Contoh Analisa Teknik

Unggahan Samuel Sitorus Lihat Profil Umum Recently ReadMy LibrarySocial Feed My UploadsMy CollectionsMy Stats AkunHelpLog keluar
Search the world's digital library.

Browse By Type Books - FictionBooks - Non FictionBrochures & CatalogsComicsGovernment DocsHow-To Guides & ManualsNewspapers & MagazinesPresentationsMenus & RecipesResearchSchool Work By Topic Art & DesignBusinessCreative WritingEntertainmentFictionFoodGovernment & PoliticsHealth & FitnessReligionScienceLiterature Read without ads and support Scribd by becoming a Scribd Premium Reader. See Premium Plans Bahasa: Bahasa Indonesia

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

1/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

2/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

3/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

4/17

12/06/13

Contoh Analisa Teknik

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan Satuan/Unit Analisa : Beton Cor 1 : 2 : 3 : M3 : Anl. B.05

No.
(1) A. 1 2 3 4 Tenaga Kerja Pekerja Tukang Kepala Tukang Mandor

Uraian
(2)

Satuan
(3)

Kuantitas/ Koefisien
(4)

Harga Satuan Dasar (Rp)


(5)

Harga (Rp.)
(6) = (4) x (5)

OH OH OH OH

1.3200 0.2050 0.0200 0.0600

45,000.00 50,000.00 55,000.00 46,000.00

59,400.00 10,250.00 1,100.00 2,760.00

Sub Jumlah A

73,510.00

B. 1 2 3 4

Bahan Semen PC Pasir Pasang Kerikil Air Kg M3 M3 Ltr 326.0000 0.5430 0.7620 215.0000 1,175.00 22,000.00 90,000.00 50.00 383,050.00 11,946.00 68,580.00 10,750.00

Sub Jumlah B

474,326.00

C. 1

Peralatan Molen 0,35 m3 Unit/Hari 0.2000 192,000.00 38,400.00

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

5/17

12/06/13

Contoh Analisa Teknik

Sub Jumlah C

38,400.00

D E Overhead + Keuntungan 5 % x Sub Jumlah (D)

Sub Jumlah ( A + B + C )

586,236.00 29,311.80

Jumlah Harga = ( D + E ) Harga Satuan Pekerjaan (Dibulatkan)

615,547.80

615,547.00

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan Satuan/Unit Analisa : Drain Hole Dia. 1,0" : Bh : Dihitung

No.
(1) A. 1 2 Tenaga Kerja Pekerja Tukang

Uraian
(2)

Satuan
(3)

Kuantitas/ Koefisien
(4)

Harga Satuan Dasar (Rp)


(5)

Harga (Rp.)
(6) = (4) x (5)

OH OH

0.0080 0.0800

45,000.00 50,000.00

360.00 4,000.00

Sub Jumlah A

4,360.00

B. 1 2 3

Bahan Pipa PVC Dia. 1,0" Kerikil Ijuk M M3 Kg 0.5000 0.0200 0.2000 2,000.00 90,000.00 3,000.00 1,000.00 1,800.00 600.00

Sub Jumlah B

3,400.00

C.

Peralatan -

Sub Jumlah C D E Overhead + Keuntungan 5 % x Sub Jumlah (D) Jumlah Harga = ( D + E ) Harga Satuan Pekerjaan (Dibulatkan) Sub Jumlah ( A + B + C )

7,760.00 388.00 8,148.00

8,148.00

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

6/17

12/06/13

Contoh Analisa Teknik

DAFTAR HARGA UPAH, BAHAN, DAN PERALATAN


SKPA Lokasi Kegiatan : : : 0 0 0 0 0 Uraian Satuan

Nama Pekerjaan :

Tahun Anggaran : No.

