered or licensed under the
Engineers and Geoscientists Act to provide professional engineering services in
British Columbia;
(p) “Evaluation Committee” means the RFP evaluation committee as described in
Subsection 6.1 (c) ;
(q) “Funding Partner Representatives” means representatives of those agencies identified
in Schedule “C” that are contributing to the Project;
(r) “G.S.T.” means the goods and services tax imposed under the Excise Tax Act
(Canada);
(s) “Improvement(s)” includes anything made, constructed, erected, built, altered,
repaired or added to, in, on or under Project Land, and attached to it or intended to
become a part of it, and also includes any clearing, excavating, digging, drilling,
tunnelling, filling, grading or ditching of, in, on or under Project Land;
(t) “Major Road Network” has the meaning set out in the SCBCTA Act;
(u) “Milestone Dates” means the milestone dates set out in Schedule “D” to this
Agreement as they may be amended in writing by the Parties hereto;
(v) “Multi-Modal Use” means the safe, uninterrupted, and unobstructed use of a highway
including travelled lanes, sidewalks, pathways and shoulders by all forms of traffic
including automobiles, bicycles, motorcycles, buses, trucks and pedestrians;
(w) “Owner’s Engineer” means Delcan Corporation, or any other person approved in
advance in accordance with the Approval Matrix, who has been retained to provide
engineering services for the Project on behalf of the Township;
(x) “Owner Partner Representatives” means representatives of those agencies that will
own and/or have jurisdiction over the Project’s infrastructure at completion, being BC
MoT, Township and TransLink for its interest in the Major Road Network and transit
services within the Project;
2904702.1 Page 4
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(y) “Parties” means BC MoT, TransLink, Port Metro Vancouver and Township.
(z) “Port Metro Vancouver” means Vancouver Fraser Port Authority;
(aa) “Process Advisor” means the person who is appointed by the Township to review the
procurement process for the Project;
(bb) “Produced Material” means all accounting records, findings, software, data,
specifications, drawings, reports, documents and other material produced by the
Contractor (or any of its employees) or any of its subcontractors (or its employees) as
a result of the Contract including all such material which is in existence prior to the
start of the Term or developed independently of the Contract;
(cc) “Project” means the Design and Construction of Improvements shown on the
Conceptual Plan together with all associated works and infrastructure, the scope of
which is described in Schedule “E” to this Agreement;
(dd) “Project Budget” means the project budget described in Schedule “C” to this
Agreement as it may be amended in accordance with the terms of this Agreement;
(ee) “Project Change Request” means the written request referred to in Section 8.1;
(ff) “Project Costs” means the actual eligible costs of completing the Project as defined in
Schedule “C”;
(gg) “Project Implementation Plan” means the plan described in Subsection 6.1(a) as
maybe amended in writing from time to time during the Term;
(hh) “Project Manager” means Doug Hyde or any other person approved in advance in
accordance with the Approval Matrix, who has been appointed or retained by the
Township to provide project management services for the Project on behalf of the
Township;
(ii) “Project Land” means the land upon which the Project is constructed;
(jj) “Project Organization and Human Resource Plan” means the organization and
identification of human resources for the Project identified in Section 5;
(kk) “Project Procurement Plan” means the procurement plan identified in Section 5 and
approved in accordance with the Approval Matrix;
(ll) “Project Schedule” means the detailed schedule for the Design, Construction and
completion of the Project set out in the Project Implementation Plan, which will be
consistent with the Milestone Dates;
(mm) “Project Scope” means the description in Schedule “E” to this Agreement and as
generally shown on the Conceptual Plan in Schedule “B” to this Agreement that will
be more fully developed and designed in accordance with the Project Implementation
Plan and the Document of Requirements all in accordance with this Agreement;
(nn) “Property Costs” means Project Costs relating to the acquisition of real property;
(oo) “Project Steering Committee” means the committee established by the RBRC Program
as described in Schedule “F”;
2904702.1 Page 5
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
with the exception of defects and deficiencies and incomplete works that do not
affect its appearance or impair its use provided the total value of all incomplete,
defective and deficient Work does not exceed 3% of the Project Budget set out in
Schedule “C” to this Agreement;
(xx) “Term” means the period of time as set out in Section 3.5;
2904702.1 Page 6
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(yy) “Total Completion” means that the entire Work (including the grant of a non-
exclusive, non-transferable, perpetual, irrevocable, royalty-free, worldwide licence of
the as-built drawings along with all moral rights therein from the Contractor to the
Township and MoT) except for those items which are or may be the subject of a
warranty claim, has been performed to the requirements of the Contract and is so
certified by the Contractor through the Contractor’s Engineer;
(zz) “Township” means the Corporation of the Township of Langley;
(aaa) “TransLink” means the South Coast British Columbia Transportation Authority;
(bbb) “Work” or “Works” means everything to be provided and performed by the Township
in relation to the Project including the provision of all professional, technical, skilled
and unskilled labour, services, material, equipment and including, without limitation,
all Design and Construction, and any action as necessary for the Contractor,
subcontractors and other contractors to complete and perform their respective
obligations arising from and in accordance with the terms and conditions of the
Contract or contracts.
