TECHNICAL CALCULATION AND ESTIMATOR'S MAN-HOUR MANUAL

Marko Buli

Marko Buli

TECHNICAL CALCULATION AND ESTIMATOR'S MAN-HOUR MANUAL

ERECTION OF PROCESS OR CHEMICAL PLANTS

I. II. III. IV. V. VI. VII. VIII. IX. X.

PIPING ABOVE GROUND PIPELINES STEEL STRUCTURES PROCESS EQUIPMENT STORAGE TANKS CYLINDRICAL AND SPHEROIDAL WELDING AND FLAME CUTTING CORROSION PROTECTION THERMAL INSULATION ESTIMATES PIPING ABOVE GROUND ESTIMATE POINTS FOR BUILD-IN ITEMS XI. WEIGHT FACTORS XII. TECHNICAL CALCULATION MANNER OF DATAS COMPILING XIII. MAN HOURS FOR OVERHAULS IN PETROCHEMICAL PLANTS XIV. FACTORS AND MAN HOURS FOR PIPING AND STEEL STRUCTURE WORKS IN CALL FOR TENDERS OF TECHNIP COMPANY XV. APPENDIX

ZAGREB, 2003. (Completed edition)


All right reserved. This book, or parts thereof, may not be reproduced in any form without permission of the author.

Thank you for showing interest in buying our book TECHNICAL CALCULATION AND ESTIMATOR'S MANHOURS MANUAL You can buy the electronic version of the Manual containing all the figurest and other related data at the following prices: Individuals 1. COMPLETE MANUAL (239 pages) US$ 600 Legal entity US$ 1000

2. I II III IV V VI VII VIII IX X XI XII XIII XIV

EACH CHAPTER PIPING ABOVE GROUND - 36 pages + 20* PIPELINES - 7 pages + 20* STEEL STRUCTURES - 7 pages + 20* PROCESS EQUIPMENT - 10 pages + 20* STORAGE TANKS - CYLINDRICAL & SPHERICAL - 11 pages + 20* WELDING AND FLAME CUTTING - 18 pages + 20* CORROSION PROTECTION - 3 pages + 20* THERMAL INSULATION - 3 pages + 20* ESTIMATES - 11 pages + 20* PIPING ABOVE GROUND - ESTIMATE POINTS FOR BUILD-IN ITEMS - 76 pages + 20* WEIGHT FACTORS - 7 pages TECHNICAL CALCULATION MANNER OF DATA COMPILING - 4 pages MANHOURS FOR OVERHAULS IN PETROCHEMICAL PLANTS - 16 pages + 20* FACTORS AND MANHOURS FOR PIPING AND STEEL STRUCTURE WORKS IN CALL FOR TENDERS OF TECHNIP COMPANY - 3 pages + 20* US$ 180 US$ 75 US$ 80 US$ 70 US$ 80 US$ 75 US$ 35 US$ 35 US$ 100 US$ 130 US$ 15 US$ 6 US$ US$ US$ US$ 300 120 130 110

US$ 130 US$ 120 US$ 55 US$ 55 US$ 165 US$ 215 US$ 25 US$ 10

US$ 80

US$ 130

US$ 60

US$ 100

NOTE: +20* = THE FIRST 13 PAGES OF THE MANUAL AND 7 PAGES OF THE APPENDIX

3. 4.

A PERSONALISED ANALOGUE VERSION OF THE MANUAL COULD BE ORDERED AS WELL. Please, email us your full address and indicate the purchase option you have decided for. We shall send you the electronic manual immediately. As soon as your payment is received we shall send you the password that will enable you to open and use the e-manual. We congratulate you on your choice and thank you for buying our electronic Manual.

PREFACE

All 40 years of my working life, I spent on erection of different process plants most of which were oil industry projects in the country and abroad, in Europe and North Africa. Since 1978 with occasional interruptions because of simultaneous involvement in several different projects, I worked mostly on technical calculations. I have made hundreds and hundreds calculations based on all kinds of tenders and erection of mech anical equipment. The tenders were written in various foreign languages and alphabet, even in Cyrillic. I am fully aware of the problems an estimator encounters when working on technical calculations for specific technologies. Very often tenders were not complete and not detailed enough, and the time required for a good technical calculation is getting every day shorter. It is not easy to present exact technical figures and quantities for the equipment or operations not fully defined, hard to comprehend, or even unknown to the estimator. Technical terms and expressions written in different languages and dialects are often incorrect and specific for individual branches. Enormous experience is needed, an ability to assess and estimate, and even the courage to write down the technical quantities and figures. That was the reason for collecting various technical bibliography, standards, catalogues, man hours and rates from the European and USA countries. I have made the analyses, comparisons, simulations, new measures, and manhour tables. A great deal of that was verified in practice during the plant erection. I surveyed the results and analyses of as-built designs. On many occasions, I sought a compromise between different opinions and standpoints. Too many things collected on too many places. Finally, I decided to write this manual for discriminative estimators. It is important to understand that there are no identical projects or jobs in this business, that each project is specific and that no automatism or copying is possible. Approach to any job should be serious and professional and a technical calculation should be made with the assistance of this Manual. Many people try to include the man hours from the tables into the computer systems, which I oppose. Those are the people, which instead of using a computer, a computer uses them. An estimator himself must choose the values and define the man hours taking into account all the elements that might have any influence on them. Only when the relevant man hours are estimated and selected, a computer can be used. A saying Switch on your brain before switching on the computer should be followed. The most complex work in developing these man hours was the work on the man hours for piping above ground. A basis I used was a system for estimating the value of erection works of a German Company LINDE, which I completed and modified. Generally, for elaboration of the man hours for erection/installation of process equipment, I used the English man hours of the Oil and Chemical Plant Constructors Association, but I used other sources as well. The source or the author was noted for other tables and if I modified them, I provided the modification basis. Where there are no such notes, I am the only author. A complete edition of this manual in the Croatian language and its sections were published in 1997 and 2000. This is why I have not given a unified percentage of the production efficiency but each chapter has its own.

Marko Buli

Zagreb Croatia, 2003

CONTENTS
page PREFACE...........................................................................................................................2 INTRODUCTION..............................................................................................................11 ABBREVIATIONS & UNITS.................................................................................................13 CHAPTER I. PIPING ABOVE GROUND................................................................................14 DERIVED OPERATING TIME STANDARD FOR TABLES FACTOR OF BASIC ASSEMBLY 1. PIPES (ANSI B. 36.10)...................................................................................14 1.1 1.2 2. 2.1 2.2 2.3 2.3.1 2.3.2 2.4 1.1 1.2 1.3 1.4 1.5 1.6 PIPE - INSTALLATION ON PROCESS PLANT...............................................................14 PIPE - INSTALLATION ON PIPE RACK OR SLEEPER WAY............................................15 FITTINGS (ANSI B. 16.9).......................................................................................16 ELBOWS...............................................................................................................16 CAPS....................................................................................................................16 TEES....................................................................................................................17 STRAIGHT TEE.....................................................................................................17 REDUCED TEE......................................................................................................17 REDUCERS - CONCENTRIC AND ECCENTRIC..........................................................18 1. PIPES (DIN 2448/2458)..............................................................................19 PIPE - INSTALLATION IN PROCESS PLANT..............................................................19 PIPE - INSTALLATION ON PIPE RACK OR SLEEPER WAY............................................21 STEAM TRACING (ANSI & DIN)..............................................................................23 INSTRUMENT AND CONTROL PIPING.....................................................................23 STEAM DISTRIBUTORS AND CONDENSATE COLLECTORS FABRICATED FROM PIPES AND FITTINGS...............................................................23 STEAM DISTRIBUTORS AND CONDENSATE COLLECTORS FABRICATED FROM READY MADE DISTRIBUTORS FOR 4 CONNECTIONS.....................................23 2. FITTINGS (DIN)............................................................................................24 2.1 2.2 2.3 2.4 3.1 3.2 3.3 3.4 3.5 3.6 4.1 4.2 4.3 4.4 ELBOWS..............................................................................................................24 CAPS...................................................................................................................24 TEES...................................................................................................................26 REDUCERS - CONCENTRIC AND ECCENTRIC..........................................................28 3. FLANGES.......................................................................................................30 WELDING NECKS..................................................................................................30 SLIP - ON.............................................................................................................31 SOCKET WELDING................................................................................................31 LAP JOINT + STUB END........................................................................................31 BLIND..................................................................................................................31 ORIFICE COMPLETE..............................................................................................31 4. SMALL FITTINGS...........................................................................................32 WELDOLETS, SOCKOLETS, NIPOLETS, etc..............................................................32 HALF COUPLINGS FOR WELDINGS.........................................................................32 FITTINGS WITH SOCKET ENDS..............................................................................32 THREADED FITTINGS............................................................................................32
3

5. VALVES................................... ........ ..........................................................33 5.1 5.2 5.3 5.4 5.5 1. 2. 2.1 2.2 2.3 2.4 2.5 2.6 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. VALVES WITH FLANGED ENDS...............................................................................33 VALVES WITH WELDING ENDS..............................................................................34 VALVES FOR THREADED ENDS..............................................................................34 PRESSURE GAUGES..............................................................................................34 THERMOMETERS..................................................................................................34 RATES FOR TENDER CALCULATIONS...............................................................35 MANHOUR ESTIMATE FOR INSTALLATION OF PIPING.............................................35 EFFECT ASSESSMENT FOR QUICK CALCULATION...................................................36 PIPING IN PROCESS PLANT...................................................................................36 PIPES (CARBON STEEL - NOT INSULATED) - MEAN VALUE......................................37 FITTINGS (CARBON STEEL) - MEAN VALUE.............................................................38 VALVES - MEAN VALUE..........................................................................................39 PIPE SUPPORTS....................................................................................................39 AVERAGE DIAMETER - Manner of Calculation..........................................................39 RATES FOR INSTALLATION OF POLYETHYLENE PIPING...........................................40 RATES FOR ERECTION OF PVC & FRP PIPING........................................................41 CARBON STEEL PIPING CEMENT LINED INSIDE......................................................41 PIPING MADE OF STEEL AND GREY CAST-IRON......................................................42 RATES FOR PIPING BASED ON INCH-DIAMETER (ID)...............................................43 RATES FOR UNITS OF OPERATION - BASED ON INCH-DIAMETER (ID).......................44 RATES FOR PIPING WELDING...............................................................................46 MAN HOURS FOR WELDING OF PIPING................................................................47 WORK CALCULATION - MAN HOURS FOR PIPING MODIFICATION AT SITE...............48 INSTALLATION OF PIPING ABOVE - GROUND Prefabrication and installation breakdown..............................................................49 CHAPTER 1. 2. 3. 4. 5. 6. 7. 8. 8.1 8.2 8.3 8.4 8.5 8.6 8.7 9. 10. II. PIPELINES...................................................................................................50 PIPE TRANSPORT..................................................................................................50 PIPE STRINGING..................................................................................................51 BENDING OF PIPES...............................................................................................51 PIPE JOINTING.....................................................................................................52 WELDING.............................................................................................................53 WRAPPING...........................................................................................................53 LAYING IN TRENCH...............................................................................................53 SPECIAL POINTS...................................................................................................54 BORING UNDER ROADS AND RAILROADS...............................................................54 BREAK OUT OF ROADS..........................................................................................54 CONNECTING PIPELINE SECTIONS........................................................................54 CROSSING WATERCOURSES..................................................................................55 INSTALATION OF CLEANING STATIONS..................................................................55 PUTTING UP PIPELINE MARKERS...........................................................................55 OTHER SPECIAL POINTS.......................................................................................55 PRESSURE TESTS.................................................................................................56 PRELIMINARY AND FINISHING WORKS.................................................................56
4

CHAPTER 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.1

III. STEEL STRUCTURE ERECTION....................................... . ... ...................57 1. BASIC MAN HOURS - UNIT.....................................................................57 SORTING THE STRUCTURE....................................................................................57 PRE-ERECTION OF STRUCTURE.............................................................................57 TRANSPORT OF STRUCTURE TO ERECTION PLACE.................................................57 INSTALLATION OF ANCHOR BOLTS........................................................................57 STRUCTURE ERECTION.........................................................................................57 INSTALLATION OF LOST FORMWORK.....................................................................58 INSTALLATION OF WIRE ROPE CLAMPS..................................................................58 REAMING OF HOLES.............................................................................................58 BOLTING FROM SCAFFOLDING...............................................................................58 2. ERECTION OF MISCELLANEOUS STEEL STRUCTURES.................................59 BASIC MANHOUR RATES.......................................................................................59 3. CORRECTION FACTORS................................................................................59 4. STEEL STRUCTURES IN OIL REFINERIES AND PETROCHEMICAL PLANTS...61

4.1 4.2 4.3 4.4 4.5

LIGHT STRUCTURE (to 30 kg/m)...........................................................................61 MEDIUM-WEIGHT STRUCTURE (31 60 kg/m)......................................................61 HEAVY STRUCTURE (above 60 kg/m).......................................................................61 MISCELLANEOUS STRUCTURES..............................................................................61 PIPE HANGERS AND SUPPORTS.............................................................................61 5. ERECTION AND DISMANTLING OF MISCELLANEOUS STEEL STRUCTURES.............................................................62

5.1 5.2 5.3 CHAPTER 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.1 2.1.1 2.1.2 2.1.3 2.2 2.2.1 2.2.2

ERECTION OF STEEL STRUCTURES - ACC. TO THE WEIGHT....................................62 MISCELLANEOUS STRUCTURES.............................................................................62 REMOVAL OF STEEL STRUCTURE AND MISCELLANEOUS ITEMS...............................66 IV. ERECTION OF EQUIPMENT IN PETROCHEMICAL INDUSTRY....................67 1. STATIONARY EQUIPMENT............................................................................67 ALL EQUIPMENT TO 0,5 TON.................................................................................67 TOWERS above 0,5 TON........................................................................................67 TOWERS CONSISTING OF MORE PIECES...............................................................67 PACKAGE UNIT....................................................................................................67 OTHER EQUIPMENT.............................................................................................67 BRIDGE CRANES..................................................................................................67 LIFTS...................................................................................................................67 ELECTROSTATIC PRECIPITATORS...........................................................................68 MARINE LOADING ARMS.......................................................................................68 2. ROTARY EQUIPMENT....................................................................................68 CENTRIFUGAL PUMPS...........................................................................................68 MAN HOURS BASED ON POWER [kW]....................................................................68 MAN HOURS BASED ON WEIGHT [kg]....................................................................69 MAN HOURS BASED ON THE CAPACITY..................................................................69 COMPRESSORS.....................................................................................................70 COMPRESSORS DRIVEN BY ELECTRIC MOTOR........................................................70 COMPRESSORS DRIVEN BY GAS TURBINE..............................................................70
5

3. TOWERS & VESSELS - INSTALLATION OF INTERIOR COMPONENTS & EQUIPMENT.....................................................................71 3.1 3.2 3.3 3.4 4.1 4.2 CHAPTER 1. 1.1 2. 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 3. CHAPTER 1. 2. 3. 4. 5. CHAPTER 1. 2. 3. CHAPTER 1. 2. INSTALLATION OF TRAYS AND DEMISTERING PADS...............................................71 VESSELS & TOWER PACKINGS...............................................................................71 OPENING AND CLOSING OF MANHOLES.................................................................71 ERECTION OF PLATFORMS, LADDERS AND FLOOR GRIDS.......................................72 4. EQUIPMENT SCAFFOLDING.........................................................................72 TUBULAR SCAFFOLD.............................................................................................72 PATENT SCAFFOLDING.........................................................................................73 V. STORAGE TANKS - CYLINDRICAL AND SPHEROIDAL.................................74 APPROX. WEIGHTS AND ERECTION EFFECTS OF CYLINDRICAL STORAGE TANKS........74 STATISTICAL PARTICIPATION OF STORAGE TANK COMPONENTS IN TOTAL WEIGHT..........................................................................75 ERECTION OF CYLINDRICAL STORAGE TANKS - DETAILS........................................76 PRELIMINARY WORKS..........................................................................................76 STORAGE TANK BOTTOM......................................................................................76 STORAGE TANK SHELL..........................................................................................77 WIND BINDINGS - RINGS FOR SHELL STIFFENING.................................................77 FIXED ROOF.........................................................................................................78 FLOATING ROOF...................................................................................................79 AUXILIARY STRUCTURE........................................................................................80 CONNECTIONS AND OPENINGS.............................................................................81 STORAGE TANK EQUIPMENT..................................................................................82 FINISHING WORKS...............................................................................................83 ERECTION OF SPHERICAL AND SPHEROIDAL STORAGE TANKS...............................84 VI. WELDING AND FLAME CUTTING................................................................85 MANUAL ARC WELDING OF CYLINDRICAL TANKS - SMAW........................................85 SUBMERGED ARC WELDING..................................................................................90 WELDING WITH SEMIAUTOMATIC (GMAW)............................................................95 WELDING OF SPHERICAL STORAGE TANKS..........................................................100 MANUAL GAS CUTTING AND GAS CONSUMPTION.................................................102 VII. CORROSION PROTECTION......................................................................103 SAND BLASTING AND PAINTING OF PIPING.........................................................103 SAND BLASTING AND PAINTING OF STEEL STRUCTURES......................................104 SAND BLASTING AND PAINTING OF STORAGE TANKS...........................................105 VIII. THERMAL INSULATION..........................................................................106 THERMAL INSULATION FOR PIPING.....................................................................106 THERMAL INSULATION OF VESSELS AND KILNS...................................................108

CHAPTER 1. 2.

1. 2. 3. 4.

1. 2.

9.1 9.2 9.3 9.4 9.5 9.6 9.7 10.1 10.2 10.3 10.4

1. 2. 3.

1. 2. 3. 4. 5.

IX. ESTIMATES...........................................................................................109 1. ESTIMATE OF SCAFFOLDS........................................ . .............................109 ESTIMATES OF SCAFFOLDING WHEN CONTRACTED TO A SPECIALIST FIRM..........109 ESTIMATE OF SCAFFOLDING WHEN DONE BY AN ERECTION COMPANY.................110 2. ESTIMATE OF WELDING ROD CONSUMPTION AND ADDITIONAL WELDING MATERIAL........................................................112 PIPING...............................................................................................................112 STEEL STRUCTURES............................................................................................113 CYLINDRICAL STORAGE TANKS............................................................................113 EQUIPMENT IN PETROCHEMICAL INDUSTRY.........................................................113 3. ESTIMATE OF CONSUMPTION OF TECHNICAL GAS AND GRINDING PLATES..........................................................................114 4. ESTIMATE OF ELECTRICITY CONSUMPTION.............................................115 5. ESTIMATE OF CONSUMPTION OF FUEL AND LUBRICANT.........................116 FUEL CONSUMPTION...........................................................................................116 LUBRICANT CONSUMPTION.................................................................................116 6. TOOL COST ESTIMATE AT THE JOB SITE...................................................117 7. ESTIMATE OF SAFETY AT WORK MEANS...................................................117 8. ESTIMATE OF ERECTION TIME...................................................................117 9. SELECTION OF HOISTING MACHINERY.....................................................118 SELECTION OF THE LARGEST CRANE...................................................................119 PIPING IN PLANTS..............................................................................................119 PIPING BETWEEN PLANTS...................................................................................120 PIPELINES.........................................................................................................120 ERECTION OF STEEL STRUCTURE.......................................................................120 INSTALLATION OF PROCESS EQUIPMENT.............................................................120 ERECTION OF CYLINDRICAL STORAGE TANKS......................................................120 10. UNLOADING, HANDLING AND SORTING OF THE MATERIAL.....................121 MATERIAL FOR PIPING.......................................................................................121 STEEL STRUCTURE.............................................................................................121 PROCESS EQUIPMENT.........................................................................................121 CYLINDRICAL STORAGE TANKS...........................................................................121 11. TEMPORARY WORKS, SPACE REQUIRED AND CONNECTIONS AT THE SITE...................................................................122 TEMPORARY WORKS...........................................................................................122 AREA NEEDED....................................................................................................123 CONNECTIONS NEEDED......................................................................................123 12. ESTIMATE OF THE NUMBER OF WELDS AND RADIOGRAMS FOR PIPING....................................................................124 ESTIMATE OF BUTTWELDS BASED ON A LIST OF MATERIAL - PIPES, FITTINGS AND FLANGES.........................................................................124 ESTIMATE OF BUTTWELDS BASED ON A LIST OF MATERIAL - FITTINGS AND FLANGES ONLY...........................................................................124 ESTIMATE OF BUTTWELDS BASED ON THE PIPING LENGTHS................................125 ESTIMATE OF TOTAL WELDS (ALL TYPES)............................................................125 ESTIMATE OF RADIOGRAMS ON THE PIPING........................................................125
7

CHAPTER

X. PIPING ABOVE GROUND EXPLANATION TO THE ERECTION ITEMS............................................................127 1.0 PIPING......................................................................................................127

1.1 1.2 1.3 2.1 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10

PIPE INSTALLATION IN PLANTS..........................................................................127 PIPE INSTALLATION ON PIPERACKS.....................................................................127 PIPE DISMANTLING............................................................................................127 2.0 FITTING.....................................................................................................127 ADJUSTMENT OF FITTINGS WITH ONE CONNECTION END....................................128 ADJUSTMENT OF FITTINGS WITH TWO CONNECTION ENDS................................128 ADJUSTMENT OF FITTINGS WITH THREE CONNECTION ENDS..............................128 3.0 PIPEWELD MAKE-ON AND WELDING.......................................................128 BUTT WELD MAKE-ON AND WELDING..................................................................128 FILLET (SOCKET) WELD - PERFORMANCE AND WELDING......................................128 MITRE WELD MAKE-ON AND WELD......................................................................129 NOZZLE WELD MAKE-ON AND WELDING..............................................................129 WELDOLET, NIPOLET - INSTALLATION AND WELDING..........................................129 REINFORCEMENT PAD MAKE-ON AND WELDING...................................................129 SEAL RING MAKE-ON AND WELDING (ACC. TO DIN 2695).....................................129 INSERT RING (FOR AL ONLY)..............................................................................130 WELD CUTTING FOR MODIFICATIONS.................................................................130 MATERIAL MULTIPLIER FACTORS (f)....................................................................130 4.0 FLANGED AND THREADED JOINTS, BENDING OF PIPES..........................130 FLANGED JOINT...................................... .................................................130

4.1 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2

INSTALLATION OF MEASURING ORIFICES, BLANKING PLATES, etc.........................130 PIPE BENDING....................................................................................................130 PREPARATION OF THREADED ENDS....................................................................131 THREADED CONNECTION MAKE-ON....................................................................131 DISASSEMBLING Item 4.1 4.4 and 4.7.................................................................131 5.0 VALVES......................................................................................................131 VALVE INSTALLATION (WITH AND WITHOUT HAND DRIVE)..................................131 VALVE INSTALLATION WITH ACTUATORS (SOLENOID, AIR)...................................131 BUTTERFLY VALVE INSTALLATION WITH ACTUATOR.............................................131 BUTTERFLY VALVE INSTALLATION........................................................................131 CONTROL VALVE INSTALLATION..........................................................................131 SAFETY VALVE INSTALLATION.............................................................................132 HYDRANT INSTALLATION....................................................................................132 SPINDLE EXTENSIONS.........................................................................................132 DISMANTLING OF VALVES...................................................................................132 6.0 PRESSURE TESTING..................................................................................132 PRESSURE TEST..................................................................................................132 SERVICE TEST.....................................................................................................132

7.0 MISCELLANEOUS.......................................... . ......................................132 7.1 7.2 7.3 7.4 7.5 8.1 8.1.1 8.1.2 8.1.3 8.1.4 8.1.5 8.2 8.2.1 8.2.2 8.2.3 8.2.4 8.2.5 8.3 8.3.1 8.3.2 8.3.3 8.3.4 8.4 8.4.1 8.5 8.5.1 8.5.2 8.6 8.7 SUPPORTS - FABRICATION AND WELDING...........................................................132 SUPPORT INSTALLATION (WITHOUT FABRICATION).............................................132 INSTALLATION OF SPRING HANGERS AND SUSPENSIONS.....................................133 GRINDING OF EXCESS MATERIAL ON WELDING ROOTS........................................133 INSTRUMENT CONNECTION - DRILLING..............................................................133 8.0 ACTIVITIES DERIVED FROM BASIC ITEMS.............................................133 PIPES...............................................................................................................133 PIPE HANDLLING AND CUTTING IN PREFABRICATION...........................................133 INSTALLATION OF PREFABRICATED SPOOLS.........................................................133 SPATIAL SHIFTING OF PIPES...............................................................................133 MAKE-ON OF OUTSIDE PIPE FOR A DOUBLE-WALL PIPING (JACKETED PIPING)................................................................................134 MAKE-ON AND INSTALLATION OF LINE PIPING DN 20/25 ON JACKETED PIPING..........................................................................134 MISCELLANEOUS FITTINGS............................................................................134 HALF COUPLINGS................................................................................................134 WELD COMPENSATOR.........................................................................................134 WELD METER RUNS............................................................................................134 PREFABRICATED OF SPOOLS FOR WELDING.........................................................134 MEASURING ORIFICES - MEASURING FLANGES....................................................135 WELDING........................................................................................................135 TACK WELDING ON VALVE SIMULATORS..............................................................135 LONGITUDINAL WELDS ON PIPE HALF SHELLS....................................................135 THERMOMETER BRANCH (TI).............................................................................135 PREFABRICATED WELDS AT INSTALLATION OF PREFABRICATED SECTIONS (SPOOLS).................................................................135 FLANGED JOINTS............................................................................................135 REPLACEMENT OF BOLTS....................................................................................135 VALVES.............................................................................................................136 ROTATING THE VALVE INSTALLATED....................................................................136 EXPANSION JOINTS WITH FLANGED ENDS...........................................................136 WALL PASS FOR PIPES...................................................................................136 MISCELLANEOUS.............................................................................................136 HANGERS, AND SUPPORTS (to 100 kg per item)...................................................136 8.7.2 8.7.3 8.8 8.8.1 8.8.2 DISMANTLING OF PIPE HOLDERS, HANGERS, AND SUPPORTS...............................136 HOLE DRILLING IN CONCRETE............................................................................136 EXTRAS............................................................................................................136 CHANGE IN BILL OF QUANTITIES BEFORE THE CLIENT'S APPROVAL FOR FABRICATION..............................................................136 CHANGE IN ISOMETRY PRIOR TO THE CLIENT'S APPROVAL FOR FABRICATION...............................................................136

8.7.1. FABRICATION AND INSTALLATION OF PIPE HOLDERS,

8.8.3 8.8.4 8.8.5 8.8.6 8.8.7 8.8.8

HAND DRAFTING OF ISOMETRY ACCORDING TO THE CLIENT'S INSTRUCTION..........................................................................137 INSTALLATION OF MISSING MATERIAL.................................................................137 PIPING MODIFICATION.......................................................................................137 SAND BLASTING HANDLING, PRIMER COAT ON PIPING, AND PIPE SUPPORTS...........137 UNDERGROUND PIPING......................................................................................137 FACTORS FOR CALCULATION OF MAN HOURS FOR PREFABRICATION AND INSTALLATION OF PIPING................................................138

TABLE Item. 3.10 MULTIPL. FACTORS FOR DIFF. KIND OF MATERIALS.................139 FORMS FOR CALCULATION OF MAN HOUR RATES...................................................142 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 CHAPTER 1. 2. 3. 4. CHAPTER CHAPTER 1. 2. CHAPTER A. B. CHAPTER 1. 2. 3. 4. 5. PIPES......................................................................................................142 FITTINGS................................................................................................142 FLANGES.................................................................................................143 SMALL FITTINGS......................................................................................143 VALVES....................................................................................................144 PIPE EXPANSION JOINTS AND FLOWRATE METERS....................................145 OTHER INSTALLATION WORKS.................................................................145 ESTIMATE POINTS FOR BUILD-IN ITEMS OF A. G. PIPING.........................147

XI. WEIGHT FACTORS.....................................................................................203 PIPING...............................................................................................................203 STEEL STRUCTURES............................................................................................206 PROCESS EQUIPMENT.........................................................................................208 CYLINDRICAL STORAGE TANKS............................................................................209 XII. TECHNICAL CALCULATION MANNER OF DATA COMPILING..................210 XIII. MAN HOURS FOR OVERHAULS IN PETROCHEMICAL PLANTS..............214 PIPING ERECTION AND DISMANTLING.................................................................214 MAN HOURS FOR OVERHAUL OF EQUIPMENT IN PETROCHEMICAL PLANTS...........229 XIV. FACTORS AND MAN HOURS FOR PIPING AND STEEL STRUCTURE WORKS IN CALL FOR TENDERS OF "TECHNIP" COMPANY......230 PIPING BETWEEN PLANTS AND IN PLANTS...........................................................230 STEEL STRUCTURE ERECTION.............................................................................232 XV. APPENDIX..................................................................................................233 ISO R7 DIN 2448/2458 SUMMARY OF PIPE SCHEDULED SIZES..............................233 ANSI B 36.10 SUMMARY OF PIPE SCHEDULED SIZES............................................235 PIPE AND FITTINGS DIMENSIONS - TABLE MANUAL.............................................236 STEEL STRUCTURE - SURFACES OF SECTIONS in m2/m........................................237 CONVERSIONS BETWEEN ENGLISH AND (SI) STANDARDS UNITS..........................238

10

INTRODUCTION
With proper and conscientious application of these data for making estimates, the estimator will calculate hourly time requirements i.e. the man hours required for the erection. The man hours (Mhr) do not refer to any condition or PRODUCTIVITY EFFICIENCY PERCENTAGES (PEP, Leistungsfhigkeit - Prozentsatz), but to precisely determined below stated PEPs. The standard ranges of productivity efficiency percentages are: 1. Very low 1040 % 2. Low 4160% 3. Average 6180% 4. Very good 8190% 5. Excellent 91100% 6. Extraordinary 101120% Man hours in this Manual refer to the following Productivity Efficiency Percentages:

1. PIPING ABOVE GROUND IN PLANTS 1.1Calculation based on the estimate points of basic erection items and man hours and ef fects derived thereby PEP = high average 80% 1.2Calculation based on man hours and ef fects for quick calculation and special man hours PEP = high average 75% 1.3Calculation based on man hou rs for piping per inch - diameter (ID) PEP = high average 80% 1.4Calculation based on man hours f or units of operation PEP = very good 2.PIPELINES PEP = high average 75 % 3.STEEL STRUCTURES PEP = high average 75 % 4.PROCESS EQUIPMENT IN PL ANTS PEP = average 70% 85 %

5.CYLINDRICAL ST ORAGE TANKS PEP = very good 6.WELDING AND CUT TING PEP = average 7. CORROSION PROTECTION PEP = high average 80 % 8. THERMAL INSULATION PEP = very good 85 % 11 70 % 85 %

For each project, before the labour value is calculated, the Productivity Efficiency Percentage should be determined. This is done by the project manager with the assistance of his collaborators. John S. Page (USA) stated six production elements that have an impact on PEP determination. They are: 1. Project Management and Supervision 2. Labour Conditions 3. Job Conditions 4. Machinery and Equipment 5. Weather Conditions 6. General Economy (for J. S. P. this is a leading element, which I shall not consider) 1. Project Management and Supervision Has the company alr eady executed such pr ojects? How often? What is the calibre of your supervision? Are skilled and experienced staff available? What can you afford to pay them? Will they be satisfied with the accommodation? Will they be satisfied with the salaries? Will you have enough money at the site (down payments)? After evaluating these questions, estimate the percentage according to the PEP table. 2. Labour Conditions Does the company have a good labour relations man? Has the company sufficient number of skilled and trained labour? What are the foremen like? Will they be satisfied with their salaries? Will they be satisfied with accommodation, food, transport? How often will they be able to visit their families? Estimate the percentage according to the PEP table. 3. Job Conditions What is the scope of the work and just what is involved in the job? What is the schedule? Is it tight, or do you have ample time to complete the work? What is the condition of the site? Is it low and muddy, and hard to drain, or is it high and dry? Does it involve a plant already in operation? Will there be tie-ins to the existing systems? What will the relationship be between the pr oduction personnel and office personnel? Will most of the operations be manual or mechanized? What kind of material procurement will you have? Estimate the percentage according to the PEP table. 4. Machinery and Equipment Do you have ample equipment to finish your job? What kind of shape is it in, and will you have good maintenance and repair help? The qualifications and experience of crane and other operators? The plant-hire company for the machinery? Past experience? Estimate the percentage according to the PEP table. 5. Weather Conditions What were past weather conditions for the area? If necessary, can they be checked? What future weather forecasts? Will there be much rain or snow? What differences are expected in the weather with regard to Central Europe - Zagreb? Estimate the percentage according to PEP table. When we have considered and analysed all the percentages, we have to divide the total sum by five to arrive at an average percentage of productivity that is the Productivity Efficiency Percentage (PEP). Dividing the PEP declared by the average PEP we obtain a factor. This factor is multiplied by the calculated man hours (MHr) and will give actually needed man hours (MHr). The number of hours can be either increased or decreased.

12

ABBREVIATIONS & UNITS

PEP = Productivity efficiency percentage Mhr = Man Hours mm = millimeters = 0.03937 inches m = linear meters = 3.281 feet km = kilometers = 0.6214 miles m2= square meters = 10. 764 feet m3= cubic meters = 35.314 f eet ft = linear feet = 0.3048 meters l = liters = 61.023 cu inches = 0.03531 cu feet = 0.2642 u.s. gal kg = kilogram = 2.2046 lbs lbs = pound = 0.4536 kg t or ton = metric tons = 1000 kg ea = each pc = piece PN = pressure nominal or NP bar = 14.5 psi ( lb/sq in) Dn = diametar nominal OD or do = outer diametar ID = inch diametar MID = meter inch diametar t = thickness mm V = volume max. = maximum min. = minimum = phi ( Greek) = round kW = kilowatts = 1.341 horse power kWh = kilowatthours kVA = kilovoltampers kg/Mhr = kilograms per man hour Mhr/m = man hours per meter f = factor k = coefficient

Notice: Decimal numbers are listed with a comma (European way).

13

I. PIPING ABOVE GROUND DERIVED OPERATING TIME STANDARD FOR TABLES FACTOR OF BASIC ASSEMBLY POSITION CHAPTER X, ACCORDING TO FORMS ON PAGE 142 146 Productivity efficiency percentage (PEP) = 80% 1. PIPES (ANSI B 36.10) 1.1 PIPE INSTALLATION ON PROCESS PLANT [Mhr/m] CARBON STEEL - NONWRAPPED - ABOVE GROUND Sch 40 Sch 60 XS Sch 80 Sch 100 Sch 120 Sch 140 Sch 160

FOR PREFABRICATION : 8% FOR INSTALLATION : 92%

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

OD-mm 21,3 26,7 33,4 42,2 48,3 60,3 73 88,9 114,3 141,3 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

Sch 10

Sch 20

Sch 30

Std

XXS

Sch 5S

STAINLESS STEEL Sch 10S Sch 40S Sch 80S -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

14

Man hour included next activities : - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: alloy steel prewrapped galvanized aluminium alloy

[Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

k x 1,10 x 1,15 (underground install.) x 0,70 x 0,85

Mhr/m x 0,3048 = Mhr/ft

1. PIPES (ANSI B. 36.10) 1.2 INSTALLATION ON PIPE RACK OR SLEEPER WAY [Mhr/m] CARBON STEEL NONWRAPPED Sch 60 XS Sch 80 Sch 100 Sch 120

FOR PREFABRICATION : 8% FOR INSTALLATION : 92% STAINLESS STEEL Sch 10S Sch 40S Sch 80S

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

Inch OD-mm 1/2 21,3 3/4 26,7 1 33,4 1 1/4 42,4 1 1/2 48,3 2 60,3 2 1/2 73 3 88,9 4 114,3 5 141,3 6 168,3 8 219,1 10 273 12 323,9 14 355,6 16 406,4 18 457 20 508 22 559 24 610 26 660 28 711 30 762 32 813 34 864 36 914

Sch 10

Sch 20

Sch 30

Std

Sch 40

Sch 140 Sch 160

XXS

Sch 5S

Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

15

Man hour include the next activities: - handling - erection - on-site transport - welding - prefabrication - pressure testing

Materials: - alloy steel - galvanized - aluminium alloy

k [Mhr/m] x 1,10 [Mhr/m] x 0,70 [Mhr/m] x 0,85

Mhr/m x 0,3048 = Mhr/ft

2. FITTINGS (ANSI 36.10) 2.1 ELBOWS [Mhr/ea] CARBON STEEL XS Sch 80 Sch 100

FOR PREFABRICATION : FOR INSTALLATION:

85% 15%

DN-m m 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

-Inch OD-mm Sch 10 1/2 21,3 3/4 26,7 1 33,4 1 1/4 42,2 1 1/2 48,3 2 60,3 2 1/2 73 3 88,9 4 114,3 5 141,3 6 168,3 8 219,1 10 273 12 323,9 14 355,6 16 406,4 18 457 20 508 22 559 24 610 26 660 28 711 30 762 32 813 34 864 36 914 2.2 CAPS

Sch 20

Sch 30

Std

Sch 40

Sch 60

Sch 120

Sch 140 Sch 160

XXS

Sch 5S

STAINLESS STEEL Sch 10S Sch 40S Sch 80S -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 f 1,00 1,80 1,60 1,50

16

[Mhr/ea] x

Materials: - Cr-Mo alloy steel - Copper alloy - Killed C.S.

f 1,40 1,60 1,20 1,00 1,25

- High temp. alloy steel - Alloy steel Ni - Aluminium alloy

2. FITTINGS (ANSI B.36.10) 2.3 TEES 2.3.1 STRAIGHT TEE [Mhr/ea] CARBON Sch 40 Sch 60 STEEL XS Sch 80

FOR PREFABRICATION : FOR INSTALLATION :

85% 15%

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

OD-mm Sch 10 21,3 26,7 33,4 42,4 48,3 60,3 73 88,9 114,3 141,3 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

Sch 20

Sch 30

Std

Sch 100

Sch 120

Sch 140

Sch 160

XXS

Sch 5S

STAINLESS Sch 10S Sch 40S

STEEL Sch 80S -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

17

2.3.2 REDUCED TEE

[Mhr/ea] x

Materials: - Cr-Mo alloy steel - Copper alloy - Killed C.S.

f 1,40 1,60 1,20 1,00 1,25

- High temp. alloy steel - Alloy steel Ni - Auminium alloy

f 1,00 1,80 1,60 1,50

2. FITTINGS (ANSI) 2.4 REDUCERS - CONCENTRIC AND ECCENTRIC [Mhr/ea] CARBON STEEL Sch 80 Sch 100

FOR PREFABRICATION : FOR INSTALLATION:

85% 15%

Dn-mm 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

-Inch OD-mm 3/4 26,7 1 33,4 1 1/4 42,2 1 1/2 48,3 2 60,3 2 1/2 73 3 88,9 4 114,3 5 141,3 6 168,3 8 219,1 10 273 12 323,9 14 355,6 16 406,4 18 457 20 508 22 559 24 610 26 660 28 711 30 762 32 813 34 864 36 914

Sch 10

Sch 20 Sch 30

Std

Sch 40

Sch 60

XS

Sch 120

Sch 140

Sch 160

XXS

Sch 5S

STAINLESS STEEL Sch 10S Sch 40S Sch 80S

-Inch 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

18

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: - Cr-Mo alloy steel - Copper alloy - Killed C.S

f 1,40 1,60 1,20 1,00 1,25

- High temp. alloy steel - Alloy steel Ni - Aluminium alloy

f 1,00 1,80 1,60 1,50

1. PIPES (DIN 2448/2458) 1.1 INSTALLATION IN PROCESS PLANT [Mhr/m] CARBON STEEL - NONWRAPPED - ABOVE GROUND - WALL THICKNESS 2 - 12,5 mm 2,6 2,9 3,2 3,6 4 4,5 5 5,6 6,3 FOR PREFABRICATION : FOR INSTALLATION : 8% 92%

Dn-mm OD-mm t - Std|Ext 15 21,3 2\2 20 26,9 2\2,3 25 33,7 2\2,6 32 42,4 2\2,6 40 48,3 2,3\2,6 50 60,3 2,3\2,9 65 73,1 2,6\2,9 65 76,1 2,6\2,9 80 88,9 2,9\3,2 100 114,3 3,2\3,6 125 139,7 3,6\4 150 168,3 4\4,5 200 219,1 4,5\6,3 250 273 5\6,3 300 323,9 5,6\7,1 350 355,6 5,6\8 400 406,4 6,3\8,8 450 457 6,3\10 500 508 6,3\11 550 559 6,3\12,5 600 610 6,3\12,5 650 660 7,1\14,2 700 711 7,1 750 762 8 800 813 8 850 864 8,8 900 914 10

2,3

7,1

8,8

10

11

12,5

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

19

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: Stainless steel High temp. alloy steel Prewrapped Galvanized Aluminium alloy

[Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

k x 1,10 x 1,10 x 1,15 (underground install.) x 0,70 x 0,85

Mhr/m x 0,3048 = Mhr/ft

1. PIPES (DIN 2448/2458) 1.1 INSTALLATION IN PROCESS PLANT [Mhr/m] CARBON STEEL - NONWRAPPED - ABOVE GROUND - WALL THICKNESS 14,2 - 60 mm 17,5 20 22,2 25 28 30 32 36 40

FOR PREFABRICATION : 8% FOR INSTALLATION : 92%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

t - Std|Ext 14,2 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10

16

45

50

55

60

65

70

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

20

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: Stainless steel High temp. alloy steel Prewrapped Galvanized Aluminium alloy

k [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

x x x x x

1,10 1,10 1,15 0,70 0,85

Mhr/m x 0,3048 = Mhr/ft

1. PIPES (DIN 2448/2458) 1.2 INSTALLATION ON PIPE RACK OR SLEEPER WAY [Mhr/m] CARBON STEEL - NONINSULATED - WALL THICKNESS - 2 mm - 12,5 mm 3,2 3,6 4 4,5 5 5,6 6,3 7,1

FOR PREFABRICATION : 8% FOR INSTALLATION : 92%

Dn-mm OD-mm t - Std|Ext 15 21,3 2\2 20 26,9 2\2,3 25 33,7 2\2,6 32 42,4 2\2,6 40 48,3 2,3\2,6 50 60,3 2,3\2,9 65 73,1 2,6\2,9 65 76,1 2,6\2,9 80 88,9 2,9\3,2 100 114,3 3,2\3,6 125 139,7 3,6\4 150 168,3 4\4,5 200 219,1 4,5\6,3 250 273 5\6,3 300 323,9 5,6\7,1 350 355,6 5,6\8 400 406 6,3\8,8 450 457 6,3\10 500 508 6,3\11 550 559 6,3\12,5 600 610 6,3\12,5 650 660 7,1\14,2 700 711 7,1 750 762 8 800 813 8 850 864 8,8 900 914 10

2,3

2,6

2,9

8,8

10

11

12,5

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

21

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: Stainless steel High temp. alloy steel Prewraped Aluminium alloy

[Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

k x 1,10 x 1,10 x 0,70 x 0,85

Mhr/m x 0,3048 = Mhr/ft

1. PIPES (DIN 2448/2458) 1.2 INSTALLATION ON PIPE RACK OR SLEEPER WAY [Mhr/m] CARBON STEEL - NONINSULATED - WALL THICKNESS 14,2 - 60 mm 22,2 25 28 30 32 36 40

FOR PREFABRICATION : FOR INSTALLATION :

8% 92%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

t - Std|Ext 14,2 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10

16

17,5

20

45

50

55

60

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

22

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: - Stainless steel - High temp. alloy steel - Galvanized - Aluminium alloy

k [Mhr/m] x 1,10 Mhr/m x 0,3048 = Mhr/ft [Mhr/m] x 0,70 [Mhr/m] x 0,85

1. PIPES (ANSI and DIN) 1.3 STEAM TRACING [Mhr/m] Dn-mm 15 20 25 32 40 50 65 80 -Inch OD-mm Sch 10 1/2 21,3 3/4 26,7 1 33,4 1 1/4 42,2 1 1/2 48,3 2 60,3 2 1/2 76,1 3 88,9 Std

( Values in this table apply only to piping in plants. For steam tracing of pipe lines on piperacks or sleepeways other table for the installation of pipes on piperacks are applied.) CARBON STEEL STAINLESS STEEL Sch 40 XS Sch 80 Sch 160 XXS Sch 5S Sch 10S Sch 40S Sch 80S

STEAM TRACING ON PROCESS LINES (manhour per meter of process line incl. steam supply and condensate return) number [Mhr/m] Dn tracer of tubes (proc.) to 3" 1/2 1 4 8 3/4 1 10 16 3/4 2 18 36 3/4 3 above 36 3/4 4

Dn-mm OD-mmt -Std|Ext 15 21,3 2\2 20 26,9 2\2,3 25 33,7 2\2,6 32 42,4 2\2,6 40 48,3 2,3\2,6 50 60,3 2,3\2,9 65 73 2,6\2,9 65 76,1 2,6\2,9 80 88,9 2,9\3,2

2,3

CARBON STEEL - WALL THICKNESS 2 - 7,1 mm 2,6 2,9 3,2 3,6

4,5

5,6

6,3

7,1

COPPER TUBES - DUCTILE OD-mm Mhr/m OD-mm 10 0,12 22 12 0,14 25 14 0,18 28 15 0,20 30 16 0,21 35 18 0,24 38 20 0,27 42 COPPER TUBES - STRONG : x

[Mhr/m]

23

1.4 INSTRUMENT AND CONTROL PIPING All activityes on installation and supporting these lines, also sizes to 1/2", are included. Lines to 3 m ( 10 ft ) [Mhr] totally Lines above 3 m ( 10 ft ) [Mhr/m]

1.5 STEAM DISTRIBUTORS AND CONDENSATE COLLECTORS FABRICATED FROM PIPES AND FITTINGS 1.5.1 STEAM DISTRIBUTORS Fabrication [Mhr/ea] + [Mhr/connect.] Erection [Mhr/ea] (supporting included) 1.5.2 CONDENSATE COLLECTORS Fabrication [Mhr/ea] + [Mhr/ connect.] Erection [Mhr/ea] (supporting included)

1.6 STEAM DISTRIBUTORS AND CONDENSATE COLLECTORS FABRICATED FROM READY-MADE DISTRIBUTORS FOR 4 CONNECTIONS (ready-made distributors for 4, 8 or 12 connections) 1.6.1 STEAM DISTRIBUTORS Fabrication : [Mhr] x number of connections Erection : [Mhr/ea] (supporting included) 1.6.2 CONDENSATE COLLECTORS Fabrication: [Mhr] x number of connections Erection: [Mhr/ea] (supporting included)

