Alexandria University Faculty of Engineering

Electrical Engineering Department 4th year communication & power Eng.

PROJECT MANAGEMENT
Assignment (2)
1Draw the following network using The Activity-On-Node method and determine the critical path(s) and find activity details considering the following data: Activity A B C D E F G H I J K Duration (days) 5 4 4 10 8 3 6 8 14 12 6 Depends on ---A A B B C C G E F G E I J H Relationship & Lag ---SS=4 FS=2 FF=1 FS=0 FS=2 FF=3 SF=8 SS=1 FF=2

SS=1 FF=1 FS=1

2-

Draw the following network using The Activity-On-Node method and determine the critical path(s), find activity details; and draw Bar-chart considering the following data: Activity A B C D E F G H I J Depends upon ---A A B B C C G F E Duration (days) 6 4 2 10 8 3 6 8 14 12 Relationship & Lag ---SS=5 FS=0 SS=1 FS=1 FF=2 FF=3 SF=6 SS=4 --

Given: Contract Duration equal to 55 Days.

Page 1 of 2

Alexandria University Faculty of Engineering

Electrical Engineering Department 4th year communication & power Eng.

PROJECT MANAGEMENT
Assignment (2)
3The following tables illustrate the data for the CPM diagram for a project. The project start date on wed, 1st May 2013, Workdays per week equal six, and week start on Saturday. It is required to: Draw PDM network; and

Calculate the activity dates (ES, EF, LS, and LF).

Act. A B C D E F

Duration days 6 5 8 1 2 8

Predecessor activity(s) -A A C D D&E

Relationship --FS FF FS SS FS

Time Lag --2 3 1 2 0

4-

As Shown in problem No. 1 if Project start date is wed 1st May 2013, Workdays per week equal six, and week start on Saturday, project finish date is 31 July 2013. It is required to: Draw ADM network considering all previous relations FS=0; and Calculate the activity dates (ES, EF, LS, and LF). Given cost plus fee contract; if Min Cost equal to 2,000 EGP, Max Cost equal to 8,000 EGP, Min Price equal to 2,300 EGP. Determine the contract full analysis?

5-

6-

Given target cost contract; if Min Cost equal to 2,000 EGP, target cost equal to 4,000 EGP, Max Cost equal to 6,000 EGP, Min fee equal to 500 EGP, target fee equal to 800 EGP, Max fee equal to 1,000 EGP. Determine the contract full analysis?

7-

Given target cost contract; Cost at the end of target band = 180,000 EGP, Cost at the start of target band = 140,000 EGP, GMP = 320,000 EGP, Cost increase share by the contractor = 25%, GMC = 280,000 EGP, Target Fee = 20,000 EGP, Max Fee = 28,000 EGP, Min Fee = 15,000 EGP, Share saving by contractor = 15%. Determine the contract full analysis using sketches? and analyze the following situation in the point of contractor and owner views: Actual Cost = 50,000 EGP; Actual Cost = 150,000 EGP; Actual Cost = 250,000 EGP; Actual Cost = 350,000 EGP.

Page 2 of 2