1.2 The schedules, that shall form part of this Agreement and are attached hereto,
are as follows:
2904702.1 Page 7
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
3. PROJECT DELIVERY
3.1 The Township will deliver the Project in accordance with the terms of this
Agreement.
3.2 The Township represents and warrants that it has, or will retain, the skills and
experience necessary to carry out the Project in a professional, competent and
diligent manner.
3.3 The Township will undertake and deliver the Project to completion, or will
cause its Contractor to undertake and deliver the Project to completion, in
accordance with this Agreement and, without limitation:
(a) in accordance with Schedule “E” to this Agreement for the Project Scope;
(b) in a professional, competent, timely and diligent manner, in accordance with
acceptable standards and specifications set out in this Agreement;
(c) in compliance with all applicable laws, statutes, regulations, by-laws, and directions of
all governmental and statutory authorities issued under lawful authority; and
(d) achieve Substantial Completion by 2012 or such later date as agreed to by the Parties
in accordance with the Approval Matrix.
3.4 In order to deliver the Project on behalf of the Parties in accordance with this
Agreement, and without limiting the foregoing, the Township:
(a) will comply with and enforce all agreements that it enters into to have the Project
delivered;
(b) will ensure all consents, permits, licences, certificates and approvals, including an
environmental assessment in accordance with the Canadian Environmental
Assessment Act, necessary to complete the Project are obtained prior to
commencement of Construction;
(c) will ensure proper implementation of the Project Implementation Plan;
(d) will ensure the Project Manager facilitates review and approval of the Project
deliverables in accordance with the Approval Matrix; and
(e) will ensure that:
(i) the Project Manager promptly advises the Parties of any changes that may
have a significant impact on the scope, schedule or budget of the Project;
(ii) access to all land that is impacted by the Construction of the Project is
maintained;
(iii) the Project Manager advises the Parties promptly upon receiving notice
from the Contractor of the anticipated date of full Multi-Modal Use;
(iv) the Parties have access to the Project at all reasonable times to carry out
their obligations under this Agreement and to ensure compliance with the
Contract; and
2904702.1 Page 8
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(v) if required, a reference plan under section 107 of the Land Title Act is
prepared and deposited in the land title office in order to dedicate all
highways.
3.5 The term of this Agreement commences on the Commencement Date and
terminates on the date that all warranty and any other obligations under the
Contract are fully performed or such earlier date provided for in this Agreement.
3.6 The Township:
(a) will develop the Project Implementation Plan, the Document of Requirements and the
Project Budget; and
(b) will complete the Project in accordance with this Agreement.
3.7 The Township will ensure monthly progress reports describing the status of the
Project are provided to the Project Steering Committee 15 days following the
end of each month or such other period of time that the Parties may direct. The
Project Steering Committee will review the progress reports for general
conformance with the RBRC Program. The Parties will review for compliance
with the Project and this agreement. The monthly progress reports will contain
the following:
(a) progress of Design and Construction to date in relation to and compared against the
Project Schedule and the likelihood of meeting each of the Milestone Dates;
(b) an up-to-date Project Schedule, showing dates on which Milestones Dates have been
achieved, indicating any variances, and showing projected dates for future Milestone
Dates;
(c) a brief description of Project Work planned for the next month;
(d) an up-to-date summary of actual Project Costs, forecast of costs to Total Completion,
and variances, if any, from the Project Budget;
(e) any procurement undertaken for the Project;
(f) any material communications undertaken for the Project;
(g) any land acquisition for the Project;
(h) any required approvals;
(i) any safety issues encountered;
(j) quality management and assurance status;
(k) risk management and monitoring and any actions taken or recommended to manage or
mitigate risks;
(l) a description of any significant difficulties encountered, any anticipated claims for
extra Project Costs, or any other actual or anticipated deviations from Project Scope,
Project Budget, Project Schedule, or other plans; and
(m) any other matters requested by the Parties.
