You are on page 1of 13

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

GENERAL
CONCEPT ENGINEERING
ENGINEERING & MANAGEMENT
ENGINEERING MANAGEMENT
30ECED1090 Vendor Document Requirement List

50

12-Aug-11 A

30-Nov-12

22

12-Aug-11 A

22-Oct-12

22

12-Aug-11 A

22-Oct-12

10
10

12-Aug-11 A
15-Aug-11 A

04-Oct-12
04-Oct-12

Oct
15

Nov
16

12-Aug-11 A

21-Sep-12

WBS Summary - Engineering Management

10

12-Aug-11 A

04-Oct-12

Prepare Performance Testing

22
15

15-Aug-11 A
21-Sep-12

22-Oct-12
11-Oct-12

49ECED2010

Escape Route

10

21-Sep-12

04-Oct-12

49ECED2090

Consumables List & First Fill

22

21-Sep-12

22-Oct-12

C...

49ECED3020

WBS Summary - Process Concept Design

22

15-Aug-11 A

22-Oct-12

W...

29

26-Aug-11 A

31-Oct-12

3...

29

05-Sep-11 A

31-Oct-12

3...

29
29
20

05-Sep-11 A
05-Sep-11 A
16-Sep-11 A

31-Oct-12
31-Oct-12
18-Oct-12

3...
3...

CIVIL, SURVEY GEOT ECNICAL


CIVIL
41ECED1040 Plan of Overall Site Arrangement and Layout
Review Of Road Design Outside Property Boundary

20

10-Oct-11 A

18-Oct-12

41ECED1240

In Boundary Site Overall Drainage Plan [Drainage Table]

10

31-Jan-12 A

04-Oct-12

41ECED1250

In Boundary Site Overall Drainage Plan [Drainage Cross Sections]

31-Jan-12 A

08-Oct-12

I...

41ECED1260

In Boundary Site Overall Drainage Plan [Culvert And Detail]

31-Jan-12 A

08-Oct-12

I...

41ECED1270

In Boundary Site Overall Drainage Plan [Drainage Long Section]

31-Jan-12 A

08-Oct-12

I...

41ECED1320

Review And Approval Of Shop Dr awin gs

28

19-Sep-11 A

31-Oct-12

41ECED1322

WBS Summary - Civil, Survey, Geotech Concept Design

28

05-Sep-11 A

31-Oct-12

15

26-Aug-11 A

11-Oct-12

1...

15
15
10

26-Aug-11 A
26-Aug-11 A
06-Sep-11 A

11-Oct-12
11-Oct-12
04-Oct-12

1...
1...
T...

R...
I...

R...
W...

Plan For Landscaping Works

02-Apr-12 A

11-Oct-12

P...

44EGEN1052

WBS Summary - Architectural Concept Design

15

26-Aug-11 A

11-Oct-12

W...

25

13-Dec-11 A

25-Oct-12

5
5
5

13-Dec-11 A
13-Dec-11 A
17-Dec-11 A

27-Sep-12
27-Sep-12
27-Sep-12

2...
2...
S...

2...

42ESWI1030

Sea Water Intake &Discharge - Issued AFC Drawings

27-Sep-12

S...

42ESWI1040

WBS Summary - Sea Water Intake & Discharge AFC Dwgs

13-Dec-11 A

27-Sep-12

W...

25
25
10

17-Jul-12 A
17-Jul-12 A
21-Sep-12

25-Oct-12
25-Oct-12
04-Oct-12

F...
F...

10

21-Sep-12

04-Oct-12

42EFFP1040

WBS Summary - Fire Fighting Pump AFC Dwgs

22

21-Sep-12

22-Oct-12

42EPHS1040

WBS Summary - Tank F oundation Ser vice Water AFC Dwgs

25

17-Jul-12 A

25-Oct-12

42EPHS1050

Service Water Pump Foundation - F oundation & Detail, concrete reinforcement

10

21-Sep-12

04-Oct-12

12

21-Sep-12

08-Oct-12

WASTE WATER TREATMENT PLANT

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Oct
27

I...

44ECED1310

Fire Fighting Pumps Foundation - Concrete Reinforcement

Sep
26

P...

41ECED1200

42EFFP1005

Aug
25

E...

04-Oct-12

SERVICE WATER & FIRE FIGHTING PACKAGE


CONCRETE
42EFFP1000 Fire Fighting Pumps Foundation - Foundation Plan, Section & Detail

Jul
24

2...

27-Jan-12 A

SEA WATER INTAKE & BOOSTER PUMP


CONCRETE
42ESWI1020 Sea Water Intake & Discharge - Issued for Cli ent Review & Approved

Jun
23

P...

10

UTILITIES PACKAGES

May
22

W...

In Boundary Access Road Lighting And Drain age Cr oss Section

GENERAL
ARCHITECTURAL
44ECED1070 Technical Specification For Landscaping Works

Apr
21

L...

41ECED1190

BUILDINGS

Mar
20

2...

Level of effort of engineering management

GENERAL

Feb
19

0...
V...

30ECED1210

DETAIL ENGINEERING

Jan
18

2...

30ECED1200
PROCESS
49ECED1020

Dec
17
3...

2...
2...

W...
W...
S...
0...

Page 1 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

12
5

21-Sep-12
21-Sep-12

08-Oct-12
27-Sep-12

Oct
15
0...
W...

42EWWT1010 WWTP - Issued for Internal Review

28-Sep-12

01-Oct-12

W...

42EWWT1020 WWTP - Issued for Client Review & Approved

02-Oct-12

08-Oct-12

W...

42EWWT1040 WBS Summary - Waste Water Treatment AFC dwgs

12

21-Sep-12

08-Oct-12

W...

WAT ER STORAGE TANK


CONCRETE
42EWST1000 Water Storage Tank - Foundation, Plan, Section & Detail

12
12
5

21-Sep-12
21-Sep-12
21-Sep-12

08-Oct-12
08-Oct-12
27-Sep-12

0...
0...
W...

42EWST1010 Water Storage Tank - Issued for Internal Review

28-Sep-12

01-Oct-12

W...

42EWST1020 Water Storage Tank - Issued for Client Review & Approved

02-Oct-12

08-Oct-12

W...

42EWST1040 WBS Summary - Water Storage Tank AFC Dwgs

12

21-Sep-12

08-Oct-12

W...

12
12
10

27-Jun-12 A
27-Jun-12 A
21-Sep-12

08-Oct-12
08-Oct-12
04-Oct-12

CONCRETE
42EWWT1000 WWTP - Plan & Section

NEW TOWER - T12A


CONCRETE
42ENTT1005 New Tower - T12A - Concrete Reinforcement Plan, Section & Detail

Nov
16

New Tower - T12A - Issued for Internal Review

21-Sep-12

24-Sep-12

42ENTT1020

New Tower - T12A - Issued for Client Review & Approved

10

25-Sep-12

08-Oct-12

N...