Mhr/m x 0,3048 = Mhr/ft

2. FITTING (DIN ) 2.1 ELBOWS [Mhr/ea] CARBON STEEL - WALL THICKNESS 2 - 12,5 mm 3,2 3,6 4 4,5 5

FOR PREFABRICATION : FOR INSTALLATION:

85% 15%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 2.2 CAPS

?Std|Ext 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10

2,3

2,6

2,9

5,6

6,3

7,1

8,8

10

11

12,5

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

24

[Mhr/ea] x

Materials: - Cr-Mo alloy steel - Copper alloy - Killed C.S

f 1,401,60 1,20 1,001,25

- High temp. alloy steel - Alloy steel Ni - Aluminium alloy

1,00 1,80 1,60 1,50

2. FITTINGS (DIN) 2.1 ELBOWS [Mhr/ea]

FOR PREFABRICATION : 85% FOR INSTALLATION : 15%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm t - Std|Ext 21,3 2\2 26,9 2\2,3 33,7 2\2,6 42,4 2\2,6 48,3 2,3\2,6 60,3 2,3\2,9 73,1 2,6\2,9 76,1 2,6\2,9 88,9 2,9\3,2 114,3 3,2\3,6 139,7 3,6\4 168,3 4\4,5 219,1 4,5\6,3 273 5\6,3 323,9 5,6\7,1 355,6 5,6\8 406,4 6,3\8,8 457 6,3\10 508 6,3\11 559 6,3\12,5 610 6,3\12,5 660 7,1\14,2 711 7,1 762 8 813 8 864 8,8 914 10 2.2 CAPS

14,2

16

17,5

20

CARBON STEEL - WALL THICKNESS 14,2 - 60 mm 22,2 25 28 30 32 36

40

45

50

55

60

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 1,25 1,00 1,80 1,60 1,50

25

[Mhr/ea] x

Materials: - Cr-Mo alloy steel - Copper alloy Killed C.S

f 1,40 1,60 1,20 1,00 1,25

Stainless steel High temp. alloy steel Alloy steel Ni Aluminium alloy

2. FITTINGS (DIN) 2.3 TEES [Mhr/ea] 2.3.1 STRAIGHT TEE Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 OD-mm t - Std|Ext 21,3 2\2 26,9 2\2,3 33,7 2\2,6 42,4 2\2,6 48,3 2,3\2,6 60,3 2,3\2,9 73,1 2,6\2,9 76,1 2,6\2,9 88,9 2,9\3,2 114,3 3,2\3,6 139,7 3,6\4 168,3 4\4,5 219,1 4,5\6,3 273 5\6,3 323,9 5,6\7,1 355,6 5,6\8 406,4 6,3\8,8 457 6,3\10 508 6,3\11 559 6,3\12,5 610 6,3\12,5 660 7,1\14,2 711 7,1 762 8 813 8 864 8,8 914 10 2.3.2 REDUCED TEE 2 2,3 2,6 2,9 CARBON STEEL - WALL THICKNESS 2 mm - 12,5 mm 3,2 3,6 4 4,5 5 5,6 6,3 7,1 8

FOR PREFABRICATION : FOR INSTALLATION:

85% 15%

8,8

10

11

12,5

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

26

[Mhr/ea] x

Materials: - Cr-Mo alloy steel - Copper alloy - Killed C.S

f 1,40 1,60 1,20 1,00 1,25

- Stainless steel - High temp. alloy steel - Alloy steel Ni - Aluminium alloy

1,25 1,00 1,80 1,60 1,50

2.3 TEES 2.3.1 STRAIGHT TEE

[Mhr/ea] CARBON STEEL - WALL THICKNESS 14,2 - 60 mm 22,2 25 28 30 32 36

FOR PREFABRICATION : 85% FOR INSTALLATION : 15%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm t - Std|Ext 14,2 21,3 2\2 26,9 2\2,3 33,7 2\2,6 42,4 2\2,6 48,3 2,3\2,6 60,3 2,3\2,9 73,1 2,6\2,9 76,1 2,6\2,9 88,9 2,9\3,2 114,3 3,2\3,6 139,7 3,6\4 168,3 4\4,5 219,1 4,5\6,3 273 5\6,3 323,9 5,6\7,1 355,6 5,6\8 406,4 6,3\8,8 457 6,3\10 508 6,3\11 559 6,3\12,5 610 6,3\12,5 660 7,1\14,2 711 7,1 762 8 813 8 864 8,8 914 10 2.3.2 REDUCED TEE

16

17,5

20

40

45

50

55

60

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 1,25 1,00 1,80 1,60 1,50

27

[Mhr/ea] x

Materials: - Cr-Mo alloy steel - Copper alloy - Killed C.S

f 1,40 1,60 1,20 1,00 1,25

Stainless steel High temp. alloy steel Alloy steel Ni Aluminium alloy

2. FITTINGS (DIN) 2.4 REDUCERS - CONCENTRIC AND ECCENTRIC

[Mhr/ea] CARBON STEEL - WALL THICKNESS 2 - 12,5 mm 3,2 3,6 4 4,5 5 5,6

FOR PREFABRICATION : FOR INSTALLATION:

85% 15%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

t - Std|Ext 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10

2,3

2,6

2,9

6,3

7,1

8,8

10

11

12,5

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

28

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: - Cr Mo alloy steel - Copper alloy - Killed C.S.

f 1,40 1,60 1,20 1,00 1,25

Stainless steel High temp. alloy steel Alloy steel Ni Aluminium alloy

1,25 1,00 1,80 1,60 1,50

2. FITTINGS (DIN) 2.4 REDUCERS - CONCENTRIC AND ECCENTRIC [Mhr/ea] CARBON STEEL - WALL THICKNESS 14,2 -60 mm 22,2 25 28 30 32

FOR PREFABRICATION : 85% FOR INSTALLATION : 15%

Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914

t - Std|Ext 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10

14,2

16

17,5

20

36

40

45

50

55

60

OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73,1 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 1,25 1,00 1,80 1,60 1,50

29

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: - Cr Mo alloy steel - Copper alloy - Killed C.S.

f 1,40 1,60 1,20 1,00 1,25

Stainless steel High temp. alloy steel Alloy steel Ni Aluminium alloy

3. FLANGES 3.1 WELDING NECK [Mhr/ea] CARBON 150# PN6-16 [Mhr/ea] [kg/Mhr] STEEL 600# PN100 900# PN160

FOR PREFABRICATION : 80% FOR INSTALLATION: 20%

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

[kg] 0,5 0,7 1,1 1,5 1,8 2,7 4,4 5,2 7,5 9,2 1,0 18,3 25,0 39,0 51,0 60,0 71,0 88,0 103,5 119,0 136,0 143,0 168,0 197,0 211,0 236,0

300# 400# PN25-40 PN64 [kg] [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea][kg/Mhr] 0,8 0,9 1,3 1,5 1,7 1,9 2,2 2,6 3,2 3,3 3,6 4,7 5,4 6,5 7,4 8,7 11,9 14,0 16,0 19,0 20,0 26,0 31,0 40,0 44,0 54,0 64,0 78,0 88,0 105,0 113,0 131,0 134,0 159,0 171,0 190,0 204,5 232,5 238,0 275,0 304,0 340,0 367,0 400,0 422,0 454,0 465,0 522,0 545,0 590,0 590,0 670,0 Materials: - Cr Mo alloy steel - Copper alloy - Killed C.S.

1500# PN250
[kg/Mhr] [kg]

2500# PN320
[Mhr/ea] [kg/Mhr] -Inch

[kg] [Mhr/ea][kg/Mhr] [kg] [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea] 0,9 1,9 1,9 1,5 2,6 2,6 1,9 3,8 3,8 2,6 4,4 4,4 3,3 6,1 6,1 4,7 11,1 11,1 6,5 15,5 15,5 8,7 14,0 20,5 18,1 23,0 30,5 30,0 37,0 58,0 36,0 49,0 70,0 50,0 84,0 119,0 90,0 123,0 204,0 110,0 168,0 303,0 150,0 186,0 400,0 190,0 224,0 510,0 240,0 300,0 18 295,0 373,0 20 330,0 526,5 22 365,0 680,0 24 404,0 715,0 26 480,0 840,0 28 560,0 975,0 30 680,0 1170,0 32 750,0 1375,0 34 795,0 1565,0 36 f 1,40 1,60 1,20 1,00 1,25 Stainless steel High temp. alloy steel Alloy steel Ni Aluminium alloy 1,25 1,00 1,80 1,60 1,50

3,6 4,0 6,0 9,0 13,0 19,0 24,0 43,0 66,0 111,0 172,0 261,0 485,0 730,0 14 16 Notice: Unit weights in this table refer to welding neck flanges acc. to ANSI B 16-5.1977. for to 24 and BS-3293-1960 (1) for26 36

1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12

30

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

kg x 0,4536 = lbs kg/Mhr x 2,2046 = lbs/Mhr

3. FLANGES 3.2 SLIP - ON [Mhr/ea] CARBON 150# PN6-16 Dn-mm -Inch 15 1/2 20 3/4 25 1 32 1 1/4 40 1 1/2 50 2 65 2 1/2 80 3 100 4 125 5 150 6 200 8 250 10 300 12 350 14 400 16 450 18 500 20 550 22 600 24 650 26 700 28 750 30 800 32 850 34 900 36 3.3. 3.4. 3.5. 3.6. 300# PN25-40 400# PN64

kg x 0.4536 = lbs kg/Mhr x 2,2046 = lbs/Mhr


STEEL 600# PN100 900# PN160

FOR PREFABRICATION: 80% FOR INSTALLATION : 20%

1500# PN250

2500# PN320 -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12

[kg] [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea] [kg/Mhr] 0,4 0,7 0,8 0,7 1,1 1,4 0,8 1,4 1,6 1,1 1,8 2,1 1,4 2,6 3,1 2,2 3,4 3,7 ,6 4,4 5,4 4,1 6,1 7,3 5,6 10,1 11,5 6,3 12,5 14,5 7,5 14,1 19,0 12,6 24,8 29,0 18,5 37,1 39,5 28,0 50,0 58,0 36,0 70,0 82,0 46,0 97,0 105,0 50,0 123,0 126,0 64,0 133,0 152,0 76,5 170,5 185,0 89,0 208,0 218,0 106,0 255,0 295,0 126,0 321,0 354,0 140,0 362,0 408,0 168,0 398,0 465,0 179,0 480,0 522,0 205,0 540,0 601,0 [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x

[kg [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea] [kg/Mhr] [kg] [Mhr/ea] [kg/Mhr] 0,8 1,7 1,7 3,0 1,4 2,3 2,3 4,0 1,6 3,4 3,4 5,0 2,1 3,9 3,9 8,0 3,1 5,4 5,4 11,0 3,7 9,8 9,8 17,0 5,4 13,7 13,7 24,0 7,3 11,6 18,0 36,0 15,8 19,8 27,8 55,0 24,5 32,0 52,0 93,0 29,5 41,2 61,0 142,0 43,0 71,0 104,0 214,0 70,0 100,0 175,0 407,0 86,0 133,0 264,0 573,0 100,0 152,0 308,0 14 142,0 184,0 352,0 16 175,0 258,0 18 221,0 317,0 20 Notice: 268,0 462,5 22 Unit weights in this table refer 315,0 608,0 24 to slip on flanges 425,0 692,0 26 acc. to 470,0 817,0 28 ANSI B 16-5. 1977. 533,0 942,0 30 for to 24 624,0 1135,0 32 and BS-3293-1960 681,0 1339,0 34 for 26 36 726,0 1521,0 36 Materials: - Cr Mo alloy steel - Copper alloy - Killed C.S. f 1,40 1,60 1,20 1,00 1,25 -

31

SOCKET WELDING LAP JOINT + STUB END BLIND ORIFICE COMPLETE

Man hour include next activities: - handling - erection - on-site transport - welding - prefabrication - pressure testing

Stainless steel 1,25 High temp. alloy steel 1,00 1,80 Alloy steel Ni 1,60 Aluminium alloy 1,50

4. SMALL FITTINGS [Mhr/ea] 4.1 WELDOLETS, SOCKOLETS, NIPOLETS, etc. CARBON STEEL 1500# 3000# 6000# Std XS XXS

4.2 HALF COUPLINGS FOR WELDING CARBON STEEL 3000# 6000# XS XXS

FOR PREFABRICATION : FOR INSTALLATION:

85% 15%

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30

OD-mm 21,3 26,7 33,4 42,2 48,3 60,3 73 88,9 114,3 141,3 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762

D n -m m 15 20 25 32 40 50 65 80 100

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4

OD-mm 21,3 26,7 33,4 42,2 48,3 60,3 73 88,9 114,3

4.3 FITTINGS WITH SOCKET ENDS CARBON STEEL WITH ONE END Dn-mm -Inch OD-mm [Mhr/ea] 15 1/2 21,3 20 3/4 26,7 25 1 33,4 32 1 1/4 42,2 40 1 1/2 48,3 50 2 60,3 65 2 1/2 73 80 3 88,9 100 4 114,3 Materials: (FOR WELDED FITTINGS ONLY) f - Stainless steel 1,25 - Cr Mo alloy steel 1,40 1,60 - High temp. alloy steel 1,00 1,80 - Copper alloy 1,20 - Alloy steel Ni 1,60 - Killed C.S. 1,00 1,25 - Aluminium alloy 1,50

WITH 2 ENDS x 2 WITH 3 ENDS x 3

4.4 THREADED FITTINGS 4.4.1 CARBON STEEL WITH ONE END Dn-mm -Inch OD-mm 15 1/2 21,3 20 3/4 26,7 25 1 33,4 32 1 1/4 42,2 40 1 1/2 48,3 50 2 60,3 65 2 1/2 73 80 3 88,9 100 4 114,3

32

[Mhr/ea]

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

4.4.2 NON-FERROUS METALS VALUES FOR CARBON STEEL x 4.4.3 "HERMETO" COUPLINGS VALUES IN TABLE 4.4.1 x

5. VALVES 5.1 VALVES WITH FLANGED ENDS 5.1.1 GATE, GLOBE, CHECK, SWING CHECK, BONNET, BALL, BUTTERFLY, FILTER, etc [Mhr/ea]

VF - Factor for installation of flanged valves

for flanged valves Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 150# PN6-16 300# 25-40 400# PN64 600# PN100 900# PN160 1500# PN250 2500# PN320 PN PN PN PN PN PN PN 6 16 25 40 64 100 160 250 320 150# 300# 400# 600# 900# 1500# 2500#

Dn to 100 to 4

Dn 125 200 5 8

Dn above 250 above 10

(included in table)

33

5.1.2 CONTROL VALVES 5.1.3 SAFETY VALVES 5.1.4 HYDRANTS 5.1.5 FLOW RATE METER 5.1.6 LEVEL GAUGES 5.1.7 CONDENSATE SEPARATORS 5.1.8 SIGHT GLASS 5.1.9 VENTURI TUBE 5.1.10 VALVES WITH E.M. DRIVE

[Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x [Mhr/ea] x

5. VALVES 5.2 VALVES WITH WELDING ENDS 5.2.1 BUTT WELD

[Mhr/ea] 5.2.2 VALVES WITH SOCKET ENDS 5.3 VALVES WITH THREADED ENDS

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900

CARBON STEEL -Inch OD-mm 1/2 21,3 3/4 26,7 1 33,4 1 1/4 42,2 1 1/2 48,3 2 60,3 2 1/2 73 3 88,9 4 114,3 5 141,3 6 168,3 8 219,1 10 273 12 323,9 14 355,6 16 406,4 18 457 20 508 22 559 24 610 26 660 28 711 30 762 32 813 34 864 36 914

150# PN6-16

300# 25-40

400# PN64

600# PN100

800#

900# PN160

1500# PN250

2500# PN320

Dn-mm 15 20 25 32 40 50 65 80 100

CARBON STEEL -Inch OD-mm 1/2 21,3 3/4 26,7 1 33,4 1 1/4 42,2 1 1/2 48,3 2 60,3 2 1/2 73 3 88,9 4 114,3

[Mhr/ea]

-Inch 1/2" 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4

OD-mm 21,3 26,7 33,4 42,2 48,3 60,3 73 88,9 114,3

[Mhr/ea]

34

5.4 PRESSURE GAUGES 5.5 THERMOMETERS

[Mhr/ea] [Mhr/ea]

Man hour include next activities: - handling - on-site transport - prefabrication

- erection - welding - pressure testing

Materials: - Cr Mo alloy steel - Copper alloy - Killed C.S. - Stainless steel - High temp. alloy steel - Alloy steel Ni - Aluminium alloy

f 1,40 1,60 1,20 1,00 1,25 1,25 1,00 1,80 1,60 1,50

RATES FOR TENDER CALCULATIONS 1. MANHOUR ESTIMATE FOR INSTALLATION OF PIPING BASED ON DIAMETERS AND WEIGHTS (FOR CARBON STEEL ONLY) (Origin: Technical Journal "3R International" of April 4, 1985) Productivity Efficiency Percentage (PEP) = 75% TypeAS TypeAF Type BS -In ch [Mhr/ton] [kg/Mhr] [Mhr/ton] [kg/Mhr] [Mhr/ton] [kg/Mhr] 1 417 1 1/4 359 1 1/2 330 2 286 2 1/2 246 3 209 4 165 5 135 6 111 8 93,6 10 75,9 12 63,2 14 59,5 16 50,6 20 43,8 24 38,9 40 20,8 TypeBF
[Mhr/ton] [kg/Mhr]

Dn-mm 25 32 40 50 65 80 100 125 150 200 250 300 350 400 500 600 1000

Type AS Piping in the plant with prefabricated weld joints Type AF Piping in the plant with prefabricated flanged joints Type BS Piping outside the plant (pipe racks, sleeper ways, etc.) with prefabricated weld joints Type BF Piping outside the plant (pipe racks, sleeper ways etc.) with prefabricated flanged joints

35

kg/Mhr x 2,2046 = lbs/Mhr

Above standards do not include: - storing and store handling site grading and facilities - decrease effect of due to bad weather - scaffolding - radiographic inspection - performance tests

(calculate separately) (add %) (add %) (calculate separately) (calculate separately) (calculate separ ately)

Time allowance for - space obstruction to % - connection to the existing lines to - erection at higher elevations (above 4 m)

% %

2. EFFECT ASSESSMENT FOR QUICK CALCULATION 2.1 PIPING IN PROCESS PLANT Prefabrication and erection [kg/Mhr] Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 > 800 -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 > 32 OD-mm Sch 10 21,3 26,7 33,4 42,2 48,3 60,3 73,0 88,9 114,3 141,3 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 > 813 Sch 20 Sch 30 Std

(Use only if not possible acc. to man hours derived from basic estimate points) Productivity efficiency percentage (PEP) = 75% Sch 40 Sch 60 XS Sch 80 Sch 100 Sch 120 Sch 140 Sch 160 XXS -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 above 32

36

Included: pipes, fittings, flanges, valves and supports Material: carbon steel Approximate division of hours for prefabrication and erection Prefabrication Erection to 11/2 % % 2 5 % % 6 10 %

Piping between plants: ON PIPE RACKS [kg/Mhr] x 1,35

kg/Mhr x 2,2046 = lbs/Mhr


ON SLEEPER WAYS [kg/Mhr] x 1,50

2. RATES FOR QUICK CALCULATION 2.2 PIPES (CARBON STEEL - NOT INSULATED) MEAN VALUE

(Used only when such data provided in tendering documents ) [Mhr/m] [ kg/Mhr] Productivity Efficiency Percentage (PEP) = 75%

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200

-Inch OD-mm 1/2" 21,3 3/4" 26,7 1" 33,4 1 1/4 42,2 1 1/2 48,3 2 60,3 2 1/2 73 3" 88,9 4" 114,3 5" 141,3 6" 168,3 8" 219,1 10" 273 12" 323,9 14" 355,6 16" 406,4 18" 457 20" 508 22" 559 24" 610 26" 660 28" 711 30" 762 32" 813 34" 864 36" 914 38 966 40" 1016 42" 1066 44" 1118 46" 1168 48" 1219

FOR " TECHNIP" COMP. Sch 10 Sch 20 Std Sch 40 XS Sch 80 Sch 120 Sch 160 Average [Mhr/m][kg/Mhr] [Mhr/m][kg/Mhr] [Mhr/m][kg/Mhr][Mhr/m][kg/Mhr] [Mhr/m][kg/Mhr] [Mhr/m][kg/Mhr] [Mhr/m] [kg/Mhr] [Mhr/m] [kg/Mhr] diameter[inch] Mhr/ ton* < 0,66 0,67-0,87 0,88-1,12 1,13-1,37 1,38-1,75 1,76-2,25 2,26-2,75 2,76-3,50 3,51-4,50 4,51-5,50 5,51-7,00 7,01-9,00 9,01-11,0 11,01-13,0 13,01-15,0 15,01-17,0 17,01-19,0 19,01-21,0 21,01-23,0 23,01-25,0 25,01-27,0 27,01-29,0 29,01-31,0 31,01-33,0 33,01-35,0 35,01-37,0 37,01-39,0 >39,0

37

*Mhr/ton for one millimetre of average wall thickness

Mhr/m x 0,3048 = Mhr/ft kg/Mhr x 2,2046 = lbs/Mhr

2. EFFECT ASSESSMENT FOR QUICK CALCULATION Productivity efficiency percentage (PEP) 75% 2.3 FITTINGS (CARBON STEEL) - MEAN VALUE [kg/Mhr] All types of fittings included.

(Used only if such data provided in tendering documents)

FOR "TECHNIP" COMP. Average diameter [inch] [Mhr/ton]* XS Sch 80 Sch 120 Sch 160 XXS "SOCKET" < 0,66 0,67-0,87 0,88-1,12 1,13-1,37 1,38-1,75 1 ,7 6 -2 ,2 5 2,26-2,75 2,76-3,50 3,51-4,50 4,51-5,50 5,51-7 ,00 7,01-9,00 9,01-11,0 11,01-13,0 13,01-15,0 15,01-17,0 17,01-19,0 19,01-21,0 21,01-23,0 23,01-25,0 25,01-27,0 27,01-29,0 29,01-31,0 31,01-33,0 33,01-35,0 35,01-37,0 37,01-39,0 39,01-41,0 41,01-43,0 43,01-45,0 45,01-47,0 >47,0

Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

OD-mm Sch 10 Sch 20 Std Sch 40 21,3 26,7 33,4 42,2 48,3 60,3 73 88,9 114,3 141,3 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 966 1016 1066 1118 1168 1219 Note: Generally, socket fittings to 1 1/2" are used in petrochemical plants. *[Mhr/ton] for one millimetre of average wall thickness

38

Materials: Stainless steel High temp. alloy steel Killed C.S Cr Mo alloy steel Alloy steel Ni Copper alloy Aluminium alloy

f 1,25 1,00 1,80 1,00 1,25 1,40 1,60 1,60 1,20 1,50

kg/Mhr x 2,2046 =lbs/Mhr

2.4 VALVES MEAN ALUE V (ALL KINDS OF VALVES INCLUDED) Productivity Efficiency Percentage (PEP) = 75% 2.4.1. WITH FLANGED ENDS [Mhr/kg] 150# NP6-16 300# NP25 600# NP40 900# NP64 1500# 100-160

2.5 PIPE SUPPORTS Productivity Efficiency Percentage (PEP) = 80% PARTICIPATION IN THE PIPING QUANTITY to be estimated with % 2.5.2. FABRICATION AND INSTALLATION 2.5.2.1 DIVISION BASED ON THE UNIT WEIGHT OF SUPPORT Unit Fabrication Installation Fabrication+ weight installation [kg/pc] [kg/Mhr] [kg/Mhr] [kg/Mhr] to 5 5 20 20 50 50 75 75 100 100150 above 150 Spring supports 2.5.2.2 DIVISION BASED ON THE PIPING DIAMETER Fabrication 2.5.1.

Dn-mm 15 20 25 32 40 50 65 80 100 150 200 250 300 350 400 450 500 550 600 2.4.2.

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 6 8 10 12 14 16 18 20 22 24

39

Installation

WITH WELDING ENDS

2.4.2.1. BUTT WELDING: [Mhr/kg] x 2.4.2.2. SOCKET WELDING: [Mhr/kg] x

DN [kg/Mhr] [kg/Mhr] 15 50 2 65 100 2 4 125150 56 200350 814 above 350 above 14 2.5.2.3 EFFECT OF SUPPORT FABRICATION AND INSTALLATION WITH ALREADY KNOWN AVERAGE DIAMETER OF PIPING The effect of the fabrication and installation [kg/Mhr] is to the average diameter in inches. 2.6

Fabrication+ installation [kg/Mhr]

Mhr/kg x 0,4536 = Mhr/lbs kg/Mhr x 2,2046 = lbs/Mhr

AVERAGE DIAMETER - Manner of Calculation Average diameter of all pipings in the plant or on the project shall be calculated in the following way: Sum of the multiplication product of the diameter and length of each pipe shall be divided by the sum of all pipe lengths. (Dn1x l)1 + (Dn x2l) + 2 (Dn x l)3+ ... 3 l1+ l 2 +l+ 3 ...

3. RATES FOR INSTALLATION OF POLYETHYLENE PIPING Productivity Efficiency Percentage (PEP) = 80% 3.1 PE Pipes DIN 8074 PN 6 Dn-mm 16 20 25 32 40 50 63 75 90 110 140 160 180 200 225 250 280 315 355 t [mm] [kg/m] t [mm] 2,0 2,3 2,9 3,6 4,5 5,7 6,8 8,2 10,0 12,7 14,6 16,4 18,2 20,5 22,8 25,5 28,7 32,3 PN 10 [kg/m] 0,12 0,17 0,27 0,42 0,65 1,03 1,47 2,11 3,14 5,07 6,66 8,41 10,40 13,10 16,20 20,30 25,70 32,60 [Mhr/ea] PIPES Straight pipes Coils [Mhr/m] [Mhr/m] Bends [Mhr/ea] Tees [Mhr/ea] FITTINGS AND VALVES Reducers Caps [Mhr/ea] [Mhr/ea] Flanges [Mhr/ea] Valves [Mhr/ea]

2,0 2,0 2,3 2,8 3,6 4,3 5,1 6,2 7,9 9,1 10,2 11,4 12,8 14,2 15,9 17,9 20,1

0,15 0,17 0,29 0,43 0,68 0,97 1,38 2,04 3,60 4,33 5,45 6,77 8,55 10,50 13,20 16,70 21,10

40

3.2 Rates for installation of PE reinforcement pads for branch connection PIPE Dn-mm 40 63 90 110 125 160 180 200 225 BRANCH 32

20

25

40

50

63

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft Mhr/m x 0,3048 = Mhr/ft

4. RATES FOR ERECTION OF PVC & FRP PIPING Productivity Efficiency Percentage (PEP) 80%

5. CARBON STEEL PIPING (SCH 40) CEMENT LINED INSIDE Productivity Efficiency Percentage (PEP) 80%

Pipes Socket handling joint

Dn-mm -I nch [Mhr/m] 15 1/2 20 3/4 25 1 30 1 1/4 40 1 1/2 50 2 65 2 1/2 80 3 100 4 150 6 200 8 250 10 300 12 350 14 400 16 450 18 500 20 550 22 600 24 650 26 700 28 750 30 800 32 850 34 900 36 950 38 1000 40

[Mhr/ea]

Nozzle at Valves 90 and PVC reinforce housing ment (handling) [Mhr/ea] [Mhr/ea]

SYNTHETIC MATERIALS ABBREVIATIONS & INTERPRETATION

Pipes handling Pipe cutting

Butt weld

Sleeve joint with two fillet welds

Nozzle at 90

Repair of concrete lining on joints

FIBREGLASS RESIN POLYESTER PE POLYETHYLENE PVDF -POL YVINYLDENFLUORIDE PVC - POLYVINYLCHLORIDE, HARD PP POLYPROPYLENE FPM - (VITON A ) FLUOR INDIAN RUBBER (KAUTSCHUK) EPDM -(APTK) ETHYLENE PROPYLENEINDIAN RUBBER CR (NEOPRENE ) CHLOROPRENE INDIAN RUBBER PTFE - (TEFLON ) POLYTETRAFLUORETHYLENE PVC-C -POL YVINYLCHLORIDE, ADDITIONALLY CHLORINATED PB POLYBUTENE POM - POLYXYMETHYLENE NBR - NITRIL INDIAN RUBBER IIR BUTYL INDIAN RUBBER CSM - (HYPALON ) CHLORSULFONYLPOLYETHYLENE PEHD -POL YETHYLENE HIGH DENSITY PRFV -POL YESTER RESIN FIBREGLASS REINFORCED, INTERNAL CORE OF PVC

FRP -

Dn-mm 150 200 250 300 350 400 500 600 700 800 900 1000 1100 1200

-Inch 6 8 10 12 14 16 20 24 28 32 36 40 44 48

[Mhr/m]

[Mhr/cut.]

[Mhr/ea]

[Mhr/joint]

[Mhr/ea] [Mhr/joint]

41

Note: 1. Piping of synthetic materials to be calculated acc. to the tables for PE or PVC piping 2. For diameters larger than 40 (1000 mm), to be calculated proportionally to 40

Mhr/m x 0,3048 = Mhr/ft

6. PIPING MADE OF STEEL AND GREY CAST-IRON I made an exception and included steel and grey cast piping in the Chapter Piping Above Ground although they are in most cases laid underground. According to these man hour rates only the pipes are determined according to the unit of length whereas the man hour rates for all other fittings should be calculated acc. to the type and number of joints. For example, Tpiece with a flange at one end and a socket at two ends should be calculated as 1 x flanged end and 2 x socket end. Productivity efficiency percentage (PEP) = 80% 6.1 CAST IRON PIPES Nominal diameter DN 80 (3) 100 (4) 125 (5) 150 (6) 200 (8) 250 (10) 300 (12) 350 (14) 400 (16) 450 (18) 500 (20) 600 (24) 700 (28) 800 (32)

6.2 FITTINGS (DIN: A, E, F, FF, K, FFK, Q, MQ, MMQ, MMK, FFR, T, TT, U, MMA, MMB, MMR, X, N) When calculating man hours for each fitting each end is calculated according to its type, except for the straight end. Nominal diameter DN 80 (3) 100 (4) 125 (5) 150 (6) 200 (8) 250 (10) 300 (12) 350 (14) 400 (16) 450 (18) 500 (20) 600 (24) 700 (28) 800 (32) Socket end [Mhr/ea] Flanged end [Mhr/ea]

Pipe length [m] 3; 4; 5 3; 4; 5 3; 4; 5 3; 4; 5 5 5 5 5 5 5 5 5; 6 6 6

42

[Mhr/m] *

* Note: According to John S. Page's manual each joint between the pipes is also added man hour for the socket joint. I do not agree with that. This could apply only if the fittings are not calculated separately. Just to mention that his man hour for a socket joint is 1/3 lower than the man hour in this table.

Mhr/m x 0,3048 = Mhr/ft

6.3 VALVES Valves to be estimated by considering the handling as for the piping above ground and by adding 2 x Mhr/ea for a flanged end.

7. RATES FOR PIPING BASED ON INCH- DIAMETER (ID)

CORRECTION FACTORS: - Different materials CS Low alloy (0,5 Mo) 1,25 Cr 5 Cr 9 Cr Composite pipe Non-ferrous material Plastic resin CS pipe - cement lined inside - resin (Lining CS):glass - Place of installation: Above Ground Under Ground Pipe rack Bridge Around equipment Line pipe - Sleeper way - Prefabrication - Type of joint: Butt weld 90 Nozzle weld 90 Reinforced nozzle weld Socket weld Seal weld Threaded joint Root pass Fillet weld Mitre weld (Sockolet, weldolet, coupling, etc.) Tie-in to existing piping

Productivity efficiency percentage (PEP) 80% Some world companies ask in their call for tender for a price review according to inchdiameter (ID) and inclusion of all the operations and works involved in installation of piping.

3,5 Ni SS 304 SS 316 SS 321 SS 347

Item 3.1 x F = Mhr D ID

Item 3.1 F D

- Estimate points for butt joint of a relative diameter and wall thickness( Chapter X. P ages 147 201) - sum of factors for the activities required (see below) - diameter (or average diameter) of piping in inches ACTIVITY FACTORS - prefabrication - installation - prefabrication - installation - prefabrication - installation - installation - hydrostatic - pneumatic

43

PIPES PIPES FITTINGS FITTINGS FLANGES FLANGES VALVES PRESSURE TEST PRESSURE TEST ELEVATION IMPACT IMPACT OF SPACE OBSTRUCTION

Sum Every company has its own way of listing the prices for each activity in its call for tenders. Therefore, only the factors for the activities that are required by tenderin documents are summed up. Fabrication and installation of pipe supports is considered separately according to the tables on page 39..

8. RATES FOR UNITS OF OPERATION (BASED ON INCH-DIAMETER) Productivity efficiency percentage (PEP) = 80% 1. Cuts, bevels and welds 1.1 Cuts and bevels - all materials - Schedule 10 - Schedule 20 - Schedule 40 - Std - Schedule 60 - Schedule 80 - XS - Schedule 100 - Schedule 120 - Schedule 160 - XXS - Shop fabrication - Field fabrication 1.2 Welding 1.2.1 Carbon Steel - Schedule - Schedule - Schedule - Std - Schedule - Schedule - XS - Schedule - Schedule - Schedule - XXS - Shop fabrication - Field fabrication

[Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID]

1.2.2 Stainless steel - Schedule - Schedule - Schedule - Schedule - Schedule - Schedule - Schedule - Schedule - Schedule - Schedule

5S 10S 20 40S 60 80S 80 100 120 160

[Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID]

- Shop fabrication - Field fabrication

44

10 20 40 60 80 100 120 160

[Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID]

1.2.3 Alloy Steel - Schedule - Schedule - Schedule - Std - Schedule - Schedule - XS - Schedule - Schedule - Schedule - XXS

10 20 40 60 80 100 120 160

[Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID]

- Shop fabrication - Field fabrication

8. RATES FOR UNITS OF OPERATION (BASED ON INCH-DIAMETER)

2. Pipe - Handling Based on MID (meter-inch-diameter)

3. Miscellaneous 3.1 Temporary Items

- Temporary Supports Schedule Schedule Schedule Std Schedule Schedule XS Schedule Schedule Schedule XXS 10 20 40 60 80 100 120 160 [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] [Mhr/MID] - Temporary Spacers

[Mhr/kg] [Mhr/kg]

3.2 Tapering Wall Thickness for Fittings and Flanges

45

to 5 mm 5 10 mm 10 15 mm 15 20 mm 20 25 mm % %

[Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID] [Mhr/ID]

- Shop fabrication - Field fabrication

% - Shop fabrication % - Field fabrication 3.3 Bending of pipe

Mhr/k g x 0,4536

= Mhr/ft

- Bending of pipe to 1 1/2

[Mhr/bend]

9. RATES FOR PIPING WELDING- (Fitter's work not included) BUTT WELD (C. S.) - COMPLETE [Mhr/weld] Productivity efficiency percentage (PEP) = 90% -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Factors for calculating the rates acc. to type of weld 10 20 30 Std 40 60 XS 80 100 120 140 160 XXS -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

Factors for different kinds of materials

1. Carbon steel 2. Stainless steel 3. Chromium-Molibden steel

46

1. 2. 3. 4. 5.

Nozzle weld 90 Nozzle weld 90 w. reinforcement Nozzle weld bevelled Nozzle weld bevelled w. reinforcement Weldolet, sockolet, nipolet, etc.

6. 7. 8. 9. 10.

Fillet weld Fillet weld Fillet weld Fillet weld Mitre weld

"socket weld" "dummy" 90 "dummy" on elbow closing dummy

10. MAN HOURS FOR WELDING OF PIPING BUTT WELD - ROOT PASS AND FILLER PASSE

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

Root pass - GTAW [Mhr/weld]

10

20

30

FILLER AND COVER PASSES - SMAW [ Mhr/weld] Std 40 60 XS 80

100

120

140

160

XXS

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

47

48

12. INSTALLATION OF PIPING ABOVE - GROUND Unit standards as per integral elements Prefabrication and installation breakdown (Technical calculation manual, year 2003.) 1. 1.1. Pipes Pipes in the plant Prefabrication to 1 1/2" 2"- 48" above 48" % % % % Installation % % % %

1.2.

Pipes on pipe rack

2. Fittings 2. 1.Elbows 2.1.1.Elbows and mitre bends prefabricated to 2.2.2.Mitre bends to be manufactured 2.2. 2.3. 2.4. 2.5. 3. 3.1. 3.2. Tee - pieces to Reducing pieces completed

to 1 1/2" 2" - 48" to 48" above48" to 1 1/2" 2"- 48" to1 1/2" 2"- 36"

% %

% %

% % % % % % % %

% % % % % % % %

Caps - all bores O' lets, half - couplings and the like Flanges Flanges - for welding all types and bores, Blind flanges, orifice plates, spectacle blind and the like Valves -all kinds, types pad bores Pipe supports to 2" 3" - 6" 8"- 14" 16" and above

% %

% %

4. 5.

% % % % %

% % % % %

6. Miscellaneous 6. 1.All br anch welds 6. 1.Stiff ener rings and reinforcing pads 7. Bolts and gaskets - not to be taken into account

% %

% %

49

II. PIPELINES - Basis for calculation of man hours


Productivity efficiency percentage (PEP) = 75%

Contents: 1. 2. 3. 4. 5. 6. 6.1 6.2 7. 8. PIPE TRANSPORT STRINGING BENDING JOINTING WELDING WRAPPING MACHINE WRAPPING HAND WRAPPING LAYING IN TRENCHES SPECIAL POINTS 8.1 8.2 8.3 8.4 8.5 8.6 9. 10. 10.1 10.2 BORING UNDER ROADS OR RAILROADS BREAK OUT OF ROADS CONNECTING PIPELINE SECTIONS CROSSING WATERCOURSES INSTALLATION OF CLEANING STATIONS PUTTING UP PIPELINE MARKERS PRESSURE TESTS PRELIMINARY & FINISHING WORKS PRELIMINARY WORKS FINISHING WORKS

To make an estimate for laying a pipeline is a very sensitive operation, particularly for estimators lacking experience in the laying and installation of such pipelines. World recognized companies specializing in this kind of work have empirical rates based on diameter and length, and on inch-meter respectively. A widely recognized manual for that purpose is John S. Page's Cost Estimating Manual for Pipelines and Marine Structures. The impact of climate, ground and the state is quantified empirically. Since our company does not specialize only in pipelines, we developed rates and elements for calculation of the time needed. However, these rates cannot substitute an estimator. They can assist estimators in making their estimates. In principle, call for tenders do not provide all the elements needed to determine precisely the time needed for erection/installation/laying. Therefore, there are many variables to be taken into account and evaluated by the estimator in order to foresee in detail the conditions under which the works may be executed. The estimator has to make an accurate estimate of the rates, and when and which rates to apply. Similarly, he can change them depending on the case. 1. PIPE TRANSPORT Basic rate for pipe transport is.............................. [Mhr/ton]

The basic rate changes with the conditions by adding or deducting the following rates:

Distance: Roads:

for each kilometre more than 5 km..............plus

[Mhr/ton]

- city roads+............................................ plus [Mhr/ton] - asphalt roads to 50 %............... not considered - asphalt roads above 50 %.............. plus [Mhr/ton] - trailer truck long vehicle......................... not considered - trailer with HIAB................................... minus [Mhr/ton] ............................... plus - tracktor with a trailer [Mhr/ton]

Means of transport:

Loading:

- special crane for loading.......................... not considered - loading by HIAB......................................plus [Mhr/ton] - crane used also for loading.......................plus [Mhr/ton]

Unloading:

- unloading by a special crane to - a temporary pipe storage.........................minus [Mhr/ton] - unloading with pipe stringing along the right-of-way by a special crane.................................. not considered - unloading and pipe stringing by HIAB.........plus [Mhr/ton]

50

Pipe Diameter: 6 10 14 18 26 Pipe Type:

to4 ....................................plus [Mhr/ton] 8....................................not considered 12..................................minus [Mhr/ton] 16..................................minus [Mhr/ton] 24..................................minus [Mhr/ton] and above............................minus [Mhr/ton]

- not wrapped..................................not considered - wrapped....................................plus [Mhr/ton]

Continuity of continuous transport:..................................minus .......... - with occasional stoppagesnot considered - acc. to circumstances.................plus * Crane operators and drivers included in the price of machinery 2. PIPE STRINGING

[Mhr/ton] [Mhr/ton]

If pipe stringing is done as a separate operation by stringing pipes along the right-of-way from the reference storage, the following rates apply: to 3 ..........................plus [Mhr/pc] to 4...........................plus [Mhr/ pc] 6 to 8............................plus [Mhr/ pc] 10 to 14..............................plus [Mhr/ pc] 16 to 20.............................plus [Mhr/ pc] 22 and above..............................plus [Mhr/ pc] If no data is available on the number of pipes, it should be estimated. The manhour does not include transport of temporary timber supports. Drivers and crane operators are not included. 3. BENDING OF PIPES

- Pipe bending on the right-of-way to 3................................. 4.................................. 6 8.............................. .... 10 14.................................... 16 20..................................... 22 and above.............................

[Mhr/bending] [Mhr/bending] [Mhr/bending] [Mhr/bending] [Mhr/bending] [Mhr/bending]

- Shop bending: contractors - Bending for special points is not calculated according to this rate but is included under special points.

51

4.

PIPE JOINTING

It includes pipefitter works for joining of pipes. Welding is not included. - Basic rates: 3.................... 4.................... 6.................... 8.................... 10................... 12...................

[Mhr/joint] [Mhr/joint] [Mhr/joint] [Mhr/joint] [Mhr/joint] [Mhr/joint]

14..................... 16..................... 18..................... 20..................... 22..................... 24.....................

[Mhr/joint] [Mhr/joint] [Mhr/joint] [Mhr/joint] [Mhr/joint] [Mhr/joint]

The rate for pipe joining is calculated by increasing or decreasing the basic rate by the following percentages:

a. Place of jointing: - near trench on temp. timber supports - above trench - in trench

+ +

% % %

b. Type of pipe: - iron pipes - prewrapped pipes + % %

c. Right-of-way quality: - city street - along a road - dry rocky right-of-way - possible mud

+ +

% % % %

d. Means of production: - crane - pipe laying machine

% %

e. Average pipe length: - shorter than 8 m - longer than 8 m

% %

Example: pipe 6" basic rate is 1,75 [Mhr/joint] - a. + % - b. + % - c. % + - d. % + - e. % Total + % [Mhr/joint] + %= [Mhr/joint]

The final manhour rate is a sum of the basic rate

52

5.

WELDING SMAW SMAW ver t i c al up (conventional): Mhr/weld= X x x t / verical down (Fallnaht): Mhr/weld= X x x t /

X = values from below table; = pipe diameter in inches; t - wall thickness in mm X-value table
3 4 6 8 10 12 X 14 16 18 20 22 24 above 24 X

6.

WRAPPING

6.1 MACHINE WRAPPING (acc. t John S. Page)


[Mhr/m] [Mhr/m] to 2 20 3 22 4 24 6 26 8 28 10 30 12 32 14 34 16 36 18

I find above values overestimated, which is based on my monitoring the wrapping works. Therefore, I suggest that the following percentages of the above values are considered.

Diameter 2"-8" 10"-16" 18"-24" 26"-36"

% % % % %

Mhr/m2

Mhr/sqft

6.2 HAND WRAPPING Single-layer wrapping: Machine wr apping x Double-layer wrapping: Machine wr apping x Weld wrapping: Mhr/weld= Mhr/m for hand wrapping

Mhr/m x 0,3048 = Mhr/ft

7.

LAYING IN TRENCH

This kind of laying is considered only when the pipeline is hand wrapped near a trench or above a trench. Man hours include also collection and tr ansport of timber supports and possible installation of concrete weights in case of an underwater pipeline. to 4...................................................... ...................................................... 8 12...................................................... 16...................................................... 24...................................................... above 24...................................................... [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

6 10 14 18

53

8.

SPECIAL POINTS

The term special points means the works on pipelines where a point crew cannot do the work and the special points are left for later on. This requires special teams for executing such works. The special points are: 8.1 BORING UNDER ROADS AND RAILROADS Generally, the erection company does not perform the boring. The erection company performs the following activities: Supply of the material needed for protection and header pipe Cutting of protection conduit to the length dictated by a boring team Protection conduit welding Protection conduit wrapping Header pipe assembling and wrapping Header pipe leak test Installation of spacers and pulling in the main pipe Installation of "Z" seals (sleeve) Construction of air vents on both sides of the road/railroad Putting up necessary signs for the road/railroad works ...................................................... 4 ...................................................... 8 12...................................................... 16...................................................... 24...................................................... ...................................................... above 24 Connection to the header is included. to [Mhr] [Mhr] [Mhr] [Mhr] [Mhr] [Mhr]

6 10 14 18

8.2 BREAK OUT OF ROADS These special points can be performed without stopping the road traffic or by bypassing the traffic. This rate does not include the excavation and repair of the right-of-way. w/o protection pipe to 4............................... ............................... 6 8 10 12............................... 14 16............................... 18 24............................... ............................... above 24 with protection pipe to 4............................... 6 8............................... 10 12.............................. 14 16.............................. 18 24............................. ............................. above 24 w/o traffic [Mhr]............................... [Mhr]............................... [Mhr]............................... [Mhr]............................... [Mhr]............................... [Mhr]............................... w/o traffic [Mhr]............................... [Mhr]............................... [Mhr]............................... [Mhr].............................. [Mhr].............................. [Mhr].............................. with traffic [Mhr] [Mhr] [Mhr] [Mhr] [Mhr] [Mhr] with traffic [Mhr] [Mhr] [Mhr] [Mhr] [Mhr] [Mhr]

The connection to the header is included. 8.3 CONNECTING PIPELINE SECTIONS This item includes the works on interconnecting two pipeline sections. ..................................................... to 4 ..................................................... 6 8 10 12..................................................... 14 16..................................................... 18 24..................................................... above 24 .....................................................

