BP-17

DOORS, FRAMES, HARDWARE, SPECIALTIES AND


ASSOCIATED INSTALLATIONS

SCOPE OF WORK

DESIGNATED 100% CBE SUBCONTRACTING SET-ASIDE REQUIREMENT

DEFINITION OF PROJECT AREA:

The Scope of Work includes the doors, frames, hardware, specialties and associated
carpentry work at the Georgetown Neighborhood Library which is located at 3260 R
Street, NW, Washington, DC.

DOORS, FRAMES, HARDWARE, SPECIALTIES AND ASSOCIATED INSTALLATIONS


Contractor shall be responsible for labor, material and equipment for all new doors,
frames, hardware, specialties and associated carpentry including but not limited to
accordion fire doors, flush wood doors, door hardware, visual display boards, display
case units, toilet partitions, unit showers, louvers, signage, lockers, fire extinguishers and
cabinets, back-of-house metal storage shelving, toilet and bath accessories, projection
screens, kitchen casework and floor mats at the existing building and the new addition as
indicated in bid documents (100% Final Construction Drawings and Specifications dated
July 9, 2009). Available on CD. Work includes but is not limited to the following
specification sections Division 1 – General Requirements
Division 5 – Metals
05811 Architectural Joint Systems
Division 6 – Wood And Plastics
06105 Miscellaneous Carpentry (As applicable for your work)
Division 7 – Thermal and Moisture Protection
07920 Joint Sealants (As applicable for your work)
Division 8 – Doors and Windows
08210 Steel Frames
08211 Flush Wood Doors
08311 Access Doors and Frames
08335 Self-Opening Coiling Grilles
08352 Accordion Fire Door System
08710 Door Hardware
Division 10 – Specialties
10101 Visual Display Surfaces
10155 Toilet Compartments
10200 Louvers and Vents
10410 Directories
10505 Metal Lockers
10522 Fire Extinguisher Cabinets
10523 Fire Extinguishers
10671 Metal Storage Shelving
10801 Toilet and Bath Accessories
Division 11 – Equipment
11132 Projection Screens
Division 12 – Furnishings
12355 Institutional Casework
12356 Kitchen Casework
12484 Floor Mats and Frames

1. Furnish and install new accordion fire doors (Won-Door).


2. Furnish and install new flush wood doors, with new frame and new
finish hardware as specified.
3. This contractor is responsible for the keying of all doors. This is to be
coordinated with Owner and factory per Specification Section 08710.
4. Furnish and install any and all required in-wall blocking or other
carpentry required to provide a quality installation of doors, frames or
specialties
5. Furnish and install visual display boards
6. Furnish and install toilet partitions and urinal screens
7. Furnish and install sound absorbing panel at HVAC enclosure.
8. Furnish and install wood pergola at HVAC enclosure, work includes
posts and uplift base assembly
9. Furnish and coordinate with mechanical contractor installation of
required louvers and vents. Furnish and install copper louver vents at
replicated cupola.
10. Furnish and install bi-fold closet doors
11. Furnish and install metal locker units
12. Furnish and install fire extinguishers and fire extinguisher cabinets.
13. Furnish and install toilet accessories mounted to toilet partitions,
permanent partitions or countertops as indicated.
14. Caulking and sealing of backsplashes and counter tops.
15. Hoisting as required for this work.
16. Provide any Independent Testing & Inspection Services required for this
Work, including materials testing and inspections;
17. During the period of this work, contractor agrees that all employees
must be experienced in performing the work.
18. Contractor shall coordinate this work with other work in progress.
19. The Contractor shall ensure that no elements determined to be unstable
are left unsupported. Any and all required structural bracing for
structural systems to remain shall be included in this scope of work.
20. Contractor shall remove and transport debris resulting from erection
operations and materials to site disposal area. Recyclable materials shall
be separated and stored or stockpiled without intermixing with other
surplus materials before transporting to recycling facilities in accordance
with a recycling program consistent with the Project LEED Certification
Program.
21. Contractor shall comply with all identified performance and
specification requirements to achieve LEED points toward the Silver
certification goal as indicated in the bid documents.
22. Contractor shall take all necessary precautions to avoid damage to all
existing and completed construction in place.
23. It is Contractor’s responsibility to read the Hazardous Materials Survey
Report for Georgetown Neighborhood Library, including the July 8th
2008 addendum.
24. Contractor shall submit bids detailing their proposed means, methods
and schedule for this scope of work.
25. Provide labor for incidental project clean-up
26. Provide miscellaneous temporary protection of existing conditions
during construction as specifically specified herein and OSHA safety
barricades, rails and floor coverings, for this Work.
27. Engineering, site survey and layout for this Work including field
measurements as required.
28. Provide monthly Project construction progress documentation &
photographs, including existing building pre-construction condition
documentation.
29. Contractor shall leave the workplace in a clean and presentable
condition ready for subsequent trades and prepared for finishes as
specified.
30. Submittals will be required for approval prior to execution of the work.