42ENTT1040

WBS Summary - New Tower - T12A AFC Dwgs

12

27-Jun-12 A

08-Oct-12

W...

27

07-Dec-11 A

29-Oct-12

2...

27
27
21

07-Dec-11 A
07-Dec-11 A
21-Sep-12

29-Oct-12
29-Oct-12
19-Oct-12

2...
2...

26

07-Dec-11 A

29-Oct-12

25

10-Feb-12 A

25-Oct-12

2...

25
25
25

10-Feb-12 A
10-Feb-12 A
10-Feb-12 A

25-Oct-12
25-Oct-12
25-Oct-12

2...
2...
D...

PIPERACK
STRUCTURAL STEEL
43EPIR1030
Issued for Client Review & Approved
43EPIR1050

WBS Summary - Piperack Building AFC Dwgs

EPC CONTRACTOR
GENERAL
GENERAL
00EGEN1010

Design by EPC Contractor

01-Sep-11 A

30-Nov-12

01-Sep-11 A

18-Oct-12

STEAM TURBINE GENERATOR


GAS COMPRESSOR

31

07-Dec-11 A

02-Nov-12

50

24-Apr-12 A

30-Nov-12

DISTRIBUTION CONTROL SYSTEM

46

15-Dec-11 A

25-Nov-12

TRANSFORMER
HYBRID GIS 150KV SWITCHYARD

11

01-Aug-12 A

06-Oct-12

15

09-Apr-12 A

11-Oct-12

BALANCE of PLANT

26

09-Feb-12 A

26-Oct-12

07-Jul-12 A

29-Sep-12

2...

07-Jul-12 A

29-Sep-12

2...

6
10

07-Jul-12 A
07-Jul-12 A

29-Sep-12
29-Sep-12

2...
F...

17-Jul-12 A

26-Aug-12 A

STRUCTURAL STEEL
STPGT1058
Fabrication Structural Steel by KE for GTG Power Building
STPGT1059

Fabrication Structural Steel by KPI for Electrical Control Building

STPGT1060

Required On Site - Structural Steel by KE

TRAIN 1
GAS TURBINE GENERATOR
GTG
CONCRETE
42CGTG1030 GTG 1 Finish foundation

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

21-Sep-12

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

W...

19

STRUCTURAL STEEL

Mar
20

I...

50

SUPPLY BY OWNER SCOPE

Feb
19

N...

HEAT RECOVERY STEAM GENERATOR

SUPPLY BY KPI

Jan
18

0...
0...
N...

42ENTT1010

GENERAL STRUCTURE & STEEL WOR K

Dec
17

3...
1...
0...
3...
2...
0...
1...
2...

F...
R...

56

19-Jun-12 A

08-Dec-12

0...

56

19-Jun-12 A

08-Dec-12

0...

56

19-Jun-12 A

08-Dec-12

6
0

19-Jun-12 A

29-Sep-12
29-Sep-12

0...
2...
G...

Page 2 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

42CGTG1040 GTG 1 Foundation Misc Equipment

Oct
15
G...

Nov
16

Dec
17

19-Jun-12 A

25-Sep-12

11
14

26-Sep-12
28-Sep-12

11-Oct-12
11-Oct-12

1...
G...

14

26-Sep-12*

09-Oct-12

I...

56
0

27-Aug-12 A
01-Oct-12

08-Dec-12

45CGTG1008B Install Sol Plate

10

27-Aug-12 A

29-Sep-12

45CGTG1010 Installation of GTG Package Unit 1

71

01-Oct-12

08-Dec-12

10

25-Sep-12

09-Oct-12

10
0

25-Sep-12

09-Oct-12
25-Sep-12

F...

45CGTG-G1000Joint Survey & Handover Foundation

26-Sep-12

26-Sep-12

J...

45CGTG-G1010Install Air Inlet Duct Steel Structure

14

26-Sep-12

09-Oct-12

TRANSFORMER GTG

32

29-Jun-12 A

05-Nov-12

0...

TRANSFORMER GTG

32

29-Jun-12 A

05-Nov-12

0...

29-Jun-12 A
21-Sep-12

05-Nov-12

Start Concrete Foundation of Transformer GTG 1

32
0

Transformer GT G 1 F oundation (Rail) & F ir ewall

44

29-Jun-12 A

05-Nov-12

19

14-Jul-12 A

21-Nov-12

2...

19

14-Jul-12 A

21-Nov-12

2...

19
25

14-Jul-12 A
14-Jul-12 A

21-Nov-12
21-Nov-12

2...
H...

WHRB BYPASS

16

04-Sep-12 A

13-Oct-12

BYPASS STACK

16

04-Sep-12 A

13-Oct-12

STRUCTURAL STEEL
43CBYS1000 Installation of Support

3
5

04-Sep-12 A
04-Sep-12 A

25-Sep-12
25-Sep-12

MECHANICAL
45CBYS1000

Installation of Bypass Stack

16
25

10-Sep-12 A
10-Sep-12 A

13-Oct-12
13-Oct-12

45CBYS1030

Installation diverter damper

14-Sep-12 A

22-Sep-12

45CBYS1090

Installation bypass middle

25-Sep-12

25-Sep-12

I...

45CBYS1100

Installation bypass top

26-Sep-12

26-Sep-12

I...

45CBYS1110

Installation access platform and ladder

16-Sep-12 A

27-Sep-12

I...

45CBYS1120

Seal Welding

27-Sep-12

29-Sep-12

S...

45CBYS1130

Installation insulation and liner part

29-Sep-12

02-Oct-12

I...

45CBYS1140

Remove joint bolt

02-Oct-12

03-Oct-12

R...

45CBYS1150

Replace bolt with joined bars

03-Oct-12

04-Oct-12

R...

45CBYS1160

Cleaning

04-Oct-12

04-Oct-12

C...

PIPING
46CBYS1000

Installation of Pipe spool

11
18

21-Sep-12
21-Sep-12

08-Oct-12
08-Oct-12

ELECTRICAL
47CBYS1000

Installation of Auxiliary Local Electrical & Acessories

15
24

21-Sep-12
21-Sep-12

13-Oct-12
13-Oct-12

56

19-Jun-12 A

08-Dec-12

0...

56

19-Jun-12 A

08-Dec-12

0...

56

19-Jun-12 A

08-Dec-12

0...

STRUCTURAL STEEL
43CGTG1000 GTG 1 Main Building Structural Installation
43CGTG1020 Installation of GTG 1 Inlet Duct Supports Structure
MECHANICAL
45CGTG1005 Ready for GTG 1 set on base

AIR INLET SYSTEM


MECHANICAL
45CGTG-G0000Finishing Foundation

CONCRETE
00CGTT1000
42CGTT1010

HEAT RECOVERY STEAM GENERATOR


HRSG
CONCRETE
42CHRS1040

HRSG 1 - Foundation Misc Equipment

TRAIN 2
GAS TURBINE GENERATOR
GTG

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Jan
18

Feb
19

Mar
20

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

0...
R...
I...
I...
0...
0...