[Mhr] [Mhr] [Mhr] [Mhr] [Mhr] [Mhr]

54

8.4

CROS SING WATERCOURSES

The watercourses are rivers, streams and canals with or without water, etc. Generally, specialist firms undertake the works on river crossings whereas crossings under streams and canals are executed by erection companies, which undertake also the str aight sections. The following operations are included under this item. Bending Connecting & welding of sections Leak test of sections Wrapping - Laying in trench - Installation of concrete weights - Backfilling (Other works are the responsibility of a civil contractor) Stream with water [Mhr] [Mhr] [Mhr] [Mhr] [Mhr] [Mhr]

Canal Canal w/o water with water to 4.......................... [Mhr] .................... [Mhr].................. 6 8............................... [Mhr] .................... [Mhr].................. 10 12............................ [Mhr] .................... [Mhr].................. 14 16............................ [Mhr] .................... [Mhr].................. 18 24............................ [Mhr] .................... [Mhr].................. above 24............................ [Mhr] .................... [Mhr]..................

- Connecting to the header: - one side included - the other side according to the rate for Connecting Pipeline Sections

8.5

INSTALLATION OF CLEANING STATIONS

This item includes the installation of pipes coming out of the ground and installation of a pig launcher and a pig trap. The construction of the station is not included but it can be rated as prefabrication: to 4....................................... 6 8....................................... 10 12...................................... 14 16...................................... 18 24...................................... above 24..................................... [Mhr/station] [Mhr/station] [Mhr/station] [Mhr/station] [Mhr/station] [Mhr/station]

8.6

PUTTING UP PIPELINE MARKERS

This item covers all the operations relating to putting up the pipeline markers. Their fabrication is not included. Each marker = [Mhr]

8.7

OTHER SPECIAL POINTS - Make-on of branches on a pipeline - Installation of measuring and control stations - Installation of reducing stations - Installation of condensate drain stations - Bridge crossings - Watercourse crossings

Man hours for these special points are calculated according to the manhour rates for fabrication and installation of the piping in plants.

55

9.

PRESSURE TESTS

Generally, the pressure tests on the pipelines are performed by teams specialized for this kind of work. The team must be provided with all necessary equipment. The pipelines are constructed in sections, which start and end at a stream that is at a place with sufficient water to wash and test the pipeline washing and testing. The section length depends on the pipeline right-of-way configuration. This rate determines the time needed to test a 5 km (3 miles) long section. The following time allowances to be considered for longer sections: - Pipeline section to 5 km or 3 miles......................................= - Each kilometre longer than 5 km or 3 miles.......................plus [Mhr] [Mhr/km] or

[Mhr/mile]

10. 10.1

PRELIMINARY AND FINISHING WORKS PRELIMINARY WORKS

They include: - Setting up a camp - Setting up offices - Setting up warehouses and stores - Setting up workshops - Erection of necessary fences - Preparation of machinery - Construction of auxiliary devices The rate for the preliminary works is % of the total man hours for the works f rom 1 through 9.

10.2

FINISHING WORKS

The finishing works include: -Cleaning the right-of-way from residual material, pipes, timber supports, construction material, and other debris - Dismantling temporary works - Loading the equipment and material - Other finishing works The rate for the finishing works is % of manhours for preliminary works.

56

III. STEEL STRUCTURE ERECTION (Acc. to MONTMONTAA Co. 1980)


1. BASIC MAN HOURS - UNIT Kind of Work 1.1 Sorting the structure and preparation for erection and pre-erection 1.2 Pre-erection of structure a) by crane: 1.2.1. a Columns 1.2.2. a Beams and columns 1.2.3. a Lattice beams b) by hand: 1.2.1. b Columns and beams 1.2.2. b Lattice beams 1.3 Transport of structure to erection place 1.3.1. Columns and beams 1.3.2. Lattice beam 1.3.3. Small structure 1.4 Installation of anchor bolts and break in 1.5 Structure erection (hoisting and putting up the structure) a) by crane: 1.5.1.a Columns 1.5.2.a Beams 1.5.3.a Lattice beam 1.5.4.a Different diagonal small items b) by el. winches: 1.5.1.b Columns by supporting arms 1.5.2.b Beams " " " " 1.5.3.b Lattice supports by masts 1.5.4.b Binding joists 1.5.5.b Longitudinal beams 1.5.6.b Floor grids and chequered sheets c) By hand operated winches or haulage cranes: 1.5.1.c Columns by supporting arms 1.5.2.c Beams " " " " 1.5.3.c Trusses supports by sup. arms 1.5.4.c Binding joists 1.5.5.c Longitudinal beams 1.5.6.c Floor grids and chequered sheets 1.5.7.c Wall windows 1.5.8.c Misc. construct, diagonals & small items pcs. 1.5.9.c Staircase treads [Mhr/ea]

[Productivity efficiency percentage (PEP)=75%] Unit weight of elements in [t] and man hours [Mhr/ton] 0,35 0,5 0,8 1 2 3 4 5

0,05

0,1

0,15

0,2

0,25

8 -

10 -

12 -

15 -

20 -

57

- -

1.6

INSTALLATION OF LOST FORMWORK Trapezoidal sheets for concrete slabs

- Bolting of binding beams is performed by the manufacture the structure supplier. - Sheets are fastened by nails driven in by pistols.

1.6.1 Type "HOLORIB" or "MONTANA" (length c. 4 m, width 620 mm)


to 100 m2 weight [kg/m2] t = 0,75 mm t = 0,88 mm t = 1,0 mm 11,4 13,5 15,3 to 1000 sqft Mhr/m2 Mhr/m2 Mhr/m2 100 500 m2 1000 5000 sqft Mhr/m2 Mhr/m2 Mhr/m2 500 1000 1000 10000 10000 50000 above m2 m2 m2 50000 m2 5000 10 000 10000 100 000 above 500 000 sqft 100 000 sqft 500 000 sqft sqft Mhr/m2 Mhr/m2 Mhr/m 2 Mhr/m 2 2 2 2 Mhr/m Mhr/m Mhr/m Mhr/m 2 2 2 2 Mhr/m Mhr/m Mhr/m Mhr/m 2

1.6.2 Type "KRUPP HSCH" (length 3,6 5,8 m, width 700 800 mm)
to 100 m2 weight [kg/m2] t = 1,0 mm t = 1,25 mm t = 1,50 mm 12,8 16,0 19,2 to 1000 sqft Mhr/m2 Mhr/m2 Mhr/m2 100 500 500 1000 1000 10000 10000 50000 above m2 m2 m2 m2 50000 m2 1000 5000 5000 10 000 10000 100 000 above 500 000 sqft sqft 100 000 sqft 500 000 sqft sqft Mhr/m2 Mhr/m2 Mhr/m2 Mhr/m2 Mhr/m 2 Mhr/m2 Mhr/m2 Mhr/m2 Mhr/m2 Mhr/m 2 Mhr/m2 Mhr/m2 Mhr/m2 Mhr/m2 Mhr/m 2

Note: 1. Steel brackets for trapezoidal plates (Stahlknagge) are generally shop welded. If site welded, the rate of % is added. 2. Above rates include also placement of Z sections and seal caps.

1.7

INSTALLATION OF WIRE ROPE CLAMPS


Mhr/ea Mhr/ea 26 30 mm 31 35 mm Mhr/ea 36 40 mm 41 45 mm Mhr/ea 46 50 mm 51 55 mm Mhr/ea 56 60 mm > 60 mm

to 20 mm 21 25 mm

1.8

REAMING OF HOLES

M 20 M 22 M 24 M 27 M 30 M 36 M 42 M 48 M 56 M 64 a) by pn. or el. drilling machine from scaffold - manhour/hole b) by a reamer - man hour/hole

1.9 M 20

BOLTING FROM SCAFFOLDING - MANHOUR PER 100 PIECES M 22 M 24 M 27 M 30 M 36 M 42 M 48 M 56 M 64

mm x 0,03937 = inch m x 3,28 = ft Mhr/m2 x0,0929 = Mhr/sqft kg/m2x 0,2048 = lbs/sqft

When tightening the bolts by a torque wrench, manhours are multiplied by Note: The above manhours do not include scaffolding.

factor.

58

2. ERECTION OF MISCELLANEOUS STEEL STRUCTURES 2.1 BASIC MANHOUR RATES - TOTAL

(PEP = 75%)

2.1.1 BUILDINGS AND CANOPY FRAMING Cubic weight [kg/m3] 2 4 6 8 10 Cubic weight [kg/m3] 12 14 16 18 20 Cubic weight [kg/m3] 22 24 26 28 30 Cubic weight [kg/m3] 35 40 45 50 55

Rate [Mhr/ton]

Rate [Mhr/ton]

Rate [Mhr/ton]

Rate [Mhr/ton]

Cubic weight [kg/m3] =

Structure weight [kg]


Width [m] x Length [m] x Height [m]

Type of structure 2.1.2 Equipment & bridging supports 2.1.3 Towers for transmission lines 2.1.4 Stairs structure 2.1.5 Tower structure for chimney or similar 2.1.6 Antennas and torches 2.1.7 Single member support 2.1.8 Bridging between the buildings 2.1.9 Conveyor bridges 2.1.10 Crane tracks outside buildings 2.1.11 Bridge crane 2.1.12 Portal crane 2.1.13 Port crane 2.1.14 Construction crane 2.1.15 Stationary crane 2.1.16 Piping bridges (outside oil refinieres)

Light

Mhr/ton Medium

Heavy

Structure: light to 30 kg/m; medium-weight 30 60 kg/m; heavy above 60 kg/m 3. CORRECTION FACTORS The rate for calculation is computed by multiplying the basic rate by a medium correction factor. The medium correction factor is computed by adding up all selected factors and dividing them by 10. K1 Weather impact Month : K1 : I II III IV V VI VII VIII IX X XI XII

K2 Abnormal impact of temperature Average temp. : K2 : below - 10 C (-10) C (- 5) C (- 5) C 30 C above 30 C

kg/m x 0,672 = lbs/ft kg/m3x 2,2046 = lbs/m 3

59

K3 Impact of elevation at which the works are executed Heght in [m] to: K3 :

15

25

35

45

60

75

80

100

K4 Impact of the job site ground - hard and flat ground - fill ground consolidated by a roller and provided with drainage - loose ground with drainage - fill ground without drainage - levelled out ground without drainage - muddy ground K5 Impact of the structure engineering level - documentation fully developed - only erection process with written instruction - documentation not developed K6 Impact of installation joint type - min. 90 % bolted joints - min. 90 % welded joints - min. 90 % riveted joints K7 Impact of pre-assembling practicability - pre-erection possible - smooth - pre-erection possible - restricted - pre-erection not possible K8 Impact of the structure design - very simple - simple - normal - complex - very complex K9 Impact of the structure complexity - welded plate structure - rolled sections structure - pipe structure K10 Impact of the component bulking - delivery in bulk - basic assembling - assembled for normal transport - assembled for special transport

60

4. STEEL STRUCTURES IN OIL REFINERIES AND PETROCHEMICAL PLANTS 4.1 LIGHT STRUCTURE (to 30 kg/m) 4.1.1 Ladders and step irons 4.1.2 Floors - treads 4.1.3 Light platforms and landings 4.1.4 Railing - straight Railing - round

(PEP = 75%)

[Mhr/ton] [Mhr/ton] or [Mhr/ton] [Mhr/ton] or [Mhr/ton] or

[Mhr/ea] [Mhr/m] [Mhr/m]

4.2 MEDIUM-WEIGHT STRUCTURE (31 60 kg/m) 4.2.1 Air coolers 4.2.2 Medium platforms and landings 4.2.3 Structure on towers 4.2.4 Staircases 4.2.5 Torch structure 4.2.6 Pipe supports, trestles, supports on prepared foundations

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

4.3 HEAVY STRUCTURE (above 60kg/m) 4.3.1 Pipe racks 4.3.2 Kiln structure 4.3.3 Reactor and regenerator structure 4.3.4 Large workshops - span to 10 m - 10 20 m - above 20 m

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

4.4 MISCELLANEOUS STRUCTURES 4.4.1 Floor grids 4.4.2 Chequered plate flooring - fabrication - installation 4.4.3 Lining of large workshops and hangars - corrugated sheets - sandwich elements - roof - sandwich elements - fasade

[Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2]

4.5 PIPE HANGERS AND SUPPORTS 4.5.1 Fabrication 4.5.2 Erection 4.5.3 Spring supports erection

[kg/Mhr] [kg/Mhr] [kg/Mhr]

(Classification of steel structures acc. to UHDE Dortmund)

61

5. ERECTION AND DISMANTLING OF MISCELLANEOUS STEEL STRUCTURES (PEP = 75%) 5.1 ERECTION OF STEEL STRUCTURES - ACC. TO THE WEIGHT Bulking, raising, positioning and temporary bolting [Mhr/ton]

Structure weight

Unloading and on-site hauling [Mhr/ton]

Structure fastening [Mhr/ton] welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint welding of bolted joint

TOTAL [Mhr/ton]

to 20 tons 20 50 tons 50 100 tons 100 250 tons 250 500 tons 500 750 tons 750 1000 tons 1000 1500 tons 1500 3000 tons 3000 5000 tons above 5000 tons

Above man hours do not include painting and scaffolding. 5.2 MISCELLANEOUS STRUCTURES

5.2.1 STRAN STEEL FRAMING - stud system - rafter system - joist system Man hours do not include covering, painting and scaffolding. 5.2.2 STEEL OVERHEAD PIPE, BRIDGES, ETC. - unloading - bulking, hoisting, positioning and temporary bolting fastening: - welded design - bolted design Total:-welded design - bolted design Man hours do not include covering, painting and scaffolding.

[Mhr/m 2] [Mhr/m 2] [Mhr/m 2]

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

62

5.2.3 DOCK AND CANOPY FRAMING - unloading - raising, positioning and temporary bolting - fastening: - welded design - bolted design Total: - welded design - bolted design

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

Man hours do not include covering, painting and scaffolding. 5.2.4 PLATFORMS AND FLOORS - unloading - erection: - platform framing - catwalk framing - chequered floor plate

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

[kg/Mhr] or

Man hours do not include painting and scaffolding. 5.2.5 BAR JOISTS, PARTITION FRAMING, MONORAILS AND EQUIPMENT SUPPOR TS a) bar joists - unloading - erection and fastening Total: b) partition framing - unloading - fabrication cutting out - erection and fastening Total: c) monorails - unloading - erection and fastening Total: d) equipment supports - unloading - fabrication cutting out - erection and fastening Total:

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

Man hours do not include erection of equipment, painting and scaff olding. 5.2.6 STAIRS & LADDERS - unloading miscellaneous steel items a) stairs: - fabrication of all sizes - field erection 915 mm (3' 0) wide - field erection 1067 mm (3' 6) wide - field erection 1220 mm (4' 0) wide - landing fabrication

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

63

b) ladders - fabrication of straight ladders - fabrication of ships ladders - fabrication of safety cages - erection of straight ladders - erection of ships ladders - erection of safety cages - rung erection 19 mm (3/4) Man hours do not include painting and scaffolding.

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

5.2.7 HANDRAILS a) Standard Pipe Handrails - 1067 mm (3' 6) High fabrication 1 1/4 & 1 1/2 - straight runs fabrication 1 1/4 & 1 1/2 - angled runs erection 1 1/4 pipe - straight free standing erection 1 1/4 pipe - angled free standing erection 1 1/2 pipe - straight free standing erection 1 1/2 pipe - angled free standing [kg/Mhr] or [kg/Mhr] or [Mhr/ton] [Mhr/ton] [Mhr/m]* [Mhr/m]* [Mhr/m]* [Mhr/m]*

b) Single Pipe Handrail - Wall Attached: fabrication 1 1/4 & 1 1/2 pipe erection 1 1/4 pipe erection 1 1/2 pipe erection of wall brackets [kg/Mhr] or [Mhr/ton] [Mhr/m]* [Mhr/m]* [Mhr/ea]

c) Standard Angled Iron Handrail - 1067 mm (3' 6) High fabrication - straight runs fabrication- angled runs erection 50x50x6 mm - straight free standing erection 50x50x6 mm - angled free standing erection 50x50x6 mm - straight free standing erection 50x50x6 mm - angled free standing [kg/Mhr] or [kg/Mhr] or [Mhr/ton] [Mhr/ton] [Mhr/m]* [Mhr/m]* [Mhr/m]* [Mhr/m]*

d) STANDARD TOE OR KICK PLATES 3,5 mm x 150 (6) 4,76 mm x 150 (6) 6,35 mm x 150 (6) [Mhr/m] [Mhr/m] [Mhr/m]

[Mhr/m]* refers to the length of handrail and not the length of a pipe or a section. - Straight runs are those with all connecting members at 90o angles. o - Angles runs are those with all connecting members at an angle larger or smaller than 90 . - For erection of handrails made of light tubes and solid round and flat sections, use the man hours for angled handrails. - For handrails with expanded metal panels, increase angle iron man hours thirty (30) percent. - Man hours do not include painting.
kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

5.2.8 DOOR, LOUVER AND DUCT FRAMES a) Door Frames - unloading - fabrication - installation

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

64

b) Louver Frames - unloading - fabrication - erection c) Duct Frames - unloading - fabrication - erection

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

Man hours do not include painting and scaffolding. 5.2.9 MISCALLANEOUS IRON & STEEL a) Bins & Hoppers - unloading - fabrication - erection b) Miscallaneous Hangers - fabrications - erection c) Metal Thresholds - Installation d) Wheel Guards - installation e) Trench Framing - Unloading - Fabrication - Installation f) Trench Covers - Plates installation - Grating installation g) Curb Angles - unloading - fabrication - installation h) Steel Curbing - unloading - fabrication - installation i) Pipe Sleeves - fabrication - installation j) Anchor Bolts - fabrication - installation
kg/Mhr x 2,2046 = lbs/Mhr

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[kg/Mhr] [kg/Mhr]

or or

[Mhr/ton] [Mhr/ton]

[Mhr/ea]

[Mhr/ea]

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[Mhr/m2] [Mhr/m2]

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[kg/Mhr] [kg/Mhr] [kg/Mhr]

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

[kg/Mhr] [kg/Mhr]

or or

[Mhr/ton] [Mhr/ton]

[kg/Mhr] [kg/Mhr]

or or

[Mhr/ton] [Mhr/ton]

k) Ledger Angles - unloading [kg/Mhr] - fabrication [kg/Mhr] - installation [kg/Mhr] Man hours do not include painting and scaffolding.

or or or

[Mhr/ton] [Mhr/ton] [Mhr/ton]

65

5.2.10 STEEL GRATING - Installation of floor grids Grating Bar Size Weight [kg/m2] 19,05 x 4,76 mm 28,80 25,04 x 3,18 mm 25,39 25,04 x 4,76 mm 37,11 31,3 x 3,18 mm 30,76 31,3 x 4,76 mm 44,92 38,1 x 3,18 mm 36,13 38,1 x 4,76 mm 53,22 44,45 x 4,76 mm 61,52 50,8 x 4,76 mm 69,82 57,15 x 4,76 mm 77,64 63,5 x 4,76 mm 85,94 - Fabrication and modification of floor grids: - straight and diagonal cutting - circular cutting - straight and diagonal banding - circular banding - welding of curb angles - rounding of curbs by grinding Man hours do not include painting and scaffolding. 5.2.11 SIDING OF LARGE WORKSHOPS AND HANGARS - section sheets - section aluminium plates - stainless steel sheets - insulation boards (sandwich) Man hours do not include sealing and scaffolding. 5.3 REMOVAL OF STEEL STRUCTURE AND MISCELLANEOUS ITEMS - Steel structure - Miscellaneous steel items - Machinery: light heavy - Pipes (C.S.) to 2 3 6 8 12 14 16 18 24 26 36 - Railroads: Ties and tracks Turnouts - Miscellaneous Fence of three strand barbed wire Fence of five strand barbed wire Chain link fence Guard rail [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/ea] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

[Mhr/m2]

[Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

[Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2]

Man hours do not include loading, transport and unloading and scaffolding.
kg/m2x 0,2048 = lbs/ft Mhr/m2x 0,0929 = Mhr/sqft Mhr/m x 0,3048 = Mhr/ft kg/Mhr x 2,2046 = lbs/ft

66

IV. ERECTION OF EQUIPMENT IN PETROCHEMICAL INDUSTRY


Productivity Efficiency Percentage (PEP) = 75% 1. STATIONARY EQUIPMENT (towers, heat exchangers, reactors, regenerators, small storage tanks, air coolers, etc.) These man hours include the erection of equipment delivered as a whole or in sections that are completed but not fully assembled because of their overall dimensions (transport). Man hours include: - Unloading - Hauling from storage to the place of erection - Hoisting by usual hoisting means - Putting up to the design elevation - Positioning of connection points - Position inspection

TIME ALLOWANCE FOR ERECTION OF EQUIPMENT AT ELEVATION All stated below, man hours for erection of equipment are applicable when the equipment base is at an elevation of up to 2 m above the site zero level. Apply the following factors for higher elevations: Elevation Factor 0 2 m.............................................. 2 4 m.............................................. 4 6 m.............................................. 6 10 m.............................................. above 10 m..............................................

1.1 All Equipment to 0,5 ton 1.2 Towers above 0,5 ton 1.3 Towers consisting of more pieces: Joint: 1.4 Package Unit to 10 tons : above 10 tons : 1.5 Other Equipment 0,5 2 tons : 2,1 10 tons : 10,1 20 tons : above 20 tons : 1.6 Bridge Cranes - Erection of crane track (rails) - Erection of crane with a trolley and a drive 1.7 Lifts [Mhr/m2] shaft + Mhr per meter of elevation

[Mhr/ea] or [Mhr/ea] +

[kg/Mhr] [Mhr/ton]

[Mhr/ea] + [Mhr/ton] + joint [Mhr/m] of joint circumference

[Mhr/ea] + [Mhr/ea] +

[Mhr/ton] [Mhr/ton]

[Mhr/ea] + [Mhr/ea] + [Mhr/ea] + [Mhr/ea] + [Mhr/m] [Mhr/m] span

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

67

1.8 Electrostatic Precipitators Weight [ton] to 100 ton/unit 100 250 ton/unit above 250 ton/unit 1.9 Marine loading arms (acc. to John S. Page) - assembling and erection [Mhr/ea] Effect [kg/Mhr]

Load. arm diam. inch 4 6 8 10 12 14 16 18 20 24

to 6

Total length of loading arm (meters) 69 9 12 12 15 15 18

18 21

21 24

24 27

27 - 30

NOTE: I find above man hours for loading arms too stringent, so I suggest they are increased by %.

2. ROTARY EQUIPMENT (pumps, compressors, fans, blowers, mixers, etc.) These man hours include the following: - Hauling from storage to the place of erection - Placing onto previously built foundations - Vertical positioning - Machine positioning and inspection - Installation of guards and covers - Completion with pertaining parts

m x 3,281 = ft kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

2.1 CENTRIFUGAL PUMPS 2.1.1 MAN HOURS BASED ON POWER [kW] Power [kW] to 10 kW 10 50 kW 50 100 kW 100 150 kW 150 200 kW 200 250 kW above 250 kW [Mhr/kW] + + + [Mhr/ea] Minimum hours

68

Pumps supplied with a coupling on one pedestal Pumps and drive motors supplied separately Pumps, drive motors and reduction gears supplied separately Vertical pumps Fans Blowers Gear pumps Mixers Compressors to 200 kW

x x x x x x x x x

2.1.2 MAN HOURS BASED ON WEIGHT [kg] Weight [kg] to 100 101 200 201 300 301 400 401 500 501 600 601 700 701 800 801 900 901 1000 1001 1250 1251 1500 1501 2000 2001 2500 above 2500 Effect [kg/Mhr] Min. [Mhr/ea]

vertical pumps fans blowers gear pumps mixers compressors

[kg/Mhr] x [kg/Mhr] x [kg/Mhr] x [kg/Mhr] x [kg/Mhr] x [kg/Mhr] x

kg x 0,4536 = lbs kg/Mhr x 2,2046 = lbs/Mhr

NOTE: If the data on power and weight are available, perform the calculation on both bases and take the mean value.
3 2.1.3 MAN HOURS BASED ON THE CAPACITY [m/hr] (FOR LIQUID MEDIA ONLY)

[m/hr] to 10 10,1 20 20,1 30 30,1 40 40,1 50 50,1 60 60,1 70 70,1 80 80,1 90 90,1 100 100,1 110 110,1 120 120,1 130 130,1 140 140,1 150 150,1 160

Mhr x [m/hr]

[m/hr] 160,1 170 170,1 180 180,1 190 190,1 200 200,1 210 210,1 220 220,1 230 230,1 240 240,1250 250,1260 260,1270 270,1280 280,1290 290,1300 300,1750 above 750

Mhr x [m/hr]

69

Conversion of Units l/s x 3,6 = m3/hr US gallons per minute: Cubic feet per minute: Cubic feet per hour: l/min x 0,06 = m3/hr US gpm x 0,227 = m3/hr cfpm x 1,7 = m3/hr cfphr x 0,283 = m3/hr

2.2 2.2.1

C OMPRESSORS COMPRESSORS DRIVEN BY ELECTRIC MOTOR to 200 kW 201 300 kW 301 500 kW 501 750 kW 751 1000 kW 1001 1500 kW 1501 2250 kW 2251 3000 kW 3001 4000 kW 4001 5000 kW above 5000 kW Acc. to Table 2.1.1 [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW]

(min. (min. (min. (min. (min. (min. (min. (min. (min. (min.

Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr)

2.2.2

COMPRESSORS DRIVEN BY GAS TURBINE to 250 251 350 351 450 451 600 601 750 751 900 901 1100 1101 1300 1301 1500 1501 1750 1751 2000 2001 2500 2501 3000 3001 4000 above 4000 kW kW kW kW kW kW kW kW kW kW kW kW kW kW kW [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] [Mhr/kW] (min. (min. (min. (min. (min. (min. (min. (min. (min. (min. (min. (min. (min. (min. (min. Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr) Mhr)

70

3. TOWERS & VESSELS - INSTALLATION OF INTERIOR COMPONENTS & EQUIPMENT 3.1 INSTALLATION OF TRAYS AND DEMISTERING PADS

Tower Diameter [mm] to 1000 1001 1200 1201 1400 1401 1600 1601 1800 1801 2000 2001 2250 2251 2500 2501 2750 2751 3000 3001 3250 3251 3500 above 3500

[Mhr/m2] 1. 2. 3. 4. 5. 6. *

[kg/Mhr] 6.

1. Single downflow valve type trays 2. Double downflow valve type trays 3. Single downflow bubble cap type trays 4. Double downflow bubble cap type trays 5. Sieve or perforated type trays 6. Demisting pads* *If the bottom and roof of a demisting pads are already installed, the man hours should be decreased by %. 3.2 VESSELS & TOWER PACKING Packing the vessels and towers with different solid packings in bulk condition: towers : vessels : [Mhr/ea] + [Mhr/ea] + [Mhr/m3] or [Mhr/m3] or [Mhr/ton] [Mhr/ton]

3.3 OPENING AND CLOSING OF MANHOLES ON VESSELS AND TOWERS Manhole Size to 14 16 18 20 24 28 30 32 36 40 42 [Mhr/ea]

Class : 150#x 1,0 300#x 1,15 600#x 1,30


Mhr/m2x 0,0929 = Mhr/sqft Mhr/m3x 0,02831 = Mhr/cuft kg/Mhr x 2,2046 = lbs/Mhr

71

3.4 ERECTION OF PLATFORMS, LADDERS AND FLOOR GRIDS ON VESSELS AND TOWERS (PREDRESSING) 3.4.1 Erection average effect : [kg/Mhr] 3.4.2Estimate of quantit y of platforms, ladders and floor grids It is calculated per [m2] of the shell surface area (without bottom and roof). Elevation to 10 m 10,1 15 m 15,1 20 m 20,1 25 m 25,1 30 m 30,1 35 m 35,1 40 m 40,1 45 m 45,1 50 m 50,1 55 m 55,1 60 m above 60 m [kg/m2]* [Mhr/m2]*

* These data should be regularly monitored and occasionally revised.

4. EQUIPMENT SCAFFOLDING 4.1 Tubular scaffold (for each piece of equipment separately) to 10 m Scaffold erection [Mhr/m ]or [Mhr/m ] Scaffold dismantling [Mhr/m ]or [Mhr/m ] Total Elevation factor at which the scaffold is erected or dismantled: 0 5m 5 10 m 10 15 m 15 20 m 20 25 m 25 30 m above 30 m
2 3 2 3 3

10 50 m

50 100 m

100 500 m

500 1000 m

above 1000 m

kg/Mhr x 2,2046 = lbs/Mhr kg/m2x 0,2048 = lbs/sqft Mhr/m2x 0,0929 = Mhr/sqft Mhr/m3x 0,02831 = Mhr/cuft m3x 35,32 = cuft

72

4.2 Patent Scaffolding Sections: Length : Width : Height : 7 feet;2,1 m 5 feet;1,5 m 5 feet;1,5 m

Length

Manhours per section One or Two Sections High Erection Dismantling Total Erection

More Than Two Sections High Dismantling

Total

One to Two Sections Long Three to Five Sections Long Six and More Sections Long

73

V. STORAGE TANKS - CYLINDRICAL AND SPHEROIDAL


Productivity Efficiency Percentage (PPE) = 85% 1. APPROXIMATE WEIGHTS AND ERECTION EFFECTS OF CYLINDRICAL STORAGE TANKS (The weights are based on already designed storage tanks, mostly pursuant to API-650. Nowadays, storage tanks are also designed according to other standards so some 75% storage tanks have smaller weight.)
RATED VOLUME [m3 ] 50 100 150 200 250 300 400 5 00 600 700 800 900 1.000 1.200 1.400 1.500 1.800 2.000 2.200 2.400 2.500 2.600 3.000 3.500 4.000 4.500 5.000 5.500 6.000 6.500 7.000 7.500 8.000 10.000 11.000 12.000 13.000 15.000 Fixed Roof Conventional [kg/Mhr] Floating Roof Weight Erection c. [kg] [kg/Mhr] Fixed + Floating Roof Weight Erection c. [kg] [kg/Mhr]

Weight c. [kg] 4.715 8.100 9.740 11.440 12.400 14.000 16.800 19.950 22.750 23.800 26.400 29.000 35.980 36.820 52.470 59.295 48.600 52.000 56.650 61.200 63.800 66.300 75.000 87.200 99.200 111.100 123.000 135.000 147.000 158.900 170.000 182.600 194.400 241.000 288.000 351.000 420.000 474.000

Bygging* [kg/Mhr]

14.350 17.600 20.700 26.625 31.800 36.500 40.600 44.150 47.325 50.000 53.300 57.100 60.000 67.500 72.800 78.200 83.600 86.300 88.100 96.900 107.800 119.600 131.000 143.000 157.900 172.800 174.400 190.400 201.800 217.600 261.000 278.100 295.200 353.600 372.000

12.850 15.300 17.450 21.000 22.500 26.300 29.700 33.000 36.300 40.800 44.900 51.000 54.500 58.000 62.400 67.400 72.400 75.00 77.000 86.000 97.500 109.400 121.000 131.200 145.600 160.000 170.000 188.000 200.000 215.000 262.000 283.500 305.000 342.500 380.000

74

RATED VOLUME 3 [m] 20.000 22.500 25.000 30.000 35.000 40.000 50.000 60.000 70.000 80.000 90.000 100.000

Weight c. [kg] 566.000 594.000 622.500 684.000 742.000 804.000 976.000 1.148.300

Fixed Roof Conventional [kg/Mhr]

Bygging* [kg/Mhr]

Floating Roof Weight Erection c. [kg] [kg/Mhr] 449.000 500.700 552.500 660.000 766.500 872.000 1.002.100 1.151.500 1.360.500 1.520.600 1.710.000 1.890.000

Fixed + Floating Roof Weight Erection c. [kg] c. [kg/Mhr] 460.000 540.000

*Bygging a method of erection by hydraulic jacks

- a series of identical storage tanks: each next storage tank x

up to the maximum

% effect increase

Effect of storage tank erection with a steel berm (double shell and bottom) - Inside tank is calculated acc. to man hours in the table - Effect for the berm acc. to man hours in the table .....................................x - If the total weight is known, then acc. to man hours in the table ......................x

m3 x35,32 = cu ft kg x 0,4536 = lbs kg/Mhr x 2,2046 = lbs/Mhr

1.1 STATISTICAL PARTICIPATION OF STORAGE TANK COMPONENTS IN TOTAL WEIGHT Based on the analysis of 33 cylindrical storage tank projects of total 16.500 tons, 300 m to 3 80.000 m , an average participation of the components in the storage tank total weight is as follows: - Bottom - Shell - Roof - Supporting structures - Nozzles and manholes c. c. c. c. c. % % % (of which: steel sections roofing plates %) % %
3

%,

Storage tanks with a berm: The berm weight is c. % of the inside storage tank weight of which c. % for the bottom.

% accounts for the shell and

75

2. ERECTION OF CYLINDRICAL STORAGE TANKS - DETAILS The above table defines approximate effects of complete erection of cylindrical storage tanks according to the volume, type and method of erection. It is often the case that a very detailed erection estimate is required for already completed projects. This could be done if you follow this chapter. For some storage tank components, man hours are given only for erection without welding. In that case the welding should be computed and estimated according to the man hours for welding under the Chapter WELDING AND FLAME CUTTING. Similarly, the following correction factors should be considered: 1. Impact of average outside temperature - 5 C to +10 C 10 C to 30 C 30 C to 40 C above 40 C 2. Impact of the job site ground - Hard and flat ground - Fill ground consolidated by a roller provided with drainage - Fill ground, not consolidated provided with drainage - Fill ground consolidated by a roller without drainage - Ground levelled out without drainage 2.1 PRELIMINARY WORKS - Unloading plates - Material disposal - Inspection and take over of foundation, measurement, and other: [Mhr/ton] [Mhr/ton] Tank diameter to 15 m 16 25 m 26 40 m 40 50 m above 50 m [Mhr/m2]

factor factor factor factor

factor factor factor factor factor


mm x 0,03937 = inch m x 3,281 = ft Mhr/m2 x 0,0929 = Mhr/sq ft kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

2.2 2.2.1

STORAGE TANK BOTTOM Installation of tank bottom Installation w/o welding [kg/Mhr] Installation and welding* [kg/Mhr]

plate thicknness 6 mm 6,5 mm 7 mm 8 mm - Annular ring to be computed with the effect for the central part decreased by 25 % * welding: 10 % SMAW; 90 % automated machine 2.2.2 Corrosion protection of plates (underside) Tank diameter [Mhr/m2] to 15 m 16 30 m 31 50 m above 50 m Weld vacuuming on the tank bottom [Mhr/m]

2.2.3

76

2.3 STORAGE TANK SHELL 2.3.1Shell Erection - Con ventional (from bottom to top)

[Mhr/plate] Plate thickness [mm]

Course 1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

36

32

28

24

20

16

15

14

13

12

11

10

- Correction factors according to the plate length: Length [m] Factor to 5 6 7 8 9 10 12

- Welding not included. 2.3.2Erection of shell plates (by h ydraulic jacks) ("Bygging" hydraulic jacks, from top to bottom)

27 [Mhr/plate]

24

20

16

15

Plate Thickness [mm] 14 13 12 11

10

- Correction factor according to the plate length as under item 2.3.1 - Welding not included - Installation of hydraulic jacks [Mhr/ea] - Removal of hydraulic jacks [Mhr/ea] 2.3.3Weld grinding on the inner side of shell (storage tank with a floating roof) [Mhr/m] or [m/Mhr]
mm x 0,03937 = inc m x 3,281 = ft Mhr/m2 x 0,0929 = Mhr/sq ft kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

2.4

WIND BINDINGS - RINGS FOR SHELL STIFFENING Erection w/o welding [Mhr/m] Erection and welding (SMAW) [Mhr/m]

2.4.1Top angle piece - Placing angle piece with conventionally installed shell and no walkway - Placing angle piece with conventionally installed shell and a walkway

[Mhr/m]

[Mhr/m]

- Placing angle piece with a shell installed by hydraulic jacks [Mhr/m] [Mhr/m]

77

2.4.2

Primary windscreen with a walkway Erection w/o welding [kg/Mhr] Erection and welding [kg/Mhr]

2.4.3

Secondary and additional windscreens

2.4.3.1Placing windscreens with conv entionally erected shell Erection w/o Welding w/o reinforec. with reinforc. 1st windscreen, from the bottom up nd 2 windscreen, from the bottom up 3rd windscreen, from the bottom up [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] Erection and Welding (SMAW) w/o reinforc. with reinforc. [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

2.4.3.2Placing windscreens when a shell is er ected by hydraulic jacks Erection w/o Welding w/o reinforc. with reinforc. all windscreens not used as walkways [Mhr/m] [Mhr/m] Erection and Welding (SMAW) w/o reinforc. with reinforc. [Mhr/m] [Mhr/m]

2.5 2.5.1

FIXED ROOF Erection of roof and support structure

2.5.1.1Erection of the structure with a con ventionally installed shell Erection w/o Erection and welding welding * [kg/Mhr] [kg/Mhr] 2.5.1.2Structure er ection with a shell installed by hydraulic jacks Erection w/o Erection and welding welding* [kg/Mhr] [kg/Mhr] 2.5.2 Installation of roofing plates Erection w/o welding effect [kg/Mhr] Erection and welding * [kg/Mhr]
mm x 0,03937 = inc m x 3,281 = ft Mhr/m2 x 0,0929 = Mhr/sq ft kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

plate thickness[mm] 5,00 5,50 6,00 6,50

* welding: 50 % SMAW; 50 % semiautomatic (MAG)

78

2.6

FLOATING ROOF 2.6.1 Erection of plates for the floating roof lower slab

2.6.1.1 For raising to the surface (water/air) Erection w/o welding plate thickness [mm] effect [kg/Mhr] 5,0 5,50 6,0 6,50 7,0

Erection and welding* [kg/Mhr]

* welding: 10 % SMAW; 50 % MAG; 40 % automated machine 2.6.1.2On a "spider net" steel structure Above effects to be increased by % - "spider net" installation not included (Item 2.6.10) 2.6.2 Erection of concentric rings, radial partitions and supporting channels Erection w/o Erection and welding welding * Storage tank diameter effect [kg/Mhr] [kg/Mhr] to 20 m 20 30 m 30 40 m above 40 m * welding: 50 % SMAW; 50 % MAG 2.6.3 Erection of roofing plates (upper slab) Erection w/o welding plate thickness [mm] efect [kg/Mhr] 5,0 5,50 6,0 6,50 7,0

mm x 0,03937 = inch m x 3,281 = ft 2 Mhr/m x0,0929 = Mhr/sq ft kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

Erection and welding* [kg/Mhr]

* welding: 20 % SMAW; 40 % MAG; 40 % automated machine 2.6.4 Installation of sleeves and reinforcements for the floating roof supports (legs) Erection w/o Erection and welding welding (SMAW) [Mhr/ea] [Mhr/ea] Installation of manholes on the floating roof Erection w/o welding - manhole to the storage tank through the floating roof [Mhr/ea] - manhole to the floating roof chambers [Mhr/ea] - welding not included

2.6.5

Erection and welding (SMAW) [Mhr/ea] [Mhr/ea]

79

2.6.6

Foam wall installation Erection and welding [kg/Mhr]


mm x 0,03937 = inch m x 3,281 = ft Mhr/m2 x 0,0929 = Mhr/sq ft kg/Mhr x 2,2046 = lbs/Mhr Mhr/m x 0,3048 = Mhr/ft

2.6.7

Preparation and raising the floating roof to the surface Storage tank capacity to 10.000 m 3 10.000 20.000 m 3 20.000 30.000 m 3 30.000 50.000 m 3 above 50.000 m 3

= = = = =

[Mhr/ea] [Mhr/ea] [Mhr/ea]

+ + +

Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3

2.6.8

Installation of floating roof supports (legs) Erection and welding (SMAW) [Mhr/ea] Placing the packers under the legs Erection and welding (SMAW) [Mhr/ea]

2.6.9

2.6.10Erection of supporting structure (spider net) The supporting structure (spider net) is generally made of the remaining pipes or sections. It is made to the elevation at which the floating roof is supported on its supports or min. 1500 mm. To estimate the quantity of the supporting structure, the roof load of 110 130 kg/m2 should be considered (total roof weight to be divided by the lower slab surface area). - Steel structure quantity: - Erection and dismantling effect: c. [kg/m2 ] [kg/Mhr]

m3 x 35,32 = cuft kg/m2 x 0,2048 = lbs/sqft

2.7

AUXILIARY STRUCTURE 2.7.1 Erection and welding of spiral stairs and landings [kg/Mhr] 2.7.2 Erection and welding of inclined stairs and landings [kg/Mhr] 2.7.3 Erection and welding of vertical stairs and ladder cages [kg/Mhr] 2.7.4 Erection and welding of sliding stairs with a bearing and a guide Erection and welding of a foam ejector holder [kg/Mhr] 2.7.6 Erection and welding of prefabricated railings [kg/Mhr]

[kg/Mhr]

2.7.5

80

2.8

CONNECTIONS AND OPENINGS 2.8.1 Manholes on the shell (generally welded during prefabrication) Installation and welding (SMAW) [Mhr/ea]

Manhole 20 24 30 36 2.8.2

Installation [Mhr/ea]

Cleaning door (generally welded during prefabrication) Installation [Mhr/ea] Installation and welding (SMAW) [Mhr/ea]

Dimensions 8 x 16 (203,2 x 406,4) 24 x 24 (609,6 x 609,6) 36 x 48 (914,4 x 1219,2) 48 x 48 (1219,2 x 1219,2) 2.8.3

Connection points with a flange on the shell 1 1/2 2 3 4 6 8 10 12 14 16 18 20 22 - Welding included [Mhr/ea] 24 26 28 30 32 34 36 38 40 42 44 46 48 [Mhr/ea]

2.8.4

Connection points with a thread on the shell 3/4 1 1 1/2 2 3 - Welding included [Mhr/ea]

2.8.5

Manholes on the roof 20 (508,0) 24 (609,6) Installation [Mhr/ea]

Installation and welding (SMAW) [Mhr/ea]

81

2.8.6 Connection points with a flange on the roof 1 1/2 2 3 4 6 8 10 12 2.8.7 Connection points with a thread on the roof 3/4 1 1 1/2 2 3 4 - Welding included [Mhr/ea] [Mhr/ea]

2.9

STORAGE TANK EQUIPMENT 2.9.1 Floating roof guide railing Installation and welding [kg/Mhr] 2.9.2 Installation of floating roof drainage - Installation of precipitation drain valve with a lever - Installation of a flexible steel pipe assembly - Installation of a flexible drain hose of synthetic material Installation of air vent valves - on fixed roof - on floating roof Installation of sampling and inspection holes [Mhr/ea] 2.9.5 Placing davits and welding [kg/Mhr]

[Mhr/ea] [kg/Mhr] [Mhr/ea]

2.9.3

[Mhr/ea] [Mhr/ea]

2.9.4

2.9.6 Installation of level indicators -for fixed roof - for floating roof - connections not included

[Mhr/package] [Mhr/ package]

kg/Mhr x 2,2046 = lbs/Mhr

82

2.9.7

Erection and welding of a floating roof seal 1. General American Transportation Corporation / Wiggins - "Safety seal" 2. Pittsburgh Des Moines Steel Comp. - "Hydroseal" - "Hammond Tubeseal" - "Hammond Spring - Tite seal" 3. Chicago Bridge & Iron Company - Seal "SR - 1" - Seal "SR - 3" - Seal "SR - 5" - Seal "SR - 7" - Seal "SR - 8" - Seal "SR - 9"

[Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m] [Mhr/m]

2.9.8

Installation of the storage tank bottom heating Pipe Diam. [Mhr/m] 1 1/2 2 3 - Bending, welding, supporting and tests included.

2.9.9

Installation of an energy-saving heater - Welding also included

[kg/Mhr]

2.10

FINISHING WORKS 2.10.1Stor age Tank Hydrostatic Testing Volume to 5.000 m3 5.000 10.000 m3 10.000 20.000 m3 20.000 30.000 m3 30.000 40.000 m3 40.000 50.000 m3 above 50.000 m3 2.10.2Stor age Tank Final Cleaning - Hydrostatic testing performed with water from the hydrant network - Hydrostatic testing performed with silt water Hours [Mhr/ea] + [Mhr/ea] + [Mhr/ea] +

3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m 3 Mhr/1000m

[Mhr/m2] tank bottom surface area [Mhr/m2] tank bottom surface area

1000 m3 = 35320 cu ft Mhr/m x 0,3048 = Mhr/ft kg/Mhr x 2,2046 = lbs/Mhr 2 Mhr/mx 0,0929 = Mhr/sq ft

83

3. ERECTION OF SPHERICAL AND SPHEROIDAL STORAGE TANKS For this kind of works I neither had available nor was familiar with any bibliography that would provide me with practical parameters and man hours for a technical calculation. Only John S. Page (USA) provided some tables for spheroidal storage tanks to 800.000 gallons (3.028 m3) and spherical storage tanks to 200.000 gallons (757 m3). I found his manhour calculation too stringent. They allow for too few hours for erection. During my practice I had to make the calculations for such storage tanks many times. I did it in the following way: 1. Unloading & storing material 2. Shell welding Calculate the weld runs and determine the hours according to the tables under the Chapter VI/4 Welding of Spherical Storage Tanks [Mhr/ton]

3. Assembling prefabricated plates and supports of tank Shell welding manhours x 4. Placing and welding the connections and equipment Use man hours for cylindrical storage tanks and other respective items 5. Hydrostatic Testing [Mhr/m3] hours at least

84

VI. WELDING AND FLAME CUTTING


Productivity efficiency percentage (PEP) = 70% 1. MANUAL ARC WELDING OF CYLINDRICAL TANKS - SMAW (Man hours for calculation)

1.1 Fillet joint

Overlap joint

Plate thickn. "b" [mm] 3 4 5 6 7 8 9 10 12 14 15 16 18 20 22 24 25

Weld reinforc. "a" [mm] 2,1 2,8 3,5 4,2 5,0 5,6 6,4 7,1 8,5 8,9 10,6 11,3 12,7 14,1 15,6 17 17,5

Deposit weight [kg/m] 0,07 0,09 0,13 0,18 0,25 0,33 0,41 0,5 0,75 1,04 1,18 1,33 1,62 2,14 2,52 2,9 3,1

FILLET 2F [m/Mhr] [Mhr/m]

VERTICAL 3F [m/Mhr] [Mhr/m]

OVERHEAD 4F [m/Mhr] [Mhr/m]

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

85

b
1.2 Single "V" butt joint

Distance thickn. "s" "b" [mm] [mm] 3 1 4 1,5 5 2 6 2 7 2 8 2 9 3 10 3 11 3 12 3 14 3 16 3 18 3 20 3 22 3 25 3 28 3


Plate

Angle " 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60

Deposit HORIZONT AL VERTICAL HORIZ. VERTIC. OVERHEAD weight 1G 3G 2G 4G [kg/m] [m /M h r ] [M h r /m ] [m /M h r ] [M h r /m ] [m /M h r ] [M h r /m ] [m /M h r ][M h r /m] 0,08 0,12 0,2 0,26 0,33 0,41 0,53 0,67 0,78 0,9 1,15 1,41 1,96 2,14 2,58 3,2 3,87

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

86

1.3.Double "V" butt joint

Plate thickn. "s" [mm] 10 11 12 14 15 16 18 20 22 24 25 26 28 30 32 34 36 40

Distance "b" [mm] 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Deposit weight [kg/m] 0,45 0,51 0,57 0,77 0,86 0,94 1,12 1,34 1,56 1,76 2,13 2,26 2,53 2,85 3,13 3,45 3,79 4,57

VERTICAL 3G

HORIZ.-VERTIC. 2G [m/Mhr] [Mhr/m]

[m/Mhr]

[Mhr/m]

NOTE : Double V butt joint can also appear under different angles, also under irregular. In that cases standard is calculated with value for single V butt joint.

