Professional Documents
Culture Documents
Board of Airport Commissioners Meeting 9 July 2013 Presented by: Roger A. Johnson, Deputy Executive Director
Key Findings
The audit report includes seven major findings that examine LAWAs capital development activity. These findings are in the areas of:
Program Management
Long Term Program Management Strategy (Section 7) Value Engineering (Section 1)
The number of change orders on this project was not driven by the selection of the CMAR delivery method. LAWA anticipated a large volume of change orders on this project due to the fact that we went out to bid with incomplete design in order to achieve an accelerated schedule.
7
The quote attributed to the CMAR that the number of change orders have been higher than expected and have contributed to cost escalation and impeded their ability to manage the project effectively is self-serving and untrue.
10
11
13
14
All work in place was inspected and signed off by LAWA inspectors. LAWA inspectors have logged over 50,000 inspection requests.
In addition, LAWA inspectors walk the job and sign off on all work submitted for payment. LAWA does not pay for defective work.
15
16
LAWA ADG will review the Inspection Request (IREQ) process for standardization.
17
18
The auditors evaluation of the cost of consultants compared to city staff is flawed. Applying the same methodology to City and consultant staff, using the Controllers overhead rate for City staff, the cost for consultants is approximately 8.6% less than the cost for City staff. The cost analysis does not take into account the long-term costs of converting consultants to City staff.
City staff are fully engaged in the development program.
19
7.2 Build upon and broaden its recent effort with the Airport Engineer classification to identify any airport-specific job classifications that could be established by the City and enable LAWA to recruit and retain appropriate capital development staff. Any such proposed classifications should be provided to the Department of Human Resources for review.
LAWA agrees and has already engaged Human Resources in this process.
20
21
22
23
24
25
26
27
LAWA agrees, and a traditional five-year CIP was completed in June 2013. However, LAWA disagrees that budgets are overstated. Project estimates are developed using industry standard metrics and refined along design milestones.
Identified Needs
CIP
Contract Awards
28
28
30
31
Audit Abbreviations
(in order of use) ADG Airports Development Group
32