I...

0...
S...
T...

1...
1...
2...
I...
1...
I...
I...

0...
I...
1...
I...

Page 3 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15
2...
G...

Nov
16

Dec
17

6
0

19-Jun-12 A

29-Sep-12
29-Sep-12

19-Jun-12 A

25-Sep-12

7
9

28-Sep-12
28-Sep-12

09-Oct-12
06-Oct-12

0...
G...

10

01-Oct-12

09-Oct-12

I...

56
0

30-Aug-12 A
01-Oct-12

08-Dec-12

45CGTG2008B Install Sole Plate

10

30-Aug-12 A

29-Sep-12

45CGTG2010 Installation of GTG Package Unit 2

71

01-Oct-12

08-Dec-12

10

25-Sep-12

09-Oct-12

10
0

25-Sep-12

09-Oct-12
25-Sep-12

F...

45CGTG-G2000Joint Survey & Handover Foundation

26-Sep-12

26-Sep-12

J...

45CGTG-G2010Install Air Inlet Duct Steel Structure

14

26-Sep-12

09-Oct-12

TRANSFORMER GTG

32

02-Jul-12 A

05-Nov-12

0...

TRANSFORMER GTG

32

02-Jul-12 A

05-Nov-12

0...

02-Jul-12 A
21-Sep-12

05-Nov-12

Start Concrete Foundation of Transformer GTG 2

32
0

Transformer GT G 2 F oundation (Rail) & F ir ewall

44

02-Jul-12 A

05-Nov-12

43

14-Jul-12 A

21-Nov-12

2...

43

14-Jul-12 A

21-Nov-12

2...

14-Jul-12 A
21-Sep-12

21-Nov-12

Start Concrete Foundation of HRSG 2

43
0

HRSG 2 - Foundation Auxiliary Equipment

CONCRETE
42CGTG2030 GTG 2 Finish Foundation
42CGTG2040 GTG 2 Foundation Misc Equipment
STRUCTURAL STEEL
43CGTG2000 GTG 2 Main Building Structural Installation
43CGTG2020 Installation of GTG 2 Inlet Duct Supports Structure
MECHANICAL
45CGTG2005 Ready for GTG 2 set on base

AIR INLET SYSTEM


MECHANICAL
45CGTG-G0002Finishing Foundation

CONCRETE
00CGTT2000
42CGTT2010

HEAT RECOVERY STEAM GENERATOR


HRSG
CONCRETE
00CHRS2000
42CHRS2040

14-Jul-12 A

21-Nov-12

08-Sep-12 A

06-Nov-12

BYPASS STACK

Aug
25

Sep
26

Oct
27

I...
0...
0...

I...

0...
T...

2...
H...
0...

08-Sep-12 A

06-Nov-12

08-Sep-12 A
08-Sep-12 A

25-Sep-12
25-Sep-12

MECHANICAL
45CBYS2000

Installation of WHRB Bypass System

16
25

14-Sep-12 A
21-Sep-12

13-Oct-12
13-Oct-12

45CBYS2030

Installation diverter damper

14-Sep-12 A

25-Sep-12

I...

45CBYS2090

Installation bypass middle

25-Sep-12

25-Sep-12

I...

45CBYS2100

Installation bypass top

26-Sep-12

26-Sep-12

I...

45CBYS2110

Installation access platform and ladder

16-Sep-12 A

27-Sep-12

I...

45CBYS2120

Seal Welding

27-Sep-12

29-Sep-12

S...

45CBYS2130

Installation insulation and liner part

29-Sep-12

02-Oct-12

I...

45CBYS2140

Remove joint bolt

02-Oct-12

03-Oct-12

R...

45CBYS2150

Replace bolt with joined bars

03-Oct-12

04-Oct-12

R...

45CBYS2160

Cleaning

04-Oct-12

04-Oct-12

C...

PIPING
46CBYS2000

Installation of Pipe spool

25
36

02-Oct-12
02-Oct-12

06-Nov-12
06-Nov-12

ELECTRICAL
47CBYS2000

Installation of Auxiliary local Electrical & Acessorie s

16
24

02-Oct-12
02-Oct-12

24-Oct-12
24-Oct-12

69

27-May-12 A

27-Dec-12

Summary

Jul
24

I...

3
5

Remaining Work

Jun
23

0...

32

Milestone

May
22

G...

STRUCTURAL STEEL
43CBYS2000 Installation of Support Structure

Critical Remaining Work

Apr
21

S...

32

Actual Work

Mar
20

S...

25

Actual Level of Effort

Feb
19

R...

WHRB BYPASS

STEAM TURBINE GENERATOR

Jan
18

0...
2...
I...
1...
I...

0...
I...
2...
I...
2...

Page 4 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

69

27-May-12 A

27-Dec-12

Jan
18
2...

69

27-May-12 A

27-Dec-12

2...

Steam Turbine STG Foundation

69
31

27-May-12 A
27-Jun-12 A

27-Dec-12
06-Dec-12

42CSTG1010

Steam Turbine Foundation STG Auxilia ry

50

27-May-12 A

27-Dec-12

42CSTG1014

Power Building STG - Slab Concrete

20

26-Sep-12

11-Oct-12

42CSTG1016

Power Building STG - Foundation (Pedestal PB)

STEAM TURBINE GENERATOR


STG
CONCRETE
42CSTG1000

Oct
15

Nov
16

Dec
17

28-Sep-12
17-Oct-12
17-Oct-12

TRANSFORMER STG

32

14-Jul-12 A

05-Nov-12

0...

TRANSFORMER STG

32

14-Jul-12 A

05-Nov-12

0...

14-Jul-12 A
21-Sep-12

05-Nov-12

Start Concrete Foundation of Transformer STG

32
0

Transformer s - Foundation ( Rail ) & Firewall

44

14-Jul-12 A

05-Nov-12

47

05-Jun-12 A

27-Nov-12

2...

PIPE RACK

47

05-Jun-12 A

27-Nov-12

2...

Pipe Rack

47

05-Jun-12 A

27-Nov-12

05-Jun-12 A
05-Jun-12 A

03-Oct-12
03-Oct-12
27-Nov-12
21-Sep-12

T...

2...

47
0

05-Sep-12 A

Pouring Concrete Foundation of Pipe Rack

42CHRS1050

Foundation Pipe Rack - West 1 (HRSG 1, STG, HRSG 2)

20

05-Sep-12 A

27-Nov-12

42CHRS2050

Foundation Pipe Rack - West 2 (Gas Comp & BoP)

24

03-Oct-12

25-Oct-12

42CPIR1010

Foundation Pipe Rack East - (Switchyard & PEECC 1)

39

03-Oct-12

09-Nov-12

42CSTG1030

Foundation Pipe Rack - North Admin Building

34

03-Oct-12

05-Nov-12

18

10-Sep-12 A

17-Oct-12

1...