2904702.1 Page 9
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
3.8 The Parties agree that a Project Steering Committee will review all key Project
decisions for general conformance with the RBRC Program as described in the
Approval Matrix in accordance with the terms of reference set out in Schedule
“F” to this Agreement.
3.9 Each of the Township, TransLink and BC MoT will appoint an Owner Partner
Representative who will have the authority to take any actions required and to
make timely decisions and approvals on behalf of his or her respective agency
for this Project as described in the Approval Matrix.
5.1 The primary purpose of the RBRC Program Manager is to undertake the day-to-
day activities of the program on behalf of the Partners Committee. Specific
responsibilities related to this Project include:
(a) acting as secretariat to the Project Steering Committee:
(i) ensuring that the Project Steering Committee functions in an effective and
efficient way;
(ii) coordinating distribution and collection of Project and relevant RBRC
Program documentation to and from relevant parties in a timely manner;
and
2904702.1 Page 10
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(iii) ensuring that the items requiring attention and decision from the RBRC
Propgram Partners are expediently brought forward to the attention of the
Parties.
(b) providing independent oversight and verification of Project Costs and financial
accountability throughout lifetime of the project:
(i) verifying Project Costs, assessing their conformance with overall RBRC
Program objectives and making a recommendation for payment to
individual RBRC Program Partners providing funding to the Project,
following the agreed-upon principles for Project Costs as described in
Schedule “C”.
(ii) ensuring that the Project, where possible will benefit from available
economies of scale during RBRC Program implementation; and
(iii) establishing and maintaining a financial planning framework to facilitate
RBRC Program and Project cash flow planning and financial tracking to
the Project.
2904702.1 Page 11
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
2904702.1 Page 12
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
2904702.1 Page 13
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
7.6 Subject to the Process Advisor’s opinion obtained by the Township that the
procurement process has been fair, equitable, open, transparent and competitive,
the evaluation and ranking of the proposals and award of the Contract will be
reviewed and approved by the Parties in accordance with the Approval Matrix
whereupon the Project Manager will forward to the Township the Evaluation
Committee’s recommendation and Owner Partier Representatives’ approval and
, if accepted by the Township Council, the Township will negotiate the Contract
with the successful proponent in compliance with the process described in the
RFP.
7.7 Upon the successful negotiation of the Contract, the Project Manager will advise
the Owner Partner Representatives and the RBRC Program Manager of that fact
and, upon approval by the Owner Partner Representatives, and if accepted by the
Township Council, the Township will, in accordance with the RFP, ensure that
the Contract is executed by the Contractor and the Township.
7.8 The Parties acknowledge that it is their intention to deliver the Project utilizing a
design- build process, however, if no acceptable proposal is submitted in
accordance with the RFP, the Parties will consider delivering the Project by
another delivery method and, if they determine to do so, another RFP or other
appropriate procurement process will be issued by the Township and the
provisions of this Section will apply to the issuance of that subsequent RFP or
procurement process.
2904702.1 Page 14
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
reviews of Design and Construction of the Project to ensure compliance with the
design and engineering standards. The Project Manager will provide the quality
management plan to the Owner Partner Representatives for review for general
compliance with the RBRC Program.
9. CHANGE MANAGEMENT
9.3 The Project Manager will advise the Parties of the Project Change Request and
its assessed impact on the Project.
9.4 If the Parties agree that the Project Change Request should be considered
further, subject to Section 9.5, the Project Manager will forward the request to
the Project Steering Committee who will review the Project Change Request for
general conformance to the RBRC Program and will provide any comments and
advise of any non-conformances to the Project Manager, who will then advise
the Parties of such feedback. .
9.5 Any material change to the Project Scope, Project Budget or Project Schedule
will require the approval of the Parties in accordance with the Approval Matrix.
9.6 If a Project Change Request is substantially caused by or required by one Party,
after considering the Project Change Request, the Parties may decide to approve
the Project Change Request provided that the Party or Parties benefiting from
the Project Change Request first agrees to bear all of the costs that are incurred
as a result of that Project Change Request at no cost to the Project.
2904702.1 Page 15
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
9.7 If the Project Change Request is approved and it changes Project Costs, the
Parties agree to amend the Project Budget and Contribution Amounts by each
Party as required in accordance with Section 10.