Harga (Rp)

Keterangan

A 1 2 3 4 5 6

TENAGA KERJA Pekerja Mandor Tukang Kepala Tukang Operator Co. Operator Hari Hari Hari Hari Hari Hari 45,000.00 46,000.00 50,000.00 55,000.00 80,000.00 50,000.00

B 1 2 3

BAHAN Kerikil Tanah Timbun Semen PC 40 Kg Semen PC 40 Kg M3 M3 Sak Kg M2 M Kg Ltr Ltr Ltr Ltr 90,000.00 25,000.00 47,000.00 1,175.00 22,000.00 2,000.00 3,000.00 50.00 7,000.00 7,000.00 30,000.00

4 5 6 7 8 9 10

Wiremesh Dia. 5 mm (Ulir) Pipa PVC dia 1" Ijuk Air Solar Bensin Oli Mesin/Pelumas

PERALATAN Chainsaw Stamper Molen 0,35 m3 Mesin Potong Besi Jam Hr-Sewa Unit/Hari Hari 35,900.00 141,000.00 192,000.00 150,000.00

Download KembaliAdd Note Tautan Tanam Simpan


9

1 2 3 4

dari 19

Readcast Tidak diReadcast Catatan: Anda akan selalu dapat mengklik di tombol Readcast untuk berbagi dengan pengikut Scribd Anda. Auto-Readcasting: OnView Past Readcasts Undo

Tambahkan komentar Kirim

Auto-Readcasting: OnView Past Readcasts


Like Tw eet 0

ANALISA TEKNIS
Nama Pekerjaan Kegiatan Tahun Anggaran 1 hari kerja = I. 1 PEKERJAAN PERSIAPAN Pembersihan Lapangan Volume Peralatan Yang Dipakai Bahan Yang digunakan Faktor Tenaga Kerja Jumlah Tenaga Kerja Produktifitas Produksi per hari Waktu dibutuhkan : : : 0 0 0 0 7.000 Jam

: 200.00 M2 : Manual + Alat Bantu (Chain Saw) : : : : : 0.013 3 Orang 76.923 M2 /Pekerja/Hari 3.00 x 76.923 M2 200.00 / 230.77

= =

230.77 M2 /Hari 1.00 hari 1.00 Minggu

Dewatering Volume Peralatan Yang Dipakai Jumlah Tenaga Kerja Waktu Yang Dibutuhkan

: 1.00 Ls : Manual + alat Bantu (Pompa air) Cari Dokumen Ini : Sesuai kebutuhan : 98.00 Hari : 14.00 Minggu

II.

PEKERJAAN POKOK

Cari Riwayat Pencarian: Mencari...

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

7/17

12/06/13
II. 1 PEKERJAAN POKOK Galian Tanah Biasa (MP) Volume Peralatan Yang Dipakai Bahan Yang digunakan Faktor Tenaga Kerja Jumlah Tenaga Kerja Produktifitas Produksi per hari Waktu dibutuhkan

Contoh Analisa Teknik Mencari...


: 618.63 M3 : Manual : : : : :

Hasil00 dari00 00hasil untukhasil untuk p.


0.582 6 Orang 1.718 M3 /Pekerja/Hari 6.00 x 1.718 M3 618.63 / 10.31

= =

10.31 M3 /Hari 61.00 hari 9.00 Minggu

Tanah Hasil Galian, Diratakan dan Dipadatkan (MP) Volume Peralatan Yang Dipakai Faktor Tenaga Kerja Jumlah Tenaga Kerja Produktifitas Produksi per hari Waktu dibutuhkan : 307.37 M3 : Manual + alat Bantu (Stamper) : 0.342 : 3 Orang : 2.924 M3 /Pekerja/Hari : 3.00 x 2.924 M3 : 307.37 / 8.77

= =

8.77 M3 /Hari 36.00 hari 6.00 Minggu

Timbunan Tanah Didatangkan, Diratakan dan Dipadatkan (MP) Volume : Peralatan Yang Dipakai : Manual Bahan Yang digunakan - Tanah Timbun 1.200 M3 : Faktor Tenaga Kerja : Jumlah Tenaga Kerja : Produktifitas : Produksi per hari : Waktu dibutuhkan :