14

10-Sep-12 A

17-Oct-12

1...

14
0

10-Sep-12 A
27-Sep-12

17-Oct-12

42CGCM1000 Foundation Gas Compressor Package

20

10-Sep-12 A

16-Oct-12

42CGCM1020 Foundation Gas Metering System

20

10-Sep-12 A

17-Oct-12

16

21-Sep-12

13-Oct-12

0...
P...
2...
P...
F...
F...
F...
F...

1...
S...
F...
F...
1...

CIVIL
41CVST1000

Vent Stack - Piling

1
2

21-Sep-12
21-Sep-12

22-Sep-12
22-Sep-12

CONCRETE
42CVST1000

Concrete Pile Caps Vent Stack

15
10

22-Sep-12
04-Oct-12

13-Oct-12
13-Oct-12

Concrete for Pipe Stack

12

22-Sep-12*

04-Oct-12

Installation Mechanical Equipment of Vent Stack

7
10

04-Oct-12
04-Oct-12

13-Oct-12
13-Oct-12

23

27-Sep-12

30-Oct-12

3...

23

27-Sep-12

30-Oct-12

3...

Earthworks - excavation

23
30

27-Sep-12
28-Sep-12*

30-Oct-12
25-Oct-12

3...
E...

Piling - Sea Cooling Water Booster Pumps

27-Sep-12

04-Oct-12

42CVST1020
MECHANICAL
45CVST1000

COOLING WATER
SEA WATER INTAKE & DISCHARGE
CIVIL
41CSWI1000
41CSWI1005

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Oct
27

0...

Pipe rack Piling

VENT STACK

Sep
26

S...

CONCRETE
00CPIR1000

CONCRETE
00CGCM1000 Start Concrete Foundation of Compressor Package

Aug
25

1...
I...

8
13

GAS COMPRESSOR & METERING

Jul
24

P...

CIVIL
41CPIR1000

FUEL GAS SUPPLY

Jun
23

S...

01-Oct-12
01-Oct-12

42CSTT1020

May
22

P...

20-Jul-12 A

BALANCE OF PLANT

Apr
21

2...

CONCRETE
42CSTT1000

Mar
20

S...

13
18

STRUCTURAL STEEL
43CSTG1000 Installation of Structural Steel STG Building

Feb
19

2...
V...
1...
C...
C...
1...
I...

P...

Page 5 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

41CSWI1010
CONCRETE
42CSWI1020
42CSWI1024

Oct
15

Nov
16
S...

Dec
17

Sand Bedding

30

01-Oct-12

30-Oct-12

Foundation of Main Sea Cooling Water Booster Pump

15
22

04-Oct-12
04-Oct-12

24-Oct-12
24-Oct-12

2...
F...

Foundation of Auxilary Sea Cooling Water Booster Pump

22

04-Oct-12

24-Oct-12

F...

46

21-Sep-12

23-Nov-12

42

21-Sep-12

19-Nov-12

1...

42
60

21-Sep-12
21-Sep-12*

19-Nov-12
19-Nov-12

1...
F...

45

21-Sep-12

22-Nov-12

20
0

21-Sep-12
21-Sep-12

18-Oct-12

30

21-Sep-12*

18-Oct-12

45
45

21-Sep-12
21-Sep-12

22-Nov-12
22-Nov-12*

2...
F...

41

27-Sep-12

23-Nov-12

2...

41
0

27-Sep-12
27-Sep-12

23-Nov-12

41

27-Sep-12

23-Nov-12

27-Sep-12

09-Oct-12

0...

8
10

27-Sep-12
27-Sep-12

09-Oct-12
06-Oct-12

0...
E...

PROCESS WATER
SERVICE WATER & FIRE FIGHTING PACKAGE
CONCRETE
42CPSW1020 Foundation for Tank

DEMIN WATER PACKAGE


CONCRETE
00CDWP1000 Start Concrete Foundation of Pump Service Water
42CDWP1005 Foundation for Tank
MECHANICAL
45CDWP1010 Fabrication Demin Water Tank

POTABLE WATER PAC KAGE


CONCRETE
00CPWP1000 Start Concrete Foundation of Tank
42CPWP1020 Foundation for Tank

WASTE WATER TREATMENT


CIVIL
41CWWT1000 Earthworks
41CWWT1010 Waste Water Treatment - Piling

04-Oct-12

15

21-Sep-12

04-Oct-12

15

27-Sep-12

18-Oct-12

1...

COMPRESSED AIR

15

27-Sep-12

18-Oct-12

1...

CONCRETE
00CCAP1000

27-Sep-12
27-Sep-12

18-Oct-12

Start Concrete Foundation of Instrument Air Package

15
0

42CCAP1005

Foundation for Compressed Air Package

22

27-Sep-12

18-Oct-12

42CCAP1010

Foundation for Pipe Supports

22

27-Sep-12

18-Oct-12

15

21-Sep-12

11-Oct-12

1...

W...
0...
S...
F...

1...
S...
F...
F...

15

21-Sep-12

11-Oct-12

1...

10
15

27-Sep-12
27-Sep-12*

11-Oct-12
11-Oct-12

1...
C...

PIPING
46CTWS1000 Installation of Turbine Washing Skid Pipe

10
15

21-Sep-12
21-Sep-12

04-Oct-12
04-Oct-12

51

06-Sep-12 A

03-Dec-12

0...

51

06-Sep-12 A

03-Dec-12

0...

51

06-Sep-12 A

03-Dec-12

0...

06-Sep-12 A
04-Oct-12

03-Dec-12

Start Concrete Foundation Switchyard

51
0

Switchyard - Piling

06-Sep-12 A

03-Oct-12

CONCRETE
00CSIY1002
42CSIY1000

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Oct
27

0...

CONCRETE
42CTWS1000 Concrete Foundation Turbine Washing Skid

HYBRID GIS 150KV SWITCHYARD

Sep
26

F...

21-Sep-12
21-Sep-12

150KV SWITCHYARD

Aug
25

2...

10
0

SWITCHYARD

Jul
24

S...

04-Oct-12

TURBINE WASHING SKID

Jun
23

F...

09-Oct-12

RECOVERY PITS

May
22

S...

21-Sep-12

42CCWT1000 Foundation for Tank

Apr
21

2...

03-Oct-12

COMPRESSED AIR SYSTEM

Mar
20

1...

CONCRETE
00CCWT1000 Start Concrete Foundation of Condensate Make Up Water Tank

Feb
19

2...

10

CONDENSATE MAKE UP WATER TANK

Jan
18

0...
I...

0...
S...
S...