9.8 If the Project Change Request is approved, the Township will amend the
Document of Requirements, Project Implementation Plan and the Contract, as
applicable, to reflect the approved change to the Project Scope, the Project
Budget, Project Contributions and the Project Schedule.
Cost Overruns
10.1 The Parties will use their best efforts to keep the Project Costs within the Project
Budget, however, if at any time Project Costs are forecast to exceed the Project
Budget, the Parties may jointly agree to amend the Project Scope to
accommodate the cost increase so that Project Costs are kept within the Project
Budget while ensuring that the objectives of the RBRC Program and of the
Project are reasonably met
10.2 If the Parties are unable to amend the Project Scope to keep the Project Costs
within the Project Budget while ensuring that the objectives of the RBRC
Program and of the Project are reasonably met, the Parties may request
additional funds from either or both the RBRC Program or their respective
agencies as follows:
(a) request the RBRC Manager for additional funds from the RBRC Program, in
which case the RBRC Manager will request the RBRC Program Partners to
evaluate the request and review it for general conformance to the scope, budget
and costing of the RBRC Program, and determine availability of funds;
(b) request additional funding from their respective agencies and, if such request for
funding is approved, the Parties may agree to amend the Project Budget and
contribute additional funding to cover the overruns in their respective
proportionate share.
10.3 If no additional funds are available from the RBRC Program or the Parties’
respective agencies and the Project Cost cannot be reasonably reduced without
significantly impacting Project and RBRC Program objectives, the Parties will:
(a) consider whether any of the Program or Project objectives could be amended in
order to reduce costs to meet the Project Budget in which case the RBRC
Manager will request the RBRC Program Partners to evaluate the request and
review it for general conformance to the scope, budget and costing of the RBRC
Program; or
(b) if it is prior to award of the Construction Contract, agree to abandon the Project in
which case each Party will pay a prorated amount of its Contribution Amount of
the Project Costs incurred up to and including the date of the abandonment of the
2904702.1 Page 16
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Project and the obligations of the Parties under this Agreement will be at an end;
and
(c) if it is after the award of the Construction Contract, the Township and BC MoT
may agree to pay for overruns of the Project Costs beyond the Project Budget
provided the overruns are associated with delivery and do not result from Project
Change Requests by another Party.
10.4 If additional funds are obtained from the RBRC Program or the Parties’
respective agencies or if scope is reduced to meet the Project Budget, the
Township will amend other documents in accordance with Section 9.8 and the
RBRC Program Manager will be advised of the amendments.
Abandonment, Termination
10.5 If the Contract has not been awarded, the Project may be abandoned as a result
of an event beyond the control of the Parties provided that each Party will pay a
prorated amount of its Contribution Amount of the Project Costs incurred up to
and including the date of the abandonment of the Project and, in which case, the
obligations of the Parties under this Agreement will be at an end.
2904702.1 Page 17
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(iii) the covering letter in Subsection (ii) above will provide a summary of
what portion of the Design is to be reviewed, provide a list of all
documents within the package to be reviewed and specify the date by
which the Township requires a written response from the Owner Partner
Representatives; and
(iv) for significant Design reviews, at the request of the Owner Partner
Representatives, the Project Manager will organize a Design review
meeting between the Contractor and the Owner Partner Representatives.
Such meetings will be scheduled to permit reasonable time for review of
the Contractor’s Design submission prior to the meeting and to allow
sufficient time for written feedback within 14 days as aforementioned in
this Section.
2904702.1 Page 18
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(d) deliver to each Owner Partner Representative as they may require, a copy in both
paper and electronic formats of autoCAD drawings prepared on the latest version of
autoCAD, of all Produced Material together with an non-exclusive, non-transferable,
perpetual, irrevocable, royalty-free, worldwide licence to use, reproduce, modify and
distribute the Produced Material granted from the Contractor to the Township and BC
MoT; and
(e) ensure the Contractor has completed all incomplete work and rectified all identified
defects and deficiencies, except for warranty obligations, in accordance with the
Contract and to the satisfaction of the Parties.
2904702.1 Page 19
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
14.5 . If, after review of the invoice and documentation provided by the Project
Manager in accordance with Section 14.2 above, a Party or the RBRC Program
Manager identifies any error or omission in the invoice within 10 days of receipt
of the invoice, it will notify the Project Manager and the RBRC Program
Manager with a copy to the other Parties. The Project Manager will promptly
investigate such discrepancy and amend and resubmit the invoice or, if no
amendment is warranted, provide further documentation to the Parties clarifying
the matter.
