You are on page 1of 1

Activity Revise Proposal

Time Scale Feb-May 12

Additional Comments

Progress to date
complete

Literature Review

Feb-Aug 12

ongoing

Data Collection

May-Dec 12

Will seek clearance from the Directors of Education in Falkirk and Stirling Councils in Feb 12 Will start to target school to participate once clearance is granted Meetings with Head Teachers, class teachers and pupils

Complete

Data Transcription

July-Dec 12

Complete

Coding and analysis

Sept 12 May13

Consideration about P7 pupils who have participated is required as they may have produced data in May but will no longer be at Primary to analyse it. Some aspects of coding and analysis may have to be brought forward to deal with this.

ongoing

Initial drafting of chapters Final editing and submission

Dec 12- Jul 13

ongoing

Nov 13 Feb 14

Not started

You might also like