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

87

S1 S

c b 50

Area = ( 0,25 x s1 x 2tg ") + ( s x b )

1.4 Double bevel butt joint

Plate s mm 10 12 14 15 16 18 20 22 25 30 35 40

Angle

"
50 50 50 50 50 50 50 50 50 50 50 50

b 3 3 3 3 3 3 3 3 3 3 3 3

MEASURES [mm] c s1 2 13 2 15 2 18 2 19 2 20 2 22 2 24 2 26 2 29 2 36 2 41 2 46

Area [mm] 81 104 139 153 168 199 233 269 327 479 609 755

Deposit Weight [kg/m ] 0,63 0,82 1,09 1,2 1,32 1,56 1,83 2,11 2,57 3,76 4,78 5,93

HORIZ . - VERTICAL 2G [m/Mhr] [Mhr/m]

NOTE : When horizontal joints of the tank shell are welded by SMAW process, two different thickness mostly are used. In that case a mean value is used for operating time.

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

88

= 45 b

s1

1.5 Single bevel butt joint

"s" [mm] 5 6 7 8 9 10 11 12 12 14 15 16 18 20 22 24

"b" [mm] 12 12 12 23 23 23 23 23 23 23 23 23 23 23 23 23

Weight [kg/m] 0,244 0,313 0,41 0,58 0,686 0,8 0,922 1,079 1,31 1,464 1,624 1,793 2,154 2,547 2,971 3,426

HORIZ. - VERTICAL (2G) [Mhr/m] [m/Mhr]

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

89

2. SUBMERGED ARC WELDING (Data for calculation) 2.1 Welding machine "Lincoln Lt-3"

2.1.1 Welding of overlap joint Wire EPP - 2 4 mm


s [mm] a [mm] v [cm/min] Number of Passes

s s

Wire EPP - 2 3 mm
s a [mm] [mm] v [cm/min] Number of Passes

[Mhr/m] [m/Mhr]

[Mhr/m] [m/Mhr]

5 5,5 6 6,5 7

3,5 4 4,5 5 5,5

85 75 65 54 42

1 1 1 1 1

5 5,5 6 6,5 7

3,5 4 4,5 5 5,5

80 70 60 50 38

1 1 1 1 1

v = travel speed

2.1.2 Welding of fillet joint ( bottom shell, internal site )

Wire EPP - 2 4 mm
a [mm] v [cm/min] Number of Passes a [mm]

Wire EPP - 2 3 mm
v [cm/min] Number of Passes

[Mhr/m]

[m/Mhr]

[Mhr/m]

[m/Mhr]

8 9

18 14

3 3

8 9

13,5 10,5

3 3
mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

v = travel speed

90

2.2 Machine welding, "ESAB A-2T"

2.2.1 Welding of overlap joint Wire EPP - 2 4 mm


s [mm] a [mm] v [cm/min] Number of Passes

s s

Wire EPP - 2 3 mm
s [mm] a [mm] v [cm/min] Number of Passess

[Mhr/m] [m/Mhr]

[Mhr/m]

[m/Mhr]

5 5,5 6 6,5 7

3,5 4 4,5 5 5,5

85 75 65 55 50

1 1 1 1 1

5 5,5 6 6,5 7

3,5 4 4,5 5 5,5

80 70 60 50 45

1 1 1 1 1

v = travel speed

2.2.2 Welding of fillet joint ( bottom shell, inside of tank ) Wire EPP - 2 4 mm Wire EPP - 2 3 mm

a [mm]

v [cm/min]

Number of Passes

a
a [mm]

[Mhr/m]

[m/Mhr]

v [cm/min]

Number of Passes

[Mhr/m]

[m/Mhr]

8 9

18 14

3 3

8 9

13,5 10,5

3 3

v = travel speed

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

91

2.3 Welding with Vertomatic "ARCOS" Gas shielded, flux cored welding rod - outershield

s mm 36 35 32 30 28 25 24 22 20 20 16 15 14 13 12 11 10 20 16 15 14 13 12 11 10 9 8 7

TY PE OF JOINT

a mm 3 3 3 2 2 2 2 2 2 3 2 2 2 2 2 2 2 13 12 11 11 11 11 11 11 11 11 11

b mm 17 16.6 15.6 13.6 12.7 11.5 11.1 10.3 9.5 19 15 12.4 11.6 10.7 10 9.1 8.3

v cm/min 6.3 6.5 6.8 7.2 7.5 8.3 8.7 9.1 10 11.7 14.9 15.8 17 18.3 19.9 20 20 7 8.7 9.2 9.9 10.7 11.6 11.7 11.7 13.1 14.7 16.8

Mhr/Vertical Weld Height of One Vertical Weld [mm] to 1600 1800 2000 2200 > 2400

s s
s

v = travel speed When calculating the welding time for one tank shell, the following to be added: - Lifting welding machine on tank shell - Taking off welding machine from tank shell - Shifting welding machines from one tank shell to another tank shell

Mhr Mhr Mhr

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

92

2.4 Welding with Circomatic "ARCOS" When calculating the welding time for each horizontal joint, to be added: Positioning and taking off welding machine: Mhr

platenumber travel speed mm of passes [cm/min] 6 6 1 6075 6 8 1 6070 8 10 1 6065 10 13 1 5560 23 13 45 16 1 5055 16 18 1 4550 18 22 2 2227 22 25 3 1215 45 27 30 4 911 35 40 6 68 Root pass, SMAW using Ductilend 55 stick welding rod
01

TYPE OF JOINT

rate [m/Mhr] [Mhr/m]

22 45 25 5 810 27 30 6 68 35 40 9 4,55,5 Root pass will be calculated acc. to the man hour for SMAW.
3

01

01

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

93

2.5 Welding with Circomatic "ESAB" Welding with flux-cored welding rods outershield. TYPE OF JOINT
BEFORE FILLING WITH SAW, FIRST PASS WILL BE WELDED BY SMAW OR GMAW PROCESS
01

Plate mm 8 10 10 12 12 14 14 17 17 20 20 23 23 26 26 30 8 8 8 10

Number of Passes 2

Travel Speed Rate [cm/min] [m/Mhr] [Mhr/m] 3035

2 4 6 6 8 10 12 2 2

3035 1420 1015 912 69 58 46 3436 3436

45
01

45
3

ROOT PASS FULL PENETRATION - SMAW

45

10 13 13 16 16 18 18 21 21 24

4 4 4 6 7

1720 1619 1518 911 710

Root pass full penetration will be calculated according to SMAW or GMAW process. When calculating the welding time for each horizontal joint, to be added: - Each shifting of welding machine (the number of shifting is defined by weld eng.) - Positioning and taking off - When two welding machines are used (simultaneos from both sides) positioning and taking off Mhr

Mhr

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

Mhr

94

3. WELDING WITH SEMIAUTOMATIC (GMAW) (Data for calculation) 3.1 Semiautomatic - GMAW (CO) 2

3.1.1 Welding of fillet joints

s mm 3 4 5 6 7 8 9 10 12 14 16 18 20 22 24

a mm 2,1 2,8 3,5 4,2 5 5,6 6,4 7,1 8,5 8,9 11,3 12,7 14,1 15,6 17

Deposit Weight [kg/m] 0,07 0,09 0,13 0,18 0,25 0,33 0,41 0,5 0,75 1,04 1,33 1,62 2,14 2,52 2,9

HORIZONTAL (2F) [Mhr/m] [m/Mhr]

S
VERTICAL (3F) [Mhr/m] [m/Mhr]
mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

95

3.1.2 Welding of single "V" butt joint

60

s mm 4 5 6 7 8 9 10 11 12 14 16 18 20

Angle

"
60 60 60 60 60 60 60 60 60 60 60 60 60

b mm 1,5 2 2 2 2 3 3 3 3 3 3 3 3

Deposit Weight [kg/m ] 0,12 0,2 0,26 0,33 0,41 0,53 0,67 0,78 0,9 1,15 1,41 1,76 2,14

HORIZONTAL (1G) [Mhr/m] [m/Mhr]

VERTICAL (3G) [Mhr/m] [m/Mhr]

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

96

3.1.3 Welding of double "V" butt joint

s mm 12 14 15 16 20 22 24 25 26 28 30 32 34 36 40

b mm 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

= 60 Deposit Weight [kg/m] 0,57 0,77 0,86 0,94 1,34 1,56 1,76 2,13 2,25 2,53 2,85 3,13 3,45 3,79 4,57

s
b mm 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 = 45 Deposit Weight [kg/m] 0,39 0,52 0,59 0,77 0,92 1,07 1,2 1,46 1,55 1,73 1,95 2,14 2,37 2,6 3,13

VERTICAL (3G) [Mhr/m] [m/Mhr]

s mm 12 14 15 18 20 22 24 25 26 28 30 32 34 36 40

VERTICAL (3G) [Mhr/m] [m/Mhr]

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

97

3.1.4 Welding of double-bevel butt joint


mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

=50

S1

When hori zontal joints of the tank shell are welded two diff erent thicknesses mostly occur ( S = S1 ) in which case a mean value is used for the man hour time.

s b mm mm 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3

10

11

12

13

14

15

16

18

20

22

24

Deposit Weight [kg/m] 0,47 0,55 0,63 0,54 0,63 0,72 0,62 0,71 0,8 0,74 0,84 0,94 0,82 0,93 1,04 0,96 1,08 1,2 1,06 1,18 1,31 1,27 1,43 1,6 1,5 1,68 1,86 1,75 1,94 2,14 2,08 2,27 2,46

H O R I Z . - V E RT I C . (2G) [Mhr/m] [m/Mhr]

s mm

b mm 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3

25

26

27

28

30

32

34

35

36

38

40

Deposit Weight [kg/m] 2,3 2,49 2,69 2,59 2,81 3,03 2,75 2,98 3,2 2,92 3,14 3,36 3,26 3,5 3,73 3,62 3,88 4,13 4,0 4,27 4,54 4,2 4,48 4,75 4,4 4,69 4,97 4,82 5,12 5,42 5,26 5,57 5,89

HORIZ. - VERTIC. (2G) [Mhr/m] [m/Mhr]

98

3.1.5 Welding of single bevel butt joint


mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

s
= 45

When the tank shell horizontal joints are welded, two different thickness of plate are mostly used ( S = S1 ). In that case a mean v alue is used for manhour calculation.

s1

s mm 5 6 7

b mm 01 12 01 12 01 12 01 12 23 0 1 12 23 01 12 23 01 12 23 01 12 23 01 12 23 01 12 23 01 12 23 01 12 23

10

11

12

13

14

15

16

Deposit Weight [kg/m] 0,205 0,244 0,267 0,315 0,355 0,41 0,455 0,517 0,58 0,545 0,615 0,685 0,643 0,721 0,8 0,749 0,835 0,922 0,891 0,985 1,079 1,106 1,208 1,31 1,244 1,354 1,464 1,389 1,506 1,624 1,542 1,667 1,793

HORIZ. - VERTIC. (2G) [Mhr/m] [m/Mhr]

s mm

b mm 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 0 1 2 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3

18

20

22

24

25

26

27

28

30

32

34

Deposit Weight [kg/m] 1,872 2,013 2,154 2,233 2,39 2,547 2,625 2,798 2,971 3,049 3,237 3,426 3,273 3,469 3,665 3,505 3,709 3,913 3,744 3,956 4,168 3,991 4,211 4,431 4,509 4,744 4,98 5,059 5,31 5,561 5,64 5,907 6,174

HORIZ. - VER TIC. (2G) [Mhr/m] [m/Mhr]

99

4. WELDING OF SPHERICAL STORAGE TANKS

Upper section Upper strip Horizontal Equator Vertical Lower strip Lower section

4.1 Manual welding of slices of lower and upper section Plate Thickness [mm] 14 15 16 17 18 20 22 Deposit Weight [kg/m] 0,73 0,79 0,93 1,0 1,11 1,31 1,56 Rate [Mhr/m] Plate Thickness [mm] 24 25 26 27 28 29 30 Deposit Weight [kg/m] 1,82 1,94 2,12 2,26 2,43 2,54 2,73 Rate [Mhr/m] Plate Thickness [mm] 32 34 35 36 37 38 40 Deposit Weight [kg/m] 3,04 3,48 3,65 3,97 4,1 4,23 4,77 Rate [Mhr/m]

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

100

4.2 Manual welding of vertical joint of Equator, upper and lower section Plate Thickness [mm] 14 15 16 17 18 20 22 24 25 26 27 28 29 30 32 34 35 36 38 40

EQUATOR [Mhr/m]

UPPER STRIP [Mhr/m]

LOWER STRIP [Mhr/m]

mm x 0,03937 = inch kg/m x 0,672 = lbs/ft m/Mhr x 3,281 =ft/Mhr Mhr/m x 0,3048 = Mhr/ft

4.3 Manual welding of horizontal joints Plate Thickness [mm] 14 15 16 17 18 20 22 24 25 26 27 28 29 30 32 34 35 36 38 40 LOWER SECTION LOWER STRIP [Mhr/m] LOWER STRIP EQUATOR EQUATOR UPPER STRIP [Mhr/m] [Mhr/m] UPPER STRIP UPPER SECTION [Mhr/m]

101

5. MANUAL GAS CUTTING AND GAS CONSUMPTION Plate Thickness [mm] 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Cutting Speed [m/hr] Rate [Mhr/m] Oxygen [kg/m]* 0,0323 0,04 0,0466 0,0525 0,0625 0,0715 0,079 0,0875 0,096 0,106 0,115 0,126 0,1375 0,14 0,1525 0,1745 0,186 0,197 0,207 0,2175 0,226 0,237 0,244 0,252 0,259 0,266 0,273 0,279 0,285 0,29 0,295 0,3 0,304 0,308 0,311 0,314 0,316 0,318 Acetylene [kg/m]* 0,0064 0,0073 0,0082 0,009 0,0097 0,0104 0,0111 0,0117 0,0123 0,0121 0,0135 0,014 0,0145 0,015 0,0155 0,0161 0,0167 0,0174 0,018 0,0188 0,0195 0,0202 0,0208 0,0215 0,0221 0,0227 0,0233 0,0238 0,0244 0,0249 0,0256 0,0259 0,0264 0,0268 0,0272 0,0277 0,0281 0,0285
mm x 0,03937 = inch m/hr x 3,281 = ft/hr

* Theoretical consumption of gas for machine gas cutting Mhr/m x 0,3048 = Mhr/ft (acc. to ivi-Remenar) kg/m x 0,672 = lbs/ft The consumption of gas for manual cutting is c. % higher. To estimate the oxygen and acetylene needed for manual gas cutting double the above values. NOTE: Man hours [Mhr/m] are used for cutting only to 30 m. Man hours for larger lengths to be estimated according to the cutting speed [m/hr].

102

VII. CORROSION PROTECTION


1. SAND BLASTING AND PAINTING OF PIPING Dn-mm 15 20 25 32 40 50 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200 1350 1500 -Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 54 60 OD-mm 21,3 26,7 33,4 42,2 48,3 60,3 73 88,9 114,3 141,3 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 965 1016 1067 1118 1168 1219 1372 1524

Productivity Efficiency Percentage (PEP) = 80%

SURFACE AREA OF PIPING ELEMENTS


Pipe 1m [m2] 0,067 0,083 0,105 0,132 0,151 0,19 0,24 0,28 0,36 0,44 0,53 0,69 0,86 1,02 1,12 1,28 1,43 1,60 1,75 1,92 2,07 2,24 2,39 2,56 2,71 2,88 3,03 3,20 3,35 3,52 3,66 3,83 4,31 4,79 Elbow r=1,5d [m2] 0,003 0,005 0,008 0,013 0,017 0,027 0,039 0,058 0,097 0,120 0,210 0,472 0,552 0,776 0,936 1,222 1,545 1,910 2,312 2,754 3,223 3,741 4,297 4,891 5,524 6,182 6,891 7,639 7,639 8,425 10,095 10,996 13,930 17,187 TEE [m2] 0,003 0,004 0,007 0,011 0,015 0,023 0,035 0,050 0,082 0,124 0,178 0,302 0,470 0,661 0,797 1,040 1,307 1,626 1,957 2,342 2,732 3,185 3,642 4,163 4,683 5,265 5,848 6,502 7,149 7,871 8,550 9,338 11,827 14,600 Reducer [m2] 0,002 0,003 0,005 0,006 0,009 0,013 0,019 0,022 0,033 0,050 0,067 0,094 0,138 0,186 0,333 0,410 0,490 0,732 0,800 0,878 1,136 1,230 1,312 1,405 1,488 1,581 1,663 1,757 2,144 2,252 2,342 2,451 2,758 3,065 Flange [m2] 0,012 0,017 0,020 0,023 0,030 0,035 0,046 0,056 0,080 0,096 0,120 0,170 0,230 0,260 0,300 0,350 0,390 0,420 0,460 0,490 0,520 0,560 0,600 0,630 0,670 0,700 0,740 0,780 0,800 0,840 0,980 0,920 1,020 1,120 Valve [m2] 0,030 0,036 0,043 0,054 0,065 0,147 0,185 0,173 0,297 0,390 0,460 0,660 0,890 1,190 1,570 1,790 2,220 2,520 3,220 3,920 3,800 3,850 4,330 4,820 5,320 5,820 6,450 7,100

RATES FOR PIPES


Blast and First Coat [Mhr/m2] Two Middle Coats

[Mhr/m2 ]

TOTAL TOTAL Coat Four Coats Four Coats [Mhr/m2] [Mhr /m 2] [Mhr/m]
Covering

-Inch 1/2 3/4 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 54 60

103

1.1 RATES FOR PIPING ELEMENTS - Pipes: above table - Elbows: [Mhr/m2 ]x - Tees: [Mhr/m2 ]x

- Reducers: - Flanges: - Valves:

[Mhr/m2 ]x [Mhr/m2 ]x [Mhr/m 2]x

1.2 MATERIAL CONSUMPTION - acc. to Item 2 (page 104)


m x 10764 = sq ft Mhr/m2 x 0,0929 = Mhr/sq ft Mhr/m x 0,3048 = Mhr/ft
2

2. 2.1

SAND BLASTING AND PAINTING OF STEEL STRUCTURES Sand blasting and primer: Material Consumption: siliceous sand for the purity grade SA 2 1/2 [kg/m2] or: corrund (Al2O3) for the purit y grade SA 2 1/2 or: [kg/m2] [Mhr/m2] + [Mhr/m2] = [Mhr/m2]

ground dross for the purity grade SA 2 1/2 [kg/m2] hot (metal sand) [kg/m2]

or:

2.2 2.2.1

Next Coats Up to 100 microns: by brush by spray gun colour by brush by spray gun [Mhr/m2] [Mhr/m2] [kg/m2] [Mhr/m ] 2 [Mhr/m ] [kg/m2]
2

Material consumption: 2.2.2 Above 100 microns:

Material consumption:

NOTE: 1. Consumption of the abrasive material depends on the corrosion pitting of the structure, wind, space and the possibility of regeneration of the abrasive used. 2. Paint consumption depends on the corrosion pitting, coat thickness, wind, and the manufacturer's instructions. 2.3 2.3.1 Time allowances for job conditions Work at elevations to 2 m 2 4m 4 10 m above 10 m Work inside - with ventilation - no ventilation 2.3.3 Work in lumbered rooms (space obstruction) + + + % % %

no allowances + % + % + %

2.3.2

104

2.4 2.4.1

MEASUREMENT AND CALCULATION OF QUANTITIES FOR CORROSION PROTECTION Machines, motors, pumps, conveyors A surface area of parallelopiped shape x

2.4.2

Steel Structure - Heavy structure - Medium-weight structure - Light structure - Floor grids: - Ladders and step iron: - Mesh railings: - Flat sheets: - Corrugated sheets: (above 60 kg/m): (31 60 kg/m): (to 30 kg/m): length x width x length x width length x height x actual painting area actual painting area x [m2/ton] [m2/ton] [m2/ton]

2.4.3

Pipe Supports - for piping - for piping to 4 above 4 [m /ton] 2 [m /ton]


2

3. 3.1

SAND BLASTING AND PAINTING OF STO Outer surfaces of storage tank - Sand blasting SA 2 1 2 : - First coat 75 : - Second coat 40 : - Third coat 125 : - Fourth finishing coat 50 : Total = 290 : Inner surfaces of storage tank - Sand blasting SA 2 1 2 : - First coat 40 : - II + III + IV coat 400 : Total = 440 :

RAGE TANKS

[Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2]

3.2

[Mhr/m2] [Mhr/m2] [Mhr/m2] [Mhr/m2]

NOTE: These man hours refer to the climate conditions prev ailing in the Centr al Europe.

105

VIII. THERMAL INSULATION


Productivity Efficiency Percentage (PEP) =85% Generally, specialized companies make calculations for insulation. This rule also applies if insulation accounts for a large portion of a project. When the scope of insulation is not so great or the bidding time is very tight, an estimator for the mechanical works should also provide the calculation elements for the insulation. That is why I worked out the manhour rates for insulation based on the manhour rates of several specialized German insulation contractors. 1. THERMAL INSULATION FOR PIPING Prefabrication of the insulation holders, sheet cutting, placing mineral wool, aluminium foil cladding, installation of sheets and sealing with durable elastic compound. 1.1 Pipe insulation Manhours per linear metre [Mhr/m]
Piping ND 25 1 32 1 1/4 40 1 1/2 50 2 65 2 1/2 80 3 100 4 125 5 150 6 200 8 250 10 300 12 350 14 400 16 450 18 500 20 600 24 700 28 800 32 900 36 1000 40 Insulation Thickness [mm] 60 80 100

30

40

50

120

150

- Insulation of pipes and fittings, except for pipe bends is included. - Insulation of valves not included. - Scaffolding not included.

mm x 0,03937 = inch Mhr/m x 0,3048 = Mhr/ft

106

1.2

Insulation of pipe bends [Mhr / ea] Piping ND 25 1 32 1 1/4 40 1 1/2 50 2 65 2 1/2 80 3 100 4 125 5 150 6 200 8 250 10 300 12 350 14 400 16 450 18 500 20 600 24 700 28 800 32 900 36 1000 40 Insulation Thickness [mm] 60 80 100 120

30

40

50

150

1.3

Valve Insulation ND 25 32 40 50 65 80 100 125 150 200 250 1 1 1/4 1 1/2 2 2 1/2 3 4 5 6 8 10 [Mhr/ea] ND 300 350 400 450 500 600 700 800 900 1000 12 14 16 18 20 24 28 32 36 40 [Mhr/ea] Factors acc. to Insulation Thickness 30 mm x 40 mm x 50 mm x 60 mm x 80 mm x 100 mm x 120 mm x 150 mm x

1.4 1.4.1

Piping insulation based on the surface area Surface area calculation

The pipe surface area is calculated by adding two insulation thicknesses to the pipe diameter. do = pipe OD [m ]
2

A=

( do + 2t ) x 3,14 1000

[mm] [mm]

t = insulation thickness

107

- Pipe bend surface area A = ( d+ 2t ) ( 2d +t) x o o [m] 2

do= pipe OD [m] t = insulation thickness [m] - Valve surface area Surface area of 1 m pipe x 1.4.2 Manhour rates [Mhr/m 2]

Insulation Thickness [mm] [Mhr /m2] Included:

30

40

50

60

80

100

120

150

Not includes: 1.4.3

- pipes - all fittings - valves - insulation holders - scaffolding

Division based on the operations - Insulation holders - Mineral wool and al. foil - Sheets % % % - Prefabrication - Erection - Prefabrication - Erection % % % %

2. 2.1

THERMAL INSULATION OF VESSELS AND KILNS Insulation with mineral wool, smooth aluminium sheets, durable elastic sealing including substructure Insulation Thickness 80 mm 100 mm 120 mm 150 mm 180 mm [Mhr/m2]

2.2

Insulation with mineral wool, trapezoidal galvanised E 40 sheets, 1-mm thickness, both side painting, durable elastic sealing substructure included. Insulation thickness 80 mm 100 mm 120 mm 150 mm 180 mm Scaffolding not included. [Mhr/m2]

mm x 0,03937 = inch m x 3,281 = ft m2 x 10,764 = sq ft Mhr/m2 x 0,0929 = Mhr/sq ft

108

IX. ESTIMATES
1. ESTIMATE OF SCAFFOLDS Quick estimates of scaffolding and the scaffolds are very difficult to make and not reliable. Estimators usually do not have the drawings, the dimensions and what is most important they do not have enough time to perform a proper calculation. Therefore, they have to make quick estimates of the quantities starting first with a decision on who is going to undertake the scaffolding. Will they subcontract this job to a specialist firm or do the scaffolding themselves? It is also necessary to see who will use the scaffolds. Will they be used for erection only, or for painting and insulation works as well? If there are several users, the rental period is longer but in that case the expenses can be shared. 1. ESTIMATES OF SCAFFOLDING WHEN CONTRACTED TO A SPECIALIST FIRM The most usual categorization and the rates of the scaffolding specialist firms are: a) Scaffold Erection - standing scaffolds - hanging scaffolds b) Scaffold Dismantling - same categorization as for erection c) Rental - same categorization per week and month The price of erection and dismantling of scaffolding varies by its height every m. When estimating the scaffolding quantity, the quantity for erection in [m3] and an average erection height are determined. 1.1 PIPING IN PLANTS - Quantity: - Type : [m3/t] piping weight standing scaffolds hanging scaffolds cantilever scaffolds platforms landings % % % % [m3 ] [m3 ] - cantilever scaffolds - platform floors [m 3] [m 2]

1.2

PIPING ON PIPERACKS - Quantity: - Type : Option I Pipe rack surface area Option II [m3/t] piping weight standing scaffold hanging scaffold cantilevel scaffold platforms floors average months [m2] scaffold % % % %

- Height : - Rental: 1.3

STEEL STRUCTURES - Quantity: - Type : [m3/t] structure weight standing % hanging % cantilever % platforms floors % average m average weeks 109

m3x 35,32 = cu ft m2 x 10764 = sq ft

- Height : - Rental:

1.4

EQUIPMENT IN PETROCHEMICAL PLANTS

When estimating the scaffolding for equipment erection one should know who is going to use the scaffolding. For instance, no scaffolding is required for erection of towers, but it is required for erection of connection piping, electrical installations, insulation or painting. The best way is to calculate all the equipment individually for each unit. Similarly, one should also determine the type of scaffolding, its height, and the rental time. When the scaffolding is used for the equipment erection only, it could be calculated in the following way: - Quantity: [m3/ton] equipment weight - Type: standing % platform floors % - Height: m - Rental: month

2.

ESTIMATE OF SCAFFOLDING WHEN DONE BY AN ERECTION COMPANY

This kind of scaffolding erection is used less and less. If used, the scope of scaffolding should be estimated in the same way as for the first case. 2.1 2.2 PIPING IN PLANTS: [m3/ton] piping quantity

PIPING ON PIPERACKS: Option I Pipe rack surface area = [m2] scaffold Option II [m3/ton] piping quantity STEEL STRUCTURES: EQUIPMENT IN PETROCHEMICAL INDUSTRY: (If used for the equipment erection only) [m3/ton] structure quantity [m3/ton] equipment quantity

2.3 2.4

2 When the scaffolding quantity is calculated in [m3] or [m], which is more or less the sam e we should estimate the material needed for tubular or patent scaffolding.

2.5

TUBULAR SCAFFOLDING

There are sets of tubular scaffolding with a list of material needed such as tubes and clamps for 500 m3 (Iron Works Sisak). If it is expected that the scaffolding will be erected and dismantled several times during the works execution, the following calculations should be considered: 2.5.1 Tubular scaffold material

Total scaffolding:

[m ] + [m ]

2 m3 or m

The scaffolding quantity to round up to hundred (100).

m3 x 35,32 = cu ft m2 x 10764 = sq ft

110

2.5.2

Planking tops for scaffolding Scaffold quantity / = m3 planking tops

2.6

SCAFFOLDING LABOUR

Determine the number of scaffolding hours by calculating: 2 Erection + dismantling = [Mhr/m3] or m x elevation factor (for average elevation)

(See "Equipment Scaffolding", page 72 - 73) After that, determine the labour needed for scaffolding and the means of transport.

111

2. ESTIMATE OF WELDING ROD CONSUMPTION AND ADDITIONAL WELDING MATERIAL 1. PIPING 1.1 WELD DEPOSIT [kg/weld]

2 3 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

Sch 10 0,009 0,011 0,017

Sch 20

Sch 30

0,263 0,3 0,337 0,376 0,413 0,45 0,73 1,27 1,36 1,459 1,542 1,633

0,161 0,186 0,239 0,393 0,449 0 505 , 0 907 , 0 992 , 1,089 2,172 2,336 2,506 2 671 , 28 ,4 3,003

0,39 0,493 0,576 0,625 0,726 1,501 1,67 1,84 2,255 3,43 3,674 3,92 4,164 4,409

Std 0,026 0,057 0,086 0,303 0,39 0,45 0,576 0,635 0,726 0,807 0,907 0,998 1,089 1,18 1,27 1,36 1,45 1,54 1,633

Sch 40 0,026 0,057 0,086 0,303 0,39 0,45 1,061 1,17 1,34 1,5 1,22 1,412 3,42

Sch 60

0,717 0,83 1,56 1,719 2,935 3,28 4,042 5,2 7,2

4,563 4,844 6,554

XS 0,043 0,085 0,208 0,558 0,717 0,83 1,061 1,17 1,338 1,5 1,67 1,84 2,0 2,172 2,336 2,504 2,671 2,84 3,003

Sch 80 0,043 0,085 0,208 0,558 0,717 1,215 2,554 3,0 3,783 5,4 9,743 10,72 12,67

Sch 120

0,383 0,821 1,565 2,345 3,81 5,19 5,92 9,58 12,52 15,94 21,42

Sch 160 0,104 0,255 0,562 1,215 2,576 3,674 6,776 8,77 11,59 17,0 19,61 24,56 31,33

XXS 0,213 0,375 0,835 1,58 2,03 3,27 3,81

kg/weld x 2,2046 = lbs/weld 1.2 PIPING IN PLANTS

The most difficult job for installation of this t ype of piping is to estimate welding rod consumption with regard to the piping weight. Since this estimate is not used for the welding rod procurement but f or calculation of price only, higher departures than the actual needs are allowed. 1.2.1 If the number of welds is known then they are calculated according to the T able 1.1 with a final increase of % (for smaller modifications, repairs, losses, etc.). If the number of welds is not known and it cannot be deter mined within a reasonable time, then the calculation should be done as follows:

1.2.2

Welding rod weight = % piping weight or [kg/ton] (Higher percentage is inversely proportionate to the pipe weight in relation to the total weight of piping). 1.2.3 Piping quantity per inchdiameter (ID) Welding rod weight = [kg/ID]

112

1.3 1.3.1

PIPING BETWEEN PLANTS AND PIPING ON PIPERACKS If the piping quantities are listed according to their diameters then the weld is assumed to come on average every 6 meters of the piping length. The number of joints estimated to be multiplied by the values from Table 1.1 and increased by %. If only the total piping weight is known: % of the piping weight or [kg/ton]

1.3.2

Welding rod weight =

1.4

PIPING (C.S.) - TOWN NETWORKS

- The best way is to estimate the number of joints and to use the Table 1.1 for the quantity of welding rod, and to apply the increase of %. 1.5 PIPELINES

- For this type of pipelines the number of joints on the header line should alwa ys be calculated. The calculation will be done with the weights from T able 1.1 increased by %. 1.6 1.6.1 PIPE SUPPORTS Support Fabrication % support weight or [kg/ton]

Welding rod weight = 1.6.2

Support Installation % support weight or [kg/ton]

Welding rod weight =

2.

STEEL STRUCTURES Fabrication Erection %or %or %or [kg/ton] [kg/ton] [kg/ton]

- Heavy structure - Medium-weight structure - Light structure

%or %or %or

[kg/ton] [kg/ton] [kg/ton]

3.

CYLINDRICAL STORAGE TANKS % storage tank weight

Welding rod weight =

4.

EQUIPMENT IN PETROCHEMICAL INDUSTRY % equipment weight


kg/ton x 2,2046 = lbs/ton

Welding rod weight=

113

3. ESTIMATE OF CONSUMPTION OF TECHNICAL GAS AND GRINDING PLATES

In plants Oxygen Acetylene Argon (2.*) Grinding & cutting plates [kg/ton] [kg/ton] [kg/ton] [pc/ton]

P I P I N G Piping between plants and town networks Pipelines

Pipe supports

Erection Equipi ment Cylindr . of steel petrochemical storage structures plants tanks

1. The quantities of other technical gas such as hydrogen, nitrogen, and CO2 are negligible and I leave it up to the estimator to estimate their quantities or not. 2.* The quantity of argon depends on the welding method and use of different types of materials. The above data of kg/t is taken into account when there is some % of stainless steel and when the root on carbon steel is welded by TIG process. If the quantity of stainless steel is known, than the calculation is done by kg/ton. 3. Technical Gas Data: - Oxygen 40 l bottle, 150 bar = 50 l bottle, 200 bar = - Acetylene40 l bott le, 15 bar= 50 l bottle, 15 bar= - Argon 40 l bottle, 150 bar = 40 l bottle, 200 bar = 50 l bottle, 200 bar = 40 l bottle, 60 bar= small bottle (27,2 l) large bottle (79 l) small bottle (27,2 l) large bottle (79 l)

6 m3 = 10 m3 = 6,5 m3 = 8,1 m3 = 6,4 m3 = 8,8 m3 = 10 m3 = 6m = = = = = 6 m3 = 10 m3 =


3

kg kg kg kg kg kg kg kg kg (max.) kg (max.) kg (max.) kg (max.) kg kg

- CO2 - Propane

- Butane

- Nitrogen40 l bott le, 150 bar = 50 l bottle, 200 bar =

114

4.

Calculating the quantities of nitrogen or air required for pressure testing The quantity of nitrogen or air is calculated by the following formula:

m=

(p) x V x 100.000 2 p 1 TxR

[kg]

kg x 2,2046 = lbs

where:

m = gas weight [kg] p2 = final pressure [bar] p1= starting pressure [bar] V = system volume (to be tested) [m3] T = temperature [K] ( = C + 273,15) R = gas constant [J/kgK] Rair = 287 ,0 [J/kgK] Rnitrogen = 296,7 [J/kgK]

EXAMPLE: A 50 m3 system should be tested to 10 bars. The pressure can be increased to 6 bars by air compressor. Outside temperature is c. 17 C (290 K). How much nitrogen and how many bottles do we need?

m=

(10- 6 ) x 50 x 100.000 290 x 296,7

= 232,44 kg

the number of 40 l bottles, 150 bar : 232,44 / 7,55 = 31 bottles

4.

ESTIMATE OF ELECTRICITY CONSUMPTION

The client often requires an estimate of electricity consumption it has to provide and the estimator must fulfil that request. If he finds that the contractor will use its own power sources from generators and generating sets, then he will estimate only the part of electricity consumption from the power grid. The total power requirements should be calculated on the basis of an estimate of the welding rods needed. 1. Piping 1.1 In plants 1.2 Piping between plants 1.3 Pipelines 2. Erection of steel structure 3. Equipment erection 4. Storage tank erection [kWh/kg] welding rod quantity [kWh/kg] welding rod quantity [kWh/kg] welding rod quantity [kWh/kg] welding rod quantity [kWh/kg] welding rod quantity [kWh/kg] welding rod quantity

kWh/kg x 0,4536 = kWh/lbs

115

5. ESTIMATE OF CONSUMPTION OF FUEL AND LUBRICANT The manufacturer provides the technical data on fuel consumed by the machinery. Such data can be used only if the motor operates continuously under the load foreseen by the manufacturer. However, this is not the case in practice because there are stoppages in operation and the machinery operates under different loads. Below is an estimate of the percentage use of the machinery and the means of transport that the estimator can evaluate at his discretion.

1. FUEL CONSUMPTION Machinery/Means 1. Power Plant 125 kW 2. Diesel Welding Set 400 A 3. Diesel Compressor 7 m 3/min 4.Pipe Laying Machine 5. Tractor 53 kW (72 HP) 6. Tractor 88 kW (120 HP) 7. Fork Lift 3 t 8. Fork Lift 5 t 9. Tank truck 10. Truck 7,5 t 11. Truck 10 t 12. Trailer truck 13. Pickup 14. Passenger van 8 + 1 seat 15. Passenger car Fuel Diesel oil Diesel oil Consumption l/h l/h % use % % l/day l/month

Diesel oil Diesel oil Diesel oil Diesel oil Diesel oil Diesel oil Diesel oil Diesel oil Diesel oil Diesel oil Gasoline Gasoline Gasoline

l/h l/h l/h l/h l/h l/h l/100 km l/100 km l/100 km l/100 km l/100 km l/100 km l/100 km

% % % % % % km/day km/day km/day km/day km/day km/day km/day

NOTE: The fuel consumption for other machinery (cranes, shovels, dredgers and the like) is not calculated because the price of fuel and lubricants is already contained in the rental fee.

2. LUBRICANT CONSUMPTION Since oil and grease are also used for other purposes at the job site and not only for the machinery, the price of lubricants can be calculated as % of the fuel prices.

l x 0,2642 = U.S. gal

116

6. TOOL COST ESTIMATE AT THE JOB SITE It is not either possible or necessary to make detailed lists of small tools to be used at the job site. In practice, only 50% of tools is purchased for a specific job and c. 50% of tools is used from the previous job sites. It can also be taken into account that c. 60 70 % of tools will be left in good condition and reused (or sold). For that reason, the cost of tools should be calculated in the following way: Type of job 1. Piping......................................................................[US$/h] in 2002 1.1 in plants................................................................ 1.2 piping between plants.............................................. 1.3 pipeline.................................................................. 2. Erection of steel structure.......................................... 3. Equipment erection................................................... 4. Storage tank erection *.............................................. *There are more tools and devices used at erection of storage tanks that are not included in this table.

7. ESTIMATE OF SAFETY AT WORK MEANS The means for safety at work are: 1. For personal protection2. F - protective clothing - protective shoes - protective gloves - protective goggles - raincoats or overalls - protective helmets or protection at different jobs - protection masks - welding aprons - welding masks - welding gloves - glass - welding clothes - goggles - belts - rubber boots - waistcoats - etc.

The estimator should evaluate the yearly costs per each labourer for maximum number of labourers. Costs per labourer/year: - climate similar to Croatia - climate colder than in Croatia - climate warmer than in Croatia - US$ - US$ - US$

8. ESTIMATE OF ERECTION TIME When the erection time is not mentioned in the call for tenders, the estimator should estimate it. In the magazine "3 R" of April 1985, there is a formula for calculating the time required for erection of piping: D = tm
0,3

where D = erection time in weeks (50 hour week) tm= hours requir ed acc. to the calculation My opinion is that this formula should be used to calculate the erection time only for the works up to 10.000 hours . For the works above 10.000 hours the erection time should be increased by c. 20% in the following way: D = tm0,3 x

117

The table below contains the erection time in weeks (a 50 hour week) for a range from 1.000 to 1.000.000 hours of work. Total Manhours 1.000 1.500 2.500 4.000 6.500 10.000 15.000 25.000 40.000 65.000 100.000 150.000 250.000 400.000 650.000 1.000.000 Erection time Weeks Months

9. SELECTION OF HOISTING MACHINERY (CRANES, FORK LIFTS, ETC.) When determining manhour rates, the costs of hoisting equipment have a significant impact. It is therefore very important to make a careful and realistic estimate of the type of crane, number of cranes and the time of use of the crane, forklift and the like. It is not a problem to determine the type of individual hoisting machine, the time and the power required for hoisting a given piece of equipment but this job is much more difficult when it has to be done for the entire project. During all the years of my service, I never found any trace of that issue. Talking to colleagues of mine I heard different opinions and methods for making estimates. Some make estimates based on weight and they consider that a crane should lift between 150 and 300 kg/hour. Others take into account the number of labourers and say that one crane should be sufficient for serving 6 to 20 labourers. There are no tables for any of these methods. I thought something should be done about it so I tried to describe the way I did it in my calculations and estimates hoping that younger colleagues would elaborate this better in future. When selecting the cranes care should be taken of the crane type because of very different rental costs. As for the operating costs, the cranes can be grouped from the cheapest to the most expensive. TYPE CAP OF CRANE
BUILDING CRANES

10 t 4

20 t 4

30 t 45 t 5 1 2 4 3 5 1 3 4 2

CAPACITY 60 t 80 t 100 t 150 t >150 t 1 3 4 2 2 3 1 23 23 1 2 3 1 3 2 1

TOWER PORTAL 1 1 CRANES MOBILE CRANE 3 3 PROJECTION MOBILE CRANE 2 2 trussed boom CATERPILL AR trussed boom (They are grouped according to

"Montage Gertebuch", Issue 1985)

118

The most suitable trucks for up to 2-ton cargo are those with a hydraulic jack. Forklifts are very suitable for the cargoes from 2 to 8 tons. To make an optimum selection of the cranes, it is important to fully familiarize with the project for which a calculation is made. The estimator should devise a concept of the erection method and possible erection technique as well as probable work organization. Before selecting the cranes, an average number of production labourers should be determined. 9.1 SELECTION OF THE LARGEST CRANE

Any erection project should be firstly identified the heaviest equipment and cargoes. Thereupon, the crane type and capacity are selected (or a combination of two cranes) thus identifying the largest and the most expensive crane. Care should be taken of the place of erection, elevation, possible access to the crane, access roads, rental possibilities, lifting technology, working time, etc. The time for using the largest crane should be estimated by lifting the heaviest pieces of equipment (above tons if possible). In this case the next largest crane that will stay longer at the job site could be of smaller capacity (c. tons) and as a result thereof its monthly rental fee would be lower as well. 9.2 9.2.1 PIPING IN PLANTS PREFABRICATION

The use of a crane is not important during the piping prefabrication. The use of one forklift of tons could be considered. From time to time, a smaller crane of to tons and HIAB truck could be used of which for prefabrication and for erection. Twenty five labourers should be allocated to one piece of lifting equipment. 9.2.2 ERECTION

At piping erection, the larger the piping diameter the greater need for a crane. The cranes of larger capacity are required for larger outreach and height otherwise relatively smaller cranes could satisfy the requirements. Twenty labourers per crane. One truck with HIAB for labourers but only its Crane capacity to be determined as follows: % to t % to t % to t 9.2.3 PREFABRICATION AND ERECTION

For technical calculations, both prefabrication and erection are considered together. This type of calculation applies when there are not enough data or time to make a calculation, which is the most often case. The means for hoisting should be determined in the following way: - forklift 3 5 t - truck with "HIAB" - mobile crane % - to % - to % - to labourers per forklift labourers per truck labourers per crane of which t capacity t " t "

119

9.3

PIPING BETWEEN PLANTS

Lower capacity cranes will mostly satisfy the requirements for erection of this kind of piping. The scope of prefabrication is smaller, and therefore the calculation should be made as follows: - truck with "HIAB" labourers per truck - car crane labourers per crane of which %-to t capacity %- to t capacity 9.4 PIPELINES

At pipeline laying special cranes are used for unloading, loading, pipe stringing and performance of special points. Generally, car crane renting should be avoided whenever a continuous work is not possible. This refers particularly to the works on right-of-ways where the pipe layers and trucks with HIAB are used. Consequently, estimator can rely on crane for some activities only, which should be elaborated separately. All manuals for calculations of pipeline erection provide for special elaboration of each activity from pipe transport to pressure testing.

9.5

ERECTION OF STEEL STRUCTURES

Erection of steel structures is not actually possible without cranes. The costs of machinery account for the largest portion of the man-hour rate. The use of truss boom cranes and particularly tower building cranes is possible. The truss boom cranes are suitable because of lower rental costs and the tower building cranes for their very high efficiency and outreach. The cranes should be calculated as follows: - heavy steel structure - medium-weight steel structure - light steel structure

labourers per crane labourers per crane labourers per crane

9.6

INSTALLATION OF PROCESS EQUIPMENT

At installation of process equipment firstly we should identify the largest crane (item 9.1.) and then decrease the total number of hours and the average number of labourers for the foreseen heavy equipment respectively. The cranes for other equipment to be calculated as follows: 1 crane on labourers of which: %- for the second largest cr ane (c. %- for t cr anes %- for t cr anes

t)

9.7

ERECTION OF CYLINDRICAL STORAGE TANKS

Special attention should be paid to the selection of a crane for erection of cylindrical storage tanks. This type of crane cannot be selected according to the number of labourers but according to the type, diameter, height, arrangement, and the number of storage tanks, etc. A mobile crane with a truss boom of maximum -ton capacity is the most adequate when we install one storage tank. If there is a group or a series of storage tanks, we should consider using tower cranes of sufficient reach and on tracks, if possible and necessary. If there are several storage tanks, we shall need another smaller crane for loading and unloading the plates and getting them closer. Generally, an adequate erection concept is required and each activity should be supported with an adequate crane. On average, labourers should be allocated per one crane.

When erecting spherical storage tanks (balls) the same measures for crane selection apply.

120

10. UNLOADING, HANDLING AND SORTING OF THE MATERIAL Almost all manhour rates include the erection activities from withdrawal of the material and equipment from the investor's store to the completion according to detail design. We shall often come across a request in tendering documents to offer unloading, handling and sorting of the material. (The quantity/volume ratio see page 213.)