14.6
14.7 The monthly invoice of Project Costs referred to in Section 12.2 must be
certified by the Project Manager as being correct and include the following
statement:
“This statement is delivered to the Township of Langley pursuant to an agreement
between TransLink, the Ministry of Transportation and Infrastructure, the
Vancouver Fraser Port Authority and the Township of Langley which is dated for
reference November ___, 2008 (the “Project Agreement”). I certify that this is a
true and correct statement of the Project Costs (as defined in the Project
Agreement) which have been incurred by the Township of Langley during the
statement period on account of the Project (as defined in the Project
Agreement).”
14.8 If:
(a) the Township is not in material breach of the Agreement; and
(b) each Party is satisfied, acting reasonably, with the supporting documentation provided
under Section 14.2 above;
each Party will pay their respective share of the progress payment requested under
Subsections 14.3 and `4.4 above within 30 days of receipt of the RBRC Invoice in
accordance with Schedule “C”.
14.9
14.10 The Project Budget specified in Schedule “C” to this Agreement will be
inclusive of all applicable taxes.
14.11 The Parties will release their final payment within 30 days after Total
Completion of the Project, receipt of all of the supporting documentation
required under Section 11.2 and the following, which are to be provided to all
Parties:
(a) a written certificate, executed by the Township’s Director of Engineering and
Operations, that the Project has been completed in accordance with this Agreement
and, in particular, meets or exceeds engineering specifications and standards set out in
Schedule “E” to this Agreement;
2904702.1 Page 20
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
(b) a statement, certified by the Township’s Chief Financial Officer, which must include
the total amount of Project Costs, a breakdown of each Party’s contribution to the
Project, and the following statement:
“I certify that the Project Costs as stated have been incurred by the Township
of Langley, are attributable to this Project, are correct, meet the definition set
out in the Project Agreement dated for reference November ___, 2008 and are
net of the Municipal GST rebate”; and
(c) a Project close-out report, prepared by the Owner’s Engineer, which sets out
recommendations for the operation, maintenance and future rehabilitation of the
Project.
2904702.1 Page 21
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
17. ASSIGNMENT
17.1 No Party may assign this Agreement without the prior written consent of the
others, such consent not to be unreasonably withheld.
17.2 The assignment of this Agreement does not release the Township from its
obligation to observe and perform all the provisions of this Agreement on its
part to be observed and performed unless the Parties specifically release the
Township from such obligation in its consent to the assignment of this
Agreement.
2904702.1 Page 22
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
2904702.1 Page 23
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
20.2 In addition to the foregoing, and notwithstanding any other term or provision
herein contained, the Township, for and on behalf of itself, its councillors,
officers, employees, agents, contractors and subcontractors, hereby
unconditionally, absolutely and irrevocably releases and forever discharges the
Indemnified Parties from any and all losses, liabilities or damages, at law or in
equity and whether direct, indirect or consequential, which relate to, arise out of,
or are in any way connected with the Design, engineering, Construction,
operation, maintenance or rehabilitation of the Project or the Work, whether
caused by, or arising through the negligence of the Indemnified Parties.
20.3 The Township acknowledges that the indemnity under Section 208.1 and the
release under Section 20.2 will not be affected in any way by the provisions of
Section 2.
21. INSURANCE
21.1 The Township will ensure that insurance and bonding or other contract security
is put in place for the Project with insurers and sureties licensed in British
Columbia with coverage of a type, and in amounts, that BC MoT specifies for
projects of the scope, size and exposure of this Project, during the term of this
Agreement and for any subsequent ongoing operation and maintenance and
rehabilitation of the resulting infrastructure.
21.2 The Township shall require and ensure that each contractor and sub-contractor
involved in the Project maintains insurance compatible with the coverage
required in Section 21.1.
