NAMA PEKERJAAN LOKASI TAHUN ANGGARAN

: Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

knga Kab Aceh Besar

REKAPITULASI RENCANA ANGGARAN BIAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar LOKASI : KECAMATAN LHOKNGA TAHUN ANGGARAN : 2013 NAMA PEKERJAAN

NO A. B. C.

JENIS PEKERJAAN PEKERJAAN PERSIAPAN PEKERJAAN POKOK PEKERJAAN LAIN JUMLAH PPN 10 % TOTAL DIBULATKAN = = = = Rp Rp Rp Rp Rp Rp Rp

JUMLAH HARGA 4,753,594.60 669,969,685.64 10,700,000.00 685,423,280.24 68,542,328.02 753,965,608.26 753,966,000.00

TERBILANG :

#NAME?

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

DAFTAR KUANTITAS HARGA


NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

NO.
1

URAIAN PEKERJAAN
2

VOLUME
3

SAT.
4

ANALISA
5

HARGA SATUAN (Rp.)


6

A PEKERJAAN PERSIAPAN 1 Pembersihan Lahan 2 Uitzet/Pemasangan Profil 3 Sewa Pondok 553.30 1.00 1.00 m2 Ls Bh T.01 Taksir Taksir Rp Rp Rp 1,362.00 1,000,000.00 3,000,000.00 Sub Jumlah =

B PEKERJAAN POKOK 1 Galian tanah (AB) 2 Tmbunan tanah Hasil Galian 3 Timbunan Tanah Didatangkan 4 Pasangan Batu 1 : 4 5 Plesteran 1 : 3 6 Drain Hole 7 Beton Cor 1 : 3 : 5 8 Beton Cor 1 : 2 : 3 9 Pembesian 10 Bekisting 11 Rumah Pompa (Bangunan Type -C) 12 Pompa + Asesoris Pemasangan Pipa Leiding 3" Galvanis Tebal 3.2 mm + 13 Asesoris 277.03 207.77 88.53 531.17 1,991.88 23.00 55.33 2.16 237.60 15.84 7.50 1.00 12.00 m3 m3 m3 m3 m3 Bh m3 m3 Kg m2 m2 Unit M' Dihitung T.07.c T.07.c-1 P.01.c P.03.e Dihitung B.02 B.05 B.17 B.22 Taksir Taksir SNI-03.GSP.3 Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp 50,753.00 19,254.00 138,054.00 801,684.00 63,688.00 23,464.00 706,233.00 807,092.00 20,097.00 200,598.00 3,500,000.00 10,000,000.00 119,711.00 Sub Jumlah =

III. PEKERJAAN LAIN-LAIN 1 Papan Nama Proyek 2 Administrasi Dan Dokumentasi 1.00 1.00 Bh Ls Taksir Taksir Rp Rp 700,000.00 10,000,000.00

Sub Jumlah =

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

JUMLAH HARGA (Rp.)


7

Rp Rp Rp Rp

753,594.60 1,000,000.00 3,000,000.00 4,753,594.60

Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp

14,060,103.59 4,000,403.58 12,221,920.62 425,830,490.28 126,858,853.44 539,672.00 39,075,871.89 1,743,318.72 4,775,047.20 3,177,472.32 26,250,000.00 10,000,000.00 1,436,532.00 669,969,685.64

Rp Rp

700,000.00 10,000,000.00

Rp

10,700,000.00

Rp

685,423,280.24

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjan Satuan/Unit Analisa No. (1) A 1 2 3 Tenaga Kerja Pekerja Tukang Tebas Mandor Uraian (2)

: Pembersihan Lapangan : m2 : T.01 Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH OH

0.0090 0.0030 0.0010

68,000.00 82,000.00 80,000.00 Sub Jumlah A

612 246 80 938

B Bahan

Sub Jumlah B C Peralatan 1 Chainsaw Jam 0.0200 15,000.00 300

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

Rp Rp Rp Rp Rp

300.00 1,238.00 123.80 1,361.80 1,362.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. Uraian : Galian Tanah Biasa ( AB) : m3 : Dihitung Satuan (3) Kuantitas/K HargaSatuan Dasar (Rp.) oefisien (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

(1) (2) A Tenaga Kerja

Sub Jumlah A B Bahan

Sub Jumlah B C Peralatan 1 Excavator Jam 0.0862 535,200.00 Rp 46,139.09

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

Rp Rp Rp Rp

46,139.09 46,139.09 4,613.91 50,752.99 50,753.00

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjan Satuan/Unit Analisa No. (1) A Tenaga Kerja 1 Pekerja 2 Mandor Uraian (2)

: Tanah Hasil Galian, Diratakan dan Dirapikan (MP) : m3 : T.07.c Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH

0.2480 0.0080

68,000.00 80,000.00

16,864.00 640.00

Sub Jumlah A B Bahan

17,504.00

Sub Jumlah B C Peralatan

0.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

Rp Rp Rp Rp

17,504.00 1,750.40 19,254.40 19,254.00

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjan Satuan/Unit Analisa No. (1) A Tenaga Kerja 1 Pekerja 2 Mandor Uraian (2)

: Timbunan Tanah Didatangkan, Diratakan dan Dirapikan (MP) : m3 : T.07.c-1 Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH

0.2480 0.0080

68,000.00 80,000.00

16,864.00 640.00

Sub Jumlah A B Bahan 1 Tanah Timbun m3 1.2000 90,000.00

17,504.00 108,000.00

Sub Jumlah B C Peralatan

108,000.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

Rp Rp Rp Rp

125,504.00 12,550.40 138,054.40 138,054.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. (1) A 1 2 3 4 B 1 2 3 Uraian (2) Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor Bahan Batu kali/ Gunung Pasir Pasang Semen PC : Pasangan Batu Kali 1:4 : m3 : P.01.c Satuan (3) OH OH OH OH Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) 2.7030 0.9000 0.0900 0.1350 68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 140,000.00 130,000.00 1,250.00 Jumlah Harga (Rp.) (6)=(4) x (5) 183,804.00 73,800.00 9,360.00 10,800.00 277,764.00 168,000.00 67,600.00 203,750.00 0.00 0.00 439,350.00 11,690.00

m3 m3 Kg

1.2000 0.5200 163.0000

Sub Jumlah B C Peralatan 1 Molen 0,35 m3 Unit/Hari 0.1670 70,000.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

11,690.00 728,804.00 72,880.40 801,684.40 801,684.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. (1) A 1 2 3 4 Uraian (2) Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor : Plesteran 1 : 3, tebal 15mm : m2 : P.03.e Satuan (3) OH OH OH OH Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) 0.3840 0.1900 0.0190 0.0190 68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 130,000.00 1,250.00 Jumlah Harga (Rp.) (6)=(4) x (5) 26,112.00 15,580.00 1,976.00 1,520.00 45,188.00 2,990.00 9,720.00

B Bahan 1 Pasir Pasang 2 Semen PC

m3 Kg

0.0230 7.7760

Sub Jumlah B C Peralatan

12,710.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

57,898.00 5,789.80 63,687.80 63,688.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa : Beton Cor 1 : 2 : 3 : m3 : B.05

No. (1) A 1 2 3 4 B 1 2 3 4

Uraian (2) Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor Bahan Semen PC Pasir Pasang Kerikil Air

Satuan (3)

Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5)

Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH OH OH

1.32000 0.20500 0.02000 0.06000

68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 1,250.00 130,000.00 140,000.00 100.00 Sub Jumlah B

89,760.00 16,810.00 2,080.00 4,800.00 113,450.00 407,500.00 70,590.00 106,680.00 21,500.00 606,270.00 14,000.00

Kg m3 m3 Ltr

326.0000 0.5430 0.7620 215.0000

C Peralatan 1 Molen 0.35 m3

Unit/hari

0.2000

70,000.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

14,000.00 733,720.00 73,372.00 807,092.00 807,092.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa : Beton Cor 1 : 3 : 5 : m3 : B.02

No. (1) A 1 2 3 4 B 1 2 3 4

Uraian (2) Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor Bahan Semen PC Pasir Pasang Kerikil Air

Satuan (3)

Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5)

Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH OH OH

1.32000 0.20500 0.02000 0.06000

68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 1,250.00 130,000.00 140,000.00 100.00 Sub Jumlah B

89,760.00 16,810.00 2,080.00 4,800.00 113,450.00 308,750.00 80,730.00 103,600.00 21,500.00 514,580.00 14,000.00

Kg m3 m3 Ltr

247.0000 0.6210 0.7400 215.0000

C Peralatan 1 Molen 0.35 m3

Unit/hari

0.2000

70,000.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

14,000.00 642,030.00 64,203.00 706,233.00 706,233.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. (1) A 1 2 3 4 B 1 2 3 4 Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor Bahan Papan Kayu Klass III Kaso 5/7 Cm Paku Kayu Minyak Bekisting Uraian (2) : Bekisting (Asumsi 2x pakai) : m2 : B.22 Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH OH OH

0.66000 0.33000 0.03300 0.03300

68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 3,500,000.00 3,500,000.00 18,000.00 22,000.00 Sub Jumlah B

44,880.00 27,060.00 3,432.00 2,640.00 78,012.00 87,500.00 5,250.00 7,200.00 4,400.00 104,350.00

m3 m3 Kg Ltr

0.0250 0.0015 0.4000 0.2000

C Peralatan

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

182,362.00 18,236.20 200,598.20 200,598.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. (1) A Tenaga Kerja 1 Pekerja 2 Tukang Uraian (2) : Drain Hole PVC Dia. 1.0" : Bh : Dihitung Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH

0.0080 0.0800

68,000.00 104,000.00

544.00 8,320.00

Sub Jumlah A B 1 2 3 Bahan Pipa PVC Dia. 1.0" Kerikil Ijuk m' m3 Kg 0.5000 0.0200 0.2000 13,333.33 140,000.00 15,000.00

8,864.00 6,666.67 2,800.00 3,000.00

Sub Jumlah B C Peralatan

12,466.67

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

21,330.67 2,133.07 23,463.73 23,464.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. (1) A 1 2 3 4 Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor Uraian (2) : Pembesian : Kg : B.17 Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH OH OH

0.00700 0.00700 0.00070 0.00040

68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 16,000.00 21,000.00

476.00 574.00 72.80 32.00 1,154.80 16,800.00 315.00

B Bahan 1 Besi Beton 2 Kawat Beton

Kg Kg

1.0500 0.0150

Sub Jumlah B C Peralatan 1 Mesin Potong Besi Hari 0.0005 20,000.00

17,115.00 10.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

18,269.80 1,826.98 20,096.78 20,097.00

ANALISA HARGA SATUAN PEKERJAAN Jenis Pekerjan Satuan/Unit Analisa No. (1) A 1 2 3 4 Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor Uraian (2) : Pemasangan Pipa Leiding 3" Galvanis Tebal 3.2 mm Asesoris : m' : SNI-03.GSP.3 Satuan (3) Kuantitas/K HargaSatuan Dasar oefisien (Rp.) (4) (5) Jumlah Harga (Rp.) (6)=(4) x (5)

OH OH OH OH

0.10800 0.18000 0.01800 0.00540

68,000.00 82,000.00 104,000.00 80,000.00 Sub Jumlah A 75,000.00 20,000.00

7,344.00 14,760.00 1,872.00 432.00 24,408.00 75,000.00 9,420.00

B Bahan 1 Pipa Leiding 3" Galvanis 2 Pengelasan Keliling

m' m'

1.0000 0.4710

Sub Jumlah B C Peralatan 1 Alat Bantu m' 1.0000 500

84,420.00 500.00

D E Overhead + Keuntungan

Sub Jumlah C Sub Jumlah ( A+B+C) 10% x Sub Jumlah (D) Jumlah Harga = (D + E) Harga Satuan Pekerjaan (Dibulatakan)

108,828.00 10,882.80 119,710.80 119,711.00

TAKSIRAN PRODUKSI ALAT GALIAN TANAH

1 Asumsi Jam Kerja Efektif Perhari 2 Perhitungan Kapasitas Bucket a. Kapasitas Bucket b. Faktor Bucket c. Faktor Efisiensi Alat d. Swell e Kapasitas Nyata 3 Perhitungan Waktu Siklus (Ts1) a. Pengangkatan & Swing (Loaded) b. Pembuangan Dumping) c. Penggalian (Cutting) d. Swing Kembali (Unloaded)

7 Jam

(V) (Fb) (Sa) (Sw) (Kn) 1/ (1 + Sw) x V

= = = = =

0.93 m3 1 0.83 0.9 % 0.4895

= = = =

10 10 30 10 60

detik detik detik detik detik

Siklus Per Jam Produksi Max. Teoritis (PMT)

(60 x 60)/Ts1 (Kn x Cm)

60 kali 29.368421 m3/jam

4 Faktor Koreksi a. Efisiensi Kerja b. Keadaan Cuaca c. Faktor Swing d. Faktor Muat e. Faktor Kondisi Kerja

= = = = =

0.602 0.9 0.9 0.9 0.9

Taksiran Produksi Koef.Alat/m3 Pekerja Mandor

= = = =

11.5997 m3/jam 0.0862 Jam 1.2069 OH/M3 0.6035 OH/M3

= =

2 Orang 1 Orang

ANALISA HARGA SATUAN ALAT BERAT


I. DATA PERALATAN
1 Nama Alat 2 Merk 3 Tenaga 4 Kapasitas 3 Harga 6 Umur Ekonomis (Tahun) 7 Jam Kerja per tahun (Tahun) 8 Harga Pokok 9 Harga Bahan Pokok/ Ban 10 Harga Sisa 11 Harga Penyusutan = UE = h = Rp Rp 10% x HP (HP-hbp-HS) = = Rp Rp Rp N = 105 HP 0.7 m3 800,000,000.00 5.00 Thn 2,000.00 jam 800,000,000.00 35,000,000.00 76,500,000.00 688,500,000.00 0.7 M3

