KRISHNAPATTNAM 400kV GIS SITE STATUS

HV TEST STATUS High Voltage Test for Line -1, ST-1 and GT-1 was started on 04.02.2014 and is completed at Main Bus bar 1 side on 09.02.2014.

ERECTION STATUS Erection of GIS Circuit breakers, Bus and bays are completed for Bay 21, 22, 23, 24, 25, 26, 27, 28, and 29. Erections of GIB Bus ducts up to bushing are completed for Bay 22, 23 and 26. GIB Bus ducts are erected up to Elbow for Bay 27.

Bus coupler Y Phase CT Leakage Issue Due to Leakage in Current Transformer Y Phase at bay 5, the same was dismantled on 07.02.2014, and same was transported to Alstom on 10.02.2014

KRISHNAPATTNAM 400kV GIS SITE STATUS


LINE CHARGING ACTIVITIES AIS Equipment Erection is in progress and Line Stringing is completed from Transmission line to Intermediate Gantry tower.

WORK FRONT STATUS Bus Enclosures and Bus bars are kept ready for Bay 27 and Bay 28. The Erection work can be continued up to 10 days for the same. But there is no clearance to start the erection in Bay 21, Bay 24, and Bay 29 due to excavation activities on South side for Bus Reactor-1 foundation. And we are in need of a Surveyor to mark the foundation Co Ordinates.

KRISHNAPATTNAM 400kV GIS SITE STATUS