2904702.1 Page 24
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
with the intent that the Parties resolve any dispute within 14 days of the dispute
arising (or within such other time period agreed to by the Parties) through
amicable negotiations, failing which, the Parties will resolve the dispute as
follows:
(a) by referring the matter to the Parties’ representatives for a unanimous resolution; and
(b) failing the unanimous resolution of the matter within 14 days of the dispute being
referred to it under Subsection (a), by referring the matter to the following
representatives of the Parties for resolution or such other representatives as may be
appointed by the Parties from time to time:
(i) the Municipal Administrator of the Township;
(ii) the Vice President, Capital Management and Engineering of TransLink;
(iii) the Vice President, Business Development of Port Metro Vancouver; and
(iv) the Assistant Deputy Minister, Partnerships of BC MoT,
and, subject to applicable laws, the Parties will provide candid and timely disclosure to
each other of all relevant facts, information and documents to facilitate the resolution of
the dispute.
22.2 Subject to Section 22.5 below, if a dispute under this Agreement is not resolved
under Subsection 22.1(b) within 30 days of the dispute being referred to the
persons identified in Subsection 22.1(b), or within such other time period agreed
to in writing by the Parties, any Party may refer the dispute to arbitration
conducted by a sole arbitrator appointed under the British Columbia Commercial
Arbitration Act. The Parties will agree on the arbitrator or, failing agreement,
the arbitrator will be appointed in accordance with the rules of the British
Columbia International Commercial Arbitration Centre and the Commercial
Arbitration Act.
22.3 The cost of the arbitration referred to in Section 22.2 will be shared equally by
the Parties and the arbitration will be governed by the laws of the Province of
British Columbia.
22.4 The arbitration will be conducted at a location agreed upon by the Parties.
22.5 A dispute under this Agreement in respect of a matter within the sole discretion
of a Party cannot, unless the other Party agrees, be referred to arbitration as set
out in Section 22.2.
2904702.1 Page 25
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
2904702.1 Page 26
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
25. GENERAL
25.1 The Parties will make all decisions required of them under this Agreement in an
expeditious and timely manner.
25.2 Each of the Parties will at all times, from time to time and upon reasonable
request, do, execute and deliver all further assurances, acts and documents for
the purpose of evidencing and giving full force and effect to the covenants,
agreements and provisions in this Agreement.
25.3 Time will be of the essence under this Agreement.
2904702.1 Page 27
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
25.4 Nothing contained or implied herein will prejudice or affect the rights and
powers of the Township or the Township’s approving officer in the exercise of
its or his functions under any public and private statutes, bylaws, orders, and
regulations, all of which may be fully and effectively exercised as if this
Agreement had not been executed and delivered by the Parties.
25.5 The warranties, representations and agreements contained in this Agreement will
not be subject to merger but will survive the completion of the Project.
25.6 All notices, demands, claims or other communications required or permitted
hereunder will be in writing and may be delivered prepaid, sent by facsimile or
sent by prepaid first class mail, except that delivery of material documents, plans
and money to be delivered to a Party in accordance with the terms of this
Agreement will be effected by hand or courier to the address specified below,
such deliveries to be effective only on actual receipt.
Any notice will be deemed to have been given or received at the time of delivery to the
address of the recipient as set out below. Any notice delivered by facsimile will be
deemed to be delivered on the next business day following the date of transmission
thereof. Any notice mailed as aforesaid will be deemed to have been given and received
on the fourth business day following the date of its mailing. Any notice will be addressed
as follows:
To: TransLink
1600 – 4720 Kingsway
Burnaby, B.C., V5H 4N2
Attention: Manager, Roads and Bridges
Facsimile No.: (604) 453-4600
2904702.1 Page 28
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
provided, however, that a Party may, by notice in writing to the other Parties, specify
another address for service of notices under this Agreement and, where another address is
specified by a Party, notice must be delivered to that address in accordance with this
Section.
25.7 Wherever this Agreement provides that an action may be taken, a consent or
approval must be obtained or a determination must be made, then such Party will
act reasonably in taking such action, deciding whether to provide such consent
or approval or making such determination; but where this Agreement states that
a Party has sole discretion to take an action, provide a consent or approval or
make a determination, there will be no requirement to show reasonableness or to
act reasonably in taking that action, providing that consent or approval or
making that determination.
25.8 If, due to a strike, lockout, labour dispute, act of God, inability to obtain labour
or materials, law, ordinance, rule, regulation or order of a competent
governmental authority, enemy or hostile action, civil commotion, fire or other
casualty or any condition or a cause beyond the Township’s reasonable control,
the Township is delayed in performing any of its obligations under this
Agreement, the time for the performance of that obligation will be extended by a
period of time equal to the period of time of the delay so long as the Township:
(a) gives notice to the Parties of the delay setting forth the nature of the delay and an
estimated time frame for the performance of the Township obligation; and
(b) diligently attempts to remove the delay if it is within its power to do so;
and all costs associated with such delay will be Project Costs.