Page 6 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15

Nov
16
C...

Dec
17

42CSIY1010

Concrete Works Electrical Switchyard Building

45

22-Sep-12

05-Nov-12

42CSIY1020

Concrete Foundation of Feeder Bay Structure Incld Cable Duct

60

04-Oct-12

03-Dec-12

51

14-Nov-11 A

03-Dec-12

SITE FACILITIES

29

14-Nov-11 A

31-Oct-12

3...

SITE FACILITIES

29

14-Nov-11 A

31-Oct-12

3...

29
7

14-Nov-11 A
27-Dec-11 A

31-Oct-12
27-Sep-12

41CGEN1070 Temporary Access Road, Drainage Outside to Inside Plant

20

14-Nov-11 A

09-Oct-12

41CGEN1080 Temporary Access Road, Drainage & Parking Inside Plant

33

21-Sep-12

20-Oct-12

41CSIT1010

10

15-Mar-12 A

31-Oct-12

29

01-Jun-12 A

03-Dec-12

0...

29

01-Jun-12 A

03-Dec-12

0...

29
40

01-Jun-12 A
01-Jun-12 A

03-Dec-12
03-Dec-12

0...
D...

31

30-Aug-12 A

03-Nov-12

22

30-Aug-12 A

23-Oct-12

2...

22
34

30-Aug-12 A
30-Aug-12 A

23-Oct-12
23-Oct-12

2...
I...

21

13-Sep-12 A

24-Oct-12

2...

21
0

13-Sep-12 A
25-Sep-12

24-Oct-12

31

13-Sep-12 A

24-Oct-12

31

21-Sep-12

03-Nov-12

21-Sep-12
21-Sep-12

03-Nov-12

Start Concrete Foundation of Analyzer Building

31
0

Concrete Pile Caps Analyzer Building

46

21-Sep-12

03-Nov-12

52

08-May-12 A

03-Dec-12

30

29-Jun-12 A

01-Nov-12

0...

30

29-Jun-12 A

01-Nov-12

0...

30
30
20

29-Jun-12 A
29-Jun-12 A
29-Jun-12 A

01-Nov-12
01-Nov-12
13-Oct-12

0...
0...

20

23-Jul-12 A

01-Nov-12

F...

29

21-Sep-12

31-Oct-12

3...

29
29
7

21-Sep-12
21-Sep-12
21-Sep-12

31-Oct-12
31-Oct-12
28-Sep-12

3...
3...

KE-42CHRS1070
F ormwork

29-Sep-12

03-Oct-12

F...

KE-42CHRS1080
Pouring Concrete K-450

02-Oct-12

03-Oct-12

P...

KE-42CHRS1090
Q A/QC Check List (t Reinforcement, Formwork, elevation, centre line)

02-Oct-12

03-Oct-12

Q...

KE-42CHRS1100W ork permit

02-Oct-12

03-Oct-12

W...

KE-42CHRS1110Curring Time

28

04-Oct-12

31-Oct-12

C...

30

02-Jul-12 A

01-Nov-12

0...

30

02-Jul-12 A

01-Nov-12

0...

SITE INFRASTRUCTURE

CIVIL
41CGEN1015 Soil Improvement by Owner

Installation temporary warehouse c/w utilities

DRAINAGE & LANDSCAPE


DRAINAGE & LANDSCAPE
CIVIL
41CDRL1000

Drainage Dict & Side Slope treatment

BUILDINGS
EB, AD MIN & CCB BUILD ING
STRUCTURAL STEEL
43CCCB1000 Installation of Structural Steel for Electrical & Control Building

WAREHOUSE & WORKSHOP


CONCRETE
00CWWS1000 Start Concrete Foundation of Warehouse & Workshop
42CWWS1000 Concrete Foundation

Analyzer Building
CONCRETE
00CANB1001
42CANB1020

OWNER SCOPE
TRAIN 1
TRANSFORMER
TRANSFORMER GTG
CONCRETE
KE-42GTT1140 Reinforcement pedetal+ wall
KE-42GTT1150 Formwork pedestal+wall

HEAT RECOVERY STEAM GENERATOR


PEDESTAL SHELTER
CONCRETE
KE-42CHRS1060
Reinforcement

TRAIN 2
TRANSFORMER

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Jan
18

Feb
19

Mar
20

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

C...
0...

3...
S...
T...
T...
I...

0...

2...
S...
C...
0...
0...
S...
C...
0...

R...

R...

Page 7 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15

Nov
16
0...
0...

Dec
17

TRANSFORMER GTG
CONCRETE
KE-42GTT2140 Reinforce pedestal+wall

30
30
20

02-Jul-12 A
02-Jul-12 A
02-Jul-12 A

01-Nov-12
01-Nov-12
13-Oct-12

KE-42GTT2150 Formwork pedestal+wall

20

27-Jul-12 A

01-Nov-12

F...

29

21-Sep-12

31-Oct-12

3...

29
29
7

21-Sep-12
21-Sep-12
21-Sep-12

31-Oct-12
31-Oct-12
28-Sep-12

3...
3...

KE-42CHRS2070
F ormwork

29-Sep-12

03-Oct-12

F...

KE-42CHRS2080
Q A/QC Check List (t Reinforcement, Formwork, elevation, centre line)

02-Oct-12

03-Oct-12

Q...

KE-42CHRS2090
W ork permit

02-Oct-12

03-Oct-12

W...

KE-42CHRS2100
Pouring Concrete K-450

02-Oct-12

03-Oct-12

P...

KE-42CHRS2110Curring Time

28

04-Oct-12

31-Oct-12

41

27-Jun-12 A

17-Nov-12

1...

41

27-Jun-12 A

17-Nov-12

1...

41
21

27-Jun-12 A
02-Jul-12 A

17-Nov-12
15-Oct-12

KE-42STG1040 Reinforcement (Foundation)

24

03-Jul-12 A

18-Oct-12

KE-42STG1050 Formworks (Foundation)

23

27-Jun-12 A

17-Nov-12

52

16-Jul-12 A

03-Dec-12

29

20-Jul-12 A

31-Oct-12

DRAWING
GENERAL
KE-00CGCM0000
Shop drawing

25
25
30

21-Sep-12
21-Sep-12
21-Sep-12

25-Oct-12
25-Oct-12
25-Oct-12

PREPARATION
CONCRETE
KE-42CGCM0020
backfill

1
1
1

20-Jul-12 A
20-Jul-12 A
20-Jul-12 A

21-Sep-12
21-Sep-12
21-Sep-12

FOUNDATION PILE CAP


CONCRETE
KE-42CGCM1020
Fabrication Reinforcement & Formworks

29
29
34

10-Sep-12 A
10-Sep-12 A
21-Sep-12

31-Oct-12
31-Oct-12
31-Oct-12

KE-42CGCM1030
Reinforcement footing

13

11-Sep-12 A

05-Oct-12

R...