HP = Hbp = HS = =

II BIAYA KEPEMILIKAN (OWNERSHIP) Rp/jam


- Penyusutan - Bunga Modal BM - Asuransi (P=2%) 1 Biaya Bahan Bakar BBM S = (Solar) E = N = Hbbm= (Harga BBM) = = = = = (i = 15%)

Jumlah II

Rp
68,850.00 /jam 36,000.00 /jam 4,800.00 /jam Rp 188,372.09 /jam

109,650.00

D = BM = Ba =

(HP-Hbp - HS)/ (UE x h) i((UE + 1)/( 2 UE) x (HP/h) p ((UE+1)/(2 x UE) x (HP/h))

Rp Rp Rp

III BIAYA OPERASIONAL (OPERTIONAL COST)

Jumlah III
Rp

425,522.73

((0,8 x N x S)/E) x Hbbm


0.15 0.602 105 9,000

Rp

2 Biaya Oli Pelumas (Mesin) BBom C = T = (jam) S = E = N = Hbop = (Harga bahan oli) 3 Biaya Transmisi BBOt C = T = (jam) S = E = N = Hbop = (Harga bahan oli) 4 Biaya Hydraulik BBH = C = (Excavator) T = (jam) S =(Excavator) E = N = Hbbh = (Harga bahan hydraulik) 5 Biaya Gemok (Grease) BBG = S =(Excavator) E = N = Hbbg= (Harga bahan gemok) 6 Biaya Saringan (filter-filter) BFF 7 Biaya Bahan Pokok/Ban BBP Hbp = T = (jam) 6 Biaya Operator/Jam Biaya Pemeliharaan/ Perbaikan (f = 90%) BBP = f x (HP - Hbp)/UE = = = = = = = = = = = = = =

((C/T) + (S/E)) x n x Hbop


0.130 (L/HP) 250.00 (jam) 0.0005 (L/HP.jam) 0.602 105 45,000

Rp

6,381.42 /jam

Rp Rp

((C/T) + (S/E)) x n x Hbop


0.223 (L/HP) 1,000.00 (jam) 0.0003 (L/HP.jam) 0.602 105 45,000.00

Rp

3,408.33 /jam

Rp

((C/T) + (S/E)) x n x Hbbh 2.875 (L/HP) 2,000.00 (jam) 0.00064 (L/HP.jam) 0.602 105.00 45,000.00

Rp

11,815.44 /jam

= = = =

(S/E) x N x Hbbg 0.0006 (L/HP.jam) 0.602 105.00 45,000.00

Rp

4,709.30 /jam

0,5 (BBM + BBO + BBH + BBG)

Rp

107,343.29 /jam

Hbp/ T 35,000,000.00 2,000.00

Rp

17,500.00 /jam

Rp

17,142.86 /jam

Rp

68,850.00 /jam

Harga Satuan Pekerjaan/ Jam ( Jumlah Biaya II + III ) Dibulatkan

Rp 535,172.73 Rp 535,200.00

DAFTAR HARGA UPAH, BAHAN DAN SEWA PERALATAN

NAMA PEKERJAAN LOKASI TAHUN ANGGARAN

: Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

NO.

URAIAN

SATUAN

HARGA SATUAN (Rp.)

KET

A. 1 2 3 4 5 6 7 8 9 10 11 12

DAFTAR TENAGA KERJA Mandor Kepala Tukang Kayu/Cat Tukang Kayu/Cat Laden Tukang Kayu/Cat Kepala Tukang Batu/Besi Tukang Batu/Besi Laden Tukang Batu/Besi Pekerja Galian Tanah Penjaga Malam/Satpam Supir Operator Operator Pompa DAFTAR BAHAN Air Batu (> 1.000) Kg Batu (250 - 1000) Kg Batu ( < 250) Kg Batu Kali/Batu Belah (Sungai/Gunung) Besi Beton Polos Ijuk Minyak Bekisting Kawat Beton Bronjong Kawat Dia. 3 mm (2,0 x 1,0 x 0,5) m (Pabrikasi) Kayu Bakau 10 cm Kayu Kelas III Karung Plasting Paku Kayu Pasir Beton/Kerikil Pasir Pasang Pelumas/Oli Pipa PVC Dia. 1,0" Pipa PVC Dia. 1,5" Pompa Air 5 Kw OH OH OH OH OH OH OH OH OH OH OH OH 80,000.00 104,000.00 82,000.00 68,000.00 104,000.00 82,000.00 68,000.00 68,000.00 60,000.00 80,000.00 120,000.00 68,000.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Ltr m3 m3 m3 m3 Kg Kg Ltr Kg Unit Btg m3 bh Kg m3 m3 Liter Btg Btg Bh

