Town North
Electric: 10/5 Gas: After Water Water:10/26-11/9 Sewer:10/26-11/9
West of 5th
Electric: 10/19-10/26 Gas: After Water Water: 11/9-11/23 Sewer: 11/9-11/23
Eagle Canyon
Electric: 10/15 5pm Gas: After Water Water: 11/9-12/7 Sewer: 11/9-12/7
River North
Electric: Evans North
ON, House by House 10/11-14
Sewer:Mains 11/2-9
Taps House by House
Confluence
Electric: House by house
4-6 weeks
Gas: After water Water: Mains 6 -8 weeks, Taps House by house Sewer: Mains 6 -8 weeks, Taps House by house
West Main
Electric:
Case by case
Gas: Ready after water Water: Case by Case Sewer: Case by case