KE-42CGCM1040
Formworks footing

13

10-Sep-12 A

05-Oct-12

F...

38

21-Sep-12

13-Nov-12

1...

38
38
45

21-Sep-12
21-Sep-12
21-Sep-12

13-Nov-12
13-Nov-12
13-Nov-12

1...
1...
S...

30

03-Oct-12

08-Nov-12

52

21-Sep-12

03-Dec-12

0...

52
52
60

21-Sep-12
21-Sep-12
21-Sep-12

03-Dec-12
03-Dec-12
03-Dec-12

0...
0...
S...

42

29-Sep-12

28-Nov-12

2...

42
42
48

29-Sep-12
29-Sep-12
29-Sep-12

28-Nov-12
28-Nov-12
28-Nov-12

2...
2...
S...

16-Jul-12 A

27-Sep-12

HEAT RECOVERY STEAM GENERATOR


PEDESTAL SHELTER
CONCRETE
KE-42CHRS2060
Reinforcement

STEAM TURBINE GENERATOR


STEAM TURBINE GENERATOR
CONCRETE
KE-42STG1030 Fabrication Reinforcement & Formwork

BALANCE OF PLANT
GAS COMPRESSOR & METERING

COOLING WATER
SEA WATER INTAKE & DISCHARGE
PIPING
KE-46CSWI1001Shop Drawing Auxiliary Cooling water
KE-46CSWI1011Shop Drawing Main Cooling water

PROCESS WATER
SERVICE WATER PACKAGE
PIPING
KE-46CPSW0000
Shop Drawing

FIRE PROTECTION/FIGHTING SYSTEM


FIRE PROTECTION/FIGHTING
PIPING
KE-46CFFP0000Shop Drawing

OIL & WASHING WATER RECOVERY PIT

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Jan
18

Feb
19

Mar
20

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

R...

R...

C...

1...
F...
R...
F...
0...
3...
2...
2...
S...
2...
2...
b...
3...
3...
F...

S...

2...

Page 8 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15

FLOOR
CONCRETE
KE-42WORP1150
Install Water Proofin g

1
1
1

18-Jul-12 A
18-Jul-12 A
18-Jul-12 A

21-Sep-12
21-Sep-12
21-Sep-12

2...
2...
I...

WALL
CONCRETE
KE-42WORP1220
Formwork

5
5
2

16-Jul-12 A
16-Jul-12 A
16-Jul-12 A

27-Sep-12
27-Sep-12
22-Sep-12

2...
2...
F...

KE-42WORP1230
QA/QC check list ( Reinforcement, Formwork, elevation, centre line)

20-Jul-12 A

22-Sep-12

Q...

KE-42WORP1240
Pouring Concrete Fc-35

20-Jul-12 A

24-Sep-12

P...

KE-42WORP1250
Install Water Proofin g

26-Sep-12

27-Sep-12

I...

2
2
2

19-Jul-12 A
19-Jul-12 A
19-Jul-12 A

25-Sep-12
25-Sep-12
24-Sep-12

2...
2...
R...

KE-42WORP1330
Formwork

19-Jul-12 A

24-Sep-12

F...

KE-42WORP1340
QA/QC check list ( Reinforcement, Formwork, elevation,centre line)

20-Jul-12 A

25-Sep-12

Q...

KE-42WORP1350
Pouring Concrete Fc-35

20-Jul-12 A

25-Sep-12

P...

17

06-Sep-12 A

15-Oct-12

17

06-Sep-12 A

15-Oct-12

TRANSMISION TOWER
GENERAL
KE-00TTSY0000Shop Drawing

11
11
14

21-Sep-12
21-Sep-12
21-Sep-12*

06-Oct-12
06-Oct-12
06-Oct-12

CIVIL
KE-41TTSY0020cutting pile

4
2

21-Sep-12
21-Sep-12

26-Sep-12
22-Sep-12

2...
c...

KE-41TTSY0030backfill / digging

24-Sep-12

26-Sep-12

b...

KE-41TTSY0040manual compaction

25-Sep-12

26-Sep-12

m...

KE-41TTSY0050bowplank lean concrete

26-Sep-12

26-Sep-12

b...

6
1

27-Sep-12
27-Sep-12

04-Oct-12
27-Sep-12

0...
p...

KE-42TTSY1020Reinforcement pile cap footing

28-Sep-12

04-Oct-12

R...

KE-42TTSY1030formwork footing

28-Sep-12

04-Oct-12

f...

12
12
6

06-Sep-12 A
06-Sep-12 A
06-Sep-12 A

15-Oct-12
15-Oct-12
03-Oct-12

P...

KE-42FBSY1010pouring lean concrete k-125

03-Oct-12

04-Oct-12

p...

KE-42FBSY1020Reinforcement pile cap footing

11

04-Oct-12

15-Oct-12

52

08-May-12 A

03-Dec-12

15

07-Jul-12 A

11-Oct-12

1...

15
15
6

07-Jul-12 A
07-Jul-12 A
07-Jul-12 A

11-Oct-12
11-Oct-12
27-Sep-12

1...
1...
F...

KE-43PBGT3120Install Column

28-Sep-12*

30-Sep-12

I...

KE-43PBGT3130Install I Beam

28-Sep-12

30-Sep-12

I...

KE-43PBGT3140Install Roof Main Structure

10

01-Oct-12

11-Oct-12

11
11
6

07-Jul-12 A
07-Jul-12 A
07-Jul-12 A

06-Oct-12
06-Oct-12
27-Sep-12

0...
0...
F...

21-Sep-12*

25-Sep-12

I...

COVER
CONCRETE
KE-42WORP1310
Reinforcement

SWITCHYARD
150KV SWITCHYARD

CONCRETE
KE-42TTSY1010pouring lean concrete k-125

FEEDER BAY
CONCRETE
KE-42FBSY1000Piling

SITE INFRASTRUCTURE
GTG POWER BUILDING
Steel Structure PB 1
STRUCTURAL STEEL
KE-43PBGT3110Fabrication

Steel Structure PB 2
STRUCTURAL STEEL
KE-43PBGT3210F abrication
KE-43PBGT3220Install Column

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Nov
16

Dec
17

Jan
18

Feb
19

Mar
20

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

1...
1...
0...
0...
S...

1...
1...

R...
0...

I...

Page 9 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

KE-43PBGT3230Install I Beam

21-Sep-12

25-Sep-12

KE-43PBGT3240Install Roof Main Structure

10

26-Sep-12

06-Oct-12*

15

07-Jul-12 A

11-Oct-12

6
6
1

20-Sep-12 A
20-Sep-12 A
20-Sep-12 A

28-Sep-12
28-Sep-12
21-Sep-12*

STG POWER BUILDING


Pile Cap Foundation
CONCRETE
KE-42PBST2070Pouring concrete Fc'35 T-Beam
KE-42PBST2080Finishing

Oct
15

Nov
16

28-Sep-12
11-Oct-12
11-Oct-12
26-Sep-12

F...

