Intersections are a major source of crashes and vehicle delay (as vehicles yield to avoid conflicts with other vehicles).
Lecture 4
11/09/2013
Lecture 4
11/09/2013
Signalised Intersection
Two simple examples in Dublin
Lecture 4
11/09/2013
Signalised Intersection
Lecture 4
11/09/2013
Traffic Signals
Lecture 4
11/09/2013
Lecture 4
11/09/2013
Lecture 4
11/09/2013
Lecture 4
11/09/2013
10
Performance Measures
throughput
Lecture 4
Terminology
Green time: The time period in which the traffic signal has the green indication Red time: The time period in which the traffic signal has the red indication Yellow time: The time period in which the traffic signal has the yellow indication
Lecture 4
Terminology
Permitted movement: A movement that is made through a conflicting pedestrian or other vehicle movement. This is commonly used for right-turning movements where right-turn volumes are reasonable and where gaps in the conflicting movement are adequate to accommodate turns. Protected movement: A movement that is made without conflict with other movements. The movement is protected by traffic control signal design with a designated green time for the specific movement.
Lecture 4
Terminology
Effective green time: The effective green time, for a phase, is the time during which vehicles are actually discharging through the intersection. Lost Time: A portion of green or yellow time which is not utilised by traffic flow movements in a cycle. Start-up lost time: At the beginning of each green indication as the first few cars in a standing queue experience start-up delays. This delay is measured as start-up lost time. The clearance lost time: It is estimated by the amount of the yellow time not used by vehicles.
Lecture 4
11/09/2013
14
Lecture 4
11/09/2013
15
Level of Service
Lecture 4
Discharge Headways
Consider N vehicles discharging from the intersection when a green indication is received.
The first discharge headway is the time between the initiation of the green indication and the rear wheels of the first vehicle to cross over the stop line. The Nth discharge headway (N>1) is the time between the rear wheels of the N-1th and Nth vehicles crossing over the stop line.
Lecture 4
11/09/2013
17
Discharge Headways
Lecture 4
Discharge Headways
The headway begins to level off with 4 or 5th vehicle. The level headway = saturation headway
Lecture 4
3600 S h
Lecture 4
11/09/2013
20
In other words, s for a lane group/approach is the maximum number of vehicles from that lane group/approach that can pass through the intersection during one hour of continuous green time under the prevailing traffic and roadway conditions.
Lecture 4
11/09/2013
21
Lecture 4
11/09/2013
22
Lecture 4
11/09/2013
23
Non-opposed Streams
For non-opposed streams saturation flow , s1 for individual lanes is given by,
Lecture 4
11/09/2013
24
Opposed Streams
Lecture 4
11/09/2013
25
Opposed Streams
Lecture 4
11/09/2013
26
Example 1
Lecture 4
11/09/2013
27
Example 2
Lecture 4
11/09/2013
28
Example 2
Lecture 4
11/09/2013
29
Capacity
The maximum hourly rate at which persons or vehicles can be reasonably expected to traverse a point or uniform segment of a lane or roadway during a given time period under prevailing traffic and roadway conditions. (HCM 2000) Unlike saturation flow, capacity considers traffic signal conditions The formula for calculating capacity (c) is, c = (g/C) s N Where:
c = capacity (pcu/hour) g = Effective green time for the phase in question (sec) C = Cycle length (sec) N = no. of lanes s = Saturation flow rate (pcu/hour)
Lecture 4
11/09/2013
30
Capacity Calculation
Capacity can be calculated for two categories of flow: uninterrupted and interrupted.
Uninterrupted-flow facilities
no fixed elements external to the traffic stream to interrupt flow Motorways, multilane highway, dual carriageway
Interrupted-flow facilities
have controlled and uncontrolled access points that can interrupt flow signalised and non-signalised intersections, urban streets
Lecture 4
11/09/2013
31
Delay
Very important performance measure for intersection signal design A measure most directly related to Drivers experience Stopped Time Delay: time a vehicle stopped waiting to pass the intersection.
Approach Delay: stopped time + acceleration + deceleration Travel Time Delay: (actual travel time-desired travel time) Time-in-queue Delay: Total time from joining a queue to passing the stop line
Delay is affected by cycle time, green time and volume to capacity ratio
Lecture 4
11/09/2013
32
Delay
Total delay Stopped delay Time in queue delay
Lecture 4
11/09/2013
33
Time-in-queue Delay
Lecture 4
11/09/2013
34
Lecture 4
11/09/2013
35
LOS A
LOS B
LOS C
LOS D
LOS E
LOS F
Lecture 4
11/09/2013
36
LOS
Level of Service A - Operations with low delay, or delays of less than 5.0 seconds per vehicle. This LOS is reached when most of the oncoming vehicles enter the signal during the green phase, and the driving conditions are ideal in all other respects as well. Level of Service B - Operations with delays between 5.1 and 15.0 seconds per vehicle. This LOS implies good progression, with some vehicles arriving during the red phase. Level of Service C - Operations with delays between 15.1 and 25.0 seconds per vehicle. This LOS witnesses longer cycle lengths and fair progression.
Lecture 4
11/09/2013
37
LOS
Level of Service D - Operations with delays between 25.1 and 40.0 seconds per vehicle. At this LOS, congestion is noticeable and longer delays may result from a combination of unfavorable progression, long cycle lengths, and high V/c ratios. Level of Service E - Operations with delay between 40.1 and 60.0 seconds per vehicle. This LOS is considered unacceptable by most drivers. This occurs under oversaturated intersection conditions (V/c ratios over 1.0), and can also be attributed to long cycle lengths and poor progression.