25.9 The Parties agree that nothing in this Agreement constitutes any of them as the
agent, joint venturer or partner of the other Parties or gives any of them any
authority or power to bind the other Parties in any way and that all obligations
imposed under this Agreement shall be several and not joint.
25.10 This Agreement is binding upon and enures to the benefit of the Parties and their
successors and permitted assigns.
25.11 No remedy conferred upon or reserved to either Party is exclusive of any other
remedy in this Agreement or provided by law, but such remedy will be
cumulative and will be in addition to any other remedy in this Agreement or now
or hereafter existing at law, in equity or by statute.
2904702.1 Page 29
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
25.12 This Agreement may be executed in counterparts and when the counterparts
have been executed by the Parties, each originally executed counterpart, whether
a facsimile, photocopy or original, will be effective as if one original copy had
been executed by the Parties to this Agreement.
25.13 Each Party confirms that it has not, nor has any person on its behalf, given,
promised or offered to any official or employee of Port Metro Vancouver or Her
Majesty the Queen in Right of Canada for or with a view to obtaining this
Agreement any bribe, gift or other inducement and that it has not nor has any
person on its behalf, employed any person to solicit or secure this Agreement for
a commission, percentage, brokerage or contingent fee.
IN WITNESS WHEREOF the Parties hereto have executed this Agreement the day and year first
above written.
_______________________________________________
(Authorized Signatory)
_______________________________________________
Name, Title (Please print)
_______________________________________________
(Authorized Signatory)
_______________________________________________
Name, Title (Please print)
2904702.1 Page 30
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
_______________________________________________
(Authorized Signatory)
_______________________________________________
Name, Title (Please print)
_________________________________ ______________
(Authorized Signatory)
_______________________________________________
Name, Title (Please print)
_______________________________________________
(Authorized Signatory)
_______________________________________________
Name, Title (Please print)
_________________________________ ______________
(Authorized Signatory)
_______________________________________________
Name, Title (Please print)
2904702.1 Page 31
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Schedule “A”
Approval Matrix
1 Any change to the Project Manager or Township Review for general Project Steering
Owner’s Engineer (including, criteria, compliance with RBRC Committee
selection and assignment) Program.
Approve Owner Partner
Representatives
2 Project Implementation Plan Township Review for general Project Steering
(as described in Subsection 6.2) compliance with RBRC Committee
Program.
Approve Parties
4 DB RFP
Procurement Plan (as described in Township Review for general Project Steering
Subsection 6.1) compliance with RBRC Committee
Program.
Approve Owner Partner
Representatives
Evaluation and Selection Township, BC Review for general Project Steering
MoT compliance with RBRC Committee
Program.
Approve Owner Partner
Representatives
Award/Contract Township Approve Owner Partner
Representatives
5 Acceptance of Technical Compliance at Owner’s Accept Owner Partner
all phases and including all exceptions to Engineer Representatives,
design standards City of Langley
6 Any Material Change to Project Township Review for general Project Steering
Parameters (scope, schedule, budget) compliance with RBRC Committee
Program.
Approve Owner Partner
Representatives
7 All Other contracts (after execution of Township none required.
this agreement)
2904702.1 Page 1
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
2904702.1 Page 2
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Schedule “B”
Conceptual Plan
[To be inserted by the Township]
2904702.1 Page 1
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Schedule “C”
Project Costs, Contribution Amounts and Project Budget
Project Costs
Project Costs will mean all direct costs properly and reasonably incurred and paid solely and
specifically in relation to the Project including capital costs that would usually be capitalized in
the financial records of the Township.
