JUNE 2013

ROAD PROJECTS 2013


In 2013 the City of Edmonton is spending $441.8 million on 177 road projects. This investment includes $87.2 million for major arterial work, $166.6 million for bridges and interchanges and $167 million for Neighbourhood Renewal projects. It also includes $12 million that City Council reallocated for additional arterial milling and overlay projects, in recognition of the Citys need to enhance its approach to roadway rehabilitation. City Council also added an extra $9 million to the 2013 road projects budget for 50 additional triage neighbourhood milling and overlay projects. In keeping with a more robust approach to arterial roadway rehabilitation, City Council has already increased the 2014 budget for road projects from $15 million to $30 million by reallocating $9 million and adding $6 million from Edmontons share of the Government of Albertas Municipal Sustainability Initiative (MSI) fund. This additional $15 million investment will pave the equivalent of a two-lane road that is 35 kilometres long, roughly the distance between downtown Edmonton and Leduc.

MAJOR ARTERIAL ROADS - $87.2 M (25 projects)


New in 2013 (9 projects) 23 Avenue/Gateway Boulevard 34 Avenue widening (34 St to 48 St) 63 Avenue (99 St to 104 St) Including 63 Ave/104 St intersection 99 Street (82 Ave to Saskatchewan Drive) 153 Avenue (Manning Drive to 50 St) Allendale Road rehabilitation (61 Ave to 104 St) Guardian Road/Lewis Estates Boulevard (Grantham Gate to Potter Greens Drive) NW Roadway Maintenance Yard improvements Stony Plain Road streetscape (149 St to 158 St) Including SPR/156 St intersection Carried over from 2012 (8 projects) 17 Street (23 Ave to Silverberry Road) 66 Street (TUC to 195 Ave) 108 Street/Capital Boulevard 112 Avenue rehabilitation (76 St to 82 St) 118 Avenue streetscape (103 St to 106A St) 178 Street rehabilitation (Callingwood Road to 69 Ave) Central LRT Station rehabilitation and Jasper Avenue streetscape (100 Ave to 102 Ave) Including Jasper Ave/100 St intersection 17 Street at Whitemud Drive interchange

Intersections (8 projects) Calgary Trail/Whitemud Drive Eastbound 50 Street/137 Avenue Gateway Boulevard/Whitemud Drive Eastbound Manning Drive/137 Avenue Victoria Trail/137 Avenue 97 Street/122 Avenue 109 Street/104 Avenue 87 Avenue/178 Street

BRIDGES & INTERCHANGES - $166.6 M (5 projects)


30 Avenue SW over Blackmud Creek Bridge replacement 41 Avenue/Queen Elizabeth II Highway Interchange Rossdale Road Bridge over MacDougall Hill Road Stony Plain Road over Groat Road Bridge rehabilitation Walterdale Bridge replacement project
For details see Construction On Your Streets map:

http://www.edmonton.ca/transportation/on_your_streets/construction-on-your-streets.aspx

ARTERIAL MILLING & OVERLAY - $12 M


By Ward (23 projects) Ward 1 (2 projects) 87 Avenue (182 St to 189 St) 163 Street (95 Ave to Stony Plain Road) Ward 2 (2 projects) 153 Avenue westbound (97 St to Castle Downs Road) Princess Elizabeth Avenue (97 St to Kingsway Ave) Including PE Ave/101 St intersection Ward 4 (1 project) 50 Street (128 Ave to 137 Ave) Ward 5 (1 project) 159 Street (Whitemud Drive to 87 Ave) Ward 6 (6 projects) 100 Street (MacDonald Drive to 103A Ave) 101 Avenue (95 St to 95A St) 105 Street (Jasper Ave to 105 Ave) 116 Street (100 Ave to 104 Ave) 124 Street (Jasper Ave to 107 Ave) Grierson Hill (Rossdale Road to 95A St) Ward 7 (2 projects) 111 Avenue (90 St to 97 St) Fort Road (80 St to Wayne Gretzky Drive) Ward 8 (2 projects) 98 Avenue (50 St to 75 St) Terrace Road (50 St to 98 Ave) Ward 9 (1 project) 111 Street (9 Ave to Saddleback Road) Ward 10 (2 projects) 104 Street (51 Ave to 63 Ave) 111 Street southbound (Whitemud Drive to 37 Ave) Ward 11 (2 projects) 50 Street (68 Ave to 76 Ave) 91 Street southbound (34 Ave to 23 Ave) Ward 12 (2 projects) 50 Street (Ellerslie Road to TUC) Mill Woods Road east (23 Ave to 38 Ave)