10.1

MATERIAL FOR PIPING - Unloading: - Handling and sorting: Piping in plants Piping between plants Pipeline STEEL STRUCTURE - Unloading: - Handling and sorting: Heavy structure Medium-weight structure Light structure PROCESS EQUIPMENT - Unloading: Bulk material (packings) Equipment Equipment Equipment - Handling and sorting: Bulk material (packings) Equipment Equipment Equipment - Sorting near foundationabov Equipment - Sorting at store CYLINDRICAL STORAGE TANKS - Unloading: - Handling and sorting: - Handling and sorting:

[Mhr/ton] 60 % 60 % 60 % and above and above and above [Mhr/ton] [Mhr/ton] [Mhr/ton]

10.2

[Mhr/ton] (above 60 kg/m) (31 60 kg/m) (to 30 kg/m) [Mhr/ton] [Mhr/ton] [Mhr/ton]

10.3

to 5 [t/pc] 5 10 [t/pc] above 10 [t/pc]

[Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton] [Mhr/ton]

to 5 [t/pc] 5 10 [t/pc] e 10 [t/pc] above 10 [t/pc]

10.4

near foundation in store

[Mhr/ton] [Mhr/ton] [Mhr/ton]

121

11. TEMPORARY WORKS, SPACE REQUIRED AND CONNECTIONS AT THE SITE

1. TEMPORARY WORKS 1.1 MANAGEMENT SITE OFFICES 1.2 SITE OFFICES 1.3 LOCKER ROOM 1.4 TOOLS STORE 1.5 ENCLOSED STORE 1.6 SANITARY FACILITIES 1.7 MESS ROOMS 1.8 PREFABRICATION HANGAR 1.9 MAINTENANCE WORKSHOP 1.10 CANOPIES FOR TECHNICAL GAS 1.11 ENCLOSED STORE FOR CAPITAL EQUIPMENT

OPTION 1 OFFICE BUILDINGS & CANOPIES [ m2 ] Average number of staff x =.m2 No of foremen x =.m2 Maximum number of workers x 0,3 = .m2 Average number o workers x =.m2 Average number of workers x =.m2 1 container for workers Average number of workers x =.m2 Average number of workers x =.m2 m2 for each maintenance worker (electrician, mechanic) Average number of workers x =.m2 On principle, the investor is responsible for providing such store) The store area to be determined as follows: Total weight of erection equipment (piping + steel structure + equipment) in tons 2 x m/ton

OPTION 2 CONTAINERS [pc.] 1 container for 1 container for office workers foremen

1 container for direct labourers 1 office + 1 cargo container for direct labourers 1 cargo container for direct labourers 1 container for workers

1 container for maintenance workers (electrician, mechanic)

122

2. AREA NEEDED 2.1 OUTDOOR AREA FOR THE JOB SITE MANAGEMENT SITE OFFICE BUILDINGS

METHOD OF CALCULATING THE AREA IN [m] A sum of net area from each item: 1.1 + 1.3 + 1.6 + 1.7 increased times A sum of net area from each item: 1.4 + 1.8 + 1.9 + 1.10 increased times Double the area of item

2.2 OUTDOOR AREA FOR WORKSHOPS AND BULKING OF EQUIPMENT 2.3 OUTDOOR AREA FOR SORTING PREFABRICATED ITEMS 2.4 OUTDOOR STORE AT THE JOB SITE

Generally, every job site has a few plants. On each plant the contractor needs a fenced area for storing the capital equipment and consumables. The area for that purpose would be: m2 Job sites to: above: direct labourers direct labourers direct labourers m2 m2 m2

2.5 OUTDOOR AREA FOR PARKING MACHINERY

2.6 OUTDOOR REA FOR STORING CAPITAL EQUIPMENT 3. CONNECTIONS NEEDED 3.1 POWER CONNECTIONS

1,5 m2 per ton of capital equipment

METHOD OF ESTIMATE 1 main connection: maximum number of welding rectifiers x kVA Connections at the plants: at least off kVA power connection for each plant If there is a hydrant network: determine the quantity required. If there is no hydrant network: determine the quantity needed, storing in water storage tanks or supply by tank lorries. Quantity: litre/man/day Connections: every sanitary facility connection for each sanitary facility telephone lines at least

3.2 PROCESS WATER CONNECTIONS

3.3 DRINKING WATER CONNECTIONS

3.4 SEWERAGE CONNECTIONS 3.5 TELEPHONE LINES

123

12. ESTIMATE OF THE NUMBER OF WELDS AND RADIOGRAMS FOR PIPING Data on the number of welds are not often given in the call for tenders. Of course, this cannot be calculated without complete detail documentation. To make a technical calculation an estimator needs the data on the number of welds. If he wants to estimate the quantity of radiograms, he should know only the quantity of butt welds and if he wants to calculate precisely the quantity of welding rods and electric power, he should know the quantity of all types of welds. The estimate of the quantity of other types of welds such as nozzle welds and socket welds, the estimator can base on the butt welds quantity. The quantity of butt welds can be estimated in several ways: 1. ESTIMATE OF BUTT WELDS BASED ON A LIST OF MATERIAL - PIPES, FITTINGS AND FLANGES Piping in plants 1.2. Pipe Bends Tees Pipe caps Reducers Weldolets Neck flanges weld/24 m weld/piece weld/piece weld/piece weld/piece weld/piece weld/piece

1.1.

Piping between plants piperacks and sleeper ways pipes pipes pipes pipes pipes to 3" 4"- 6" 8"-10" 12"-14" above 16" 1 1 1 1 1 weld/ weld/ weld/ weld/ weld/ m m m m m

- fittings and flanges: as for the piping in a plant (item 1.1.) 1.3. Combined piping (in plants and between the plants)

If there are no separate lists of materials for piping in the plant and for the piping between the plants, but we know there are both of them, the quantity of butt welds should be calculated as follows: Pipes: calculate 1 weld to the lengths that are twice the length of the piping between the plants (item 1.2.). If the estimator can estimate proportional relations of two kinds of piping then he can make the calculation with other piping lengths as well. - Fittings and flanges: As for the piping in plants (item 1.1) 2. ESTIMATE OF BUTT WELDS BASED ON A LIST OF MATERIAL - FITTINGS AND FLANGES ONLY Bends Tees Pipe caps Reducers Weldolets Neck flanges weld/piece weld/piece weld/piece weld/piece weld/piece weld/piece

The pipe-to-pipe welds are not considered because it is deemed that the quantity of such welds is deemed to be similar to the number of fitting-to-fitting welds. This is the most widely used method for estimating the butt welds. I know from experience that this method is not a reliable one. If applied, it should be calculated in the following way: - Piping in the plant: decrease the weld number by - Combined piping (in plants and between the plants): increase by c. c. % %

124

3. ESTIMATE OF BUTT WELDS BASED ON THE PIPING LENGTHS - MEASURED ON THE LINE AXIS 1 butt weld/length [m] Line Combined

Diameter to 1 1/2" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20" 24" 28" 30" 32" above 34"

Plant *

Town network

*In the case of to 11/2" piping, the fittings are mostly with the socket welds and therefore there are fewer butt welds.

m x 3,2281 = ft

4. ESTIMATE OF TOTAL WELDS (ALL TYPES) This estimate can be used for calculation of welding rod consumption (item 2, page 112) and the power consumption costs (item 4, page 115). Once the quantity of butt welds is calculated by any of previously described methods, the quantity of other welds can be calculated as well. This is done in such a way that the quantity of butt welds is increased by the following percentage: - Piping in plants: - Piping between plants (piperacks and sleeper ways): - Combined piping: - Town networks: % % % %

5. ESTIMATE OF RADIOGRAMS ON THE PIPING The number of radiograms depends on the media, working pressure, working temperature, materials and special safety regulations. Generally, the estimator i.e. the process engineer determines the percentage of radiographic tests and include them in the piping line list. The percentages are different and can vary from 5% to almost 200%. (200% is in special cases when highly alloyed materials are used and the radiography is required before and after thermal treatment of the weld).

125

The following table is mostly used to determine the percentage of radiographic inspection. WORKING TEMPERATURE [ C] 20 100 101 300 301 400 - 45 - 21 - 20 300 301 450 - 20 450 451 580 - 99 500 501 700 196 - 100

TYPE OF STEEL CARBON STEEL C - STEEL LOW TEMPERATURE Mo - STEEL

Class 3 125 lb 150 lb 0% 5% 0% 5%

150 lb 5% 5% 10% 5% 5% 10% 30% 30%

Class 2 300 lb 5% 10% 30% 10% 10% 30% 30% 100% 30% 30% 100%

Class 1 >900 lb 600 lb 10% 100% 30% 100% 30% 100% 30% 30% 100% 100% 100% 30% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

0% 5%

CrMo - STEEL AUSTENITE STEEL (STAINLESS) -

10% 30% 30%

Source: Code for Pressure Piping, Petroleum Refinery Section ANSI B31.3, Chapter VI

If we know the quantity of butt welds according to their diameter, material and class, then it will not be difficult to determine the number of welds to be tested. In most cases, however this information is not available and cannot be determined within the scheduled time. Because of that the estimator will monitor and develop statistics of the projects executed, he will ask for professional opinions of more experienced colleagues, and decide for an average percentage of radiography. When the estimator determines the percentage, he will calculate the number of radiograms according to the table below. The number of radiograms and lengths of films according to API - STD.1104 ("ZIT" - Institute for Welding, Testing and Technology - Zagreb) Outside Number of Film diameter radiograms size to 1 1/2" (40 mm) (ellipse) 10 X 12 2"- 3 1/2" (50-90 mm) (ellipse) 10 X 16 4" - 5" (100-140 mm) 10 X 16 6" - 7" (150-190 mm) 10 X 24 8" - 11" (200-280 mm) 10 X 32 12" - 13" (300-360 mm) 10 X 40 14" - 18" (360-450 mm) 10 X 48 20" (500 mm) and more: Number of films depends on diameter 10 X 48 20" - 22" (500-550 mm) 10 X 48 24" - 28" (600-700 mm) 10 X 48 30" - 34" (750-850 mm) 10 X 48 36" - 40" (900-1000 mm) 10 X 48 42" - 46" (1050-1150 mm) 10 X 48 48" - 52" (1200-1300 mm) 10 X 48

cm cm cm cm cm cm cm cm cm cm cm cm cm cm

When the quantity of radiograms is calculated, it should be increased by: % % % % % for weld repair for incorrectly issued orders or undefined needs and samples for certifying processes and welders Total

126

X. PIPING ABOVE GROUND


ESTIMATE POINTS OF BASIC ERECTION ITEMS The estimate points of basic erection items are used for payment and monitoring of the works progress during erection of piping above ground. One estimate point equals one man hour (Mhr) at Productivity Efficiency Percentage (PEP) of 90% for unit quantity and for carbon steel. The tables contain the values of erection items for dimension used most frequently in erection of piping. Any intermediate value can be calculated for the needs of an estimate or derived by interpolation. Under the section EXPLANATION TO THE ERECTION ITEMS, the estimate points and the related activities are given for items 1.1 to 7.5. The same section (items 8.1 8.8) provides the method for calculating the activities derived from basic items. The influence of different material is calculated by the material multiplier factors (factors for different kind of materials) (f) for items 2.2 to 3.8. By way of an exception, the factors (k) on the page 142 are used for items 1.1 to 1.3. The section FORMS FOR CALCULATION OF MAN-HOUR RATES contains the erection items on which basis the time required for installation of each piping element is calculated. These forms have been used to calculate all man hour rates in the section.

EXPLANATION TO THE ERECTION ITEMS (Basic Erection/Installation Items) 1.0 1.1 PIPING PIPE INSTALLATION IN PLANTS

Withdrawal from the store, hauling to the erection site, alignment, temporary supporting and fastening are calculated on the basis of listed lengths excluding fittings, flanges, valves, etc. Compensation: per linear meter of pipe 1.2 PIPE INSTALLATION ON PIPERACKS

The work is identical to PIPE INSTALLATION IN PLANTS. Compensation: per linear meter of pipe 1.3 PIPE DISMANTLING

Dismantling works including necessary reconditioning work for parts to be reutilized, hauling to a storing place and unloading. Compensation: per linear meter of pipe 2.0 FITTING

Valid only for welded fittings. Not valid for parts such as weldolets, sockolets, nipolets, einforced nozzles, half couplings, etc. Similarly, not valid for fittings with a socket joint and thread. If reductions are made on the pipe directly, it is considered as a fitting with two welds). The rate for reducer is taken for the biggerr diameter. Fittings are considered only those MITRE BENDS that are delivered ready for installation, which means they are listed in the bill of material as a finished part. Mitre bends contracted for field fabrication will be considered as pipes from which the bends must be made. If this is the case, the calculation should be made according to the table (pipe laying, welds, pressure test).

127

2.1

ADJUSTMENT OF FITTINGS WITH ONE CONNECTION END

Adjustment of fittings with one connection end, a pipe cap or a flange for instance, is included in welding so it is not compensated separately.

2.2

ADJUSTMENT OF FITTINGS WITH TWO CONNECTION ENDS

It includes measurement, angularity and ovality check of ends, if necessary correction work matching by cutting, bevelling, cleaning and fitting. This refers to pipe elbow, bend, reduction and mitre elbow (bends made from pipe segments). Compensation: per item 2.3 ADJUSTMENT OF FITTINGS WITH THREE CONNECTION ENDS

It includes a check of dimension, check o f ovality of ends, check of one angularity , if necessary correction works (possible cutting as well) matching by cutting, bevelling, cleaning and fitting. It refers to T-piece and Y-piece. Compensation: per item

3.0

PIPE WELD MAKE-ON AND WELDING

It includes all necessar y preheating and possible protection from inclement weather . Heat treatment in terms of stress relieving not included. 3.1 BUTT WELD MAKE-ON AND WELDING

Measurement, placing and sortin g of pies, marking of cut ting line, cut ting, deburring, remo val of paint, cleaning, alignment, adjustment, temporary supporting, tack welding, check, and welding, It includes also possible stress relieving at flanges. Compensation: per weld - Weld joint at installation of prefabricated sections: 2 x Item 3.1 3.2 FILLET (SOCKET) WELD - MAKE-ON AND WELDING

It includes the same activities as for BUT T WELD . It applies to the items with socket weld end connection (sock et weld flanges, sock et couplings, etc. ). Following fix ed wall thicknesses ar e valid f or different outside diameters of pipes: to DN < 80 or < 3: - all materials PN to 160 bar PN to 320 bar Above DN to 80 or 3 : - Cr Ni Ti - steels PN to 100 bar or to 600 lbs : PN abov e 100 baror abov e 600 lbs : (Schedule) t = Sch10S t = STD or 3000 lbs : or 6000 lbs : t = 3.9 mm t = 6.4 mm

128

- all other material PN to 100 bar PN above 100 bar or to 600 lbs : or above 600 lbs : t = STD t = XS

Slip-on flanges according to ANSI B16.5 and plain flanges according to DIN 2655 and 2656 will be compensated twice. Compensation: per weld 3.3 MITRE WELD MAKE-ON AND WELDING As for BUTT JOINT Compensation: per weld 3.4 NOZZLE WELD MAKE-ON AND WELDING

Header line measurement, marking of bore, cutting of bore, paint cleaning, matching up branch, tack-welding, levelling, alignment, welding. Nozzles without reinforcement are considered according to the outside diameter and the branch wall thickness. Nozzles with reinforcement are considered according to the larger outside diameter and larger w all thickness. This value is then added the v alue of the REINFORCEMENT PAD. The value for inclined nozzle joints is increased by 50%. Compensation: per weld 3.5 WELDOLET, NIPOLET - INSTALLATION AND WELDING

Header line measurement, marking of bore, cutting of bore, grinding, removal of paint, matchingup weldolet, sockolet, etc., tack-welding, levelling and welding. For calculation of a joint with a branch connection, take the outside diameter and the wall thickness of the branch connection. With nipolets, sockolets and thredolets to DN 80 or 3, the following will be used instead of the connecting branch wall thickness: PN to 3000 lbs : PN to 6000 lbs : t = 4.3 mm t = 6.0 mm

Wall thickness as for SOCKET JOINT is valid above DN 80 or 3. Compensation: per item 3.6 REINFORCEMENT PAD MAKE-ON AND WELDING

Fabrication of reinforcement pad according to to drawing: cutting out from the remaining pipe (pipe same as header line), edge working, drilling and threading of vent hole, matching-up, tack welding, welding closing of vent hole with mastic. Factor for this item is considered for outside diameter of branch connecting and the wall thickness of reinforcement pad. For a complete reinforced branch connection with pad NOZZLE JOINT should be added. Compensation: per item 3.7 SEAL RING MAKE-ON AND WELDING (ACC. TO DIN 2695)

Cleaning of seal ring faces, positioning of seal ring, tack welding and welding. After connecting two flanges and tightening: tack welding and welding of interfacing seal rings. Because of welding, the bolts will be removed and retightened. Compensation: per item (without flanged joint) Basis for the number of factors is a standardized wall thickness of 4 mm. They are printed in the tables only once per diameter of pipe. The flange joint is compensated subject to the nominal pressure.

129

3.8

INSERT RING (FOR ALUMINIUM ONLY)

Cutting of insert rings to necessary length and matching up, welding of longitudinal seams and tack welding to the pipe. Compensation: per item Basis for the number of factors is a standardized wall thickness of 4 mm. They are printed in the tables only once per diameter of pipe. 3.9 WELD CUTTING FOR MODIFICATIONS

Measurement, marking of cutting line, removal of paint, machine cutting, removal of remaining welding seam, and preparation of the cutting face for joining. Compensation: per item - cutting. This item is considered once only for each weld to be cut. It is used only when the piping parts are reutilized. 3.10MA TERIAL MULTIPLIER FACTORS (f) All values in the tables are valid for carbon steel. For different kind of materials a special table is given under the section MATERIAL MULTIPLIER FACTORS (3.10). It is calculated by multiplying the carbon steel value by the factor (f) from the table 3.10. Valid for items 3.1 to 3.8 only.

4.0

FLANGED AND THREADED JOINTS, BENDING OF PIPES 4.1 4.3 FLANGED JOINT

Cleaning of flange faces, preparation and positioning of gasket, lubrication of bolts with graphite grease, fitting and tightening of bolts. Compensation: per joint This item includes all flanged joints regardless of the flange t ype. Values for higher pressure are obtained by multiplying item 4.3 value by the following factors: Item 4.3 x 1,3 for PN 160 ANSI 900 Item 4.3 x 1,7 for PN 250 ANSI 1500 Item 4.3 x 2,2 for PN 320 400 ANSI 2500 4.4 INSTALLATION OF MEASURING ORIFICES, BLANKING PLATES, etc.

Make-on as for FLANGED JOINT. Additional installation of all intermediate rings and plates such as blanking plates, measuring rings, safety rings, measuring orifices and the like. This item is only an addition to the flanged joint values. 4.5 PIPE BENDING 1. (For pipes to DN 50 or 2) Pipe measurement, bending according to the standards. 2. (For pipes above DN 50 or 2 to DN 200 or 8) These pipes are mostly bent for fire protection of cylindrical storage tanks. Values are compensated per [m of bending angle].

130

4.6

PREPARATION OF THREADED ENDS

Pipe handling, placement, measurement, marking the spooling length, cutting, threading, thr ead and cut deburring. Compensation: per item 4.7 THREADED CONNECTION MAKE-ON

Thread cleaning, preparation of thread according to specification, screwing in, and tightening. Compensation: per joint This item will also be compensated for dismantling of threaded connection (unions with gasket, etc.). 4.8 DISASSEMBLING Item 4.1 4.4 and 4.7

Joint disconnection, dismantling, tr ansport of dismantled material to the advised storing place and unloading. Compensation: per item

5.0 5.1

VALVES VALVE INSTALLATION (WITH AND WITHOUT HAND DRIVE)

Valves, gate v alves, cocks, f aucets, non-return v alves, dampers, str ainers, level indicators, lev el controllers, floats, etc. Checking, blowing ou t, remo val of possible f oreign objects, check open/close operations, supporting, fastening of hand wheel or installation of hand wheels or handles. Compensation: per item 5.2 VALVE INSTALLATION WITH ACTUATORS (SOLENOID, AIR)

A valve with an actuat or means all pneumatic-, mot or or manual gear oper ated valves for openclose operations. Activities are the same as f or the V ALVES. This item is compensated only f or complete valves including actuator. Compensation: per item 5.3 BUTTERFLY VALVE INSTALLATION WITH ACTUATOR

As for VALVE WITH ACTUATOR Compensation: per item For this position, only one flanged joint will be compensated. 5.4 BUTTERFLY VALVE INSTALLATION

As for VALVE. Compensation: per item Same as under BUTTERFLY VALVE WITH ACTUATOR. 5.5 CONTROL VALVE INSTALLATION

As for VALVE. Additional: special protection and dismantling for pressure tests Compensation: per item

131

5.6

SAFETY VALVE INSTALLATION

As for VALVE. Additional: dismantling for calibration and reassembling. For safety valves, it will be compensated according to the nominal diameter of the pressure side (inlet). Compensation: per item 5.7 HYDRANT INSTALLATION

As for VALVE. Compensation: per item 5.8 SPINDLE EXTENSION

According to the dimensions it refers to the extensions between 1 and 3 meters. Compensation: per item 5.9 DISMANTLING OF VALVES

The scope of works includes: dismantling, cleaning by blowing or purging, transport and unloading at an intermediate storage place. Disassembling of connections will be compensated as for DISASSEMBLY OF PIPE CONNECTIONS. Compensation: per item

6.0 6.1

PRESSURE TESTING PRESSURE TEST

Pressure test with water and water mixtures, air, inert gas, or steam. It includes the make-on of provisional connections for filling and draining, installation of blanking plates, removal of items exempted from pressure test, filling and venting of system, pressure increase to specified level. Pressure and leak test to be applied to all welds, flange and threaded joints - following the regulation. In case of pneumatic or gas test all connections are to be leak tested with a foaming agent. Carrying out the inspection of tests following the regulations, draining of system, removal of blanking plates, installation of parts, which were removed prior to pressure test and installation of flange unions with specified gaskets, bolts and nuts have to be tightened. Unlock spring hangers and spring supports. Remove temporary piping test components. Compensation: per meter of pipe 6.2 SERVICE TEST

Service test is a leak test with air or gas at a low pressure setting. It is done when not performed with the pressure test and when required by the specification. Compensation: per meter of pipe

7.0 7.1

MISCELLANEOUS SUPPORTS - FABRICATION AND WELDING

Fabrication, matching up, welding. Fabricated from the remaining pipes. Compensation: per item 7.2 SUPPORT INSTALLATION (WITHOUT FABRICATION)

Installation of supplied supports fabricated by other contractors, bolting, placing the insulating parts, complete welding and possible adjustment. Removal of temporary supports included as well. The values are the manhour rates that is the man hours per kg respectively.

132

7.3

INSTALLATION OF SPRING HANGERS AND SUSPENSIONS

The installation is the same as for the SUPPORT INSTALLATION. In addition adjustment of prestressing. 7.4 GRINDING OF EXCESS MATERIAL ON WELDING ROOTS

Careful grinding of excess material on welding roots of specified welds, removing grinding dust. This is particularly used with rubber-lined piping and with installation of measuring flanges. Compensation: per weld 7.5 INSTRUMENT CONNECTION - DRILLING

Drilling, deburring of instrument connection in pipe according to the given bore in flange, removal of drilling chips. Compensation: per drilled hole

8.0 8.1

ACTIVITIES DERIVED FROM BASIC ITEMS PIPES

In the following items, only the lengths of straight run pipes included in the bill of quantities are compensated (cutting lengths as listed). Fittings, flanges and the like will not be compensated. 8.1.1 PIPE HANDLING AND CUTTING IN PREFABRICATION Prefabrication as for Item 1.1. Transport to a spools storing place. x number of points Item 1.1 = [hours per meter of pipe]

Make-on: Compensation:

It is compensated only if the installation is not done by the prefabrication labour. 8.1.2 INSTALLATION OF PREFABRICATED SPOOLS Installation as for Item 1.1. Transport from the spools storing place to the place of installation.

Make-on:

Compensation: 2 5 6 10 12 14 above 16

x no of points Item 1.1 x no of points Item 1.1 x no of points Item 1.1 x no of points Item 1.1

= = = =

[hours per linear meter of pipe] [hours per linear meter of pipe] [hours per linear meter of pipe] [hours per linear meter of pipe]

Valves and pipe supports will be compensated separately. It will be compensated only if another company does the prefabrication. - Alternative: Activity 8.2.4 8.1.3 SPATIAL SHIFTING OF PIPES Spatial shifting of already installed piping, dismantling and installation of holders, installation of additional steel packers. x no of points Item 1.1 (1.2)

Make-on:

Compensation:

133

8.1.4

MAKE-ON OF OUTSIDE PIPE FOR A DOUBLE-WALL PIPING (JACKETED PIPING)

Make-on: Cutting, placement, positioning the outside pipe with double-wall piping (jacketed piping). Compensation: x no of points Item1.1 (1.2)

It is compensated only if the installation is not done by the prefabrication labour. 8.1.5 MAKE-ON AND INSTALLATION OF LINE PIPING DN 20/25 ON JACKETED PIPING As for Item 1.1 x no of points Item 1.1 (1.2) for union fittings between the jacketed pipes

Make-on: Compensation:

x no of points Item 1.1 (1.2) for union fittings on valves and fittings

8.2 8.2.1

MISCELLANEOUS FITTINGS HALF COUPLINGS

The connecting seam between a half coupling and a header pipe is a fillet weld. To allow for the additional work as drilling the hole etc. a butt weld according to Item 3.1 will be compensated. The following points for nominal diameter of half-coupling or adequate outside diameter of connecting pipe (not the header pipe) and wall thickness are used: PN to 3000 lbs : PN to 6000 lbs : t = 10,6 mm t = 13,8 mm

NOTE: The wall thicknesses considered for compensation are fictitious. There are no points for these thicknesses. Therefore, the points for the closest thickness are taken and divided with that thickness and multiplied by fictitious thickness of 10.6 mm or 13.8 mm dependent on the halfcoupling category. The result is the points for a joint between the half coupling and the header pipe. Item 3.2 is followed for compensation of next socket joint of pipe. Compensation: Points per item 8.2.2 WELD COMPENSATOR Measurement, positioning, supporting of weld compensators x no of points Item 2.2

Make-on: Compensation: 8.2.3

WELD METER RUNS Measurement, placement positioning and supporting of weld meter runs x no of points Item 2.2

Make-on: Compensation: 8.2.4

PREFABRICATED OF SPOOLS FOR WELDING Finding of pref abricated piping sections, tr ansport, measurement, placement, positioning, supporting, and fastening x no of points Item 2.2 [Mhr/spool]

Make-on: Compensation:

Valves and pipe supports are compensated separate. It is compensated only if another company does the prefabrication. - Alternative: Activity 8.1.2

134

8.2.5

MEASURING ORIFICES - MEASURING FLANGES

This item includes the operations for performance of a flanged measuring orifice, which is assembled at the site from individual parts excluding the measuring orifice plates and the meter runs delivered as an assembly. Weld both flanges according to the existing specification of the measuring orifice and grind the excess material on the welding roots. Drill holes for instrument connection for slip-on flanges and remove drilling chips, weld outgoing instrument connections and close off (watertight welding) the flange hole not used, make-on of flange joint by installing a measuring orifice. (Battery limits of the works marked on drawing) Compensation of instrument connection assembly: x Item 4.1 (4.2 or 4.3) + Item 4.4 In addition the points for the following to be included: Grinding of excess material on the welding root along the flange seam according to the nominal diameter of the flange. x Item 7.4 Grinding and removal of drilling chips on the measuring line connection according to the nominal diameter of flange. x Item 7.5

8.3 8.3.1

WELDING TACK WELDING ON VALVE SIMULATORS

Make-on: as Item 3.1 Compensation: x no of points Item 3.1

8.3.2

LONGITUDINAL WELDS ON PIPE HALF SHELLS

Make-on: As Item 3.1 Compensation: x no of points Item 3.1 for both longitudinal welds 8.3.3 THERMOMETER BRANCH (TI)

Welding of a thermometer branch to a pipe DN 150 and abov e is compensated instead of a nozzle joint x socket joint of corresponding Item 3.2 (s = 6,4 mm). Compensation: Points per item 8.3.4 PREFABRICATED WELDS AT INSTALLATION OF PREFABRICATED SECTIONS (SPOOLS)

Performance:As Item 3.1 Compensation: x no of points Item 3.1 8.4 8.4.1 FLANGED JOINTS REPLACEMENT OF BOLTS

Performance:Take out of bolts, preparing them f or reutilization, bolt greasing, placing, and tightening. Compensation: x no of points of corresponding Item 4 .1, 4.2 or 4 .3

135

8.5 8.5.1

VALVES ROTATING THE VALVE INSTALLED Positioning, supporting, fastening x no of points Item 5.1, 5.2, 5.3, 5.4, 5.5, 5.6 or 5.7

Make-on: Compensation: 8.5.2

EXPANSION JOINTS WITH FLANGED ENDS As Item 5.1 x no of points Item 5.1

Make-on: Compensation: 8.6

WALL PASS FOR PIPES

Make-on: Fabrication and installation of wall passes. Use of larger diameter pipes or sheet metal bending, wall breaking, setting the pass in position and fastening. Compensation: x no of points Item 3.1 for corresponding diameter of he header line

8.7 8.7.1

MISCELLANEOUS FABRICATION AND INSTALLATION OF PIPE HOLDERS, HANGERS AND SUPPORTS (to 100 kg per item)

Make-on: as Item 7.2 inclusive of fabrication according to the Client's drawings. Compensation: x no of points Item 7.2 if the Client supplies the material x no of points Item 7.2 if the Client supplies the material 8.7.2 DISMANTLING OF PIPE HOLDERS, HANGERS AND SUPPORTS

Performance: Dismantling holders and return the usable parts to the store. Compensation: x no of points of corresponding Pos 7.2 8.7.3 HOLE DRILLING IN CONCRETE

Performance: Drilling a hole and inserting a screw anchor Compensation: x points for holes to 10 mm x points for holes x points for holes 8.8 8.8.1 EXTRAS CHANGE IN BILL OF QUANTITIES BEFORE THE CLIENT'S APPROVAL FOR FABRICATION points per piping item. 12 16 mm above 16 mm

Compensation: The change in bill of quantities is compensated by 8.8.2

CHANGE IN ISOMETRY PRIOR TO THE CLIENT'S APPROVAL FOR FABRICATION points per pipe item

Compensation: The change in isometry is compensated by

136

8.8.3

HAND DRAFTING OF ISOMETRY ACCORDING TO THE CLIENT'S INSTRUCTION points per

Hand drafting (sketches) of isometry including a bill of quantities is calculated with sketch and bill. 8.8.4 INSTALLATION OF MISSING MATERIAL

Make-on:

Subsequent installation of the piping parts in already prefabricated and installed piping.

Compensation: Subsequent installation of the piping parts is compensated by x number of points of corresponding installation item and the installation and/or welding item. 8.8.5 PIPING MODIFICATION Modification works on already installed piping at the Client's request. As-built documentation of the modifications made in isometry and bill of items.

Make-on: Compensation:

OPTION I: Modification on finished and installed piping is paid according to the calculation x number of points of that item. For handling only the straight run pipes are considered. OPTION II: Calculation according to the table "Man hours for piping modification at site," Page 48 8.8.6 SAND BLASTING HANDLING, PRIMER COAT ON PIPING, AND PIPE SUPPORTS Designation of prefabricated sections and pipe supports on the protected side. Preparation of piping for sandblasting and application of primer. Protection of sealing surfaces and bevelled welding edges against damage and protection against ingress of sand into the piping.

Performance:

Transport of piping to the sandblasting and painting site. Co-ordination and work with sandblasting/painting company. Compensation: Sandblasting handling and corrosion primer is compensated at prefabricated material. 8.8.7 UNDERGROUND PIPING [Mhr/ton] of

This refers to the piping laid in an excavated trench in the plant but it is not valid for pipelines. They are calculated as the piping above ground with a % increase. A precondition is that the pipes are already wrapped in which case there is no need to calculate separately the wrapping of joints separately. If the pipes are not prewrapped, the insulation shall be calculated separately.

137

8.8.8

FACTORS FOR CALCULATION OF MAN HOURS FOR PREFABRICATION AND INSTALLATION OF PIPING

The estimate points for basic erection items and the rates derived for the piping elements will give the total values for prefabrication and for installation. Sometimes the rates are requested to be given separate for prefabrication and separate for installation, which is done in the following way:

1.

PIPES (Item 1.1; 1.2)

Pipe handling is one installation item, which is performed both in prefabrication and in installation. That is why the estimate points and the rates have to be divided. Prefabrication: Installation: 2. ( ( %) %) factor factor

FITTINGS (Item 2.2; 2.3) Prefabrication: Installation: factor factor

3.

JOINTS - WELDING (Item 3.1 3.9) Prefabrication: Installation: factor factor

4.

FLANGES AND OTHER (Item 4.1 4.7) Prefabrication: Installation: factor factor

5.

VALVES INSTALLATION (Item 5.1 5.8) Prefabrication: Installation: factor factor (exception)

6.

TESTS (Item 6.1; 6.3) Prefabrication: Installation: factor factor

7.

MISCELLANEOUS - (Item 7.1) Prefabrication: factor Installation: factor - (Item 7.2; 7.3) Prefabrication: no Installation: factor - (Item 7.4; 7.5) Prefabrication: factor Installation: factor OPTION: According to the unit rates per each component, a division to pref abrication and installation, page 49.

8.

138

TABLE Item. 3.10 (pages 147 202) MULTIPLIER FACTORS FOR DIFFERENT KIND OF MATERIALS FOR ITEMS 3.1 TO 3.8 (f) Group of materials (GM) Carbon steel (CS) Chrom-molybden alloy steel (CR) Copper alloy (CU) Low temp. alloy steel (N), (N1), (TT) Stainless steel (CN) High temp. alloy steel (W), (W1), (W2), (W3) Nickel alloy (NI) Aluminium alloy (AL)

(f ) CARBON STEEL

GM CS

DIN - MATERIAL St 35 St 35,8 St 37-2 RSt 37-2 RRoSt 37 -2 St 42-2 RSt 42-2 St 45 St 45.8 C 21 C 22 C 22.8 H II

WS - No 1,0308 1,0305 1,0112 1,0038 1,0174 1,0132 1,0042 1,0408 1,0405 1,0432 1,0402 1,046 1,0425

ASTM - material A53 A106 Gr. A, A234 Gr. WPA A53 Gr. A A135 A283 Gr. B, C (killed) A285 Gr. B (killed) A53 Gr. B A135 Gr. B A181 Gr. Class 60 A53 A106 Gr. B, A234 Gr. WPB A105 A181, A234 A105, A181 Gr. II A671 Gr. CA55, CB60 CB65 A182 Gr. F304L, A269 Gr. TP304L, A312 Gr. TP304L, A403 Gr.WP304L A269 Gr. TP316L, A312 Gr. TP316L, AISI Gr. 316L AISI Gr. 316N A182 Gr. F304, A269 Gr. TP304, A312 Gr.TP304, A358 Gr. 304, A403 Gr.WP304, WP304H

STAINLESS STEEL CN X2 CrNi 19 11 (X2 CrNi 18 9) 1,4306

X2 CrNiMo 17 13 2 (X2 CrNiMo 18 10) X2 CrNiMo 18 14 3 (X2 CrNiMo 18 12) X2 CrNiMoN 17 13 X5 CrNi 18 10 (X5 CrNi 18 9)

1,4404 1,4435 1,491

1,4301

139

(f ) STAINLESS STEEL

GM CN

DIN - MATERIAL X5 CrNiMo 17 12 2 (X5 NiCrMo 18 10)

WS - No 1,4401

ASTM - material A182 Gr. F316, A269 Gr. TP316, A312 Gr. TP316, A358 Gr. 316 A789 ? ? A182 Gr. F347, A269 Gr TP347, A358 Gr. 347, A358 Gr. 348, A403 Gr. WP347, A403 Gr. WP348 A182 Gr. F321, A269 Gr. TP321, A312 Gr. TP321, A358 Gr. 321, A403 Gr. WP321, A403 Gr. WP321H A312 Gr. TP316H, A403 Gr. WP316 AISI Gr. 321

X2 CrNiMoN 22 5 X5 NiCrMoCuNb 20 18 X6 CrNiNb 18 10 (X10 CrNiNb 18 9)

1,4462 1,4505 1,455

X6 CrNiTi 18 10 X10 CrNiNb 18 9)

1,4541

X6 CrNiMoTi 17 12 2 (X10 CrNiMoTi 18 10) X10 CrNiTi 18 10

1,4571 1,6903

(f ) Cr - Mo ALLOY STEEL

GM CR

DIN - MATERIAL

WS - No

ASTM - material

X20 CrMoV 12 1 1,4922 ? All customary steels with head alloying element "Cr", referes to key for steels.

(f ) COPPER ALLOY

GM CU

DIN - MATERIAL CUNI 10 FE CUNI 30 FE

WS - No 2,0872 2,0882

ASTM - material B466 - C70600 SB111 - C71500 B466 - C71500 ASTM - material A333 Gr. 3, A334 Gr. 3, A350 Gr. LF3, A420 Gr. WPL3 A333 Gr. 9, A334 Gr. 9, A403 Gr. TP316H A333 Gr. 8, A334 Gr. 8, A420 GR. WPL8 A333 Gr. 6, A334 Gr. 6, A420 Gr. WPL6 A333 Gr. 1, A334 Gr. 1 A350 Gr. LF1 A350 Gr. LF2 A420 A671 GR. CD70, A691 Gr. CMSH70

(f ) GM LOW TEMPERATURE STEEL N

DIN - MATERIAL 10 Ni 14

WS - No 1,5637

14 Ni 6 N1 TT X8 Ni 9 TTSt E29 TTStE35 TTSt 35V TTSt 41V TTSt E41 TTSt E36

1,5622 1,5622 1,0488 1,0356 1,0356 1,0437 1,0437 1,0566

140

(f ) GM HIGH TEMPERATURE ALLOY STEEL W

DIN - MATERIAL 10 CrMo 11 10 CrMo 9 10

WS - No 1,7276 1,738

ASTM - material A182 Gr. F5A A182 Gr. F22 A234 Gr. WP22 A335 Gr. P21 A335 Gr. P22 A182 Gr. F5, A234 Gr. WP5, A335 Gr. P5b, A335 Gr. P5d ? ? ? ? ? ? A182 Gr. F9 A213 Gr. T9 A182 Gr. F1, A335 Gr. WP1, A335 Gr. P1, A691 Gr. CM65 A182 Gr. F12 A234 Gr. WP11, A335 Gr. P2, A335 Gr. P11 A335 Gr. P12, A691 Gr. 1CR ? ASTM - material Alloy 5052-0 Alloy 5083-0 ? ASTM - material Incoloy 800 Incoloy 825 Incoloy 625

12 CrMo 19 5

1,7362

15 NiCuMoNb 5 17 CrMoNb 10 20CrMoV 13 5 X8 CrNiNb 16 13 X8 CrNiMoNb 16 16 X8 CrNiMoVNb 16 13 X12 CrMo 9 1 W1 15 Mo 3

1,6368 1,7766 1,7779 1,4961 1,4981 1,4988 1,7386 1,5415

W2

13 CrMo 44

1,7335

W3 GM ALUMINIUM ALLOY AL

14 MoV 6 3 DIN - MATERIAL ALMG 3 ALMG 4.5 Mn ALMG 5 DIN - MATERIAL X10 NiCrAlTi 32 20 NiCr 21 Mo NiCr 22 Mo 9 Nb

1,7715 WS - No 3,3535

GM NICKEL ALLOY

WS - No 1,4876 2,4858 2,4856

NI

141

FORMS FOR CALCULATION OF MANHOUR RATES (Derived Erection Items) Productivity Efficiency Percentage (PEP) = 80% 1.0 1.1 PIPES IN PLANT Item 1.1 x k + Item 3.1/24 x k + Item 6.1 + Item 6.3 = [Mhr/m] 1.2 ON PIPE RACK Item 1.2 x k + Item 3.1/6 x k + Item 6.1 + Item 6.3 = [Mhr/m] 1.3 STEAM TRACING (Item 1.1 x k + Item 3.1/6 x k + Item 6.1 + Item 6.3) x 2,5 = [Mhr/m]

MATERIALS carbon steel stainless steel alloy steel prewrapped (undergr. install.) galvanised aluminium 2.0 2.1 FITTINGS PIPE BENDS ELBOWS 45 and 90

(k) 1,00 1,10 1,10 1,15 0,70 0,85

Mhr/ m x 0,3048 = Mhr/ft

(Item 2.2 + Item 3.1 x 1,8) x f = [Mhr/ea] 2.2 PIPE CAPS (Item 2.2/2 + Item 3.1) x f = [Mhr/ea] 2.3 TEE - PIECES

2.3.1STRAIGHT TEES (Item 2.3 + Item 3.1 x 2,75) x f = [Mhr/ea] 2.3.2REDUCED TEES (Item 2.3 + Item 3.1 x 2,5) x f = [Mhr/ea] 2.4 REDUCERS CONCENTRIC AND ECCENTRIC (Item 2.2 + Item 3.1 for + Item 3.1 for ) x f = [Mhr/ea] MATERIALS (f) See section FACTORS FOR DIFFERENT MATERIALS FOR ITEMS 3.1 TO 3.8 (f) page 139 141

142

3.0 3.1

FLANGES NECK (Item 3.1 + Item 4.1 4.3) x f = [Mhr/ea]

3.2

SLIP-ON, PLAINE (Item 3.2 x 2 + Item 4.1 4.3) x f = [Mhr/ea]

3.3

SOCKET (Item 3.2 + Item 4.1 4.3) x f= [Mhr/ea]

3.4

FREE FLANGE + CIRCUMFERENCE (Brdel) (Item 3.1 + Item 4.1 4.3) x 0,9 x f = [Mhr/ea]

3.5

BLIND FLANGE Item 4.1 4.3 x 1,3 = [Mhr/ea]

3.6

MEASURING ORIFICE ASSEMBLY (Item 4.1 4.3 + Item 3.1 + Item 7.4 + Item 7.5 + Item 4.4) x 2 x f = [Mhr/joint]

3.7

FLANGES - handling only 20% of [Mhr/ea]

4.0 4.1

SMALL FITTINGS WELDOLETS, SOCKOLETS, NIPOLETS Item 2.2 + Item 3.5 x f = [Mhr/ea]

4.2

HALF COUPLINGS FOR WELDING Item 2.2 + Item 3.5 x 0,85 x f = [Mhr/ea]

4.3

FITTINGS WITH SOCKET ENDS

4.3.1WITH ONE END (Item 2.2 x 0,5 + Item 3.2 (for "XS")) x f = [Mhr/ea] 4.3.2WITH TWO ENDS (Item 2.2 + Item 3.2 (for "XS") x 2) x f = [Mhr/ea] 4.3.3WITH THREE ENDS (Item 2.3 + Item 3.2 (for "XS") x 3) x f = [Mhr/ea]

143

4.4

FITTINGS WITH THREADED ENDS

4.4.1 WITH ONE END Item 4.6 x 0,5 + Item 4.7 = [Mhr/ea] 4.4.2 WITH TWO ENDS Item 4.6 + Item 4.7 x 2 = [Mhr/ea] 4.4.3 WITH THREE ENDS Item 4.6 x 1,5 + Item 4.7 x 3 = [Mhr/ea]

5.0 5.1

VALVES WITH FLANGED ENDS

5.1.1VAL VES, GATES, COCKS, NON-RETURN VALVES, DAMPERS, FILTERS, STRAINER Item 5.1 x VF = [Mhr/ea] 5.1.2CONTROL V ALVES Item 5.5 x VF = [Mhr/ea] 5.1.3SAFET Y VALVES Item 5.6 x VF = [Mhr/ea] 5.1.4HYDRANTS Item 5.7 x VF = [Mhr/ea] VF - Factor for installation of flanged v alves NP 6 16 150 # NP 25 40 300 # NP 64 400 # NP 100 600 # NP 160 900 # NP 250 1500 # NP 320 2500 # 5.2 ND to 100 to 4 1,00 1,21 1,41 1,44 1,66 1,90 2,19 ND 125 200 5 8 1,00 1,15 1,29 1,32 1,45 1,60 1,76 ND above 200 above 10 1,00 1,10 1,16 1,21 1,33 1,46 1,61

WITH WELDING ENDS BUTT WELD

5.2.1NP 6 100, LB 150 600 (Item 3.1 (for "STD") x 2 + Item 5.1) x f = [Mhr/ea] 5.2.2NP 160 , LB 900 (Item 3.1 (for "XS") x 2 + Item 5.1) x f = [Mhr/ea] 5.2.3NP 250 320 , LB 1500 2500 (Item 3.1 (for "XXS") x 2 + Item 5.1) x f = [Mhr/ea]

144

5.3

WITH WELDING ENDS SOCKET WELD (Item 3.2 (for "XS") x 2 + Item 5.1) x f = [Mhr/ea]

5.4

WITH THREADED ENDS Item 4.7 x 2 + Item 5.1 = [Mhr/ea]

6.0 6.1

PIPE EXPANSION JOINTS AND FLOWRATE METERS WITH FLANGED ENDS (Item 4.1 4.3 x 2 + Item 5.1) x 1.5 = [Mhr/ea]

6.2

WITH WELDING ENDS (Item 2.2 + Item 3.1) x 2,3 x f = [Mhr/ea]

7.0 7.1

OTHER INSTALLATION WORKS MAKE-ON OF BRANCH CONNECTION

7.1.190 BRANCH C ONNECTION Item 3.4 x f = [Mhr/joint] 7.1.290 BRANCH C ONNECTION WITH REINFORCEMENT (Item 3.4 + Item 3.6) x f = [Mhr/joint] 7.1.3INCLINED BRANCH C ONNECTION Item 3.4 x 2 x f= [Mhr/joint] 7.1.4INCLINED BRANCH C ONNECTION WITH REINFORCEMENT (Item 3.4 + Item 3.6) x 2 x f = [Mhr/joint] 7.1.5EXTRUDED BRANCH C ONNECTION Item 3.4 x 2,5 x f = [Mhr/joint] 7.2 PIPE BENDING

7.2.1BENDING BY A PIPE BENDING MACHINE Item 4.5 = [Mhr/bending] 7.2.2BENDING ALON G RADIUS (r - above 2000 mm) Item 4.5 = [Mhr/m] m = length of pipe bent part

145

7.3

STRESS RELIEVE IN CONNECTION PIPING ON ROTARY EQUIPMENT Item 5.1 x 3 = [Mhr/ea]