The following are examples of Project Costs that will be eligible for reimbursement under this
Agreement, provided that they fall within the definition set out in the immediately preceding
paragraph:
• prior to execution of agreements: specified third Party costs related to studies, tests, reports,
consulting work and other actual costs incurred by the Parties, other than internal work, for
work directly related to development, planning, design and land acquisition necessary for the
Project (as agreed to by the Parties in advance)including work done by Delcan as Owners
Engineer, work by Pacific Land Group regarding the ALC application, Greta Soo for land
acquisition, Bramcon as process advisor, and Arcas for the archaeological works;
• costs for services related to project delivery by staff and consultants (such as Project
Manager, Owner’s Engineer, process advisor, etc.) as agreed to by the Parties in advance;
• after execution of agreements: capital costs actually and reasonably incurred for planning,
development, design, engineering, environmental work, land acquisition, construction
commissioning and management of the Project including:
o costs incurred under Design and Construction contracts;
o Actual costs of applications, permits/licences and approvals required for the
Project (excluding those required/charged by RBRC ProgramPartners) including:
environmental protection and compensation works required by
government authorities and as agreed to in writing by the Parties;
archaeological protection and compensation works required by
government authorities and as agreed to in writing by the Parties;
permitting fees required for the Project;
relocation of existing utilities if required to facilitate the Project; and
acquiring a licence to use the Produced Material, in accordance with
Section 6.4(f);
o actual costs(including legal costs) incurred for acquisition of land required for
the Project (including by expropriation if necessary) as identified and agreed to by
the Parties (exclusive of land owned by a Party which is utilized for the Project or
that not agreed to by the Parties);
o surveying;
2904702.1 Page 2
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
o traffic management;
o studies and testing;
o basic landscaping (sod/seeding and gravel only);
o restoration of existing features and infrastructure disrupted by construction of the
project (basic landscaping, driveway pavement, curbs);
o consultant/professional fees for engineering, environmental design, construction,
monitoring, inspection, testing and contract administration;
o project management costs and disbursement in relation to the Project; and
o actual costs of communications and community relations reasonably incurred for
the Project (including Project signs, events and media releases);
• legal costs incurred by the Parties for preparing and reviewing contracts or agreements
for the Project, except for legal costs incurred by the Parties for preparing and reviewing
this Agreement;
• dispute resolution costs – actual costs incurred by the Parties to enforce the contract or to
resolve claims arising from the Project; and
• any other cost as specifically agreed to in writing by the Parties.
Notwithstanding the above, the following are examples of costs that will not be eligible for
reimbursement under this Agreement:
2904702.1 Page 3
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Project Budget
The Project Budget as of January 2009 is based on the Conceptual Design set out in Schedule
“B” and as more particularly described in the Project Scope described in Schedule “E” is
summarized below.
TransLink $24,000,000
BC MoT $12,500,000
Township $9,300,000
* Note: Transport Canada will be advancing their funds through a separate contribution
agreement between Transport Canada and the Township.
2904702.1 Page 4
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Schedule “D”
Estimated Milestone Dates
Milestone Date
NOTE: Total Completion must not extend beyond March 2014 (termination of federal
funding.)
2904702.1 Page 1
Project Agreement Roberts Bank Rail Corridor Program
64th Avenue Rail Overpass at Highway 10
(RBRC) Project
Schedule “E”
Project Scope
The Township will implement the Project including the Design and Construction of the Project,
the scope of which includes the following:
• new four-lane overpass, northeast of the existing Mufford Crescent crossing over the
railroad and Glover Road (an approximate overpass structure of 440 m with a
superstructure span of 220 m with shoulders on each side);
• new four-lane west approach road from Mufford Crescent (northwest of 62nd Avenue)
to the overpass along with two cul-de-sacs closing Mufford Crescent between existing
at-grade crossings of RBRC and the new approach road (including shoulders);
• closing of the access to Highway 10 from Mufford Crescent;
• new four-lane east approach road to connect the overpass with 216th Street at 64th
Avenue (including shoulders);
• new bridge over North Creek;
• intersection improvements at 64th Avenue, west of 216th Street including additional
east and westbound left turn lanes from the new road to 64th Avenue and rebuild of
64th Avenue at the intersection;
• intersection improvements at 64th Avenue and 216th Street including east and
westbound left turn lanes from 64th Avenue to 216th Street;
• two lane access road to farms approximately 650 m in length from Mufford Crescent,
under the overpass and along the railway;
• utility adjustments or relocations;
• land acquisition.
The Township will implement the Project in accordance with the following standards and
specifications:
Provincial Engineering Standards and Specifications
Provincial infrastructure (overpass and highway connections) to be designed and
constructed to BC MoT design and engineering standards and specifications as approved
by BC MoT South Coast Region.
2904702.1 Page 1
ATTACHMENT D
OPEN HOUSE QUESTIIONNAIRE SUMMARY
3. If you said yes to question 2, which option best meets the needs of the Township of Langley?
No. of 39 9 9 78 11 22 27 195
Responses
Results 20% 5% 5% 40% 5% 11% 14% 100%
6. Are you in favour of streetlights through the rural portion of the project?