100 260,000.00 210,000.00 200,000.00 140,000.00 16,000.00 15,000.00 22,000.00 21,000.00 400,000.00 10,000.00 3,500,000.00 2,000.00 18,000.00 140,000.00 130,000.00 45,000.00 80,000.00 105,000.00 5,000,000.00

21 22 23 24 25 26 27 C. 1 2 3 4 5 6 7 8 9

Semen @ 40 Kg Solar Tanah Timbun Tali Rapia/Plastik Wiremesh (Ulir) dia.5" Geotextile (Non Wooven Pipa Leiding 3" Galvanis tebal 3.2 mm DAFTAR PERALATAN Excavator Chainsaw Jack Hammer + Operator Palu/Godam Gergaji Besi Pahat Beton Stamper Molen Mesin Potong Besi

Zak Liter m3 m m2 m2 Btg Jam jam Bh Bh Bh Bh Unit/M3 Unit/Hari Unit/Hari

50,000.00 9,000.00 90,000.00 100.00 50,000.00 450,000.00 535,200.00 15,000.00 100,000.00 50,000.00 50,000.00 50,000.00 70,000.00 20,000.00

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

JADWAL WAKTU PELAKSANAAN NAMA PENAWAR NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : CV.LAMPULO JAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

BOBOT No URAIAN PEKERJAAN VOL SAT. RENCANA (%) 1 BULAN I 2 3 4 1 BULAN II 2 3 4 1

MASA PELAKSANAAN BULAN III 2 3 4 1 BULAN IV 2 3 4 1 BULAN V 2 3 4

A 1 2 3 B 1 1 2 3 4 5 6 7 8 9 10 11 12 13

PEKERJAAN PERSIAPAN Pembersihan Lahan Uitzet/Pemasangan Profil Sewa Pondok 553.30 1.00 1.00 m2 Ls Bh 0.110% 0.146% 0.438% 0.001 0.0015 0.004

PEKERJAAN POKOK Galian tanah (AB) Tmbunan tanah Hasil Galian Timbunan Tanah Didatangkan Pasangan Batu 1 : 4 Plesteran 1 : 3 Drain Hole Beton Cor 1 : 3 : 5 Beton Cor 1 : 2 : 3 Pembesian Bekisting Rumah Pompa (Bangunan Type -C) Pompa + Asesoris Pemasangan Pipa Leiding 3" Galvanis Tebal 3.2 mm + Asesoris 277.03 207.77 88.53 531.17 1,991.88 23.00 55.33 2.16 237.60 15.84 7.50 1.00 12.00 m3 m3 m3 m3 m3 Bh m3 m3 Kg m2 m2 Unit M' 2.051% 0.584% 1.783% 62.127% 18.508% 0.079% 5.701% 0.254% 0.697% 0.464% 3.830% 1.459% 0.210% 0.124 0.124 0.124 0.124 0.124 0.046 0.046 0.046 0.046 0.001 0.057 0.003 0.007 0.005 0.013 0.013 0.013 0.015 0.002 0.010 0.010 0.002 0.002 0.002 0.018

C 1 2

PEKERJAAN LAIN-LAIN Papan Nama Proyek Administrasi Dan Dokumentasi TOTAL BOBOT PROGRES RENCANA MINGGUAN (%) PROGRES RENCANA KUMULATIF MINGGUAN (%) 1.00 1.00 Bh Ls 0.102% 1.459% 100.00% 1.160% 1.160% 1.026% 2.186% 13.451% 15.637% 12.425% 28.062% 12.425% 40.488% 12.425% 52.913% 17.052% 69.965% 4.627% 74.592% 4.992% 79.584% 4.706% 84.290% 5.955% 90.245% 0.195% 90.440% 0.559% 90.999% 0.195% 91.194% 2.943% 94.137% 1.277% 95.414% 1.641% 97.055% 1.277% 98.331% 1.669% 100.000% 0.000% 100.000% 0.001 0.004 0.004 0.004 0.004

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

JADWAL PENGGUNAAN MATERIAL/BAHAN


NAMA PENAWAR NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : CV.LAMPULO JAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013 Jadwal Penggunaan Bahan/Material BULAN III 1 2 3

No

Jenis Bahan/Material

Jumlah

SAT. 1

BULAN I 2

BULAN II 2

BULAN IV 2

BULAN V 2

1 Timbunan Tanah Didatangkan Tanah Timbun 2 Pasangan Batu 1 : 4 Batu kali/ Gunung Pasir Pasang Semen PC 3 Plesteran 1 : 3 Pasir Pasang Semen PC 4 Drain Hole Pipa PVC Dia. 1.0" Kerikil Ijuk 5 Beton Cor 1 : 3 : 5 Semen PC Pasir Pasang Kerikil Air 6 Beton Cor 1 : 2 : 3 Semen PC Pasir Pasang Kerikil Air 7 Pembesian Besi Beton Kawat Beton 8 Bekisting Papan Kayu Klass III Kaso 5/7 Cm Paku Kayu Minyak Bekisting 9 Pompa + Asesoris Pompa