KE-42PBST2160Pouring concrete Console Fc' 35

27-Sep-12

27-Sep-12

P...

KE-42PBST2170QA/QC check list Reinforcement, Formwork, elevation, centre line

27-Sep-12

27-Sep-12

Q...

KE-42PBST2180work permit

27-Sep-12

27-Sep-12

w...

KE-42PBST2190Curing Time

14

28-Sep-12

11-Oct-12

C...

8
8
2

28-Sep-12
28-Sep-12
28-Sep-12

09-Oct-12
09-Oct-12
29-Sep-12

0...
0...
s...

KE-42PBST2370Manual soil compaction

28-Sep-12

29-Sep-12

M...

KE-42PBST2380Pouring lean concrete slab floor K-125

01-Oct-12

01-Oct-12

P...

KE-42PBST2390Reinforcement slab floor

02-Oct-12

09-Oct-12

11
11
6

07-Jul-12 A
07-Jul-12 A
07-Jul-12 A

05-Oct-12
05-Oct-12
27-Sep-12

0...
0...
F...

KE-43PBST3020Install Column

01-Oct-12*

05-Oct-12

I...

KE-43PBST3030Install I Beam

01-Oct-12

05-Oct-12

I...

52

08-May-12 A

03-Dec-12

DRAWING
GENERAL
KE-00CWWS0000
Shop Drawing

1
1
2

08-May-12 A
08-May-12 A
08-May-12 A

22-Sep-12
22-Sep-12
22-Sep-12

CONCRETE PILE CAP


CONCRETE
KE-42CWWS1020
Fabrication reinforcement & formworks

52
52
60

13-Sep-12 A
13-Sep-12 A
21-Sep-12

03-Dec-12
03-Dec-12
03-Dec-12

KE-42CWWS1030
Reinforcement footing

13-Sep-12 A

30-Sep-12

R...

KE-42CWWS1040
Formworks footing

13-Sep-12 A

30-Sep-12

F...

KE-42CWWS1050
Pouring concrete Fc' 35 footing foundation

01-Oct-12*

01-Oct-12

P...

KE-42CWWS1060
Reinforcement T-Beam

13-Sep-12 A

06-Oct-12

R...

KE-42CWWS1070
Formwork T-Beam

13

13-Sep-12 A

06-Oct-12

F...

KE-42CWWS1080
Installation anchor bolt

29-Sep-12

08-Oct-12

I...

T-BEAM
CONCRETE
KE-42CWWS2010
Backfill inside

2
2
3

04-Oct-12
04-Oct-12
04-Oct-12

06-Oct-12
06-Oct-12
06-Oct-12

0...
0...
B...

STRUCTURAL STEEL
STRUCTURAL STEEL
KE-43CWWS3010
Fabrication

5
5
5

24-Sep-12
24-Sep-12
24-Sep-12

28-Sep-12
28-Sep-12
28-Sep-12

26

14-Sep-12 A

26-Oct-12

21

21-Sep-12

20-Oct-12

ELECTRICAL SWITCHYARD BUILDING


PREPARATION

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

1...

21-Sep-12
21-Sep-12
21-Sep-12

WAREHOUSE & WORKSHOP

Mar
20

2...
2...
P...

28-Sep-12

Steel Structure
STRUCTURAL STEEL
KE-43PBST3010Fabrication

Feb
19

I...

Floor
CONCRETE
KE-42PBST2360soil backfill inside

Jan
18

I...

15
15
5

Console
CONCRETE
KE-42PBST2150Formwork

Dec
17

F...
1...
1...

R...

0...
2...
2...
S...
0...
0...
F...

2...
2...
F...
2...
2...

Page 10 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15

Nov
16

21
30

21-Sep-12
21-Sep-12*

20-Oct-12
20-Oct-12

2...
S...

26
26
30

14-Sep-12 A
14-Sep-12 A
21-Sep-12

26-Oct-12
26-Oct-12
20-Oct-12

2...
2...
F...

KE-42CESB1020Reinforcement Pedestal

15

14-Sep-12 A

05-Oct-12

R...

KE-42CESB1030Formwork Footing & Pedestal

15

15-Sep-12 A

07-Oct-12

F...

KE-42CESB1060Reinforcement T-Beam

15

14-Sep-12 A

24-Oct-12

KE-42CESB1080Formwork T-Beam

15

14-Sep-12 A

26-Oct-12

15

28-Aug-12 A

11-Oct-12

1...

15

12-Sep-12 A

11-Oct-12

1...

15

12-Sep-12 A

11-Oct-12

1...

15
15
1

12-Sep-12 A
12-Sep-12 A
12-Sep-12 A

11-Oct-12
11-Oct-12
21-Sep-12

1...
1...
I...

45CGTG-B1020Grouting Work

16-Sep-12 A

22-Sep-12

G...

45CGTG-B1025Curring Time

23-Sep-12

28-Sep-12

C...

45CGTG-B1030Inspection of Sub Sole Plate & Packer Plate Grouting

29-Sep-12

29-Sep-12

I...

45CGTG-B1035Cleaning & Covering Sub Sole Plate & Anchor Bolt

30-Sep-12

30-Sep-12

C...

45CGTG-C1000Transport Material & Opern Case Material

01-Oct-12

01-Oct-12

T...

45CGTG-C1005Cleaning Shim Plate

02-Oct-12

02-Oct-12

C...

45CGTG-C1010Check Surface Top Shim Pla te to Bottom Frame GTG

03-Oct-12

11-Oct-12

C...

5
15

30-Sep-12
12-Sep-12 A

05-Oct-12
11-Oct-12

0...
1...

15
15
1

12-Sep-12 A
12-Sep-12 A
12-Sep-12 A

11-Oct-12
11-Oct-12
21-Sep-12

1...
1...
I...

45CGTG-B2020Grouting Work

16-Sep-12 A

22-Sep-12

G...

45CGTG-B2025Curring Time

23-Sep-12

28-Sep-12

C...

45CGTG-B2030Inspection of Sub Sole Plate & Packer Plate Grouting

29-Sep-12

29-Sep-12

I...

45CGTG-B2035Cleaning & Covering Sub Sole Plate & Anchor Bolt

30-Sep-12

30-Sep-12

C...

45CGTG-C2000Transport Material & Opern Case Material

01-Oct-12

01-Oct-12

T...

45CGTG-C2005Cleaning Shim Plate

02-Oct-12

02-Oct-12

C...

45CGTG-C2010Check Surface Top Shim Pla te to Bottom Frame GTG

03-Oct-12

11-Oct-12

MAIN EQUIPMENT
MECHANICAL
45CGTG-E2000Centering GT, Generator & Load Gear

5
5
3

30-Sep-12
30-Sep-12
30-Sep-12

05-Oct-12
05-Oct-12
02-Oct-12

0...
0...
C...

