C ITY OF D ALLAS B ECKLEY / C OLORADO S IDEWALK I MPROVEMENTS

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

Streetscape
Improving the current condition to 8-foot sidewalks Lighting along sidewalks Keeping existing trees where possible Additional trees along W. Colorado Blvd & N. Beckley Ave. Bioswales with native plantings where possible.

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

Looking North on N Beckley Ave


(at Madison Ave)

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

Looking East on W Colorado Blvd


(at N Beckley Ave)

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

Project Budget
2006 Bond Fund - $ 1,690,693 Available Funding
Design Cost - $ 218,000 Construction Cost (estimate) - $ 1,471,875 Project Length 4,852 LF Improvement Elements 8 foot concrete sidewalk 66,500 SF x $15.50/SF = Street / Pedestrian lights (acorn style) 60 lights x $5,000/light = Trees (200 gallon type) 125 trees x $1,129/tree = Current Project Cost =

$ 1,030,750 $ 300,000 $ 141,125 $1,689,875

BECKLEY / COLORADO SIDEWALK ENHANCEMENTS

Project Schedule

Begin Design:

August 2013

Complete Design (estimate):

September 2014

Begin Construction (estimate):

January 2015

Complete Construction (estimate):

December 2015