7.4

FIELD FABRICATION OF CONCENTRIC AND ECCENTRIC REDUCERS

7.4.1CONCENTRIC REDUCER Item 3.5 = [Mhr/ea] 7.4.2 ECCENTRIC REDUCER Item 3.5 x 1,2 = [Mhr/ea] 7.5 FABRICATION OF MITRE BENDS FROM PIPES Item 3.3 x 1,2 = [Mhr/joint]

146

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule || [kg/m] Unit Build-in Items m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

1,2 10S 0,27

6 = 1/8" 10,3 1,7 2,4 1,7 40 STD 80 XS 10S 0,36 0,47 0,50

8 = 1/4" 13,7 2,2 3,0 1,7 40 STD 80 XS 5S 0,63 0,79 0,65

2,0 0,75

10 = 3/8" 17,1 2,3 2,6 40 STD 0,84 0,93

2,9 1,02

3,2 80 XS 1,10

0,56 0,70 0,78 0,11 0,19 0,10 0,09 0,10 0,14 0,06 0,02 0,39 0,44 0,19 0,56 0,04 0,03 0,26 0,21 0,11 0,10

0,57 0,71 0,79 0,11 0,19 0,11 0,09 0,13 0,18 0,08 0,03 0,51 0,58 0,26 0,56 0,04 0,03 0,26 0,21 0,11 0,11

0,57 0,71 0,80 0,11 0,20 0,11 0,10 0,16 0,22 0,10 0,03 0,64 0,72 0,32 0,56 0,04 0,03 0,26 0,21 0,11 0,11

147

0,78

1,00

0,78

1,00

0,78

1,00

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

10 = 3/8" 17,1 4,0 4,5 5S 1,29 1,40

1,7 10S 0,82

2,0 0,95

2,1 1,00

2,3 40 STD 1,08 1,20

15 = 1/2" 21,3 2,6 2,8 1,28

2,9 80 XS 1,32

3,2 1,43

3,7 1,61

3,9 1,68

0,57 0,71 0,80 0,11 0,20 0,11 0,10 0,16 0,22 0,10 0,03 0,64 0,72 0,32

0,59 0,74 0,82 0,12 0,22 0,12 0,10 0,24 0,34 0,14 0,05 0,96 1,08 0,48 0,56 0,05 0,03 0,26 0,20 0,12 0,12

148

0,78

1,00

0,04 0,028 0,26 0,21 0,11 0,11

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

15 4,0 160 1,71 4,3 1,81 4,8 1,96 5,6 2,17

= 1/2" 21,3 6,0 6,3 7,1 XXS 2,27 2,33 2,49

7,5 2,56

10,6 5S 2,80

13,8 10S

20 = 3/4" 26,7 1,7 2,1 1,05 1,28

0,59 0,74 0,82 0,12 0,22 0,12 0,10 0,24 0,34 0,14 0,05 0,96 1,08 0,48

0,60 0,75 0,84 0,12 0,24 0,13 0,11 0,32 0,44 0,19 0,06 1,26 1,42 0,63 0,55 0,05 0,03 0,25 0,20 0,12 0,13

149

0,77

0,05 0,03 0,26 0,20 0,12 0,12

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] 20 Outer diameter [mm] Wall thickness t = [mm] 2,9 3,9 Schedule 40 STD 80 XS Unit Build-in Items || [kg/m] 1,70 2,20 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 0,60 each "" "" NP 25 64 bar, ANSI 300 400 lbs 0,75 each "" "" NP100 bar, ANSI 600 lbs 0,84 each ORIFICE PLATE INSERTING 0,12 bend PIPE BENDING FOR below 45, FOR > 45 x 2 0,24 piece PIPE THREADING 0,13 each MAKING ON THREADED CONNECTION 0,11 multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 0,32 piece VALVE WITH DRIVE - INSTALLING 0,44 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 0,19 piece BUTTERFLY VALVE - INSTALLING 0,06 piece CONTROL VALVE 1,26 piece SAFETY VALVE 1,42 piece HYDRANT 0,63 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m 0,99 piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 0,05 m SERVICE TEST 0,03 piece SUPPORT FABRICATION 0,25 kg SUPPORT INSTALLATION 0,20 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 0,12 piece GAUGE CONNECTION DRILLING 0,13

4,3 2,38

5,6 160 2,92

= 26,7 6,0 3,07

3/4" 7,1 3,44

20 26,9 7,8 10,6 XXS 3,64 4,21

13,8 4,40

2,0 1,23

2,3 1,40

2,6 1,56

0,60 0,75 0,84 0,12 0,24 0,13 0,11 0,32 0,44 0,19 0,06 1,26 1,42 0,63 0,55 0,05 0,03 0,25 0,20 0,12 0,13

150

0,77

0,99

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build- in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

2,9 1,72

20 26,9 3,6 4,5 2,07 2,49

6,3 3,20

1,7 5S 1,33

2,8 3,4 10S 40 STD 2,12 2,52

25 = 1" 33,4 3,9 4,3 2,84 3,09

4,5 80 XS 3,21

6,0 4,06

6,4 160 4,27

0,60 0,75 0,84 0,12 0,24 0,13 0,11 0,31 0,44 0,19 0,06 1,26 1,42 0,63

0,62 0,78 0,87 0,13 0,27 0,15 0,13 0,39 0,55 0,24 0,08 1,57 1,76 0,78 0,55 0,05 0,04 0,25 0,20 0,13 0,15

151

0,77

0,98

0,05 0,03 0,25 0,20 0,12 0,13

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

7,1 4,61

25 = 1" 33,4 9,1 10,6 XXS 5,46 5,97

13,8 6,68

2,0 1,57

2,3 1,78

2,6 2,00

3,2 2,41

25 33,7 4,0 2,93

5,0 3,54

5,6 3,89

6,3 4,26

0,62 0,78 0,87 0,13 0,27 0,15 0,13 0,39 0,55 0,24 0,08 1,57 1,76 0,78

0,62 0,78 0,87 0,13 0,27 0,15 0,13 0,39 0,55 0,24 0,08 1,57 1,76 0,78 0,55 0,05 0,04 0,25 0,20 0,13 0,15

152

0,77

0,98

0,05 0,04 0,25 0,20 0,13 0,15

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

25 33,7 7,1 4,66 1,7 5S 1,70 2,8 1 0S 2,72 3,6 3,9 40 STD 3,43 3,69

32 = 1 1/4" 42,2 4,0 4,3 3,77 4,02

4,5 4,19

4,9 80 XS 4,51

6,0 5,36

6,4 160 5,66

0,62 0,78 0,87 0,13 0,27 0,15 0,13 0,39 0,55 0,24 0,08 1,57 1,76 0,78

0,66 0,82 0,92 0,13 0,32 0,17 0,14 0,50 0,70 0,30 0,10 1,99 2,24 1,00 0,59 0,06 0,04 0,25 0,20 0,13

153

0,81

1,03

0,05 0,04 0,25 0,20 0,13 0,15

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

7,1 6,15

32 = 1 1/4" 42,2 9,7 10,6 XXS 7,78 8,27

13,8 9,68

2,0 2,00

2,3 2,28

2,6 2,56

32 42,4 2,9 3,6 2,83 3,45

4,5 4,21

5,6 5,09

6,3 5,62

0,66 0,82 0,92 0,13 0,31 0,17 0,14 0,50 0,70 0,30 0,10 1,99 2,24 1,00

0,66 0,82 0,92 0,13 0,31 0,17 0,14 0,50 0,70 0,30 0,10 1,99 2,24 1,00 0,59 0,06 0,25 0,20 0,13

154

0,81

1,03

0,06 0,04 0,25 0,20 0,13

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

1,7 5S 1,96

2,0 2,29

2,3 2,61

2,6 2,93

= 1 1/2" 48,3 2,8 3,2 3,7 3,9 4,3 10S 40 STD 3,15 3,56 4,07 4,28 4,67

40

4,5 4,87

5,0 5,35

5,1 80 XS 5,44

0,69 0,86 0,96 0,14 0,36 0,20 0,17 0,61 0,86 0,37 0,12 2,45 2,76 1,23 0,63 0,07 0,05 0,25 0,20 0,14

155

0,85

1,07

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

6,0 6,27

6,3 6,53

40 = 1 1/2" 48,3 7,1 8,8 10,2 160 XXS 7,22 8,58 9,60

50 = 2" 60,3 10,6 13,8 9,87 11,8 1,7 5S 2,46 2,0 2,88 2,6 3,70 2,8 10S 3,98 2,9 4,11

0,69 0,86 0,96 0,14 0,36 0,20 0,17 0,61 0,86 0,37 0,12 2,45 2,76 1,23

0,73 0,91 1,02 0,15 0,43 0,24 0,20 0,75 1,05 0,45 0,15 3,00 3,38 1,50 0,68 0,07 0,05 0,24 0,19 0,15

156

0,90

1,12

0,07 0,05 0,25 0,20 0,14

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter[mm= inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

3,2 4,51

3,9 4,3 40 STD 5,04 5,43 5,95

3,6

50 60,3 4,5 5,5 80 XS 6,20 7,44

= 5,6 6,0

2" 6,3 7,1 8,7 160 10,6

0,73 0,91 1,02 0,15 0,43 0,24 0,20 0,75 1,05 0,45 0,15 3,00 3,38 1,50

157

0,07 0,05 0,24 0,19 0,15

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

50 = 2" 60,3 11,1 13,8 5S 10S 13,5 15,8

2,1 3,1 40 STD80 XS 3,68 5,35

65 = 2 1/2" 73,0 5,2 7,0 160 XXS 8,71 11,4

9,5 14,9

14,0 20,4

2,0 3,66

65 76,1 2,3 2,9 4,19 5,24

3,2 5,76

0,73 0,91 1,02 0,15 0,43 0,24 0,20 0,75 1,05 0,45 0,15 3,00 3,38 1,50

0,80 1,00 1,12 0,16 0,51 0,31 0,26 0,96 1,34 0,57 0,19 3,82 4,30 1,91 0,75 0,08 0,06 0,24 0,17 0,16

0,80 1,00 1,12 0,16 0,51 0,31 0,26 0,96 1,34 0,57 0,19 3,82 4,30 1,91 0,75 0,08 0,06 0,24 0,17 0,16

158

0,97

1,19

0,97

1,19

0,07 0,05 0,24 0,19 0,15

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

65 3,5 6,27 3,6 6,44 4,0 7,12 5,0 8,78 76,1 5,6 9,75 6,3 10,9 7,1 12,1 8,0 13,5 2,0 5S 4,29

80 = 3" 88,9 2,1 2,3 4,50 4,92

2,5 5,33

0,80 1,00 1,12 0,16 0,51 0,31 0,26 0,96 1,34 0,57 0,19 3,82 4,30 1,91

0,88 1,10 1,23 0,18 0,59 0,40 0,34 1,15 1,61 0,69 0,23 4,60 5,18 2,30 0,83 0,09 0,07 0,23 0,16 0,18

159

1,04

1,26

0,08 0,06 0,24 0,17 0,16

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

2,6 5,54

3,1 10S 6,57

3,2 6,77

3,6 7,58

80 = 3" 88,9 4,5 5,5 5,6 40 STD 9,38 11,3 11,5

6,3 12,8

7,1 80 XS 14,3

7,6 15,3

8,8 160 17,4

11,1 21,3

0,88 1,10 1,23 0,18 0,59 0,40 0,34 1,15 1,61 0,69 0,23 4,60 5,18 2,30

160

0,09 0,07 0,23 0,16 0,18

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

80 = 3" 88,9 15,2 XXS 27,7

2,0 5,55

2,1 5S 5,82

2,6 7,17

2,9 7,98

100 = 4" 114,3 3,1 3,6 10S 8,51 9,84

4,0 10,9

5,0 13,5

5,6 15,0

6,0 40 STD 16,0

0,88 1,10 1,23 0,18 0,59 0,40 0,34 1,15 1,61 0,69 0,23 4,60 5,18 2,30

0,96 1,21 1,35 0,19 0,74 0,52 0,44 1,38 1,93 0,83 0,28 5,50 6,19 2,75 0,90 0,11 0,07 0,15 0,19

161

1,12

1,34

0,09 0,07 0,23 0,16 0,18

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

6,3 16,8

7,1 80 XS 18,8

8,0 21,0

100 = 4" 114,3 8,6 10,0 11,1 120 160 22,4 25,8 28,3

12,5 XXS 31,4

13,5 33,6

17,1 41,0

2,6 8,80

125 139, 7 2,9 9,80

3,2 10,8

0,96 1,21 1,35 0,19 0,74 0,52 0,44 1,38 1,93 0,83 0,28 5,50 6,19 2,75

1,08 1,35 1,51 0,22 0,85 0,69 0,59 1,64 2,30 0,99 0,33 6,57 7,39 3,28 0,99 0,12 0,08 0,13 0,22

162

1,21

1,43

0,11 0,07 0,15 0,19

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

3,6 12,1

4,0 13,4

4,5 15,0

5,0 16,6

125 139,7 5,6 6,3 18,5 20,8

7,1 23,2

8,0 26,0

8,8 28,4

10,0 32,0

11,0 35,0

12,5 39,3

1,08 1,35 1,51 0,22 0,85 0,69 0,59

163

2,30 0,99 0,33 6,57 7,39 3,28

0,12 0,08 0,13 0,22

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

125 139,7 14,2 44,0 2,8 5S 9,58 3,4 10S 11,6

125 = 5" 141,3 6,6 9,5 12,7 40 STD80 XS 120 22,0 30,9 40,3

15,9 160 49,2

19,1 XXS 57,6

150 = 6" 168,3 2,0 2,8 2,9 5S 8,21 11,4 11,8

1,08 1,35 1,51 0,85 0,69 0,59 1,64 2,30 0,99 0,33 6,57 7,39 3,28

1,08 1,35 1,51 0,22 0,85 0,69 0,59 1,64 2,30 0,99 0,33 6,57 7,39 3,28 0,99 0,12 0,08 0,13 0,22

1,19 1,49 1,67 0,22 0,95 0,88 0,75 1,88 2,63 1,13 0,38 7,50 8,44 3,75 1,07 0,13 0,09 0,12 0,24 0,24

164

1,21

1,43

1,29

1,51

0,12 0,08 0,13 0,22

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch]] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

3,4 10S 13,8

3,6 14,6

4,0 16,2

4,5 18,2

5,0 20,2

150 = 6" 168,3 5,6 6,3 22,5

7,1 40 STD 25,2 28,3

8,0 31,7

8,8 34,7

10,0 39,1

11,0 80 XS 42,7

1,19 1,49 1,67 0,24 0,95 0,88 0,75 1,88 2,63 1,13 0,38 7,50 8,44 3,75

165

0,13 0,09 0,12 0,24

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

12,5 120 48,1

150 = 6" 168,3 14,3 16,0 18,3 160 XXS 54,4 60,2 67,8

21,9 5S 79,2

2,8 15,0

3,2 17,1

200 = 8" 219,1 3,6 3,8 10S 19,2 20,2

4,5 23,8

5,6 29,5

5,9 31,1

1,19 1,49 1,67 0,24 0,95 0,88 0,75 1,88 2,63 1,13 0,38 7,50 8,44 3,75

1,54 1,92 2,16 0,31 1,20

166

2,50 3,50 1,50 0,50 10,00 11,25 5,00 1,33 0,17 0,12 0,12 0,31

1,55

1,77

0,13 0,09 0,12 0,24

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

6,3 33,1

6,4 20 33,6

7,0 30 36,7

8,0 41,7

200 = 8" 219,1 8,2 8,8 40 STD 42,7 45,7

10,3 60 53,1

12,7 80 XS 64,7

14,2 71,8

15,1 100 76,1

16,0 80,2

18,3 120 90,7

1,54 1,92 2,16 0,31 1,20

167

2,50 3,50 1,50 0,50 10,00 11,25 5,00

0,17 0,12 0,12 0,31

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

20,6 140 101

200 = 8" 219,1 22,2 23,0 XXS 160 108 111

28,0 132

2,9 19,3

3,2 21,3

3,4 5S 22,6

250 = 10" 273,0 3,6 4,0 23,9 26,6

4,2 10S 27,9

5,0 33,1

5,6 37,0

1,54 1,92 2,16 0,31 1,20

1,92 2,39 2,68 0,38

168

2,50 3,50 1,50 0,50 10,00 11,25 5,00

4,25 5,95 2,55 0,85 17,00 19,13 8,50 1,58 0,20 0,14 0,10 0,38

1,80

2,02

0,17 0,12 0,12 0,31

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] 6,3 Schedule Unit Build-in Items || [kg/m] 41,5 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 1,92 each "" "" NP 25 64 bar, ANSI 300 400 lbs 2,39 each "" "" NP100 bar, ANSI 600 lbs 2,68 each ORIFICE PLATE INSERTING 0,38 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 4,25 piece VALVE WITH DRIVE - INSTALLING 5,95 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 2,55 piece BUTTERFLY VALVE - INSTALLING 0,85 piece CONTROL VALVE 17,00 piece SAFETY VALVE 19,13 piece HYDRANT 8,50 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 0,20 m SERVICE TEST 0,14 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,10 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 0,38 piece GAUGE CONNECTION DRILLING

6,4 20 42,1

7,1 46,6

7,8 30 51,1

8,0 52,3

250 = 10" 273,0 8,8 9,3


40 STD

10,0 64,9

11,0 71,2

57,4

60,6

12,7 80S 60 77,3 81,6

12,0

14,2 XS 90,7

169

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

15,1 80 96,2

16,0 102

17,5 110

18,0 113

250 = 10" 273,0 18,3 20,0 100 115 125

21,4 120 133

22,2 137

25,4 155

28,6 173

300 = 12" 323,9 3,2 3,6 25,3 28,5

140 XXS 160

1,92 2,39 2,68 0,38

2,31 2,89 3,24 0,46

170

4,25 5,95 2,55 0,85 17,00 19,13 8,50

5,10 7,14 3,06 1,02 20,40 22,95 10,20 1,84 0,24 0,17 0,10 0,46

2,06

0,20 0,14 0,10 0,38

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

4,0 5S 31,6

4,6 10S 36,3

5,0 39,4

5,6 44,0

6,4 20 50,2

300 = 12" 323,9 7,1 8,0 55,5 62,4

8,4 30 65,4

9,5 10,3 40S STD 40 68,5 73,8 79,8

8,8

11,0 85,0

2,31 2,89 3,24 0,46

171

5,10 7,14 3,06 1,02 20,40 22,95 10,20 2,28 0,24 0,17 0,10 0,46

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] 12,7 Schedule 80S XS Unit Build-in Items || [kg/m] 97,6 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 2,31 each "" "" NP 25 64 bar, ANSI 300 400 lbs 2,89 each "" "" NP100 bar, ANSI 600 lbs 3,24 each ORIFICE PLATE INSERTING 0,46 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 5,10 piece VALVE WITH DRIVE - INSTALLING 7,14 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 3,06 piece BUTTERFLY VALVE - INSTALLING 1,02 piece CONTROL VALVE 20,40 piece SAFETY VALVE 22,95 piece HYDRANT 10,20 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 0,24 m SERVICE TEST 0,17 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,10 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 0,46 piece GAUGE CONNECTION DRILLING

14,3 60 109

16,0 122

17,5 80 132

300 = 12" 323,9 20,0 21,4 100 150 160

22,2 165

25,4
120 XXS

187

28,6 140 209

33,3 160 239

350 = 14" 355,6 3,2 3,6 27,8 31,3

2,73 3,42 3,83 0,55

172

5,95 8,33 3,57 1,19 23,80 26,78 11,90 2,09 0,27 0,19 0,10 0,55

2,31

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

4,0 5S 34,7

4,8 10S 41,6

5,0 43,3

5,6 48,4

6,4 10 55,2

350 = 14" 355,6 7,1 7,9 20 61,1 67,8

8,8

9,5 30 STD 75,4 81,2

11,1 40 94,4

12,7 XS 108

14,2 120

2,73 3,42 3,83 0,55

173

5,95 8,33 3,57 1,19 23,80 26,78 11,90 2,53 0,27 0,19 0,10 0,55

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

15,1 60 127

17,5 146

19,1 80 159

350 = 14" 355,6 22,2 23,8 25,0 100 183 195 204

27,8 120 225

31,8 140 254

35,7 160 282

400 = 16" 406,4 3,6 4,0 4,2 5S 35,8 39,7 41,7

2,73 3,42 3,83 0,55

3,17 3,97 4,44 0,63

174

5,95 8,33 3,57 1,19 23,80 26,78 11,90

6,80 9,52 4,08 1,36 27,20 30,60 13,60 2,35 0,31 0,21 0,08 0,63

2,57

2,79

0,27 0,19 0,10 0,55

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] 4,8 Schedule 10S Unit Build-in Items || [kg/m] 47,6 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 3,17 each "" "" NP 25 64 bar, ANSI 300 400 lbs 3,97 each "" "" NP100 bar, ANSI 600 lbs 4,44 each ORIFICE PLATE INSERTING 0,63 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 6,80 piece VALVE WITH DRIVE - INSTALLING 9,52 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 4,08 piece BUTTERFLY VALVE - INSTALLING 1,36 piece CONTROL VALVE 27,20 piece SAFETY VALVE 30,60 piece HYDRANT 13,60 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 0,31 m SERVICE TEST 0,21 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,08 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 0,63 piece GAUGE CONNECTION DRILLING

5,6 55,4

6,4 10 63,2

7,1 70,0

7,9 20 77,7

400 = 16" 406,4 8,8 9,5 11,0 30 STD 86,4 93,1 107

12,7 40 XS 123

14,2 138

16,0 154

16,7 60 161

175

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

17,5 80 168

20,0 191

21,4 203

400 = 16" 406,4 22,2 25,0 26,2 100 120 140 211 235 246

31,0 160 287

36,5 333

40,5 366

450 = 18" 457,0 3,6 4,0 5S 40,3 44,7

4,2 47,0

3,17 3,97 4,44 0,63

3,63 4,53 5,08 0,73

176

6,80 9,52 4,08 1,36 27,20 30,60 13,60

7,65 10,71 4,59 1,53 30,60 34,43 15,30 2,60 0,34 0,24 0,08 0,73

2,82

3,04

0,31 0,21 0,08 0,63

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

4,8 10S 53,6

5,6 62,4

6,4 10 71,2

7,1 78,9

7,9 20 87,6

450 = 18" 457,0 8,8 9,5 STD 97,4 105

11,1 30 122

12,7 XS 139

14,3 40 156

16,0 174

17,5 190

3,63 4,53 5,08 0,73

177

7,65 10,71 4,59 1,53 30,60 34,43 15,30

0,34 0,24 0,08 0,73

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

19,1 60 207

22,2 238

23,8 80 255

450 = 18" 457,0 25,0 29,4 100 267 310

34,9 120 364

39,7 140 409

45,2 160 460

2,9 36,2

500 = 20" 508,0 4,0 4,5 49,8 55,9

4,8 5S 59,6

3,63 4,53 5,08 0,73

4,10 5,12 5,74 0,82

178

7,65 10,71 4,59 1,53 30,60 34,43 15,30

8,50 11,90 5,10 1,70 34,00 38,25 17,00 2,86 0,38 0,26 0,08 0,82

3,08

3,30

0,34 0,24 0,08 0,73

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

5,0 62,1

5,5 10S 68,2

6,3 78,0

6,4 10 79,3

7,1 87,8

500 = 20" 508,0 8,0 8,8 98,8 108

9,5 10,0 20 STD 117 123

11,0 135

12,7 30 XS 155

14,2 173

4,10 5,12 5,74 0,82

179

8,50 11,90 5,10 1,70 34,00 38,25 17,00

0,38 0,26 0,08 0,82

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter[mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

15,1 40 184

16,0 194

17,5 212

20,0 241

20,6 60 248

500 = 20" 508,0 22,2 25,0 266 298

26,2 80 312

32,5 100 382

38,1 120 442

44,4 140 508

50,0 160 565

4,10 5,12 5,74 0,82

180

8,50 11,90 5,10 1,70 34,00 38,25 17,00

0,38 0,26 0,08 0,82

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

4,5 61,6

4,8 5S 65,7

5,0 68,4

5,5 10S 75,2

6,4 10 87,3

550 = 22" 559,0 7,1 8,0 96,8 109

8,8 120

9,5 20 STD 129

11,0 149

12,7 30 XS 171

14,2 191

4,58 5,73 6,42 0,92

181

9,35 13,09 7,48 3,74 37,40 42,08 18,70 3,11 0,41 0,29 0,08 0,92

3,33

3,55

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

15,9 40 213

17,5 234

20,0 266

22,2 60 294

550 = 22" 559,0 25,0 28,6 80 330 375

34,9 100 452

41,3 120 528

47,6 140 601

54,0 160 673

600 = 24" 610,0 4,0 4,5 59,9 67,3

4,58 5,73 6,42 0,92

5,08 6,35 7,11 1,02

182

9,35 13,09 7,48 3,74 37,40 42,08 18,70

10,20 14,28 8,16 4,08 40,80 45,90 20,40 3,37 0,45 0,31 0,08 1,02

3,59

0,41 0,29 0,08 0,92

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

5,0 74,7

5,5 5S 82,1

5,6 83,6

6,3 93,9

6,4 10 95,4

600 = 24" 610,0 7,1 8,0 106 119

8,8 131

9,5 10,0 20 STD 141 148

12,7 XS 187

14,3 30 210

5,08 6,35 7,11 1,02

183

10,20 14,28 8,16 4,08 40,80 45,90 20,40 3,81 0,45 0,31 0,08 1,02

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

16,0 235

17,5 40 256

20,0 291

22,2 322

24,6 60 356

600 = 24" 610,0 25,0 31,0 80 361 443

38,9 100 549

46,0 120 641

52,4 140 721

59,5 160 809

5,08 6,35 7,11 1,02

184

10,20 14,28 8,16 4,08 40,80 45,90 20,40

0,45 0,31 0,08 1,02

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

5,0 80,9

5,6 90,5

6,3 102

7,1 114

7,9 10 127

650 = 26" 660,0 8,8 9,5 STD 142 153

11,0 176

12,7 20 XS 203

14,2 226

17,5 278

22,2 35

5,59 6,99 7,83 1,12

185

11,05 15,47 8,84 4,42 44,20 49,73 22,10 3,63 0,48 0,34 0,08 1,12

3,84

4,06

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

4,0 69,8

5,0 87,2

5,6 97,5

6,0 104

6,3 110

700 = 28" 711,0 7,1 7,9 10 123 137

8,8 STD 153

9,5 165

10,0 173

11,0 12,7 20 XS 190 219

6,11 7,64 8,56 1,22

186

11,90 16,66 9,52 4,76 47,60 53,55 23,80 3,88 0,52 0,37 0,08 1,22

4,10

4,32

8. ESTIMATE POINTS FOR BUILD- IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

14,2 244

700 = 28" 711,0 15,9 17,5 30 273 300

20,0 341

5,6 105

6,3 118

6,4 5S 119

750 = 30" 762,0 7,1 7,9 10 132 147

8,8 164

9,5 STD 177

11,0 204

6,11 7,64 8,56 1,22

6,65 8,31 9,31 1,33

187

11,90 16,66 9,52 4,76 47,60 53,55 23,80

12,75 17,85 10,20 5,10 51,00 57,38 25,50 4,13 0,55 0,39 0,08 1,33

4,35

4,57

0,52 0,36 0,08 1,22

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

12,7 20 XS 235

750 = 30" 762,0 14,2 15,9 17,5 30 262 293 322

20,0 366

4,0 79,9

5,0 99,8

800 = 32" 813,0 5,6 6,0 6,3 112 120 125

7,1 141

7,9 10 157

6,65 8,31 9,31 1,33

7,19 8,99 10,07 1,44

188

12,75 17,85 10,20 5,10 51,00 57,38 25,50

13,60 19,04 10,88 5,44 54,40 61,20 27,20 4,39 0,59 0,41 0,08 1,44

4,61

4,83

0,55 0,39 0,08 1,33

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

8,8 175

9,5 STD 188

10,0 198

11,0 218

800 = 32" 813,0 12,7 14,2 20 XS 251 280

15,9 30 313

17,5 40 344

20,0 392

22,2 434

850 = 34" 864,0 6,3 7,1 133 150

7,19 8,99 10,07 1,44

7,75 9,68 10,85 1,55

189

13,60 19,04 10,88 5,44 54,40 61,20 27,20

14,45 20,23 11,56 5,78 57,80 65,03 28,90 4,64 0,62 0,43 0,08 1,55

4,86

0,59 0,41 0,08 1,44

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

7,9 10 167

8,8 186

9,5 STD 200

11,0 232

850 = 34" 864,0 12,7 14,2 20 XS 267 298

15,9 30 333

17,5 40 366

20,0 417

4,0 89,9

900 = 36" 914,0 5,0 5,6 112 126

7,75 9,68 10,85 1,55

8,31 10,39 11,64 1,66

190

14,45 20,23 11,56 5,78 57,80 65,03 28,90 5,08 0,62 0,43 0,08 1,55

15,30 21,42 12,24 6,12 61,20 68,85 30,60 4,90 0,66 0,46 0,08 1,66

5,12

5,34

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

6,3 141

7,1 159

7,9 10 177

8,0 179

8,8 197

900= 36" 914,0 9,5 10,0 STD 212 223

11,0 245

12,7 20 XS 283

14,2 316

15,9 30 353

17,5 387

8,31 10,39 11,64 1,66

191

15,30 21,42 12,24 6,12 61,20 68,85 30,60

0,66 0,46 0,08 1,66

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

900 = 36" 914,0 19,1 20,0 22,2 40 422 442 489

5,0 125

5,6 140

6,3 157

1000 = 40" 1016,0 7,1 8,0 177 199

8,8 219

9,5 STD 236

10,0 248

11,0 273

8,31 10,39 11,64 1,66

9,47 11,84 13,26 1,89

192

15,30 21,42 12,24 6,12 61,20 68,85 30,60

17,00 23,80 13,60 6,80 68,00 76,50 34,00 5,41 0,73 0,51 0,08 1,89

5,63

5,85

0,66 0,46 0,08 1,66

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

12,5 310

12,7 XS 315

1000 = 40" 1016,0 14,2 16,0 17,5 351 395 431

20,0 492

22,2 545

6,3 165

7,1 186

1050 = 42" 1067,0 8,0 8,8 209 230

9,5 STD 248

9,47 11,84 13,26 1,89

10,06 12,58 14,09 2,01

193

17,00 23,80 13,60 6,80 68,00 76,50 34,00

17,85 24,99 14,28 7,14 71,40 80,33 35,70 5,66 0,76 0,53 0,08 2,01

5,88

6,10

0,73 0,51 0,08 1,89

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

11,0 287

1050=42" 1067,0 12,7 14,2 XS 331 369

17,5 454

1100 = 44" 1118,0 7,1 9,5 12,7 STD XS 195 260 347

7,1 212

1200 = 48" 1219,0 9,5 10,3 12,7 STD XS 284 307 378

15,9 472

10,06 12,58 14,09 2,01

10,66 13,33 14,93 2,13

11,89 14,86 16,65 2,38

194

17,85 24,99 14,28 7,14 71,40 80,33 35,70

18,70 26,18 14,96 7,48 74,80 84,15 37,40 5,92 0,80 0,56 0,08 2,13

6,14

6,36

20,40 28,56 16,32 8,16 81,60 91,80 40,80 6,43 0,87 0,61 0,08 2,38

6,65

6,87

0,76 0,53 0,08 2,01

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

5,0 150

1200 1220,0 8,0 239

10,0 229

1300=52" 1321,0 20,0 9,5 12,7 STD XS 593 308 410

1350=54" 1372,0 7,9 9,5 12,7 STD XS 266 320 426

15,9 532

1400 1420,0 6,3 220

7.1 248

11,89 14,86 16,65 2,38

13,15 16,44 18,41 2,63

13,79 17,24 19,30 2,76

14,44 18,04 20,21 2,89

195

20,40 28,56 16,32 8,16 81,60 91,80 40,80 6,43 0,87 0,61 0,08 2,38

6,65

6,87

22,10 30,94 17,68 8,84 88,40 99,45 44,20 6,94 0,94 0,66 0,08 2,63

22,95 32,13 18,36 9,18 91,80 103,28 45,90 7,16 7,19 7,41 0,97 0,68 0,08 2,76

7,63

23,80 33,32 19,04 9,52 95,20 107,10 47,60 7,45 7,67 1,01 0,70 0,08 2,9

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] 8,0 Schedule Unit Build-in Items || [kg/m] 279 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 14,44 each "" "" NP 25 64 bar, ANSI 300 400 lbs 18,04 each "" "" NP100 bar, ANSI 600 lbs 20,21 each ORIFICE PLATE INSERTING 2,89 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 23,80 piece VALVE WITH DRIVE - INSTALLING 33,32 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 19,04 piece BUTTERFLY VALVE - INSTALLING 9,52 piece CONTROL VALVE 95,20 piece SAFETY VALVE 107,10 piece HYDRANT 47,60 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m 7,89 piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 1,01 m SERVICE TEST 0,70 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,08 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 2,89 piece GAUGE CONNECTION DRILLING

8,8 307

10,0 348

1400 1420,0 11,0 12,5 383 434

14,2 493

16,0 555

17,5 606

20,0 691

1400 = 56" 1422,0 9,5 12,7 14,3 STD XS 331 442 497

14,44 18,04 20,21 2,89

196

23,80 33,32 19,04 9,52 95,20 107,10 47,60 7,45 7,67 1,01 0,70 0,08 2,89

7,89

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] 8,0 Schedule Unit Build-in Items || [kg/m] 299 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 15,75 each "" "" NP 25 64 bar, ANSI 300 400 lbs 19,69 each "" "" NP100 bar, ANSI 600 lbs 22,05 each ORIFICE PLATE INSERTING 3,15 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 25,50 piece VALVE WITH DRIVE - INSTALLING 35,70 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 20,40 piece BUTTERFLY VALVE - INSTALLING 10,20 piece CONTROL VALVE 102,00 piece SAFETY VALVE 114,75 piece HYDRANT 51,00 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m 7,96 piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 1,08 m SERVICE TEST 0,75 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,08 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 3,15 piece GAUGE CONNECTION DRILLING

8,8 328

1500 1520,0 10,0 373

12,5 465

14,2 528

9,5 STD 355

1500 = 60" 1524,0 12,7 14,3 XS 474 533

15,9 592

5,0 199

1600 1620,0 8,0 318

8,8 350

15,75 19,69 22,05 3,15

17,09 21,36 23,93 3,42

197

8,18

8,40

25,50 35,70 20,40 10,20 102,00 114,75 51,00 7,96 8,18 1,08 0,75 0,08 3,15

8,40

27,20 38,08 21,76 10,88 108,80 122,40 54,40 8,47 1,15 0,80 0,08 3,42

8,69

8,91

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] 10,0 Schedule Unit Build-in Items || [kg/m] 398 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING- WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 17,09 each "" "" NP 25 64 bar, ANSI 300 400 lbs 21,36 each "" "" NP100 bar, ANSI 600 lbs 23,93 each ORIFICE PLATE INSERTING 3,42 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 27,20 piece VALVE WITH DRIVE - INSTALLING 38,08 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 21,76 piece BUTTERFLY VALVE - INSTALLING 10,88 piece CONTROL VALVE 108,80 piece SAFETY VALVE 122,40 piece HYDRANT 54,40 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 1,15 m SERVICE TEST 0,80 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,08 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 3,42 piece GAUGE CONNECTION DRILLING

1600 1620,0 12,5 14,2 496 563

16,0 634

9,5 STD 379

1600 = 64" 1626,0 12,7 14,3 XS 506 569

15,9 632

9,5 STD 403

1700 = 68" 1727,0 12,7 14,3 XS 538 605

17,09 21,36 23,93 3,42

18,46 23,07 25,84 3,69

198

27,20 38,08 21,76 10,88 108,80 122,40 54,40 8,47 1,15 0,85 0,08 3,42

8,69

8,91

28,90 40,46 23,12 11,56 115,60 57,80 57,80 8,98 9,20 1,22

9,42

0,08 3,69

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] Outer diameter [mm] Wall thickness t = [mm] Schedule Unit Build-in Items || [kg/m] m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs each "" "" NP 25 64 bar, ANSI 300 400 lbs each "" "" NP100 bar, ANSI 600 lbs each ORIFICE PLATE INSERTING bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING piece VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE WITH DRIVE - INSTALLING piece BUTTERFLY VALVE - INSTALLING piece CONTROL VALVE piece SAFETY VALVE piece HYDRANT piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) m SERVICE TEST piece SUPPORT FABRICATION kg SUPPORT INSTALLATION kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING piece GAUGE CONNECTION DRILLING

1800 1820,0 10,0 14,2 447 633

17,5 779

1800 = 72" 1829,0 9,5 12,7 14,3 STD XS 427 570 641

1900 = 76" 1930,0 9,5 12,7 14,3 STD XS 451 601 676

1950 = 78" 1981,0 9,5 12,7 14,3 STD XS 462 617 694

19,85 24,81 27,79 3,97

19,85 24,81 27,79 3,97

21,26 26,58 29,77 4,25

21,98 27,48 30,77 4,40

199

30,60 42,84 24,48 12,24 122,40 137,70 61,20 9,49 1,29 0,90 0,08 3,97

9,71

30,60 42,84 24,48 12,24 122,40 137,70 61,20 9,93 9,49 1,29 0,90 0,08 3,97

9,71

32,30 45,22 25,84 12,92 129,20 145,35 64,60 9,93 10,00 10,22 1,36 0,95 0,08 4,25

33,15 46,41 26,52 13,26 132,60 149,18 66,30 10,44 10,25 10,47 1,39 0,97 0,08 4,40

10,69

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] 2000 Outer diameter [mm] 2020,0 Wall thickness t = [mm] 11,0 12,5 16,0 Schedule Unit Build-in Items || [kg/m] 546 620 792 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 22,70 each "" "" NP 25 64 bar, ANSI 300 400 lbs 28,38 each "" "" NP100 bar, ANSI 600 lbs 31,78 each ORIFICE PLATE INSERTING 4,54 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 34,00 piece VALVE WITH DRIVE - INSTALLING 47,60 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 27,20 piece BUTTERFLY VALVE - INSTALLING 13,60 piece CONTROL VALVE 136,00 piece SAFETY VALVE 153,00 piece HYDRANT 68,00 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m 10,51 10,73 10,95 piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 1,43 m SERVICE TEST 1,00 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,08 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 4,54 piece GAUGE CONNECTION DRILLING

20,0 988

2000 = 80" 2032,0 9,5 12,7 14,3 STD XS 474 633 712

2050 = 82" 2083,0 9,5 12,7 14,3 STD XS 486 649 730

22,70 28,38 31,78 4,54

23,43 29,29 32,80 4,69

200

34,00 47,60 27,20 13,60 136,00 153,00 68,00 10,51 10,73 10,95 1,43 1,00 0,08 4,54

34,85 48,79 27,88 13,94 139,4 156,8 69,70 10,76 1,46 1,02 0,08 4,69

10,98

11,20

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [mm=inch] 2100 = 84" Outer diameter [mm] 2134,0 Wall thickness t = [mm] 9,5 12,7 14,3 Schedule STD XS Unit Build-in Items || [kg/m] 498 665 748 m PIPE - LAYING IN FIELD m PIPE - LAYING ON RACK m PIPE - DISMANTLING piece TWO - END FITTING - ALIGNMENT piece THREE - END FITTING - ALIGNMENT each BUTT WELD each FILLET (SOCKET) WELD each MITRE WELD each NOZZLE WELD piece WELDOLET, NIPOLET - WELDING piece SADDLE REINFORCEMENT - WELDING each SEAL RING - WELDING piece INSERT RING (ONLY FOR ALU) piece WELD CUTTING IN ALTERATIONS multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 each FLANGE BOLTING-UP NP 6 16 bar, ANSI 150 lbs 24,16 24,16 each "" "" NP 25 64 bar, ANSI 300 400 lbs 30,20 30,20 each "" "" NP100 bar, ANSI 600 lbs 33,82 33,82 each ORIFICE PLATE INSERTING 4,83 4,83 bend PIPE BENDING FOR below 45, FOR > 45 x 2 piece PIPE THREADING each MAKING ON THREADED CONNECTION multipl.DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 piece VALVE - INSTALLING 35,70 35,70 piece VALVE WITH DRIVE - INSTALLING 49,98 49,98 piece BUTTERFLY VALVE WITH DRIVE - INSTALLING 28,56 28,56 piece BUTTERFLY VALVE - INSTALLING 14,28 14,28 piece CONTROL VALVE 142,80 142,80 piece SAFETY VALVE 160,65 160,65 piece HYDRANT 71,40 71,40 piece VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m 11,02 11,24 11,46 piece DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 m PRESSURE TEST (WATER, AIR, STEAM, GAS) 1,50 1,50 m SERVICE TEST 1,05 1,05 piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 0,08 0,08 kg SPRING SUSP. AND HANG. - BUILD-IN AS ITEM 7.2 piece WELD ROOT GRINDING 4,83 4,83 piece GAUGE CONNECTION DRILLING

10,0 546

12,5 681

2200 2220,0 14,2 16,0 773 871

17,5 952

20,0 1086

25,64 32,05 35,90 5,13

201

37,40 52,36 29,92 14,96 149,60 168,30 74,80 11,53 11,75 1,57 1,10 0,08 5,13

11,97

8. ESTIMATE POINTS FOR BUILD-IN ITEMS OF ABOVE-GROUND PIPING Item 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 55.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

Nominal diameter [ mm/inch ] 8. AUFMASSFAKTORS VON Nennweite [ mm/" ] Outer diameter [mm] MONTAGEPOSITIONEN Au.Durchm. [mm] Wall thickness t [mm] OBERIRD. ROHRLEITUNGEN Wanddicke t [mm] Schedule Schedule Pos Einh. Montageposition || [kg/m] Unit Buildin Items || [kg/m] 1.1 m ROHR VERLEGEN IM FELD m PIPE LAYING IN FIELD 1.2 " " " " " ROHRBRCKE " "" " " ON RACK 1.3 " " " DEMONTIEREN " " " DISMANTLING 2.2 stck FORMSTCK MIT ZWEI ENDEN EINPASSEN piece TWOEND FITTING ALIGNMENT 2.3 " " " MIT DREI ENDEN " " " THREEEND " " " " 3.1 verb. RUNDNAHT AUSFHRUNG UND SCHWEISSUNG each PIPE BUTT WELD 3.2 " KEHLNAHT " " " "" (SOCKET) " " 3.3 " SEGMENTNAHT " " " "" MITRE " " 3.4 " T STUTZENNAHT " " " "" NOZZLE " " 3.5 stck WELDOLET, NIPOLET SCHWEISSEN piece WELDOLET, NIPOLET WELDING 3.6 " V RING SCHWEISSEN " SADDLE REINFORCEMENT WELDING 3.7 verb. SCHWEISSRING DICHTUNG each SEAL RING WELDING 3.8 stck EINLEGERING (NUR BEI ALU) piece INSERT RING (ONLY FOR ALU) 3.9 " TRENNSCHNITT BEI NDERUNGEN " WELD CUTTING IN ALTERATIONS 3.10 multipl.WERKSTOFFMULTIPLIKATOR FR ITEM 3.1 BIS 3.8 multipl.MATERIAL MULTIPLIER FOR ITEM 3.1 TO 3.8 4.1 verb. FLANSCHVERB. NP 6 16 bar, ANSI 150 each FLANGE BOLTINGUP NP 6 16 bar, ANSI 150 lbs " "" " " NP 25 64 bar, ANSI 300 400 " "" "" NP 25 64 bar, ANSI 300 400 lbs 4.2 4.3 " "" " " NP100 bar, ANSI 600 " "" "" NP100 bar, ANSI 600 lbs 4.4 " STECKSCHEIBE EINSETZEN " ORIFICE PLATE INSERTING 4.5 biegung ROHR BIEGEN FR BIS 45, FR > 45 x 2 bend PIPE BENDING FOR to 45, FOR above 45 x 2 4.6 stck GEWINDE SCHNEIDEN piece PIPE THREADING 4.7 verb. GEWINDE EINDICHTEN each MAKING ON THREADED CONNECTION DEMONTAGE : 0,7 x FAKT. ITEM 4.1 BIS 4.4 UND 4.7 DISASSEMBLY : 0,7 x PTS. ITEM 4.1 TO 4.4 AND 4.7 4.8 5.1 stck ARMATUR EINBAUEN piece VALVE INSTALLING 5.2 " ARMATUR M. ANTRIEB " " " VALVE WITH DRIVE " " 5.3 " EINKL. ARMAT. M. ANTRIEB " " " BUTTERFLY VALVE WITH DRIVE INSTALLING 5.4 " EINKLEMM ARMATUR " " " BUTTERFLY VALVE " " 5.5 " STEUERUNGSVENTIL " CONTROL VALVE 5.6 " SICHERHEITSVENTIL " SAFETY VALVE 5.7 " HYDRANT " HYDRANT 5.8 " SPINDELVERLNGERUNG BL=1/2/3 MET. " VALVE SPINDLE EXTENSION LENGHTS 1-2-3 m 5.9 " DEMONTAGE : 0,7 x FAKT. ITEM 5.1 BIS 5.8 " DISASSEMBLY : 0,7 x PTS. ITEM. 5.1 TO 5.8 6.1 m DRUCKPROBE MIT WASSER ODER GAS m PRESSURE TEST (WATER, AIR, STEAM, GAS) 6.2 " DICHTHEITSPROBE (SERVICETEST) " SERVICE TEST 7.1 stck VERSTEIFUNGSSTEG ANFERTIGEN piece SUPPORT FABRICATION kg SUPPORT INSTALLATION 7.2 kg HLTERUNGEN (UNTERST.) MONT. 7.3 " FEDERHNGER U. BCKE MONT. WIE ITEM 7.2 " SPRING SUSP. AND HANG. - B.IN AS ITEM 7.2 piece WELD ROOT GRINDING 7.4 stck SCHW. WURZEL BERH. AUSSCHL. " GAUGE CONNECTION DRILLING 7.5 " MESSLEITUNGABGANG DURCHBOHREN

8. CJEVOVODI NADZEMNO VRIJED. BODOVI OSNOVNIH MONTANIH POZICIJA Poz. 1.1 1.2 1.3 2.2 2.3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 6.1 6.2 7.1 7.2 7.3 7.4 7.5