45CGTG-E2005Alignment GT, Generator & Load Gear

03-Oct-12

05-Oct-12

A...

45CGTG-E2060Install Lube Oil Tank

03-Oct-12

05-Oct-12

I...

15

28-Aug-12 A

11-Oct-12

21-Sep-12

01-Oct-12

0...

7
0

21-Sep-12

Metal Deck

01-Oct-12
21-Sep-12

0...
M...

ECCB0040

Roofing & Siding

21-Sep-12

R...

ECCB0050

Acessories

21-Sep-12

A...

GENERAL
CESB0000

Shop Drawing

FOUNDATION
CONCRETE
KE-42CESB1015Fabrication Reinforcement

KPI
GTG
GTG 1
SUBSOLE PLATE
MECHANICAL
45CGTG-B1015Inspection of Sub Sole Plate & Packer Plate

MAIN EQUIPMENT

GTG 2
SUBSOLE PLATE
MECHANICAL
45CGTG-B2015Inspection of Sub Sole Plate & Packer Plate

ELECTRICAL ADMIN CONTROL BUILDING


Engineering
GENERAL
ECCB0030

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Dec
17

Jan
18

Feb
19

Mar
20

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

R...
F...

C...

1...

Page 11 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15

ECCB0060

Plumbing

24-Sep-12

ECCB0070

Electrical

01-Oct-12

E...

ECCB0080

Cable Tray

29-Sep-12

C...

Procurement

15

28-Aug-12 A

11-Oct-12

1...

28-Aug-12 A
28-Aug-12 A
21-Sep-12

11-Oct-12
11-Oct-12
26-Sep-12

1...
1...
R...
M...

Roof & Siding

PCBO0020

Metal Deck

21-Sep-12

26-Sep-12

PCBO0030

Acessories ( Door, Window, Louvre)

21-Sep-12

26-Sep-12

PCBO0040

Reinforce Steel + Concrete

28-Aug-12 A

22-Sep-12

R...

PCBO0050

Brick Wall

21-Sep-12

21-Sep-12

B...

PCBO0060

Painting

22-Sep-12

24-Sep-12

PCBO0070

Plumbing & Toil et

25-Sep-12

29-Sep-12

PCBO0080

Electrical

10

01-Oct-12

11-Oct-12

11

08-Sep-12 A

06-Oct-12

0...

11
11
3

21-Sep-12
21-Sep-12
21-Sep-12

06-Oct-12
06-Oct-12
24-Sep-12

0...
0...
C...

Construction
Zona 1 ( Axis 4C' - 5B / Raw A1 - B1)
STRUCTURAL STEEL
CESS1060
Column Axis 4C' - 5A / Raw A1

26-Sep-12

B...

CESS1080

Beam Axis 4C' - 5A / Raw A1 elevation + 6.525

27-Sep-12

28-Sep-12

B...

CESS1090

Beam Axis 4C' - 5A / Raw A1 elevation + 11.700

29-Sep-12

01-Oct-12

B...

CESS1100

Alignment Column

11

21-Sep-12

03-Oct-12

A...

CESS1110

Bolt Tightening

10

26-Sep-12

06-Oct-12

7
7
4

08-Sep-12 A
08-Sep-12 A
10-Sep-12 A

01-Oct-12
01-Oct-12
25-Sep-12

0...
0...
A...
B...

Bolt Tightening

08-Sep-12 A

25-Sep-12

CESS2120

Grouting pedestal (Zone 1 & 2)

26-Sep-12

01-Oct-12

G...

10
10
2

20-Sep-12 A
20-Sep-12 A
20-Sep-12 A

04-Oct-12
04-Oct-12
22-Sep-12

0...
0...
C...
B...

CETR1020

Beam

21-Sep-12 A

25-Sep-12

CETR1030

Roof Trust

28-Sep-12

02-Oct-12

CETR1040

Alignment Column

03-Oct-12

04-Oct-12

Erection Stair & Handrail


STRUCTURAL STEEL
CSTR0000
Erection Stair & Handrail

2
2
2

26-Sep-12
26-Sep-12
26-Sep-12

27-Sep-12
27-Sep-12
27-Sep-12

Concrete Work el. 1.800


CONCRETE
CONW1010
Support

8
8
4

26-Sep-12
26-Sep-12
26-Sep-12

05-Oct-12
05-Oct-12
29-Sep-12

0...
0...
S...

01-Oct-12

05-Oct-12

M...

8
8
5

26-Sep-12
26-Sep-12
26-Sep-12

06-Oct-12
06-Oct-12
01-Oct-12

0...
0...
Z...

02-Oct-12

06-Oct-12

21-Sep-12

28-Sep-12

CPSS2020

Zone 2 Elevation +6.525

ELECTRICAL SWITCHYARD BUILDING

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

B...

CESS2110

Metal Deck

Apr
21

E...

25-Sep-12

CONW1020

Mar
20

P...

Painting Steel
ARCHITECTURAL
CPSS2010
Zone 2 Elevation +11.700

Feb
19

P...

Beam Axis 4C' - 5A / Raw A1 elevation + 1.800

Tier 2 - Roof (Axis 4C -5C / Raw B1 - A1)


STRUCTURAL STEEL
CETR1010
Column

Jan
18

A...

CESS1070

Zona 2 ( Axis 5B - 6B' / Raw A1 - B1)


STRUCTURAL STEEL
CESS2100
Alignment Column

Dec
17

P...

15
15
5

Other
GENERAL
PCBO0010

Nov
16

R...
A...
2...
2...
E...

Z...
2...

Page 12 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

120 MW Combine Cycle Power Plant

Data Date 21 Sept '1

KDL Project
Activity ID

Activity Name

RD

Start

2013

Finish
Sep
14

Oct
15

21-Sep-12

21-Sep-12

2...

0
0

21-Sep-12

21-Sep-12
21-Sep-12

2...
C...

21-Sep-12

28-Sep-12

2...

Reinforce Steel + Concrete

6
7

21-Sep-12
21-Sep-12

28-Sep-12
28-Sep-12

2...
R...

PESB0030

Anchor

21-Sep-12

26-Sep-12

A...

PESB0040

Brick Wall

24-Sep-12

24-Sep-12

B...

Engineering
GENERAL
EESB0020

Concrete

Procurement
GENERAL
PESB0020

Actual Level of Effort

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Nov
16

Dec
17

Jan
18

Feb
19

Mar
20

Apr
21

May
22

Jun
23

Jul
24

Aug
25

Sep
26

Oct
27

Page 13 of 13
PP - Imeco
3 Weeks Look Ahead Schedule 120 MW CCPP

(c) Primavera Systems, Inc.

You might also like