ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Task Name Hala + Corp administrativ Suprastructura Montarea stalpilor din otel Montarea grinzilor din otel Montare tabla cutata Montare popi extensibili Montare plasa sudata in placa Turnare placa cu autopompa Cofrare scari Armare scari Turnare scari cu autopompa Timp de asteptare pt intarirea betonului Acoperis Montare grinzi acoperis Montare contravantuiri Montare pane acoperis Inchideri Montare panouri sandwich acoperis Montare panouri sandwich perete Realizarea peretilor despartitori Realizarea tavanelor false Montare ferestre aluminiu Montare usi aluminiu cu S < 2.5 mp Montare usi aluminiu cu S>2.5mp

Duration 75 days 26 days 9 days 4 days 1 day 3 days 1 day 1 day 1 day 1 day 1 day 4 days 19 days 2 days 1 day 16 days 30 days 5 days 7 days 6 days 7 days 3 days 1 day 1 day

Start Fri 6/22/12 Fri 6/22/12 Fri 6/22/12 Thu 7/5/12 Wed 7/11/12 Thu 7/12/12 Tue 7/17/12 Wed 7/18/12 Thu 7/19/12 Fri 7/20/12 Mon 7/23/12 Tue 7/24/12 Mon 7/30/12 Mon 7/30/12 Wed 8/1/12 Thu 8/2/12 Fri 8/24/12 Fri 8/24/12 Fri 8/31/12 Tue 9/11/12 Wed 9/19/12 Fri 9/28/12 Wed 10/3/12 Thu 10/4/12

Finish W Thu 10/4/12 Fri 7/27/12 Wed 7/4/12 Tue 7/10/12 Wed 7/11/12 Mon 7/16/12 Tue 7/17/12 Wed 7/18/12 Thu 7/19/12 Fri 7/20/12 Mon 7/23/12 Fri 7/27/12 Thu 8/23/12 Tue 7/31/12 Wed 8/1/12 Thu 8/23/12 Thu 10/4/12 Thu 8/30/12 Mon 9/10/12 Tue 9/18/12 Thu 9/27/12 Tue 10/2/12 Wed 10/3/12 Thu 10/4/12 T F S

Jun 24, '12 S M T W

Jul 1, '12 S M T

Jul 8, ' S M

Montator[10]

Task Project: Hala + Corp administrativ Date: Fri 6/22/12 Split Progress

Milestone Summary Project Summary Page 1

External Tasks External Milestone Deadline

2 T

Jul 15, '12 S M T

Jul 22, '12 S M T

Jul 29, '12 S M T

Aug 5, '12 S M T

Aug 12, '12 S M T W

Aug 19, '12 S M T W

Au S

Montator[10] Montator[3] Dulgher[8] Fierar[6] Betonist[6] Dulgher[2] Fierar[2] Betonist[2]

Montator[10] Montator[3] Montator[

Task Project: Hala + Corp administrativ Date: Fri 6/22/12 Split Progress

Milestone Summary Project Summary Page 2

External Tasks External Milestone Deadline

26, '12 M T W

Sep 2, '12 S M T

Sep 9, '12 S M T

Sep 16, '12 S M T W

Sep 23, '12 S M T W

Sep 30, '12 S M T W

Oct 7, '12 S M T

10]

Lacatus[10] Lacatus[9] Specialist montare gips carton[10] Specialist montare gips carton[10] Tamplar categoria speciala[7] Tamplar categoria speciala[5] Tamplar categoria speciala[6]

Task Project: Hala + Corp administrativ Date: Fri 6/22/12 Split Progress

Milestone Summary Project Summary Page 3

External Tasks External Milestone Deadline