NO / NV [ mm/" ] Vanj. promj. [mm] Deblj. stij. t [mm] Schedule Jed.mj. Montana pozicija || [kg/m] m CIJEV - POLAGANJE U POSTROJENJU " " " " " NA CJEV. MOSTU " " " - DEMONTAA kom FITING S DVA KRAJA - UPASIVANJE " " " S TRI KRAJA " " spoj SU EONI SPOJ - IZVEDBA I ZAVARIVANJE " USADNI SPOJ (SOCKET) " " " " " SEGMENTNI SPOJ " " " " " UBODNI SPOJ " " " " kom WELDOLET, NIPOLET - UGRADNJA I ZAVARIVANJE " SEDLASTO OJA ANJE - IZRADA I ZAVARIVANJE spoj BRTVENI PRSTEN - IZVEDBA I ZAVARIVANJE kom USADNI PRSTEN (SAMO ZA ALUMINIJ) " ODREZIVANJE ZAVARA KOD PREINA ENJA faktor FAKTOR ZA RAZL. MATERIJALE ZA POZ. 3.1 DO 3.8 spoj PRIRUBNIKI SPOJ NP 6 16 bar, ANSI 150 " "" " " NP 25 64 bar, ANSI 300 400 " "" " " NP100 bar, ANSI 600 " UGRADNJA MJERNE BLENDE, TEKAJBE I SL. savijanje SAVIJANJE CIJEVI ZA DO 45, ZA > 45 x 2 kom NAREZIVANJE NAVOJA spoj NAVOJNI SPOJ - IZVEDBA DEMONTAA : 0,7 x VRIJED. POZ. 4.1 DO 4.4 i 4.7 kom ARMATURA (VENTILI) - UGRADNJA " " " S POGONOM (EM, PNEUM.) " " " LEPTIR ZAKLOPKA " " " " " " " " " " " - UGRADNJA " REGULACIJSKI VENTIL " SIGURNOSNI " " " HIDRANT " PRODUENJE VRETENA VENTILA DUINA 1-2-3 m " DEMONTAA : 0,7 x VRIJEDNOSTI POZ. 5.1 DO 5.8 m TLA NA PROBA (VODA, ZRAK, PARA, PLIN) " SERVISNI TEST kom POTPORANJ - IZRADA I ZAVARIVANJE kg MONTAA SUPORTA (BEZ IZRADE) " OPR. NOSAI I OVJESI - MONTAA NORM. KAO 7.2 kom BRUENJE POVIENOG KORIJENA ZAVARA " MJERNI PRIKLJUCI - BUENJE

202

XI. WEIGHT FACTORS


(acc. to LURGI Company from Germany)

1. PIPING 1.1 1.1.1 PIPING IN PLANTS - ALL DIAMETERS PREFABRICATION - Withdrawal of material from store - Cutting and tack welding - Welding - Small parts, alignment and welding % % % % %

1.1.2

ERECTION - Transport - Hoisting, tack welding, installation of valves and other small parts - Welding - Supporting % % % % %

1.1.3

TESTING - Inspection of piping and removal of defects - Pressure test and purging - Final inspection and takeover % % % %

1.2 1.2.1

PIPING IN PLANTS above 2 PREFABRICATION - Withdrawal of material from the store - Cutting and tack welding - Welding - Small parts, alignment and welding % % % % %

1.2.2

ERECTION - Transport - Hoisting, tack welding, installation of valves and other small parts - Welding - Supporting % % % % %

1.2.3

TESTING - Inspection of piping and removal of defects - Pressure tests - Final inspection and takeover % % % %

203

1.3 1.3.1

PIPING IN PLANTS to 2 ERECTION - Withdrawal of material from the store and transport - Cutting, tack welding and welding - Valve installation - Supporting % % % % %

1.3.2

TESTING % % % %

- Inspection of piping and removal of defects - Final inspection and takeover

1.4 1.4.1

LINE PIPING ON PIPE RACKS AND SLEEPER WAYS PREFABRICATION - Withdrawal of material from the store - Cutting and tack welding - Welding - Small parts, alignment and welding % % % % %

1.4.2

ERECTION - Transport - Laying, tack welding, installation of valves and other small parts - Welding - Supporting % % % % %

1.4.3

TESTING - Inspection of piping and removal of defects - Pressure tests - Final inspection and takeover % % % %

1.5 1.5.1

UNDERGROUND PIPING - OPTION 1 EARTH WORKS - SEPARATE - Excavation - Backfilling % % %

1.5.2

PREFABRICATION - Withdrawal of material from the store - Cutting and tack welding - Welding - Small parts, alignment and welding % % % % %

204

1.5.3

INSTALLATION - Transport - Laying, tack welding, installation of valves and other small parts - Welding - Supporting % % % % %

1.5.4

TESTING - Preliminary inspection - Pressure testing - Corrosion protection, puncture test - Final inspection and take over % % % % %

1.6 1.6.1

UNDERGROUND PIPING - OPTION 2 EARTH WORKS - INCLUDED - Excavation - Backfilling % % %

1.6.2

PREFABRICATION - Withdrawal of material from the store - Cutting and tack welding - Welding - Small parts, alignment and welding % % % % %

1.6.3

INSTALLATION - Transport - Laying, tack welding, installation of valves and other small parts - Welding - Supporting % % % % %

1.6.4

TESTING - Preliminary inspection - Pressure testing - Corrosion protection and puncture tests - Final inspection and take over % % % % %

1.7 1.7.1

PIPING STEAM TRACING PREFABRICATION - Steam manifolds - Condensate collectors - Connecting piping to 1 1/2 % % % %

205

1.7.2

INSTALLATION - Steam manifolds - Condensate collectors - Connection piping to 1 1/2 - Steam pipe bundles - Condensate pipe bundles - Steam tracing % % % % % % %

1.7.3

TESTING - Preliminary inspection - Pressure testing and take over % % %

2. 2.1

STEEL STRUCTURES LARGE WORKSHOP STRUCTURES WITH A CRANE TRACK - Columns, beams, joists - Roof supports - Doors and windows - Crane supports and rails - Stairs, ladders, walkways, railings - Positioning and bolting - Inspection, possible repairs and finishing - Final inspection and take over % % % % % % % % 100 %

2.2

LARGE WORKSHOP STRUCTURE WITHOUT CRANE TRACK - Columns, beams, joists - Roof supports - Doors and windows - Crane supports and rails - Stairs, ladders, walkways, railings - Positioning and bolting - Inspection, possible repair and finishing - Final inspection and take over % % % % % % % % 100 %

2.3

PROCESS PLANT BUILDING STRUCTURES - Columns, beams, joists - Platform girders (Bhnentrger) - Platform plating (Bhnenbelge) - Stairs, ladders, platforms - Railings - Doors and windows - Positioning and bolting - Inspection and possible repair and finishing - Final inspection and take over % % % % % % % % % 100 %

2.4

BUNKER BUILDINGS, BUNKER INCLUDED - Columns, beams, joists - Bunker erection - Bunker welding - Platform girder (Bhnentrger) % % % %

206

- Platform plating (Bhnenbelge) - Stairs, ladders, railings - Doors and windows - Positioning and bolting - Inspection and possible repair and finishing - Final inspection and take over

% % % % % % 100 %

2.5

CRANE TRACKS EXTERIOR - Columns, beams, joists - Crane supports and rails - Walkways, ladders, railings - Positioning and bolting - Inspection and possible repair and finishing - Final inspection and take over % % % % % % 100 %

2.6

MACHINE SUPPORTING STRUCTURE - Columns, beams, joists - Walkways, ladders, railings - Positioning and bolting - Inspection and possible repairs and finishing - Final inspection and take over % % % % % 100 %

2.7

PROCESS EQUIPMENT SUPPORTING STRUCTURE - Columns, beams, joists - Platform girders (Bhnentrger) - Platform plating (Bhnenbelge) - Stairs, ladders, railings - Positioning and bolting - Inspection and possible repairs and finishing - Final inspection and take over % % % % % % % 100 %

2.8

PIPE AND CABLE RACKS - Columns, beams, joists - Walkways, stairs, ladders railings - Positioning and bolting - Inspection and possible repairs and finishing - Final inspection and take over % % % % % 100 %

2.9

BELT CONVEYOR STRUCTURE - Racks preliminary installation and columns - Racks installation - Walkways, stairs, ladders railings - Positioning and bolting -Inspection and possible repairs and finishing - Final inspection and take over % % % % % % 100 %

207

2.10

STAIRS, WALKWAYS, PL ATFORMS, LADDERS ONEQUIPMENT, STORAGE TANKS, ETC. - Brackets, holders - Scaffolds, supports, walkways - Stairs, ladders, baskets, etc. - Floor grids, ribbed sheets - Railings - Inspection and possible repairs and finishing - Final inspection and take over % % % % % % % 100 %

3. 3.1

PROCESS EQUIPMENT TOWERS, REACTORS, HEAT EXCHANGERS , VESSELS - Foundations steel structure preparation levelling of packers - Hauling equipment to the place of installation - Unloading equipment at the place of hoisting - Hoisting and putting onto found ations - P ositioning, levelling, checking vertical position, etc. - Anchor bolt tightening - Inspection and possible repairs and finishing - Final measurement, take over report, permission to connect the piping % 100 % % % % % % % %

3.2

AIR COOLERS without louvres - Preparing the place for installation, unloading - Steel structure erection - Drive installation incl. motors - Installation of chequered pipe bundles - Finishing and remaining works, final inspection and take over % 100 % % % % %

3.3

AIR C OOLERS with louvers - Preparing the place of installation, unloading - Steel structure erection - Drive installation incl. motors - Installation of chequered pipe bundles - Installation of louvers and siding - Finishing and remaining works, final inspection and take over % 100 % % % % % %

208

3.4

OIL REFINERY KILNS - Steel structure - Enclosure (shell, bottom, top) - Pipe system - Welding - Accessories: burner control dampers service and inspection doors explosion-proof dampers soot blowers - Inspection, final inspection and take over % % % %

% % 100 %

3.5

ROTARY EQUIPMENT PUMPS AND COMPRESSORS -Preparation and levelling of foundations -Placing on foundations, tightening of anchor bolts, permission to connect the piping -Positioning of drive coupling -Final inspection and take over % % % % 100%

4.

CYLINDRICAL STORAGE TANKS (All kinds of roofs) -Bottom -Shell with openings and connections - Roof with openings and connections -Equipment (stairs, platforms, heating, firefighting piping, railings, etc.) -Final testing and tak e over % % % % % 100 %

209

XII. TECHNICAL CALCULATION - MANNER OF DATA COMPILING


When the call for tender is received and the installation/erection technology selected, and when man hours for the works ar e calculated, the estimator shall also provide the data required for calculation of a manhour rate. Each item is assigned the number of hours per each unit and the total number of hours which is written in a special place in the document. He will provide written data for calculation of the manhour rate in the following way: To be written on the top: name of project, name of client, place of works, date, and other data for the project identification. 1. QUANTITIES AND MAN HOURS REQUIRED

The estimator will record the quantity of works mostly in kg or tons. These quantities shall be given for a group of works, type of works, buildings, kind of material, size and the like. This is not always easy to do because of insufficient data contained in the call for tenders. Anyhow, the estimator shall make some sort of estimate or exact calculation of the quantities tons, kg, etc. Each group will be entered the basic data, rates or effect, and hours required. Finally, he shall state the total weight, hours required and the effect. Similarly, each group of works shall be assigned a productivity efficiency percentage (PEP) and finally an average PEP for all the works (acc. to page11). 2. MANPOWER

- Works Schedule: If the time for execution of works is not stipulated in the call for tender or some other document, the estimator will estimate the time on the basis of his experience and from the tables on the page 118. - Hours required: Item 1 - Hours per month: this should be agreed with the project manager . Usually, it is 50 hours/week x 4,3 weeks = 215 hours/month 2.1 2.1.1 PRODUCTION MANPOWER Average number: total hours _____________________ month x hours/month

2.1.2 2.1.3

Maximum number: Foresee maximum number at top production (c. + 30 %) Manpower structure (at average number)

Number - Foreman - Fitters, highly skilled - Fitters, skilled - Welders, highly skilled - Welders, skilled - Others _____________________ Total: (Average number) 2.2 2.2.1 OFFICE STAFF Management Number - Manager - Engineer - Tehnician - Others ... Months

_____________________ Total:

210

2.2.2

Auxiliary staff in production Number - Drivers - Mechanics - Electricians - Store workers - Others _____________________________ Total: Months

3. 3.1

MACHINERY AND MEANS OF TRANSPORT Cranes and forklifts Capacity, number, months (weeks, days) of use Means of transport - Vehicles - Trucks - Trailer trucks - Tractors - Trailers - Buses - Small buses - Pickups - Passenger cars - Others The number of vehicles and time of use

3.2

4.

VITAL MEANS OF PRODUCTION - Appurtances - Generating sets - Mobile power units - Compressors - Pumps - Winches - Etc.

5.

TEMPORARY WORKS AT THE JOB SITE - Workshops - Camp facilities - Containers Estimate acc. to the table on pages 122 123

6.

AUXILIARY MATERIAL AND CONSUMABLES - Welding rods estimate acc. to pages 112 113 - Technical gas estimate acc. to page 114 115 - Grinding and cutting discs estimate acc. to page 114 - Fuel and lubricants estimate acc. to page 116 - Other - Contingencies: 10 15 % to add to the above

7.

TOOL COSTS AT THE JOB SITE Estimate the costs according to the estimate on page 117 .

211

8.

SAFETY AT WORK COSTS Estimate the costs according to the estimate on page 117.

9.

POWER CONSUMPTION COST According to the estimate on page 115

10.

SCAFFOLDS AND SCAFFOLDING Estimate according to the estimate on pages 109 111

11.

SPACE REQUIRED Estimate according to the estimate on pages 122 123

12.

CONNECTIONS REQUIRED Estimate according to the estimate on page 123

13.

CERTIFICATION OF WELDERS Estimate the number of certified welders.

14.

TRANSPORT OVERALL DIMENSIONS AND WEIGHTS Calculate the weight [ton] and the volume [m3] with the data given in the table below.

14.1 TYPE
Truck-mounted crane -Telescope " " " " " " " " " " " " " " " " " " " " " "TATRA" Forklift " Truck " " " " with "HIAB" Bus 50 seats Small bus 8+1 seats Passenger car Tractor 120 KS " 75 KS Trailer 20 T " 10 T Container 2 x 2,5 x 6 m

CAPACITY [t]
300 150 100 60 40 32 20 18 15 12 10 8 5 3 10 5 3 1,5 8

WEIGHT [t]
330 132 88,5 47 38 36 24,5 24 23 20 18 13 6 4 7 5 3,8 2 4 12 3 1,2 7,5 4,5 7 5,6 1,6

VOLUME [m3 ]
230 180 160 140 120 90 85 80 75 70 60 48 17 8 62 57 40 30 60 94 20 14 17 13,5 96 26 30

Weights and volumes are different and depend on the type and manufacturer of the means for hoisting and transportation.

212

14.2

MATERIALS Weight 1 ton 1 ton 1 ton 1 ton 1 ton Volume 2,30 m3 3 0,50 m6,00 m3 2,00 m3 1,55 m3

- Material for piping - Material for storage tanks (prefabrication) - Equipment for installation - Steel structure (prefabrication) - Other (including pipe supports)

= = = = =

15.

SERVICES BY OTHER CONTRACTORS - Transport - Connections - Maintenance and servicing - Geodetic measurement - Security guard service - Waste transport - Etc.

16.

WORKS SCHEDULE AND MANPOWER DIAGRAM

It is given if requested by call for tenders and in agreement with the project manager. The works schedule can be made in a form of a bar chart with concentrated number of activities (15 20). If possible, include the manpower diagram at its bottom.

17.

PROGRESS DIAGRAM - "S" - CURVE

It is made if requested by call for tenders and in agreement with the project manager . The estimator's name and surname, his signature and date should be written at the end

213

XIII. MANHOURS FOR OVERHAULS IN PETROCHEMICAL PLANTS


1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES
Productivity Ef ficiency Percentage PEP=90% Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ] 1/2" 1/2" 3/4" 3/4" 1" 1" 21,3 21,3 26,7 26,7 33,4 33,4 2,77 3,73 2,90 3,91 3,40 4,55 40 STD 80 XS 40 STD 80 XS 40 STD 80XS 1,28 1,61 1,70 2,20 2,52 3,21 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u 1 1/2" 1 1/2" 2" 48,3 48,3 60,3 3,70 5,16 3,90 40 STD 80XS 40 STD 4,07 5,44 5,43 Mhr/u Mhr/u Mhr/u 2" 21/2" 21/2" 3" 3" 60,3 73,0 73,0 88,9 88,9 5,54 5,20 7,00 5,50 7,60 80 XS 40STD 80 XS 40 STD 80 XS 7,44 8,71 11,40 11,3 15,3 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

Item 1.1 1.2 2. 3.1 3.2 3.3 4. 5. 6. 7. 8. 9.1 9.2 10.1 10.2 11.1 11.2 11.3 12. 13. 14. 15. 16. 17.1. 17.2. 17.3. 18.1. 18.2. 18.3. 19.1. 19.2. 19.3. 19.4.

Unit m m m pc pc pc weld weld weld weld weld weld weld weld weld weld pc pc weld weld pc ea ea ea ea ea bend bend bend joint joint joint joint

A. PREFABRICATION AND ERECTION PIPE LAYING WITHOUT PRIMER PIPE LAYING WITH PRIMER LAYING OF PROCESS PIPE IN PROTECTION CONDUIT INSTALLATION OF FITTING WITH ONE END - HANDLING INSTALLATION OF FITTING WITH TWO ENDS - HANDLING INSTALLATION OF FITTING WITH THREE ENDS - HANDLING BUTT WELD - MAKE-ON & WELDING SOCKET WELD - MAKE-ON & WELDING SEAL WELD (THREADED JOINT) MITRE WELD - MAKE-ON & WELDING WELDING NECK FLANGES WELDING SLIP-ON FLANGES INCL. PRESSURE TEST WELDING SLIP-ON FLANGES - NO PRESSURE TEST WELDING MEASURING FLANGE INCL. PRESSURE TEST WELDING MEASURING FLANGE - NO PRESSURE TEST 90o BRANCH CONNECTION - NO REINFORCEMENT COUPLING (MUFFE) - INSTALLATION AND WELDING WELDOLET, etc. - INSTALLATION AND WELDING INCLINED BRANCH CONN. - NO REINFORCEMENT REINFORCEMENT PAD - FABRICATION & WELDING SADDLE NOZZLE (SWEEPOLET) - INSTALLATION & WELDING EXPANSION U-BEND - PRESTRESSING GRINDING OF WELD ROOT EXCESS REDUCER FABRICATION, 1 DN SMALLER REDUCER FABRICATION, 2 DN SMALLER REDUCER FABRICATION, 3 DN SMALLER PIPE BENDING < 45o PIPE BENDING 45oo - 90 PIPE BENDING 90o -o180 FLANGED FLANGED FLANGED FLANGED JOINT JOINT JOINT JOINT NP 6 - 16, 150# NP 25 - 64, 300# - 400# NP 100 - 160, 600# - 900# NP 250 - 400, 1500# - 2500#

214

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Ef ficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 20.1. 20.2. 20.3. 20.4. 21. 22.1. 22.2. 22.3. 22.4. 23.1. 23.2. 23.3. 23.4. 24. 25.1. 25.2. 25.3. 25.4. 26.1. 26.2. 26.3. 26.4. 27. 28. 29. 30.1. 30.2. 31. 32.

Unit ea ea ea ea joint ea ea ea ea ea ea ea ea ea ea ea ea ea pc pc pc pc pc pc pc ea ea ea ea

A. PREFABRICATION AND ERECTION INSTALLATION OF BLIND FLANGE NP 6 - 16, 150# INSTALLATION OF BLIND FLANGE NP 25 - 64, 300# - 400# INSTALLATION OF BLIND FLANGE NP 100 -160, 600# - 900# INSTALLATION OF BLIND FLANGE NP 250 -400, 1500#- 2500# FLANGED JOINT, TIGHTENING WITH TORQUE WRENCH factor at item 19.1. - 4 and 20.1. - 4 RF - BLANKING PLATE 150# PLACING OR TAKING OUT RF - BLANKING PLATE 300#- 400# PLACING OR TAKING OUT RF - BLANKING PLATE 600#- 900# PLACING OR TAKING OUT RF - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT RTJ - BLANKING PLATE 150# PLACING OR TAKING OUT RTJ - BLANKING PLATE 300#-400# PLACING OR TAKING OUT RTJ - BLANKING PLATE 600#-900# PLACING OR TAKING OUT RTJ - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT BLANKING PLATE SPECTACLE, PLACING OR TAKING OUT factor to items 22.1. - 4. and 23.1. 23.4. MEASURING ORIFICE 150# - INSTALLATION MEASURING ORIFICE 300#-400# - INSTALLATION MEASURING ORIFICE 600#-900# - INSTALLATION MEASURING ORIFICE 1500#-2500# - INSTALLATION INSTALLATION OF VALVE WITH FLANGED END NP 6 - 16, 150# INSTALLATION OF VALVE WITH FLANGED END NP 25-64, 300# - 400# INSTALLATION OF VALVE WITH FLANGED END NP100-160, 600# - 900# INSTALLATION OF VALVE WITH FLANGED END NP250-400,1500#-2500# INSTALLATION OF MOTOR DRIVE VALVE factor to items 26.1. 26.4 INSTALLATION OF SAFETY VALVES factor to items 26.1. 26.4 INSTALLATION OF CONTROL VALVES factor to items 26.1. 26.4 DRAIN OR VENT VALVE WITH ONE REINF NOZZLE MAKE-ON & WELD. DRAIN OR VENT VALVE WITH TWO REINF.NOZZLES MAKE-ON.&WELD. MAKE-ON OF BRANCH CONNECTION -" HOT TAP" DRILLING PROCESS PIPE FOR "HOT TAP"

1/2" 21,3 2,77 40 STD 1,28 Mhr/u

1/2" 3/4" 21,3 26,7 3,73 2,90 80 XS 40 STD 1,61 1,70 Mhr/u Mhr/u

3/4" 1" 1" 1 1/2" 26,7 33,4 33,4 48,3 3,91 3,40 4,55 3,70 80 XS 40 STD 80XS 40 STD 2,20 2,52 3,21 4,07 Mhr/u Mhr/u Mhr/u Mhr/u

1 1/2" 2" 2" 48,3 60,3 60,3 5,16 3,90 5,54 80XS 40 STD 80 XS 5,44 5,43 7,44 Mhr/u Mhr/u Mhr/u

21/2" 73,0 5,20 40STD 8,71 Mhr/u

21/2" 3" 73,0 88,9 7,00 5,50 80 XS 40 STD 11,40 11,3 Mhr/u Mhr/u

3" 88,9 7,60 80 XS 15,3 Mhr/u

215

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%
Item 33.1. 33.2. 33.3. 33.4. 33.5. 33.6. 33.7. 33.8. 34. 35. 36. 37. 38.1. 38.2. 38.3. 38.4. 38.5. 38.6. 38.7. 38.8. 38.9. 39.1. 39.2. 39.3. 39.4. 40. 41. 42. 43. 44. 45.1. 45.2. 46.1. 46.2. Unit test m m m m m3 m3 m3 m ea ea ea m m ea ea ea ea ea joint m ea ea ea ea m ea ea ea ea cut cut kg kg

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

A. PREFABRICATION AND ERECTION PREPARATION OF EQUIPMENT FOR PRESSURE TESTING SYSTEM PRESSURE TEST, LENGTH TO - 100m SYSTEM PRESSURE TEST, LENGTH FROM 100 TO 200m SYSTEM PRESSURE TEST, LENGTH FROM 200 TO 500m SYSTEM PRESSURE TEST, LENGTH ABOVE - 500m VESSEL PRESSURE TEST, VOLUME TO 10m3 VESSEL PRESSURE TEST, VOLUME 10 -15m3 VESSEL PRESSURE TEST, VOLUME ABOVE 15m3 PRESSURE TEST WITH AIR OR NITROGEN PIPE THREADING FABRICATION OR DISASSEMBLING OF THREADED JOINT WELD ANNEALING BY GAS BURNER PROCESS PIPE STEAM TRACING SUPPLY OR RETURN PIPE OF STEAM TRACING FITTING TRACING (freezing protection) FLANGED JOINT TRACING 2" and above VALVE TRACING 2" and above - (FROSTSCHUTZ), flanges included VALVE TRACING 2" and above, flanges included VALVE TRACING under 2", flanges included FLANGED JOINT ON TRACER LINE INSTALLATION OF STEAM TRACING PIPING WITH SPACERS STEAM MANIFOLDS FOR 4 CONNECTIONS STEAM MANIFOLDS - ADDITION TO CONNECTION ABOVE 4 CONNECT. CONDENSATE COLLECTORS FOR 4 CONNECTIONS CONDENSATE COLLECTORS ALLOW. PER CONNEC. ABOVE 4 CONECT. STEAM TRACING ON Cr Ni PROCESS PIPE factor to items 38.1. ; 38.3. - 38. 7. INSTALLATION OR REMOVAL OF BLANKING PLATES AT PIPE END INSTALLATION OR REMOVAL OF DIRT MESH IN PIPING WELD PICKLING ON STAINLESS STEEL EXECUTION OF PASSES THROUGH WALLS OR SLABS PIPE CUTTING - COLD PIPE CUTTING - GAS BURNER PIPE SUPPORTS - FABRICATION PIPE SUPPORTS - ERECTION

1/2" 1/2" 3/4" 3/4" 1" 1" 1 1/2" 1 1/2" 2" 2" 21/2" 21/2" 3" 3" 21,3 21,3 26,7 26,7 33,4 33,4 48,3 48,3 60,3 60,3 73,0 73,0 88,9 88,9 2,77 3,73 2,90 3,91 3,40 4,55 3,70 5,16 3,90 5,54 5,20 7,00 5,50 7,60 40 STD 80 XS 40 STD 80 XS 40 STD 80XS 40 STD 80XS 40 STD 80 XS 40 STD 80 XS 40 STD 80 XS 1,28 1,61 1,70 2,20 2,52 3,21 4,07 5,44 5,43 7,44 8,71 11,40 11,3 15,3 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

216

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Ef ficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 47.1. 47.2. 48.1. 48.2. 48.3. 48.4. 49. 50. 51. 52.1. 52.2. 52.3. 52.4. 53. 54. 55. 56. 57. 58. 59.

Unit m m ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea

B. PIPING DISMANTLING PIPE DISMANTLING FOR REUTILIZATION PIPE DISMANTLING FOR USEFUL WASTE FLANGED JOINT DISMANTLING FOR REUTILIZATION 150# FLANGED JOINT DISMANTLING FOR REUTILIZ. 300# - 400# FLANGED JOINT DISMANTLING FOR REUTILIZ. 600# - 900# FLANGED JOINT DISMANTLING FOR REUTILIZ. 1500#-2500# FLANGED JOINT DISMANTLING FOR USEFUL WASTE factor to items 48.1 48.4. BLIND FLANGE DISMANTLING FOR REUTILIZATION factor to items 20.1. 20.4. FLANGED JOINT DISMANTLING FOR USEFUL WASTE factor to items 20.1. 20.4. or 50. DISMANTLING VALVE FOR REUTILIZATION 150# DISMANTLING VALVE FOR REUTILIZATION 300# - 400# DISMANTLING VALVE FOR REUTILIZATION 600# - 900# DISMANTLING VALVE FOR REUTILIZATION 1500#-2500# DISMANTLING VALVE FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING VALVE WITH MOT. DRIVE FOR REUTILIZ. factor to items 52.1. 52.4. DISMANTLING VALVE WITH MOT. DRIVE FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING SAFETY VALVES FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING SAFETY VALVES FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING CONTROL VALVE FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING CONTROL VALVE FOR USEFUL WASTE factor to items 52.1. 52.4.

1/2" 21,3 2,77 40 STD 1,28 Mhr/u

1/2" 3/4" 21,3 26,7 3,73 2,90 80 XS 40 STD 1,61 1,70 Mhr/u Mhr/u

3/4" 1" 26,7 33,4 3,91 3,40 80 XS 40 STD 2,20 2,52 Mhr/u Mhr/u

1" 33,4 4,55 80XS 3,21 Mhr/u

1 1/2" 48,3 3,70 40 STD 4,07 Mhr/u

1 1/2" 2" 48,3 60,3 5,16 3,90 80XS 40 STD 5,44 5,43 Mhr/u Mhr/u

2" 21/2" 60,3 73,0 5,54 5,20 80 XS 40STD 7,44 8,71 Mhr/u Mhr/u

21/2" 3" 73,0 88,9 7,00 5,50 80 XS 40 STD 11,40 11,3 Mhr/u Mhr/u

3" 88,9 7,60 80 XS 15,3 Mhr/u

217

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%
Item 1.1 1.2 2. 3.1 3.2 3.3 4. 5. 6. 7. 8. 9.1 9.2 10.1 10.2 11.1 11.2 11.3 12. 13. 14. 15. 16. 17.1. 17.2. 17.3. 18.1. 18.2. 18.3. 19.1. 19.2. 19.3. 19.4. Unit m m m pc pc pc weld weld weld weld weld weld weld weld weld weld pc pc weld weld pc ea ea ea ea ea bend bend bend joint joint joint joint

A. PREFABRICATION AND ERECTION PIPE LAYING WITHOUT PRIMER PIPE LAYING WITH PRIMER LAYING OF PROCESS PIPE IN PROTECTION CONDUIT INSTALLATION OF 1-END FITTINGS END - HANDLING INSTALLATION OF 2-END FITTINGS - HANDLING INSTALLATION OF 3-END FITTINGS - HANDLING BUTT WELD - MAKE-ON AND WELDING SOCKET WELD - MAKE-ON AND WELDING SEAL WELD (ON THREADED JOINT) MITRE WELD - MAKE-ON AND WELDING WELDING NECK FLANGES WELDING SLIP-ON FLANGES & PRESSURE TEST WELDING SLIP-ON FLANGES - NO PRESSURE TESTING WELDING MEASURING FLANGE & PRESSURE TEST WELDING MEASURING FLANGE - NO PRESSURE TEST BRANCH CONN. 90o - NO REINFORCEMENT COUPLING INSTALLATION AND WELDING WELDOLET I.T.D. INSTALLATION AND WELDING INCLINED BRANCH CONNECTION - NO REINFORCEMENT SADDLE REINFORCEMENT PERFORMANCE & WELDING SADDLE NOZZLE (SWEEPOLET) - INSTALL. & WELDING EXPANSION U-BEND- PRESTRESSING GRINDING OF WELD ROOT EXCESS REDUCER FABRICATION, 1 DN SMALLER REDUCER FABRICATION, 2 DN SMALLER REDUCER FABRICATION, 3 DN SMALLER PIPE BENDING < 45o PIPE BENDING 45oo - 90 PIPE BENDING 90oo -180 FLANGED JOINT NP 6 - 16, 150# FLANGED JOINT NP 25 64, 300# - 400# FLANGED JOINT NP 100 160, 600# - 900# FLANGED JOINT NP 250 400, 1500# - 2500#

Nom. dia. [ inch ] 4" 4" 6" OD [mm] 114,3 114,3 168,3 Wall thickness t [mm] 6,00 8,60 7,10 Schedule 40 STD 80 XS 40 STD Weight [kg/m] 16,0 22,4 28,3 Mhr/u Mhr/u Mhr/u

6" 8" 8" 168,3 219,1 219,1 11,00 7,09 8,20 80 XS 30 40 STD 42,7 36,7 42,7 Mhr/u Mhr/u Mhr/u

8" 10" 10" 10" 219,1 273,1 273,1 273,1 12,70 7,80 9,30 12,70 80 XS 30 40 STD 80S 60 64,7 51,1 60,6 81,6 Mhr/u Mhr/u Mhr/u Mhr/u

12" 12" 12" 323,9 323,9 323,9 8,38 9,50 12,70 XS30 40S STD 80S XS 65,4 73,8 97,6 Mhr/u Mhr/u Mhr/u

218

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Item 20.1. 20.2. 20.3. 20.4. 21. 22.1. 22.2. 22.3. 22.4. 23.1. 23.2. 23.3. 23.4. 24. 25.1. 25.2. 25.3. 25.4. 26.1. 26.2. 26.3. 26.4. 27. 28. 29. 30.1. 30.2. 31. 32.

Unit ea ea ea ea joint ea ea ea ea ea ea ea ea ea ea ea ea ea pc pc pc pc pc pc pc ea ea ea ea

A. PREFABRICATION AND ERECTION INSTALLATION OF BLIND FLANGE NP 6 - 16, 150# INSTALLATION OF BLIND FLANGE NP 25 - 64, 300# - 400# INSTALLATION OF BLIND FLANGE NP 100 -160, 600# - 900# INSTALLATION OF BLIND FLANGE NP 250 -400, 1500#- 2500# FLANGED JOINT, TIGHTENING WITH A TORQUE WRENCH factor to items 19.1. - 4 and 20.1. - 4 RF - BLANKING PLATE 150# PLACING OR TAKING OUT RF - BLANKING PLATE 300#- 400# PLACING OR TAKING OUT RF - BLANKING PLATE 600#- 900# PLACING OR TAKING OUT RF - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT RTJ - BLANKING PLATE 150# PLACING OR TAKING OUT RTJ - BLANKING PLATE 300#-400# PLACING OR TAKING OUT RTJ - BLANKING PLATE 600#-900# PLACING OR TAKING OUT RTJ - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT BLANKING PLATE - SPECTACLE, PLACING OR TAKING OUT factor to items 22.1. - 4. and 23.1. - 4. MEASURING ORIFICE 150# - INSTALLATION MEASURING ORIFICE 300#-400# - INSTALLATION MEASURING ORIFICE 600#-900# - INSTALLATION MEASURING ORIFICE 1500#-2500# - INSTALLATION INSTALLATION OF FLANGED-END VALVE NP 6 - 16, 150# INSTALLATION OF FLANGED-END VALVE NP 25-64, 300# - 400# INSTALLATION OF FLANGED-END VALVE NP100-160, 600# - 900# INSTALLATION OF FLANGED-END VALVE NP250-400,1500#-2500# INSTALLATION OF MOTOR DRIVE VALVE factor to items 26.1. 26.4 INSTALLATION OF SAFETY VALVE factor to items 26.1. 26.4 INSTALLATION OF CONTROL VALVE factor to items 26.1. 26.4 DRAIN OR VENT VALVE WITH REINF. NOZZLES MAKE-ON & WELD. DRAIN OR VENT VALVE WITH 2 REINF. NOZZLES- MAKE-ON. & WELD. MAKE-ON OF BRANCH CONNECTION -" HOT TAP" DRILLING PROCESS PIPE FOR "HOT TAP"

Nom. dia. [ inch ] 4" 4" 6" OD [mm] 114,3 114,3 168,3 Wall thickness t [mm] 6,00 8,60 7,10 Schedule 40 STD 80 XS 40 STD Weight [kg/m] 16,0 22,4 28,3 Mhr/u Mhr/u Mhr/u

6" 168,3 11,00


80 XS

8" 219,1 7,09


30

8" 219,1 8,20

8" 219,1 12,70

10" 273,1 7,80


30

10" 10" 273,1 273,1 9,30 12,70

12" 323,9 8,38

12" 12" 323,9 323,9 9,50 12,70


40S STD80S XS

40 STD 80 XS

40 STD 80S 60 XS 30

42,7 36,7 42,7 64,7 51,1 60,6 81,6 65,4 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

73,8 97,6 Mhr/u Mhr/u

219

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Item 33.1. 33.2. 33.3. 33.4. 33.5. 33.6. 33.7. 33.8. 34. 35. 36. 37. 38.1. 38.2. 38.3. 38.4. 38.5. 38.6. 38.7. 38.8. 38.9. 39.1. 39.2. 39.3. 39.4. 40. factor 41. 42. 43. 44. 45.1. 45.2. 46.1. 46.2.

Unit test m m m m m3 m3 m3 m ea ea ea m m ea ea ea ea ea joint m ea ea ea ea m ea ea ea ea cut cut kg kg

Nom. dia. [ inch ] 4" OD [mm] 114,3 Wall thickness t [mm] 6,00 Schedule 40 STD Weight [kg/m] 16,0 A. PREFABRICATION AND ERECTION Mhr/u PREPARATION OF EQUIPMENT FOR PRESSURE TESTING SYSTEM PRESSURE TEST, LENGTH to - 100m SYSTEM PRESSURE TEST, LENGTH from 100 - 200m SYSTEM PRESSURE TEST, LENGTH from 200 - 500m SYSTEM PRESSURE TEST, LENGTH above - 500m VESSEL PRESSURE TEST, VOLUME to 10m3 VESSEL PRESSURE TEST, VOLUME from 10 to 15m3 VESSEL PRESSURE TEST, VOLUME above 15m3 PRESSURE TEST BY AIR OR NITROGEN PIPE THREADING FABRICATION OR DISASSEMBLING OF THREADED JOINT WELD ANNEALING BY GAS BURNER PROCESS PIPE STEAM TRACING SUPPLY OR RETURN PIPE OF STEAM TRACING FITTING TRACING FLANGED JOINT TRACING 2" and above VALVE TRACING 2" and above, - (FROSTSCHUTZ), flanges included VALVE TRACING 2" and above, flanges included VALVE TRACING under 2", flanges included FLANGED JOINT ON TRACER LINE LAYING OF STEAM TRACING PIPING WITH SPACERS STEAM MANIFOLDS FOR 4 CONNECTIONS STEAM MANIFOLDS - ALLOWANCE PER EACH CONN. ABOVE 4 CONNEC. CONDENSATE COLLECTORS FOR 4 CONNECTIONS CONDENSATE COLLECTORS - ALLOWANCE PER EACH CONN. ABOVE 4 CONN. STEAM TRACING ON Cr Ni PROCESS PIPE to items 38.1. ; 38.3. - 38. 7. INSTALLATION OR REMOVAL OF CAPS AT PIPE END INSTALLATION OR REMOVAL OF DIRT MESH IN PIPING WELD PICKLING AT STAINLESS STEEL EXECUTION OF PASSES THROUGH WALLS OR SLABS PIPE CUTTING - COLD PIPE CUTTING - GAS BURNER PIPE SUPPORTS - FABRICATION PIPE SUPPORTS - ERECTION

4" 6" 114,3 168,3 8,60 7,10

6" 168,3 11,00

8" 219,1 7,09


30

8" 219,1 8,20

8" 219,1 12,70

10" 273,1 7,80


30

10" 10" 273,1 273,1 9,30 12,70


40 STD 80S 60 XS

12" 323,9 8,38


30

12" 12" 323,9 323,9 9,50 12,70


40S STD 80S XS

80 XS 40 STD 80 XS

40 STD 80 XS

22,4 28,3 42,7 36,7 42,2 64,7 51,1 60,6 81,6 65,4 73,8 97,6 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

220

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

4" 114,3 6,00


40 STD

4" 114,3 8,60


80 XS

6" 168,3 7,10


40 STD

6" 168,3 11,00


80 XS

8" 219,1 7,09


30

8" 8" 219,1 219,1 8,20 12,70


40 STD 80 XS

10" 273,1 7,80


30

10" 273,1 9,30

10" 12" 273,1 323,9 12,70 8,38


30

12" 323,9 9,50

12" 323,9 12,70 97,6 Mhr/u

40 STD 80S 60XS

40S STD 80S XS

Item 47.1. 47.2. 48.1. 48.2. 48.3. 48.4. 49. 50. 51. 52.1. 52.2. 52.3. 52.4. 53. 54. 55. 56. 57. 58. 59.

Unit m m ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea

B. PIPING DISMANTLING DISMANTLING PIPES FOR REUTILIZATION DISMANTLING PIPES FOR USEFUL WASTE DISMANTLING FLANGED JOINT FOR REUTILIZATION 150# DISMANTLING FLANGED JOINT FOR REUTILIZATION 300# - 400# DISMANTLING FLANGED JOINT FOR REUTILIZATION 600#- 900# DISMANTLING FLANGED JOINT FOR REUTILIZATION 1500#-2500# DISMANTLING FLANGED JOINT FOR USEFUL WASTE factor to items 48.1. 48.4. DISMANTLING BLIND FLANGE FOR REUTILIZATION factor to items 20.1. 20.4. DISMANTLING BLIND FLANGE FOR USEFUL WASTE factor to items 20.1. 20.4. or 50. VALVE DISMANTLING FOR REUTILIZATION 150# VALVE DISMANTLING FOR REUTILIZATION 300# - 400# VALVE DISMANTLING FOR REUTILIZATION 600# - 900# VALVE DISMANTLING FOR REUTILIZATION 1500#-2500# VALVE DISMANTLING FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING MOTOR DRIVE VALVE FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING MOTOR DRIVE VALVE FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING SAFETY VALVE FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING SAFETY VALVE FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING CONTROL VALVE FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING CONTROL VALVE FOR REUTILIZATION factor to items 52.1. 52.4.

16,0 22,4 28,3 42,7 36,7 42,7 64,7 51,1 60,6 81,6 65,4 73,8 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

221

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 1.1 1.2 2. 3.1 3.2 3.3 4. 5. 6. 7. 8. 9.1 9.2 10.1 10.2 11.1 11.2 11.3 12. 13. 14. 15. 16. 17.1. 17.2. 17.3. 18.1. 18.2. 18.3. 19.1. 19.2. 19.3. 19.4.

Unit m m m pc pc pc weld weld weld weld weld weld weld weld weld weld pc pc weld weld pc ea ea ea ea ea bend bend bend joint joint joint joint

A. PREFABRICATION AND ERECTION PIPE LAYING WITHOUT PRIMER PIPE LAYING WITH PRIMER LAYING OF PROCESS PIPE IN PROTECTION CONDUIT INSTALLATION OF 1-END FITTINGS - HANDLING INSTALLATION OF 2-END FITTINGS - HANDLING INSTALLATION OF 3-END FITTINGS - HANDLING BUTT WELD MAKE-ON AND WELDING SOCKET WELD MAKE-ON AND WELDING SEAL WELD (AT THREADED JOINT) MITRE JOINT - MAKE-ON AND WELDING WELDING NECK FLANGES WELDING SLIP-ON FLANGES & PRESSURE TEST WELDING SLIP-ON FLANGES - NO PRESSURE TEST WELDING MEASURING FLANGE & PRESSURE TEST WELDING MEASURING FLANGE - NO PRESSURE TEST NOZZLE WELD 90o - NO REINFORCEMENT COUPLING INSTALLATION & WELDING WELDOLET ETC. INSTALLATION & WELDING NOZZLE WELD- BEVELLED NO REINFORCEMENT SADDLE REINFORCEMENT FABRICATION & WELDING SADDLE NOZZLE (SWEEPOLET) - INSTALLATION & WELD. EXPANSION U-BEND PRESTRESSING GRINDING WELD ROOT EXCESS REDUCER FABRICATION, 1 DN SMALLER REDUCER FABRICATION, 2 DN SMALLER REDUCER FABRICATION, 3 DN SMALLER PIPE BENDING < 45o PIPE BENDING 45oo - 90 PIPE BENDING 90oo -180 FLANGED JOINT NP 6 - 16, 150# FLANGED JOINT NP 25 - 64, 300# - 400# FLANGED JOINT NP 100 - 160, 600# - 900# FLANGED JOINT NP 250 - 400, 1500# - 2500#

14" 14" 355,6 355,6 7,93 9,53 20 30 STD 67,8 81,2 Mhr/u Mhr/u

14" 16" 16" 355,6 406,4 406,4 12,70 7,93 9,50 XS 20 30 STD 108,0 77,7 93,1 Mhr/u Mhr/u Mhr/u

16" 18" 18" 406,4 457,2 457,2 12,70 7,93 9,50 40 XS 20 STD 123,0 87,6 105,0 Mhr/u Mhr/u Mhr/u

18" 20" 20" 457,2 508,0 508,0 12,70 6,40 9,50 XS 10 20 STD 139,0 78,0 117 Mhr/u Mhr/u Mhr/u

20" 22" 508,0 559,0 12,70 6,35 30 XS 10 155 87,3 Mhr/u Mhr/u

222

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 20.1. 20.2. 20.3. 20.4. 21. factor 22.1. 22.2. 22.3. 22.4. 23.1. 23.2. 23.3. 23.4. 24. factor 25.1. 25.2. 25.3. 25.4. 26.1. 26.2. 26.3. 26.4. 27. 28. 29. 30.1. 30.2. 31. 32.

Unit ea ea ea ea joint ea ea ea ea ea ea ea ea ea ea ea ea ea pc pc pc pc pc pc pc ea ea ea ea

A. PREFABRICATION AND ERECTION INSTALLATION OF BLIND FLANGE NP 6 - 16, 150# INSTALLATION OF BLIND FLANGE NP 25 - 64, 300# - 400# INSTALLATION OF BLIND FLANGE NP 100 -160, 600# - 900# INSTALLATION OF BLIND FLANGE NP 250 -400, 1500#- 2500# FLANGED JOINT, TIGHTENING WITH TORQUE WRENCH to items 19.1. - 4 and 20.1. 4 RF - BLANKING PLATE 150# PLACING OR TAKING OUT RF - BLANKING PLATE 300#- 400# PLACING OR TAKING OUT RF - BLANKING PLATE 600#- 900# PLACING OR TAKING OUT RF - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT RTJ - BLANKING PLATE 150# PLACING OR TAKING OUT RTJ - BLANKING PLATE 300#-400# PLACING OR TAKING OUT RTJ - BLANKING PLATE 600#-900# PLACING OR TAKING OUT RTJ - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT BLANKING PLATE - SPECTACLE, PLACING OR TAKING OUT to items 22.1. - 4. and 23.1. - 4. MEASURING ORIFICE 150# - INSTALLATION MEASURING ORIFICE 300#-400# - INSTALLATION MEASURING ORIFICE 600#-900# - INSTALLATION MEASURING ORIFICE 1500#-2500# - INSTALLATION INSTALLATION OF FLANGED END VALVE NP 6 - 16, 150# INSTALLATION OF FLANGED END VALVE NP 25-64, 300# - 400# INSTALLATION OF FLANGED END VALVE NP100-160, 600# - 900# INSTALLATION OF FLANGED END VALVE NP250-400,1500#-2500# INSTALLATION OF MOTOR DRIVE VALVE factor to items 26.1. 26.4 INSTALLATION OF SAFETY VALVES factor to items 26.1. 26.4 INSTALLATION OF CONTROL VALVES factor to items 26.1. 26.4 DRAIN OR VENT VALVE WITH 1 REINF. NOZZLE- MAKE-ON & WELD. DRAIN OR VENT VALVE WITH 2 REINF. NOZZLES MAKE-ON. & WELD MAKE-ON OF NOZZLE WELD -" HOT TAP" GRINDING OF PROCESS PIPE FOR "HOT TAP"

14" 14" 355,6 355,6 7,93 9,53 20 30 STD 67,8 81,2 Mhr/u Mhr/u

14" 16" 16" 355,6 406,4 406,4 12,70 7,93 9,50 XS 20 30 STD 108,0 77,7 93,1 Mhr/u Mhr/u Mhr/u

16" 18" 18" 406,4 457,2 457,2 12,70 7,93 9,50 40 XS 20 STD 123,0 87,6 105,0 Mhr/u Mhr/u Mhr/u

18" 20" 20" 457,2 508,0 508,0 12,70 6,40 9,50 XS 10 20 STD 139,0 78,0 117,0 Mhr/u Mhr/u Mhr/u

20" 508,0 12,70 30 XS 155,0 Mhr/u

22" 559,0 6,35 10 87,3 Mhr/u

223

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 33.1. 33.2. 33.3. 33.4. 33.5. 33.6. 33.7. 33.8. 34. 35. 36. 37. 38.1. 38.2. 38.3. 38.4. 38.5. 38.6. 38.7. 38.8. 38.9. 39.1. 39.2. 39.3. 39.4. 40. 41. 42. 43. 44. 45.1. 45.2. 46.1. 46.2.

