Streetscape
Improving the current condition to 8-foot sidewalks Lighting along sidewalks Keeping existing trees where possible Additional trees along W. Colorado Blvd & N. Beckley Ave. Bioswales with native plantings where possible.
Project Budget
2006 Bond Fund - $ 1,690,693 Available Funding
Design Cost - $ 218,000 Construction Cost (estimate) - $ 1,471,875 Project Length 4,852 LF Improvement Elements 8 foot concrete sidewalk 66,500 SF x $15.50/SF = Street / Pedestrian lights (acorn style) 60 lights x $5,000/light = Trees (200 gallon type) 125 trees x $1,129/tree = Current Project Cost =
Project Schedule
Begin Design:
August 2013
September 2014
January 2015
December 2015