106.24

m3 m3 m3 m3 m3 Kg m3 m3 Kg Bh m' m3 Kg m3 Kg m3 m3 Ltr m3 Kg m3 m3 Ltr Kg Kg Kg m2 m3 m3 Kg Ltr Unit Buah

xxx

637.40 276.21 86,580.71

xxx xxx xxx

xxx xxx xxx

xxx xxx xxx

xxx xxx xxx

xxx xxx xxx

45.81 15,488.86

xxx xxx xxx xxx xxx xxx

xxx xxx xxx

xxx xxx xxx

xxx xxx xxx

11.50 0.46 4.60

13,666.51 34.36 40.94 11,895.95

xxx xxx xxx xxx

704.16 1.17 1.65 464.40

xxx xxx xxx xxx

249.48 3.56

xxx xxx xxx xxx xxx xxx xxx

0.3960 0.0015 0.4000 0.2000

1.00

xxx

10 Pemasangan Pipa Leiding 3" Galvanis Tebal 3.2 mm + M' Asesoris Pipa Leiding 3" Galvanis 12.00

xxx

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar

Direktur

JADWAL PENGGUNAAAN PERALATAN UTAMA


NAMA PENAWAR : CV.LAMPULO JAYA

NAMA PEKERJAAN : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar LOKASI : KECAMATAN LHOKNGA TAHUN ANGGARAN : 2013

Jadwal Penggunaan Peralatan No Nama Alat Jumlah Satuan 1 2 BULAN I 3 4 1 2 BULAN II 3 4 1 2 BULAN III 3 4 1 2 BULAN IV 3 4 1 2 BULAN V 3 4

Excavator DumpTruck Concrete Mixer Concrete Vibrator Pompa Genset Waterpass

1.00 2.00 2.00 1.00 1.00 1.00 1.00

Unit Unit Unit Unit Unit Unit Unit xxx

xxx

xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx

5 6

xxx xxx

xxx xxx

xxx

xxx

xxx xxx

xxx xxx

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

JADWAL PENGGUNAAAN PERSONIL INTI


: CV.LAMPULO JAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

NAMA PENAWAR NAMA PEKERJAAN LOKASI TAHUN ANGGARAN

Jadwal Penggunaan Personil Inti dan Tenaga Kerja No Nama dan Jabatan Personil Inti Jumlah Satuan 1 1 NOVALIADI, ST 2 BUSTAMI SYARBINI 3 ABDI MURSALIN 4 ISWAHYUDI 5 MUHAMMAD, Amd 6 TANDEWIPANIKAWANI, SE 7 NURAINI, SE BULAN I 2 3 4 1 BULAN II 2 3 4 1 BULAN III 2 3 4 1 BULAN IV 2 3 4 1 BULAN V 2 3 4

Site Manager Pengawas Lapangan Juru Ukur Juru Gambar Tenaga Logistik Staf Keuangan Staf Administrasi

1.00 1.00 1.00 1.00 1.00 1.00 1.00

Orang Orang Orang Orang Orang Orang Orang

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx

xxx xxx xxx xxx xxx xxx xxx xxx

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

ANALISA TEKNIS NAMA PENAWAR NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : CV.LAMPULO JAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

No I

URAIAN PEKERJAAN PEKERJAAN PERSIAPAN 1 Pembersihan Lahan

Analisa Teknis

Volume

Satuan

Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas 2 Tukang Tebas Koefisien jumlah pekerja Produktivitas Wktu Pelaksanaan

553.30 m2

0.0090 M2/Hari 1.0000 Orang 111.1111 Hari/m2

0.0030 M2/Hari 1.0000 Orang 333.3333 Hari/m2 1.6599 Hari 1.0000 Minggu

3 Mandor Koefisien jumlah pekerja Produktivitas 2 Uitzet/Pemasangan Profil Volume Pekerjaan Wktu Pelaksanaan

0.0010 M2/Hari 1.00 Orang 1000.0000 Hari/m2

1.00 Ls 1.00 Hari 1.00 Minggu 1.00 7.00 1.00 1.00 Ls Hari Minggu Minggu

3 Sewa Pondok

Volume Pekerjaan Wktu Pelaksanaan Dibulatkan

II

PEKERJAAN POKOK 1 Galian tanah (AB) Volume Pekerjaan Alat 1 Excavator Koefisien Alat Jumlah Alat Produktivitas Durasi Bahan 1 Batu Uk. 250 - 1000 Kg 2 Tmbunan tanah Hasil Galian Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas 2 Mandor Koefisien jumlah pekerja Produktivitas Wktu Pelaksanaan 277.03 m3 277.03 m3