124.83 M3

149.80 M3 0.3420 2 Orang 2.924 M3 /Pekerja/Hari 2.00 x 2.924 M3 124.83 / 5.85

= =

5.85 M3 /Hari 22.00 hari 4.00 Minggu

Wiremesh Dia. 5 mm (Ulir) Volume Peralatan Yang Dipakai Bahan Yang digunakan - Wiremesh Dia. 5 mm (Ulir) Faktor Tenaga Kerja Jumlah Tenaga Kerja Produktifitas Produksi per hari Waktu dibutuhkan

: 1,838.43 : Manual 1.0500 M2 : : : : : :

M2

1,930.35 M2 0.0788 4 Orang 12.698 M2 /Pekerja/Hari 4.00 x 12.698 M2 1,838.43 / 50.79

= =

50.79 M2 /Hari 37.00 hari 6.00 Minggu

Beton Cor 1 : 2 : 3 Volume Peralatan Yang Dipakai Bahan Yang digunakan - Semen - Pasir Pasang - kerikil - Air Faktor Tenaga Kerja Jumlah Tenaga Kerja Produktifitas Produksi per hari Waktu dibutuhkan

: 540.80 M3 : Manual + Alat Batu (Molen) 326.000 0.543 0.762 215.000 Kg M3 M3 Ltr : : : : : : : : : 176,300.80 293.65 412.09 Kg M3 M3

116,272.00 Ltr 1.6050 13 Orang 0.623 M3 /Pekerja/Hari 13.00 x 0.623 M3 540.80 / 8.10

= =

8.10 M3 /Hari 67.00 hari 10.00 Minggu

Drain Hole Dia. 1,0" Volume Peralatan Yang Dipakai Bahan Yang digunakan '- Pipa PVC dia. 1 " - Kerikil - Ijuk Faktor Tenaga Kerja Jumlah Tenaga Kerja Produktifitas Produksi per hari Waktu dibutuhkan

: 147.00 Bh : Manual 0.500 M 0.020 M3 0.200 Kg : : : : : : : : 73.50 2.94 29.40 0.0880 2 11.364 2.00 147.00 M M3 Kg Orang Bh /Pekerja/Hari x 11.364 Bh / 22.73

= =

22.73 Bh /Hari 7.00 hari 1.00 Minggu

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

8/17

12/06/13

Contoh Analisa Teknik

JADWAL WAKTU PELAKSANAAN


Nama Pekerjaan : 0 0 Lokasi Kegiatan Tahun Anggaran : : : 0 0 0
MASA PELAKSANAAN BULAN - I 1 2 3 4 5 BULAN - II 6 7 8 9 BULAN - III 10 11 12 13 BULAN - IV 14 15 16
100

NO.

URAIAN KEGIATAN

VOL.

SAT

Bobot Rencana (%)

KET

I. 1 2

PEKERJAAN PERSIAPAN 0.033 Pembersihan Lapangan Dewatering 200.00 1.00 M2 Ls 0.066 0.017 0.239 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017 0.017
75

0.033

II 1 2 3 4 5 6

PEKERJAAN POKOK 0.610 Galian Tanah Biasa (MP) Tanah Hasil Galian, Diratakan dan Dipadatkan (MP) Ti mbunan Tanah Di datangk an, Di ratakan dan Di padatk an ( Wiremesh Dia. 5 mm (Ulir) Beton Cor 1 : 2 : 3 Drain Hole Dia. 1,0" 618.63 307.37 124.83 1,838.43 540.80 147.00 M3 M3 M3 M2 M3 Bh 4.068 0.303 1.731 0.821 1.643
1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.130 1.118