Unit test m m m m m33 m33 m33 m ea ea ea m m ea ea ea ea ea joint m ea ea ea ea m ea ea ea ea cut cut kg kg

A. PREFABRICATION AND ERECTION PREPARATION OF EQUIPMENT FOR PRESSURE TESTING SYSTEM PRESSURE TEST, LENGTH TO - 100m SYSTEM PRESSURE TEST, LENGTH from 100 to 200m SYSTEM PRESSURE TEST, LENGTH from 200 to 500m SYSTEM PRESSURE TEST, LENGTH above 500m VESSEL PRESSURE TEST, VOLUME to 10m VESSEL PRESSURE TEST, VOLUME 10 -15m VESSEL PRESSURE TEST, VOLUME above 15m PRESSURE TEST BY AIR OR NITROGEN PIPE THREADING MAKE-ON OR DISASSEMBLING OF THREADED JOINT WELD ANNEALING BY GAS BURNER PROCESS PIPE STEAM TRACING SUPPLY OR RETURN PIPE OF STEAM TRACING FITTING TRACING FLANGED JOINT TRACING 2" and above VALVE TRACING 2" and above - (FROSTSCHUTZ), flanges included VALVE TRACING 2" and above, flanges included VALVE TRACING under 2", flanges included FLANGED JOINT ON TRACER LINE LAYING STEAM TRACING PIPING WITH SPACERS STEAM MANIFOLDS FOR 4 CONNECTIONS STEAM MANIFOLDS - ALLOWANCE PER EACH CONN. ABOVE 4 CONN. CONDENSATE COLLECTORS FOR 4 CONNECTIONS CONDENSATE COLLECTORS - ALLOWANCE PER EACH CONN. ABOVE 4 CON. STEAM TRACING ON Cr Ni PROCESS PIPE factor to items 38.1. ; 38.3. 38. 7. INSTALLATION OR REMOVAL OF CAPS AT PIPE END INSTALLATION OR REMOVAL OF DIRT MESH IN PIPING WELD PICKLING AT STAINLESS STEEL EXECUTION OF PASSES IN WALLS OR SLABS PIPE CUTTING - COLD PIPE CUTTING - GAS BURNER PIPE SUPPORTS - FABRICATION PIPE SUPPORTS - ERECTION

14" 14" 355,6 355,6 7,93 9,53 20 30 STD 67,8 81,2 Mhr/u Mhr/u

14" 16" 16" 16" 18" 18" 355,6 406,4 406,4 406,4 457,2 457,2 12,70 7,93 9,50 12,70 7,93 9,50 XS 20 30 STD 40 XS 20 STD 108,0 77,7 93,1 123,0 87,6 105,0 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

18" 457,2 12,70 XS 139,0 Mhr/u

20" 508,0 6,40 10 78,0 Mhr/u

20" 508,0 9,50 20 STD 117,0 Mhr/u

20" 22" 508,0 559,0 12,70 6,35 30 XS 10 155,0 87,3 Mhr/u Mhr/u

224

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 47.1. 47.2. 48.1. 48.2. 48.3. 48.4. 49. 50. 51.

Unit m m ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea ea

52.1. 52.2. 52.3. 52.4. 53. 54. 55. 56. 57. 58. 59.

B. DISMANTLING OF PIPING DISMANTLING PIPES FOR REUTILIZATION DISMANTLING PIPES FOR USEFUL WASTE DISMANTLING FLANGED JOINT FOR REUTILIZATION 150# DISMANTLING FLANGED JOINT FOR REUTILIZATION 300# - 400# DISMANTLING FLANGED JOINT FOR REUTILIZATION 600# - 900# DISMANTLING FLANGED JOINT FOR REUTILIZATION 1500#-2500# DISMANTLING FLANGED JOINT FOR USEFUL WASTE factor to items 48.1. 48.4. DISMANTLING BLIND FLANGE FOR REUTILIZATION factor to items 20.1. 20.4. DISMANTLING BLIND FLANGE FOR USEFUL WASTE factor to items 20.1. 20.4. or 50. DISMANTLING VALVE FOR REUTILIZATION 150# DISMANTLING VALVE FOR REUTILIZATION 300# - 400# DISMANTLING VALVE FOR REUTILIZATION 600# - 900# DISMANTLING VALVE FOR REUTILIZATION 1500#-2500# DISMANTLING VALVE FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING MOTOR DRIVE VALVE FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING MOTOR DRIVE VALVE FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING SAFETY VALVES FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING SAFETY VALVES FOR USEFUL WASTE factor to items 52.1. 52.4. DISMANTLING CONTROL VALVE FOR REUTILIZATION factor to items 52.1. 52.4. DISMANTLING CONTROL VALVE FOR USEFUL WASTE factor to items 52.1. 52.4.

14" 14" 355,6 355,6 7,93 9,53 20 30 STD 67,8 81,2 Mhr/u Mhr/u

14" 355,6 12,70 XS 108,0 Mhr/u

16" 16" 406,4 406,4 7,93 9,50 20 30 STD 77,7 93,1 Mhr/u Mhr/u

16" 18" 406,4 457,2 12,70 7,93 40 XS 20 123,0 87,6 Mhr/u Mhr/u

18" 457,2 9,50 STD 105,0 Mhr/u

18" 20" 20" 457,2 508,0 508,0 12,70 6,40 9,50 XS 10 20 STD 139,0 78,0 117 Mhr/u Mhr/u Mhr/u

20" 508,0 12,70 30 XS 155 Mhr/u

225

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 1.1 1.2 2. 3.1 3.2 3.3 4. 5. 6. 7. 8. 9.1 9.2 10.1 10.2 11.1 11.2 11.3 12. 13. 14. 15. 16. 17.1. 17.2. 17.3. 18.1. 18.2. 18.3. 19.1. 19.2. 19.3. 19.4.

Unit m m m pc pc pc weld weld weld weld weld weld weld weld weld weld pc pc weld weld pc ea ea ea ea ea bend bend bend joint joint joint joint

A. PREFABRICATION AND ERECTION PIPE LAYING WITHOUT PRIMER PIPE LAYING WITH PRIMER LAYING PROCESS PIPE IN PROTECTION CONDUIT INSTALLATION OF FITTING WITH 1 END - HANDLING INSTALLATION OF FITTING WITH 2 ENDS - HANDLING INSTALLATION OF FITTING WITH 3 ENDS - HANDLING BUTT JOINT MAKE-ON & WELDING SOCKET WELD MAKE-ON & WELDING SEAL WELD (AT THREADED JOINT) MITRE WELD - MAKE-ON & WELDING WELDING NECK FLANGES WELDING SLIP-ON FLANGES & PRESSURE TESTING WELDING SLIP-ON FLANGES NO PRESSURE TESTING WELDING MEASURING FLANGE & PRESSURE TESTING WELDING MEASURING FLANGE - NO PRESSURE TESTING BRANCH CONNECTION 90o - NO REINFORCEMENT COUPLING - INSTALLATION & WELDING WELDOLET ETC. INSTALLATION & WELDING INCLINED BRANCH CONNECTION NO REINFORCEMENT SADDLE REINFORCEMENT MAKE-ON & WELDING SADDLE NOZZLE (SWEEPOLET) - INSTALLATION & WELD. EXPANSION U-BEND PRESTRESSING GRINDING WELD ROOT EXCESS REDUCER FABRICATION, 1 DN SMALLER REDUCER FABRICATION, 2 DN SMALLER REDUCER FABRICATION, 3 DN SMALLER PIPE BENDING < 45o o o - 45 PIPE BENDING 90 o-180o PIPE BENDING 90 FLANGED JOINT NP 6 - 16, 150# FLANGED JOINT NP 25 - 64, 300# - 400# FLANGED JOINT NP 100 - 160, 600# - 900# FLANGED JOINT NP 250 - 400, 1500# - 2500#

22" 22" 559,0 559,0 6,35 9,53 10 20 STD 87,3 129 Mhr/u Mhr/u

22" 559,0 12,70 30 XS 171 Mhr/u

24" 24" 609,6 609,6 6,35 9,50 10 20 STD 95,4 141 Mhr/u Mhr/u

24" 26" 609,6 660,0 12,70 9,53 XS STD 187 153 Mhr/u Mhr/u

28" 30" 32" 36" 711,2 762,2 812,8 914,0 9,53 9,53 9,53 9,53 STD STD STD STD 165 177 188 212 Mhr/u Mhr/u Mhr/u Mhr/u

226

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 20.1. 20.2. 20.3. 20.4. 21. 22.1. 22.2. 22.3. 22.4. 23.1. 23.2. 23.3. 23.4. 24. 25.1. 25.2. 25.3. 25.4. 26.1. 26.2. 26.3. 26.4. 27. 28. 29. 30.1. 30.2. 31. 32.

Unit ea ea ea ea joint ea ea ea ea ea ea ea ea ea ea ea ea ea pc pc pc pc pc pc pc ea ea ea ea

A. PREFABRICATION AND ERECTION INSTALLATION OF BLIND FLANGE NP 6 - 16, 150# INSTALLATION OF BLIND FLANGE NP 25 - 64, 300# - 400# INSTALLATION OF BLIND FLANGE NP 100 -160, 600# - 900# INSTALLATION OF BLIND FLANGE NP 250 -400, 1500#- 2500# FLANGED JOINT, TIGHTENING WITH TORQUE WRENCH factor to items 19.1. - 4 and 20.1. 21.4 RF - BLANKING PLATE 150# PLACING OR TAKING OUT RF - BLANKING PLATE 300#- 400# PLACING OR TAKING OUT RF - BLANKING PLATE 600#- 900# PLACING OR TAKING OUT RF - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT RTJ - BLANKING PLATE 150# PLACING OR TAKING OUT RTJ - BLANKING PLATE 300#-400# PLACING OR TAKING OUT RTJ - BLANKING PLATE 600#-900# PLACING OR TAKING OUT RTJ - BLANKING PLATE 1500#-2500# PLACING OR TAKING OUT BLANKING PLATE - SPECTACLE, PLACING OR TAKING OUT factor to items 22.1. - 4. and 23.1. - 4. MEASURING ORIFICE 150# - INSTALLATION MEASURING ORIFICE 300#-400# - INSTALLATION MEASURING ORIFICE 600#-900# - INSTALLATION MEASURING ORIFICE 1500#-2500# - INSTALLATION INSTALLATION OF FLANGED END VALVE NP 6 - 16, 150# INSTALLATION OF FLANGED END VALVE NP 25-64, 300# - 400# INSTALLATION OF FLANGED END VALVE NP100-160, 600# - 900# INSTALLATION OF FLANGED END VALVE NP250-400,1500#-2500# INSTALLATION OF MOTOR DRIVE VALVE factor to items 26.1. 26.4 INSTALLATION OF SAFETY VALVES factor to items 26.1. 26.4 INSTALLATION OF CONTROL VALVES factor to items 26.1. 26.4 DRAIN OR VENT VALVE WITH 1 REINF. NOZZLE- MAKE-ON & WELD. DRAIN OR AIR VENT WITH 2 REINF. NOZZLES MAKE-ON & WELD. MAKE-ON OF BRANCH CONNECTION -" HOT TAP" GRINDING OF PROCESS PIPE FOR "HOT TAP"

22" 22" 22" 559,0 559,0 559,0 6,35 9,53 12,70 10 20 STD 30 XS 87,3 129 171 Mhr/u Mhr/u Mhr/u

24" 24" 24" 609,6 609,6 609,6 6,35 9,50 12,70 10 20 STD XS 95,4 141 187 Mhr/u Mhr/u Mhr/u

26" 660,0 9,53 STD 153 Mhr/u

28" 30" 711,2 762,2 9,53 9,53 STD STD 165 177 Mhr/u Mhr/u

32" 36" 812,8 914,0 9,53 9,53 STD STD 188 212 Mhr/u Mhr/u

227

1. PIPING ERECTION AND DISMANTLING UNIT MAN HOURS PER ACTIVITIES Productivity Efficiency Percentage PEP=90%

Nom. dia. [ inch ] Outer dia. [mm] Wall thick. t [mm] Schedule Weight [ kg/m ]

Item 33.1. 33.2. 33.3. 33.4. 33.5. 33.6. 33.7. 33.8. 34. 35. 36. 37. 38.1. 38.2. 38.3. 38.4. 38.5. 38.6. 38.7. 38.8. 38.9. 39.1. 39.2. 39.3. 39.4. 40. factor 41. 42. 43. 44. 45.1. 45.2. 46.1. 46.2.

Unit test m m m m m33 m33 m33 m ea ea ea m m ea ea ea ea ea joint m ea ea ea ea m ea ea ea ea cut cut kg kg

A. PREFABRICATION AND ERECTION PREPARATION OF EQUIPMENT FOR PRESSURE TEST SYSTEM PRESSURE TEST, LENGTH to - 100m SYSTEM PRESSURE TEST, LENGTH from 100 to 200m SYSTEM PRESSURE TEST, LENGTH from 200 to 500m SYSTEM PRESSURE TEST, LENGTH above - 500m VESSEL PRESSURE TEST, VOLUME to 10m VESSEL PRESSURE TEST, VOLUME 10 15m VESSEL PRESSURE TEST, VOLUME above 15m PRESSURE TEST BY AIR OR NITROGEN PIPE THREADING MAKE-ON OR DISASSEMBLING OF THREADED JOINT WELD ANNEALING BY GAS BURNER PROCESS PIPE STEAM TRACING SUPPLY OR RETURN PIPE OF STEAM TRACING FITTING TRACING FLANGED JOINT TRACING 2" and above VALVE TRACING 2" and above, (Frostschutz), flanges included VALVE TRACING 2" and above, flanges included VALVE TRACING under2", flanges included FLANGED JOINT ON TRACER LINE LAYING OF STEAM TRACING PIPING WITH SPACERS STEAM MANIFOLDS FOR 4 CONNECTIONS STEAM MANIFOLDS - ALLOWANCE PER EACH CONN. ABOVE 4 CONN. CONDENSATE COLLECTORS FOR 4 CONNECTIONS CONDENSATE COLLECTORS - ALLOWANCE PER EACH CONN. ABOVE 4 C. Cr Ni PROCESS PIPE STEAM TRACING to items 38.1. ; 38.3. 38. 7. INSTALLATION OR REMOVAL OF CAPS AT PIPE END INSTALLATION OR REMOVAL OF DIRT MESH IN PIPING PICKLING STAINLESS STEEL WELD EXECUTION OF PASSES THROUGH WALLS OR SLABS PIPE CUTTING - COLD PIPE CUTTING - GAS BURNER PIPE SUPPORTS - FABRICATION PIPE SUPPORTS - ERECTION

22" 22" 559,0 559,0 6,35 9,53 10 20 STD 87,3 129 Mhr/u Mhr/u

22" 24" 24" 559,0 609,6 609,6 12,70 6,35 9,50 30 XS 10 20 STD 171 95,4 141 Mhr/u Mhr/u Mhr/u

24" 609,6 12,70 XS 187 Mhr/u

26" 28" 30" 32" 36" 660,0 711,2 762,2 812,8 914,0 9,53 9,53 9,53 9,53 9,53 STD STD STD STD STD 153 165 177 188 212 Mhr/u Mhr/u Mhr/u Mhr/u Mhr/u

228

2. MAN HOURS FOR OVERHAUL OF EQUIPMENT IN PETROCHEMICAL PLANTS (PEP = 90%) 1. HEAT EXCHANGERS 1.1. Type - STANDARD (HAARNADEL) : Mhr for 10mm of heat exchanger diameter 1.2. 1.3. Type - WITH A FLOAT HEAD (SCHWIMMKOPF): Mhr for 10mm of heat exchanger diameter

Type - REBOILER WITH EXPANSION (TYP REBOILER MIT KOMPENSATOR): Mhr for 10mm of heat exchanger diameter WORKS INCLUDED: - Opening and disassembling of heat exchanger head - Extraction of pipe bundle - Transport of pipe bundle to cleaning - Cylinder washing - Bolt cleaning and lubrication with graphite grease - Reassembling and completing - Pressure tests of the assembly - Possible removal of branch piping and reinstallation PLACEMENT OR REMOVAL OF BLANKING PLATES MAN HOURS FOR PIPING OVERHAUL [ITEM. 22.1. 22.4] X SPECIAL PRESSURE TESTING OF PIPE BUNDLE AND PIPE CLOSING TO CALCULATE AT OVERHEADS HOUR OR: Mhr for 10 mm of heat exchanger diameter Mhr for each pipe

1.4.

1.5.

1.5.1. PRESSURE TESTS: 1.5.2. PIPE CLOSING - PLUG: 2. 2.1.

PRESSURE VESSELS OPENING OR CLOSING OF MANHOLES ON VESSELS AND TOWERS DN 500 - 20" [Mhr/ea] DN 600 - 24" [Mhr/ea] DN 700 - 28" [Mhr/ea] DN 800 - 32" [Mhr/ea] DN 900 - 36" [Mhr/ea] DN 1000 - 40" [Mhr/ea] OPENING PASSAGES, CLEANING, INSIDE INSPECTION, CLOSING AND PRESSURE TESTING to 1m3 [Mhr/ea] 1 - 2m3 [Mhr/m3] 2 - 3m3 [Mhr/m3] 3 - 4m3 [Mhr/m3] 4 - 5m3 [Mhr/m3] 5 - 10m3 [Mhr/m3] 10 - 25m3 [Mhr/m3] 25 - 50m3 [Mhr/m3] 50 - 75m3 [Mhr/m3] 3 above 75m [Mhr/m3] DISMANTLING PLATES AND DEMISTERS AND REASSEMBLING TO CALCULATE ACC. TO TABLE 3.1 ON PAGE 71 (CHAPTER IV: ERECTION OF EQUIPMENT IN PETROCHEMICAL PLANTS) INSTALLATION OR REMOVAL OF BLANKING PLATES MAN HOURS FOR PIPING OVERHAUL [ITEM 22.1. 22.4] X

2.2.

2.3.

2.4.

3. WORK AT HIGHER ELEVATION (ABOVE A STABLE FLOOR) VALID FOR PIPING AND EQUIPMENT OVERHAUL ELEVATION FACTOR in a canal 0-3m 3-6m 6-9m 9 - 12 m 12 - 15 m above 15 m

229

XIV. MAN HOURS FOR PIPING AND STEEL STRUCTURES IN "TECHNIP" TENDERS A. 1. PIPING BETWEEN PLANTS AND IN PLANTS CALCULATION FACTORS Calculate a uniform factor for each item by multiplying below factors and enter it in front of each item. MATERIAL MULTIPLIERS MATERIAL Stainless steel AISI 304-304H-304L Stainless steel AISI 309-309S Stainless steel AISI 310-310S Stainless steel AISI 316 + Titanium Stainless steel AISI 317-317L Stainless steel AISI 321-347H Stainless steel AISI 329 Stainless steel AISI 347 Aluminium alloys welded (BW/SW)1,50 Aluminium alloys - threaded (THD)1,00 Cooper alloys Nickel alloys Monel Inconel Incoloy Hastelloy Titanium Jacketed C.S. Jacketed inox /C.S. Jacketed inox GR 1: HPVC(high vinylpolyethylene) GR 2: KS Resin (Vinyl ester resin) Factor

1.1.

- MATERIAL: Factor - Carbon steel - Galvanized C. S . - Killed C.S. - C.S. cement lined - C.S. ebonite lined - C.S. teflon lined - C.S. rubber lined - C.S. epoxy lined - Alloy steel carbon moly (0,5 Mo) - Alloy steel 1 Cr - 0,5 Mo - Alloy steel 1,25 Cr - 0,5 Mo - Alloy steel 2,25 Cr - 1,0 Mo - Alloy steel 3 Cr - 1,0 Mo - Alloy steel 5 Cr - 0,5 Mo - Alloy steel 9 Cr - 0,5 Mo - Alloy steel 12 Cr - Alloy steel 2,5 Ni - Alloy steel 3,5 Ni - Alloy steel 9 Ni - C.S. or Alloy Wet H2 S nace (Calculated to the previous factor)

1.2.

FACTORS FOR UNDERGROUND INSTALLATION (Calculated to the material mulpltipliers) - Prewrapped pipes: no prewrapping ; - Not wrapped pipes: no prewrapping ;

with prewrapping with prewrapping

1.3.

FACTORS FOR % RADIOGRAPHIC INSPECTIONS (NDE /RT) (Calculated to the material multipliers) Cost (NDE/RT) not included Cost (NDE/RT) included to 10% 20% 50% 100% FACTOR FOR HEAT TREATMENT (PWHT) If heat treatment is foreseen, calculate with the factor of This factor includes the man hours for PWHT

1.4.

to the material multipliers.

2. 2.1.

PIPES (PEP = 75%) MAN HOURS - TABLE FOR PIPES, page 37 Take the manhour [Mhr/ton] for 1-mm wall thickness for relative average diameter and enter it in the pipe weight column. Multiply the average wall thickness by the manhour and total weight in tons. If each item is not identified the wall thickness, it shall be estimated. PREFABRICATION / INSTALLATION RATIO: acc. to table on page 49 FITTINGS (PEP = 75%) MAN HOURS - TABLES FOR FITTINGS, page 38 Procedure as under item 2.1. PREFABRICATION / INSTALLATION RATIO: acc. to table on page 49

2.2. 3. 3.1.

3.2.

230

4. 4.1.

FLANGES MAN HOURS - TABLE FOR FLANGES, page 30 and 31 (PEP = 80%) Manhour [Mhr/kg] to be selected for the nearest diameter and assumed pressure. If the quantity is given in tons [Mhr/kg] multiply by 1000. If the calculation is based on PEP = 75%, the manhour should be multiplied by 1,07. PREFABRICATION / INSTALLATION RATIO: acc. to table on page 49 BRANCH CONNECTION BRANCH 90, BW /SW BRANCH 90, BW (N OF BRANCH), PREFABRICATION 100% (PEP = 75 %) to 1 1/2" Mhr /ea 2" - 6" 6" - 10" 10"- 14" 14"- 20" above 20" X aver. = Mhr/ ea X aver. = Mhr/ ea X aver. = Mhr/ ea average = Mhr/ ea X aver. = Mhr/ ea %

4.2. 5. 5.1. 5.2.

5.3.

BRANCH 45, BW, VALUES UNDER 5.2 TO BE INCREASED

6. 6.1.

VALVES, 100% INSTALLATION (PEP = 75 %) WITH FLANGED ENDS (FLG.) Table for valves on page 39 Manhour [Mhr/kg] to be selected for the nearest diameter and assumed pressure. If the quantity is given in tons [Mhr/kg], multiply by 1000.

6.2. WITH WELDING ENDS 6.2.1. FOR BUTT WELDING (BW): Triple the man hours acc. to item 6.1. 6.2.2. SOCKET WELDING AND THREADED JOINTS (SW/THD) Since in practice the most frequently used valves are < 2" and pressure 300-800#, I suggest the calculation is made with the manhour: [Mhr/ kg] or 6.3. [Mhr/ ton] (PEP = 75% )

CONTROL AND SAFETY VALVES (ON/OFF) Man hours acc. to item 6.1 to be increase

times or

[Mhr/ kg]

7.

MISCELLANEOUS, INSTALLATION 100% (PEP = 75%) This item includes all other unlisted piping elements. The effect of installation [kg/Mhr] is equal to the average diameter in inches. 1 Mhr 1000 Mhr Calculate as follows: = or = or aver. aver. kg aver. ton

kg = Mhr

8. PIPING SUPPORTS 8.1. MAN HOURS (PEP = 75%) 8.1.1. BASED ON AVERAGE DIAMETER: The effect of fabrication and installation [kg/Mhr] is equal to the average diameter in inches. kg Calculate as follows: Mhr = aver. or aver. 1 = kg Mhr or = aver. 1000 = ton Mhr

A DIVISION OF HOURS TO FABRICATION & INSTALLATION HOURS SPLIT UP FABRICATION INSTALLATION to 2" .% .% 2,1" - 4,0" .% .% 4,1" - 8,0" .% .% 8,1" - 15" .% .% above 15" .% .%

231

BASED ON UNIT WEIGHT OF SUPPORTS (PEP =75%) FABRICATION [Mhr/kg] INSTALLATION [Mhr/kg] - Small supports to 1,5 kg/pc. ------ Supports 1,51 - 5,0 kg/pc. - Supports 5,01 - 25 kg/pc. - Supports 25,01 - 50 kg/pc. - Supports 50,01 -100 kg/pc. - Supports above 1,5 kg/pc. - Spring supports -----B. STEEL STRUCTURE ERECTION Productivity Efficiency Percentage (PEP) = 75% Item 1811.01E 1811.02E 1812.01E 1812.02E 1813.01E 1813.02E 1815.01E 1814.16E 1814.08E 1814.09E 1814.10E 1814.11E 1814.12E 1814.05E 1814.06E 1814.07E 1814.14E 1814.15E 1821.01E 1821.02E 1822.01E 1822.02E 1822.03E 1823.04E 1823.05E 1823.06E STEEL STRUCTURE Steel piperack Structure - Type I Steel piperack Structure - Type II Steel process Structure - Type I Steel process Structure - Type II Steel shelter Structure - Type I Steel shelter Structure - Type II Steel structure - Type III Steel structure - Type IV Steel grating for straight platforms Steel grating for circular platforms Stair steps in steel grating Chequered plate for straight platform Chequered plate for circular platform Straight railing Sloped railing Circular railing Vertical ladder with safety cage Vertical ladder without safety cage Steel sheeting for roofing Steel sandwich panels for roofing Steel sheeting for siding Steel sandwich panels for siding Fiberglass translucid sheeting Galvanized steel gutter Steel downspout Cast iron downspout terminal Steel Structures-Type 1 (Trestle) (M) Steel Structures-Type 2 (Pipe rack) (H) Steel Structures-Type 2 (Structures) (H) Steel Structures-Type 3 (Platforms) (L) Steel Structures-Type 4 (Count. sad.) (L) Handrails, straight (L) Handrails for sloped stair (L) Handrails circular (L) Galvanized grating straight flooring Galvanized grating circular flooring Galvanized grating stair steps Chequered plate straight flooring (L) Corrugated steel plate for flooring (L) Chequered plate circular flooring (L) Chequered plate stair steps (L) Ladders with safety cage (L) Ladders without safety cage (L) Roofing Corr. Prep. Galv. Steel Sheet 8/10 Roofing type Prep. Galv. Sandwich Panels Siding Corr. Prep. Galv. Steel Sheet 8/10 Siding type Prep. Galv. Sandwich Panels Fiberglass translucid double sheet & frame Galvanized steel standard doors Galvanized steel sliding doors Galvanized steel rolling doors Galvanized steel window Metal louvers type adjustable Continuous ridge vent on top roof Unit kg kg kg kg kg kg kg kg kg kg u kg kg kg kg kg kg kg sqm sqm sqm sqm sqm m m u kg kg kg kg kg kg kg kg kg kg kg kg kg kg kg kg kg sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm m

8.1.2.

TOTAL [Mhr/kg]

Mhr/ Unit

232

XV. APPENDIX
1. Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 Dn-mm OD-mm 21,3 26,9 33,4 42,4 48,3 60,3 73 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 OD-mm ISO R7 DIN 2448/2458 SUMMARY OF PIPE SCHEDULED SIZES, WALL THICKNESS AND UNIT MASS [kg/m] Wall thick. Std|Ext 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10 Wall thick. Std|Ext 2 0,95 1,23 1,55 1,99 2,28 2,88 3,5 3,65 4,29 5,54 2,3 1,08 1,4 1,76 2,27 2,61 3,29 4,01 4,19 4,91 6,35 2,6 1,2 1,56 1,97 2,55 2,93 3,7 4,51 4,71 5,53 7,16 8,79 2,9 1,32 1,72 2,18 2,82 3,25 4,11 5,01 5,24 6,15 7,97 9,78 11,8 17 25,3 3,2 1,43 1,87 2,38 3,09 3,56 4,51 5,51 5,75 6,76 8,77 10,8 13 19,1 21,3 28,4 27,8 35,8 3,6 1,57 2,07 2,65 3,44 3,97 5,03 6,16 6,44 7,57 9,83 12,1 14,6 21,2 23,9 31,6 31,3 39,7 40,3 44,8 4 1,71 2,26 2,9 3,79 4,37 5,55 6,81 7,11 8,38 10,9 13,4 16,2 23,8 26,5 35,4 34,7 44,6 44,7 49,7 4,5 1,86 2,49 3,21 4,21 4,86 6,19 7,6 7,95 9,37 12,2 15 18,2 26,4 29,8 39,3 39 49,5 50,2 55,9 61,5 67,2 5 2,01 2,7 3,5 4,61 5,34 6,82 8,38 8,77 10,3 13,5 16,6 20,1 29,5 33 44 43,2 55,4 55,7 62 68,3 74,6 80,8 87,1 99,6 112 2 2,3 2,6 2,9 3,2 3,6 4 4,5 5 5,6 6,3 7,1 8 8,8 10 11 12,5

2,94 3,84 5,08 5,9 7,55 9,31 9,74 11,5 15 18,5 22,5 33,1 36,9 49,3 48,3 62,2 62,3 69,4 76,4 83,5 90,4 97,4 104 112 125 5,6

3,2 4,21 5,61 6,53 8,39 10,4 10,8 12,8 16,8 20,7 25,2 37,1 41,4 55,5 54,3 69,9 70 77,9 85,9 93,8 102 109 117 125 133 141 6,3

4,61 7,21 9,32 11,5 12,1 14,3 18,8 23,2 28,2 41,6 46,6 62,3 61 78,6 78,8 87,7 96,6 106 114 123 132 141 150 159 7,1 7,95 10,3 12,8 13,4 16 21 26 31,6 45,6 52,3 68,4 68,6 86,3 88,6 98,6 109 119 129 139 149 159 169 179 8 8,57 11,2 13,9 17,4 22,9 28,4 34,6 51,6 57,3 77,4 75,3 97,8 97,3 108 119 130 141 152 163 175 186 196 8,8 9,45 12,4 15,5 19,5 25,7 32 39 56,5 64,9 84,9 85,2 107 110 123 135 148 160 173 185 198 211 223 10 10,1 13,4 16,8 21,1 28 34,9 42,7 63,7 71,1 96 93,5 121 121 135 149 162 176 190 204 218 231 245 11 11 14,7 18,7 23,6 31,4 39,2 48 80,3 106 137 153 168 184 200 215 231 247 262 278 12,5

233

Above weights are for carbon and alloy steel pipe only. For austenitic stainless steel multiply by 1.02. For ferritic stainless multiply by 0.95.

kg/m x 0. 67197 = lbs/ft

(CONTINUATION ISO R7 DIN 2448/2458 PIPES)


Dn-mm 15 20 25 32 40 50 65 65 80 100 125 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 Dn-mm OD-mm 21,3 26,9 33,7 42,4 48,3 60,3 73 76,1 88,9 114,3 139,7 168,3 219,1 273 323,9 355,6 406,4 457 508 559 610 660 711 762 813 864 914 OD-mm Wall thick. Std|Ext 2\2 2\2,3 2\2,6 2\2,6 2,3\2,6 2,3\2,9 2,6\2,9 2,6\2,9 2,9\3,2 3,2\3,6 3,6\4 4\4,5 4,5\6,3 5\6,3 5,6\7,1 5,6\8 6,3\8,8 6,3\10 6,3\11 6,3\12,5 6,3\12,5 7,1\14,2 7,1 8 8 8,8 10 Wall thick. Std|Ext 14,2 16 17,5 20 22,2 25 28 30 32 36 40 45 50 55 60 65 70

16,1 20,6 26,2 35,1 43,9 54 71,8 90,6 108 120 137 155 173 191 209 226 244 262 280 298 315 14,2 28,8 38,8 60,1 80,1 101 121 134 154 174 194 214 234 254 274 294 314 335 354 16

41,8 65,1 87 110 132 146 168 190 212 234 256 277 299 321 343 365 387 17,5 73,1 98,2 125 150 166 191 216 241 266 291 316 341 366 391 416 441 20 80 108 137 165 183 210 238 266 294 322 349

120 153 184 204 235 266 298 329 361

132 169 204 226 261 296 331 367 402

234

217 241 278 316 354 391 429

230 255 295 335 376 416 456

284 329 374 419 464 510

361 411 462 512 562

457 514 570 627

565 628 691

684 753

814

433 488 22,2 25 28 30 32 36 40 45 50 55 60 65 70

Above weights are for carbon and alloy steel pipe only. For austenitic stainless steel multiply by 1.02. For ferritic stainless multiply by 0.95.

kg/m x 0. 67197 = lbs/ft

235

3. DIMENSIONS - TABLE MANUAL


ELBOW 90 - 180 R = 1,5 d

ANSI B 36.10 SUMMARY OF PIPE SCHEDULED SIZE - WALL THICKNESS [mm]


DN [inch] 1/2" OD d [mm] 5S 1,65 1.65 1.65 1.65 1.65 1.65 2.11 2.11 2.11 2.77 2.77 2.77 3.40 3.96 3.96 4.19 4.19 4.78 5.54 10S 2.11 2.11 2.77 2.77 2.77 2.77 3.05 3.05 3.05 3.40 3.40 3.76 4.19 4.57 4.78 4.78 4.78 5.54 6.35 min 1/2" 3/4" 1" 1 1/4" 1 1/2" 2" 2 1/2" 3" 4" 5" 6" 8" 10" 12" 14" 16" 18" 22" 3/8" 3/8" 1/2" 1/2" 3/4" 1" 1 1/4" 1 1/2" 2" 2 1/2" 4" 4" 5" 6" 8" 10" 12" 16" N 25 29 38 48 57 64 76 86 105 124 143 178 216 254 279 305 343 381 432 6.35 6.35 6.35 6.35 6.35 O 150# 16 16 16 16 16 20 20 20 20 23 23 23 26 26 29 29 32 32 35 6.35 6.35 6.35 7.92 7.92 7.92 9.52 9.52 7,04 7,80 8,38 9,52 9,52 11,13 12,70 14,27 O 300# 16 20 20 20 23 20 23 23 23 23 23 26 29 32 32 35 35 35 42 9.52 9.52 9.52 9.52 9.52 9.52 S 150# 60,3 69,9 79,4 88,9 98,4 120,6 139,7 152,4 190,5 215,9 241,3 298,4 361,9 431,8 476,2 539,7 577,8 635 749,3 10 20 30 21,3 26,7 33,4 42,2 48,3 60,3 73,0 88,9 114,3 141,3 168,3 219,1 273,0 323,8 355,6 406,4 457,2 508,0 609,6 Schedule STD and 40S 2,77 2.87 3.38 3.56 3.68 3.91 5.16 5.49 6.02 6.55 7.11 8.18 9.27 10.31 11.13 12.70 14.27 15.09 17.48 S 300# 66,7 82,5 88,9 98,4 114,3 127 149,2 168,3 200 234,9 269,9 330,2 387,3 450,8 514,3 571,5 628,5 685,8 812,8 10,31 12,70 14,27 15,09 16,64 19,05 20,62 24,61 Y 150# 47,6 52,4 55,6 57,1 61,9 63,5 69,8 69,8 76,2 88,9 88,9 101,6 101,6 114,3 127 127 139,7 144,5 152,4 12,70 12,70 12,70 12,70 12,70 12,70 12,70 Y 300# 52,4 57,1 61,9 65,1 68,3 69,8 76,2 79,4 85,7 98,4 98,4 111,1 117,5 130,2 142,9 146 158,7 161,9 168,3 40 60 Schedule XS and 80S 3,73 3,91 4,55 4,85 5,08 5,54 7,01 7,62 8,56 9,52 10,97 12,70 15,09 17,47 19,05 21,44 23,82 26,19 30,96 GASKET 150# 48x21 57x27 67x33 76x42 86x49 105x60 124x73 137x89 15,09 18,26 21,44 23,82 26,19 29,36 32,54 38,89 GASKET 300# 54x21 67x27 73x33 83x42 95x49 111x60 4 130x73 4 149x89 4 8 8 8 8 12 12 12 16 16 20 20 11,13 12,70 14,27 18,26 21,44 25,40 27,79 30,96 34,92 38,10 46,02 NR. OF BORE 150# 4 4 4 4 4 20,62 25,40 28,58 31,75 36,52 39,67 44,45 52,37 NR. OF BORE 300# 4 4 4 4 4 8 8 8 8 8 12 12 16 16 20 20 24 24 24 80 100 120 140 160 4,78 5,56 6,35 6,35 7,14 8,74 9,52 11,13 13,49 15,88 18,26 23,01 28,58 33,34 35,71 40,49 45,24 50,01 59,54 STUD BOLTS 150# 12x65 12x65 12x70 12x70 12x75 16x85 16x90 16x95 16x95 20x100 20x100 20x110 22x120 22x120 24x135 24x140 30x150 30x160 33x180 STUD BOLTS 300# 12x70 16x75 16x85 16x85 20x95 16x90 20x100 20x110 20x115 20x120 20x125 22x140 24x160 30x170 30x180 33x190 33x195 33x210 39x235 7,47 7,82 9,09 9,70 10,16 11,07 14,02 15,24 17,12 19,05 21,95 22,22 25,40 25,40 Schedule XXS

ELBOW 60 R = 1,5 d
K

ELBOW 45 R = 1,5 d

3/4" ELBOW 30 R = 1,5 d


H

1" 1 1/4" 1 1/2" 2" 2 1/2" 3" 4" 5" 6" O 8" 10" 12" 14" 16" 18" 20" 24"

F
C
A

d
A E

d 0 max d 0 min N 0 max M 0 min N N TEE-PIECE STRAIGHT d d Y

S WELDING NECK FLANGE R. F. ANSI B. 16-5

REDUCER

DN [mm] 1/2" 3/4" 1" 1 1/4" 1 1/2" 2" 2 1/2" 3" 4" 5" 6" 8" 10" 12" 14" 16" 18" 20" 24"

OD d 21,3 26,7 33,4 42,2 48,3 60,3 73,0 88,9 114,3 141,3 168,3 219,1 273,0 323,8 355,6 406,4 457,2 508,0 609,6 A 38 29 38 48 57 76 95 114 152 190 229 305 381 457 533 610 686 762 914 B 48 43 56 70 83 106 132 159 210 262 313 414 518 619 711 813 914 1016 1219 C 29 22 29 37 44 58 73 87 116 145 175 233 292 350 408 467 525 583 700 E 76 57 76 95 114 152 191 229 305 381 457 610 762 914 1067 1219 1372 1524 1829 F 16 11 22 25 29 35 44 51 64 79 95 127 159 190 222 254 286 318 381 G 15 11 15 19 22 30 37 44 59 74 89 119 149 178 208 238 268 297 357 H 10 8 10 15 20 32 41 61 82 102 123 143 163 183 204 245 J 10 8 10 13 15 20 25 30 40 50 60 80 99 119 139 159 179 199 239 K 22 17 22 33 44 66 88 132 176 220 264 308 352 396 440 528 L 15 20 25 30 39 49 59 79 98 119 158 197 237 276 316 355 394 473 M -38 51 51 63 76 89 89 102 127 140 152 178 203 330 356 381 508 508

236

max

175x114 181x114 197x141 216x141 222x168 251x168 279x219 308x219 340x273 362x273 410x324 422x324 451x356 486x356 515x406 540x406 550x457 595x457 605x508 655x508 720x610 775x610

237

5. CONVERSIONS BETWEEN ENGLISH AND (SI) STANDARD UNITS

QUANTITY Length Pressure* Pressure** Flow*** Flow+ Force Mass Time Volume*** Temperature Torque Power Shaft speed Frequency Displacement Kinematic viscosity Velocity

millimeter (mm) bar (bar g, or bar a) mm or mercury (mm Hg) liters per minute (l/min) 3 cubic decimeters/sec (dm/sec) Newton (N) kilogram (Kg) second (sec) liter (l) degrees Celsius (C) Newton-meters (Nm) kilowatt (kw) revolutions per minute (rpm) Hertz (Hz) millimeters/revolution (ml/rev) centistokes (cSt) meter per second (m/s)

inch (in) 1 inch = 25.4 mm pounds/sq. in. (psig or psial) 1 bar = 14.5 psi inches of mercury (in Hg) 1 in.Hg = 25.4 mm Hg U.S. gallons per minute (U.S. GPM)1 U.S. GPM = 3.79 l/min 3 cubic feet per minute (cfm) 1 dm/sec = 2.12 cfm pound (f) or lb (f) (force) 1 lb (f) = 4.44 N pound (m) or lb (m) (mass) 1 Kg = 2.2 lb (m) second (sec) gallon (U.S. gal) 1 U.S. gal = 3.79 l degrees Fahrenheit (F) C = 5/9 (F -32) pounds (f) inches [lbs(f)-in] 1 Nm = 8.88 lb (f)-in horsepower (HP) 1 kw = 1.34 HP revolutions per minute (rpm) cycles per second (cps) 1 Hz = 1 cps cubic inches per revolution (cipr) or (cir) 1 ml/rev = 0.061 cipr Saybolt Universal Seconds (SUS or SSU) cSt = (4.635) (SSU)++ feet per second (fps) 1 m/s = 3.28 fps

NOTES: *Pressure above atmospheric. **Pressure below atmospheric. ***Liquid. +Gas. ++@38C; Factor is 4.667@99C

LENGTH mm cm meters meters meters Km Km Km Km

x x x x x x x x x

0.03937 0.3937 39.37 3.281 1.0936 3280.8 1093.6 0.6214 0.5397

= = = = = = = = =

inches inches inches feet yards feet yards miles sea miles

x x x x x x x x x

25.4 2.54 0.254 0.3048 0.9144 0.0003048 0.0009144 1.609 1.853

= = = = = = = = =

mm cm cm meters meters Km Km Km Km

AREA sq mm sq cm sq meters sq meters sq Km hectares

x x x x x x

0.00155 0.155 10.764 1.196 0.3861 2.471

= = = = = =

sq inches x sq inches x sq feet x sq yards x sq milesyardsx acres x

645.2 6.452 0.0929 0.8361 2.59 0.4047

= = = = = =

sq mm sq cm sq met. sq met. sq Km hectares

VOLUME cu cm cu cm liters liters liters liters cu meters cu meters cu meters

x x x x x x x x x

0.061023 0.3381 61.023 0.03531 0.2642 0.22 35.314 6.3226 6.1104

= = = = = = = = =

cu inches fl ounces cu inches cu feet U.S. gal Imperial gal cu feet barrel (oil) barrel (Eng.)

x x x x x x x x x

16.387 29.57 0.016387 28.317 3.785 4.544 0.02832 0.158162 0.163656

= = = = = = = = =

cu cm cu cm liters liters liters liters cu met. cu met. cu met.

238

MASS (WEIGHT) grams x grams x Kg x Kg x Kg x Kg x tons (metric) x tons (metric) x

15.432 0.0353 35.27 2.2046 0.001102 0.000984 19.684 22.046

= = = = = = = =

grains oz. avoir-dupois oz. avoir-dupois lbs U.S. tons long tons cwt (Eng.) cwt (US)

x x x x x x x x

0.0648 28.35 0.02835 0.4536 907.2 1016.048 0.0508 0.04536

= = = = = = = =

grams grams Kg Kg Kg Kg tons (metric) tons (metric)

PRESSURE gr/sq cm Kg/sq cm Atmosphere Atu bar

x x x x x

0.01422 14.22 14.70 14.22 14.5

= = = = =

p.s.i. (lb/sq in) p.s.i. (lb/sq in) p.s.i. (lb/sq in) p.s.i. (lb/sq in) p.s.i. (lb/sq in)

x x x x x

70.31 0.07031 0.06804 0.07031 0.069

= = = = =

gr/sq cm Kg/sq cm Atmosphere Atu bar

UNIT VOLUME liters/min x liters/min x liters/hr x cu m/min x cu m/hr x cu m/hr x

0.2642 0.03531 0.0044 35.314 0.5886 4.4028

= = = = = =

U.S. gpm cfm U.S. gpm cfm cfm U.S. gpm

x x x x x x

3.785 28.317 227.1 0.02832 1.6992 0.2271

= = = = = =

liters/min liters/min liters/hr cu m/min cu m/hr cu m/hr

POWER Watts Kw Kw Kw cheval vap.

x x x x x

0.00134 1.3410 0.948 0.5272 0.9863

= = = = =

hp hp Btu/sec Ctu/sec hp

x x x x x

745.7 0.7457 1.05486 1.8967 1.0139

= = = = =

Watts Kw Kw Kw cheval vap.

WORK/TORQUE mkp (mkg) x mkp (mkg) x cmkp (cmkg) x Kw/hr x Kw/hr x

7.233 86.80 0.868 0.000293 0.0001628

= = = = =

ft lbs inch - lbs inch - lbs Btu Ctu

x x x x x

0.1383 0.0115 1.15 3413 6143

= = = = =

mkp (mkg) mkp (mkg) cmkp (cmkg) Kw/hr Kw/hr

MISCELLANEOUS Circumference of cyrcle = 3.1416 x Area of Circle = 0.7854 x Area Sphere = 3.1416 x Volume of Sphere = 0.5236 x 1 lb per sq in is equivalent to 0.06804 atmospheres

dia (dia) 2 2 (dia) 2 (dia) 2

= =

6.2832 x radius 3.1416 x (radius)

239