0.0862 1.0000 11.5997 81.1980 3.4118 1.0000

jam/m3 Buah m3/jam m3/hari Hari Minggu

277.03 m3

0.2480 M2/Hari 4.0000 Orang 16.1290 Hari/m2

0.0080 M2/Hari 1.0000 Orang 125.0000 Hari/m2 17.1759 Hari 3.0000 Minggu

3 Timbunan Tanah Didatangkan Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas Durasi 88.53 m2

0.2480 2.00 8.06 56.45 1.57 1.00

m2/jam m2/hari hari minggu

2 Mandor Koefisien jumlah mandor Produktivitas Durasi

0.0080 1.00 125.00 875.00 0.10 1.00

m2/jam m2/hari hari minggu

Bahan 1 Tanah Timbun 4 Pasangan Batu 1 : 4 Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas

106.24 m2

531.17 m3

2.7030 2.00 0.74 m3/jam 5.18 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.9000 2.00 2.22 15.56 34.15 5.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0900 1.00 11.11 m3/jam 77.78 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.1350 1.00 7.41 m3/jam 51.85 m3/hari

Bahan 1 Batu kali/ Gunung 2 Pasir Pasang 3 Semen PC 5 Plesteran 1 : 3 Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas

637.40 m3 276.21 m3 86580.71 Kg

1991.88 m3

0.3840 2.00 5.21 m3/jam 36.46 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.1900 2.00 10.53 73.68 27.03 4.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0190 1.00 52.63 m3/jam 368.42 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.0190 1.00 52.63 m3/jam 368.42 m3/hari

Bahan 1 Pasir Pasang 2 Semen PC

45.81 m3 15488.86 Kg

6 Drain Hole Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas 23.00 Bh

0.0080 1.00 125.00 bh/jam 875.00 bh/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi Bahan 1 Pipa PVC Dia. 1.0" 2 Kerikil 3 Ijuk 7 Beton Cor 1 : 3 : 5 Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas

0.0800 1.00 12.50 87.50 0.26 1.00

bh/jam bh/hari hari minggu

11.50 m' 0.46 m3 4.60 Kg

55.33 m3

1.3200 2.00 1.52 m3/jam 10.61 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.2050 1.00 4.88 34.15 1.62 1.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0200 1.00 50.00 m3/jam 350.00 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.0600 1.00 16.67 m3/jam 116.67 m3/hari

Bahan 1 Semen PC 2 Pasir Pasang Kerikil Air Peralatan 1 Molen 0.35 m3

18,037.58 30.04 42.16 11,895.95

Kg m3 m3 Ltr

8 Beton Cor 1 : 2 : 3 Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas 2.16 m3

1.3200 1.00 0.76 m3/jam 5.30 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.2050 1.00 4.88 34.15 0.06 1.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0200 1.00 50.00 m3/jam 350.00 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.0600 1.00 16.67 m3/jam 116.67 m3/hari

Bahan 1 2 3 4

Semen PC Pasir Pasang Kerikil Air

704.16 1.17 1.65 464.40

Kg m3 m3 Ltr

Peralatan 1 Molen 0.35 m3 9 Pembesian Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas 237.60 m3

0.0070 1.00 142.86 m3/jam 1000.00 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.0070 1.00 142.86 1000.00 0.24 1.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0007 1.00 1428.57 m3/jam 10000.00 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.0004 1.00 2500.00 m3/jam 17500.00 m3/hari

Bahan 1 Besi Beton 2 Kawat Beton Peralatan 1 Mesin Potong Besi 10 Bekisting Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas

1.05 Kg 0.02 Kg

15.84 m3

0.6600 2.00 3.03 m3/jam 21.21 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.3300 1.00 3.03 21.21 0.75 1.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0330 1.00 30.30 m3/jam 212.12 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.0330 1.00 30.30 m3/jam 212.12 m3/hari

Bahan 1 2 3 4

Papan Kayu Klass III Kaso 5/7 Cm Paku Kayu Minyak Bekisting

0.40 0.02 6.34 3.17

m3 m3 Kg Ltr

11 Rumah Pompa (Bangunan Type -C) Volume Pekerjaan Durasi pekerjaan 7.50 m3 3.00 Minggu

12 Pompa + Asesoris Volume Pekerjaan Durasi pekerjaan 1.00 m3 1.00 Minggu

13 Pemasangan Pipa Leiding 3" Galvanis Tebal 3.2 mm + Asesoris Volume Pekerjaan Tenaga Kerja 1 Pekerja Koefisien jumlah pekerja Produktivitas