0.610

0.610

0.610

0.610

0.509

0.509
50

0.303

0.303

0.303

0.260

0.260 0.821

12.420 3.977 79.547 0.041 0.286 0.041 0.041 0.041 0.041 0.041 0.041 5.966 6.761 6.761 6.761 6.761 7.159 7.955 7.955 7.955 7.955 3.580

25

TOTAL BOBOT PROGRES RENCANA MINGGUAN (%) PROGRES RENCANA KUMULATIF MINGGUAN (%)

100.00 0.033 0.033 0.660 0.693 1.757 2.451 5.735 8.186 7.723 15.909 8.519 24.428 8.458 32.886 8.458 41.344 8.253 49.597 8.650 58.247 9.446 67.693 9.446 77.139 9.390 86.529 8.231 94.761 4.418 99.179 0.821 100.00

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

9/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

10/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

11/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

12/17

12/06/13

Contoh Analisa Teknik

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

13/17

12/06/13

Contoh Analisa Teknik

Contoh Analisa Teknik


Unduh atau Cetak Tambahkan ke Koleksi 87 Reads 0 Readcasts 0 Embed Views

Published by ibaltc Ikuti:


Cari Dokumen Ini

Cari KIATTekanCtrl-FF untuk mencari dengan cepat dibagian manapun dalam dokumen.

Get Scribd Mobile


To get Scribd mobile enter your number and we'll send you a link to the Scribd app for iPhone & Android.We've sent a link to the Scribd app. If you didn't receive it, try again.
(xxx) xxx-xxxx

Text me We'll never share your phone number. Or, click here and we'll send an email to your iPad and Android tablet.We've sent you an email with the link to the Scribd app. Didn't receive it? Try again.

iTunes App Store | Google Play Store

Info dan Peringkat


Kategori: Peringkat Tidak ada kategori.

Tanggal diunggah: 04/03/2013 Hak Cipta: Attribution Non-commercial Tag: No tags Flag for inappropriate content

Unduh dan cetak dokumen ini


Baca offline di penampil PDF Sunting dokumen ini dalam Adobe Acrobat, Microsoft Excel, Notepad Simpan sebuah salinan kalau-kalau versi ini dihapus dari Scribd Baca dan cetak tanpa iklan Kirimkan berkas lewat email

Pilih sebuah format untuk mengunduh dalam

.PDF

.XLSX

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

14/17

12/06/13

Contoh Analisa Teknik

.TXT Mengunduh

Direkomendasikan

1 p. Analisa Teknis Galian 0-2M Johan Hartono 1001 Reads

1 p. analisa irigasi hendrikzainudin 3905 Reads

18 p. Metode Pelaksanaan Pekerjaan Si Ghabe Naujui 26510 Reads

Lainnya Dari Pengguna Ini

4 p. Rab Pemasangan Sunda Plafond ibaltc


id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 15/17

12/06/13

Contoh Analisa Teknik

16 Reads

1 p. Pemasangan Waterproofing Membrane ibaltc 11 Reads

1 p. Aksesoris Body Yamaha Vixion ibaltc 15 Reads

1 p. Daftar Kuantitas Dah Harga ibaltc 14 Reads Next Notes sitorus_samuel


A d dan o t e .( L i m i t4 0 0 c h a r a c t e r s )

Privacy:publicPost Note

Tentang Tentang Scribd Team Blog Bergabung dengan tim kami! Hubungi Kami Premium Premium Reader Toko Scribd Beriklan dengan kami Memulai AdChoices Dukungan
id.scribd.com/doc/133773479/Contoh-Analisa-Teknik 16/17

12/06/13

Contoh Analisa Teknik

Bantuan FAQ Tekan Mitra Pengembang / API Legal Terms Privasi Hak cipta Get Scribd Mobile

Copyright 2013 Scribd Inc. Bahasa: Bahasa Indonesia

id.scribd.com/doc/133773479/Contoh-Analisa-Teknik

17/17

You might also like