ADDITIONAL TRIAGE NEIGHBOURHOOD MILLING & OVERLAY - $9 M


By Ward (50 projects) Ward 1 (9 projects) 109 Avenue (166A St to 170 St) 89 Avenue (182 St to 178 St) 111 Avenue (163 St to 170 St) 167 Street (118 Ave to 121 Ave) 168 Street (118 Ave to 121 Ave) 121 Avenue (168 St to 167 St) 181 Street (118 Ave to 116 Ave) 180 Street (118 Ave to 116 Ave) 116 Avenue (178 St to 181 St) Ward 2 (1 project) 114A Street (150 Ave to 152 Ave) Ward 4 (2 projects)
For details see Construction On Your Streets map:

Ward 7 (6 projects) 119 Avenue (94 St to 97 St) 94 Street (119 Ave to 120 Ave) 124 Avenue (82 St to 87 St) 64 Street (119 Ave to 118 Ave) Yellowhead Trail North Service Road (89 St to 97 St) 126 Avenue (85 St to 89 St) Ward 8 (9 projects) 108 Street (83 Ave to 86 Ave) 74 Avenue (118 St to 119 St) 78 Avenue (W/114 St to 115 St) 79 Avenue (W/114 St to 115 St) 80 Avenue (W/114 St to 115 St) 115 Street (76 Ave to University Ave)

http://www.edmonton.ca/transportation/on_your_streets/construction-on-your-streets.aspx

127 Avenue (E/47 St to 50 St) 134 Avenue (40 St to 41A St) Ward 5 (1 project) Wedgewood Blvd (Weaver Dr-184 St) Ward 6 (11 projects) 98 Avenue (111 St to 112 St) 99 Avenue (111 St to 112 St) 112 Street (98 Ave to 99 Ave) 103 Ave (114 St to 116 St) 103 Ave (120 St to 123 St) 113 Street (Jasper Ave to 103 Ave) 114 Street (Jasper Ave to 103 Ave) 115 Street (Jasper Ave to 103 Ave) 117 Street (Jasper Ave to 104 Ave) 118 Street (100 Ave to Jasper Ave) 119 Street (100 Ave to Jasper Ave)

116 Street (71 Ave to 73 Ave) 119 Street (78 Ave to University Ave) Saskatchewan Drive (119 St to 76 Ave) Ward 10 (6 projects) 108 Street (61 Ave to 70 Ave) 70 Avenue (104 St to 105A St) 67 Avenue (105 St to 106 St) 66 Avenue (105 St to 106 St) 68 Avenue (106 St to 109 St) 43 Avenue North (114 St to 116 St) 92 41 88 62 66 Ward 11 (5 projects) Street (39 Ave to 41 Ave) Avenue (92 St to 97 St) Street (62 Ave to 63 Ave) Avenue/88 Street intersection Avenue/17 Street intersection

NEIGHBOURHOOD RENEWAL $167 M


COLLECTOR PAVING (34 projects) Ward 1 (5 projects) 92 Avenue (149 St to 156 St) 142 Street (Stony Plain Rd to 107 Ave) Including 142 St/107 Ave intersection 168 Street (100 Ave to Stony Plain Rd) 169 Street (100 Ave to Stony Plain Rd) Stony Plain service road (166 St to W/169 St) Ward 2 (6 projects) 117 Street (139 Ave to145 Ave) 120 Street (127 Ave to 132 Ave) 129 Street (155 Ave to 162 Ave) 131 Street (153 Ave to 155 Ave) 155 Avenue (129 St to Cairns Place) 158 Avenue (127 St to 129 St) Ward 3 (3 projects) 88 Street (153 Ave to 160 Ave) 156 Avenue (84 St to 88 St) Klarvatten Road (91 St to 170A Ave) Ward 6 (5 projects) 84 Street (Jasper Ave to 111 Ave)
For details see Construction On Your Streets map:

Ward 7 (2 projects) 38 Street (114 Ave to 118 Ave) 87 Street (137 Ave to 140 Ave) Ward 8 (1 project) 83 Avenue (112 St to 114 St) Ward 9 (1 project) Burton Road (Butterworth Dr to Burton Crescent) Ward 10 (5 projects) 42 Avenue (Gateway Blvd to Calgary Tr) 45 Avenue (Gateway Blvd to Calgary Tr) 48 Avenue (Gateway Blvd to Calgary Tr) Calgary Trail east service road/54 Avenue (Gateway Blvd to Calgary Tr) G.A. Macdonald Avenue (Gateway Blvd to Calgary Tr) Ward 11 (2 projects) 76 Avenue (50 St to 67 St) Youville Drive west (28 Ave to 31 Ave)

http://www.edmonton.ca/transportation/on_your_streets/construction-on-your-streets.aspx

103 Avenue (100 St to 101 St) 103 Street (Bellamy Hill to Jasper Ave) 107 Street (Jasper Ave to 104 Ave) 110 Street (97 Ave to Jasper Ave)

Ward 12 (4 projects) 30 Street (38 Ave to 42 Ave) 38 Avenue (34 St to 44 St) 50 Street (Ellerslie Rd to TUC) Jamha Road (Jackson Rd to 50 St)

COLLECTOR REHABILITATION (13 projects) 130 131 146 148 Ward 2 (4 projects) Avenue (St. Albert Trail to 146 St) Avenue (St. Albert Trail to 148 St) Street (130 Ave to 131 Ave) Street (128 Ave to 131 Ave) Ward 11 (6 projects) 67 Street (68 Ave to 76 Ave) 68 Avenue (50 St to75 St) 71 Street (68 Ave to Girard Rd) 72 Avenue (67 St to 71 St) Girard Road (76 Ave to south of 72 St) 71 Street (82 Ave to Argyll Rd) Ward 10 (2 projects) 22 Avenue (Saddleback Rd to 112 St) 112 Street (Saddleback Rd to 22 Ave) NORTHEAST RESIDENTIAL RECONSTRUCTION (3 projects) Hollick-Kenyon (Ward 4) Ozerna (Ward 3) Matt Berry (Ward 4)

Ward 7 (1 project) 132 Avenue (82 St to 90 St) MICROSURFACING (3 projects) Athlone (Ward 2) Rideau Park (Ward 10) Tweedle Place (Ward 11)

NEIGHBOURHOOD OVERLAY (9 projects) Aldergrove (Ward 1) Bannerman (Ward 4) Brander Gardens (Ward 9) Kennendale Industrial (Ward 4) Lago Lindo (Ward 3) Laurier Heights (east of 139 St) (Ward 5) McNamara Industrial (Ward 1) Pollard Meadows (Ward 12) Ramsay Heights (Ward 9)

NEIGHBOURHOOD RECONSTRUCTION (12 projects) Carried over from 2012 (7 projects) Canora (Ward 1) Capilano (Ward 8) Dovercourt (Ward 2) King Edward Park (Ward 11) Windsor Park (Ward 8) Terrace Heights (Ward 8) Woodcroft (Ward 2) Beginning in 2013 (5 projects) Argyll (Ward 11) Delton (Ward 7) Grovenor (Ward 6) Hazeldean (Ward 11) North Glenora (Ward 6)

For details see Construction On Your Streets map:

http://www.edmonton.ca/transportation/on_your_streets/construction-on-your-streets.aspx