12.00 m3

0.1080 2.00 18.52 m3/jam 129.63 m3/hari

2 Tukang Koefisien jumlah tukang Produktivitas Durasi

0.1800 1.00 5.56 38.89 0.31 1.00

m3/jam m3/hari hari minggu

3 Kepala Tukang Koefisien jumlah Kepala Tukang Produktivitas

0.0180 1.00 55.56 m3/jam 388.89 m3/hari

4 Mandor Koefisien jumlah mandor Produktivitas

0.0054 1.00 185.19 m3/jam 1296.30 m3/hari

Bahan 1 Pipa Leiding 3" Galvanis III PEKERJAAN LAIN-LAIN 1 Papan Nama Proyek Volume Pekerjaan Durasi

12.00 m'

1.00 Ls 1.00 hari 1.00 Minggu

2 Administrasi Dan Dokumentasi Volume Pekerjaan Durasi 1.00 Ls 1.00 Hari 1.00 minggu

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

DAFTAR USULAN PEKERJAAN YANG DISUBKONTRAKKAN


NAMA PENAWAR NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : CV.LAMPULO JAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

No. Mata Pembayaran

Jenis Pekerjaan

Persentase Dari Harga Total Mata Pembayaran (%)

Persentase Dari Harga Total Mata Pembayaran (%)

Nama SubKontraktor (Jika diperlukan)

I
T o t a l (%)

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

DAFTAR PERSONIL INTI


NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

No

Nama Personil

Posisi Di Proyek Ini

Tempat & Tanggal Lahir

Pendidikan Terakhir

Pengalaman Kerja Tahun 5 Tahun 5 Tahun 5 Tahun 5 Tahun 5 Tahun 5 Tahun 5 Tahun

No & Tanggal Ijazah

No & Tanggal SKA Atau SKTK

Ket

1 2 3 4 5 6 7

NOVALIADI, ST BUSTAMI SYARBINI ABDI MURSALIN ISWAHYUDI MUHAMMAD, Amd TANDEWIPANIKAWANI, SE NURAINI, SE

Site Manager Pengawas Lapangan Juru Ukur Juru Gambar Tenaga Logistik Staf Keuangan Staf Administrasi

Dayah Muara, 30 November 1978 Lamno, 02 April 1966 Gp. Lada, 08 Desember 1983 Lamtui, 24 April 1985 Peureulak, 10 Juli 1973 Banda Aceh, 21 Oktober 1975 Aceh Utara, 02 Oktober 1981

Teknik Sipil STM Diploma-III Teknik Sipil Diploma-III Teknik Sipil Diploma-III Teknik Sipil Sarjana Ekonomi Sarjana Ekonomi

313214/079/TS-044/2006 07 oC ou 0076472 282/4588/TS-930/05 307/4947/TS-965/06 023/1527/KS-259/97 434/288/LKM-E/155/2003 1.4.1.00386/001298

00014513/AS403/SKA/ASTTATINDO/III/2013

044651/SMK-PU/SKTK/I/2013 62930/01/198/ATAKI/SKT/VII 62933/09/069/ATAKI/SKT/VII /2011

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

TTATINDO/III/2013

DAFTAR PERALATAN UTAMA MINIMAL YANG DIBUTUHKAN


NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013 Jumlah Peralatan 2 1 2 1 1 1 1 Tahun Pembuatan Status Kepemilikan Kapasitas Peralatan Milik Sewa Sewa Sewa Sewa Sewa Sewa Sewa Sewa

No

Jenis Peralatan

Merk dan Type

Tenaga

Lokasi Alat

1 DUMP TRUCK 3,5 M3 2 LIGHT TRUCK 3 CONCRETE MIXER 4 GENSET 5 POMPA AIR 6 CONCRETE VIBRATOR 7 WATERPASS

MITSHUBISHI MITSHUBISHI TIGER HONDA YANMAR KOMATSU SOKKIA

2000 4 m3 2004 2004 2000 350 Kva 2000 2000 2000

Lhoknga Lhoknga Lhoknga Lhoknga Lhoknga Lhoknga Lhoknga

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur

STRUKTUR ORGANISASI PELAKSANA PEKERJAAN


NAMA PENAWAR NAMA PEKERJAAN LOKASI TAHUN ANGGARAN : CV.LAMPULO JAYA : Peningkatan Jaringan Irigasi Gp. Seubun Kec. Lhoknga Kab Aceh Besar : KECAMATAN LHOKNGA : 2013

Site Manager NOVALIADI, ST

Juru Ukur ABDI MURSALIN

Pengawas Lapangan BUSTAMI SYARBINI

Staf Keuangan TANDEWIPANIKAWANI, SE

Juru Gambar ISWAHYUDI

Tenaga Logistik MUHAMMAD, Amd

Staf Administrasi NURAINI, SE

Banda Aceh,5 April 2013 CV.LAMPULO JAYA

Khairil Anwar Direktur