You are on page 1of 14

INDEX PILES - TEST PILE PROGRAM

PILE DRIVING PROCESS (PG 88)

F Index piles are driven to determine:

A. Subsurface Conditions B. Driving System


Pile driving is generally divided into two areas. A. Index Pile Driving, the Test Pile Program B. Production Pile Driving

C. Pile Capacity

Pile Driving Process

Pile Driving Process

Index Piles:
F Are not required on all projects and may or may
n n n n n n n n

Index Piles (continued)


F Are driven to determine any or all of the following:

not be incorporated into the structure. F Are exploratory in nature and shall generally be driven harder (within the limits of practical refusal), deeper and to a greater bearing value than required for the permanent (production) piling. F Should be the same cross section and type, and should be driven in the same manner as the production piles.
Pile Driving Process

safe bearing value of the piles - Pile Capacity. nature of the soil. ability of the driving system to do the work. amount of work necessary to obtain minimum required pile penetration driving resistance characteristics of the various soil strata. casting lengths of the production piles required for the work. need for pile point protection (steel or composite piles). Note: Usually driven with a PDA, but sometimes without a PDA and sometimes with a pile load test.

Pile Driving Process

INSPECTORS DUTIES (PG 89)


F Check

INSPECTORS DUTIES (contd)


F Check

all the items listed on the Predriving Checklists F Inform the Contractor and RCE when the plans or specifications are not followed F The Inspector is never to instruct the Contractor in how to correct his/her problem. F If a PDA is required: make sure the onon- call PDA Consultant has been scheduled, is on site, that the PDA equipment has been attached to the pile.
Pile Driving Process

that the pile is in the proper location before driving is allowed to begin. F Inform the Bridge Construction Office of any conflicts F Check that the correct pile (length, size, etc.) is being used, that the driving head is up (stenciled end), and that pile tips have been installed per the plans and specs. (when required). F Check the batter or plumbness of the pile and the pile orientation.
Pile Driving Process

INSPECTORS DUTIES (contd)


Record on the Pile Driving Log: F Preliminary information (e.g., file #, bent #, pile #, template elevation, etc.). F Placement data including jetting or predrilling prior to driving (e.g., auger diameter and depth of drilling or jetting). F Hammer blows and blows per foot F Average stroke height (or bounce chamber pressure) for each corresponding foot of driving F General notes of observations (e.g., changed from fuel 22- o to fuel 33- o at 31 feet or pile driving stopped at 1:10 pm for 10 minutes at 35 to move template, etc.)
Pile Driving Process

INSPECTORS DUTIES (contd)


Record on the Pile Driving Log: (continued)
F Any significant rebound (over ) F Location

and severity of any pile cracking or damage including the time and driving depth. F If damage occurs, record it and, instruct the Contractor to discontinue driving and inform the RCE, and the Bridge Construction Office ; n CONCRETE: multiple horizontal hairline cracks, open horizontal cracks (dust flies out during driving), vertical cracks, diagonal cracks, significant spalling; n STEEL: any cracks, twisting, significant bending
Pile Driving Process

INSPECTORS DUTIES (contd)


F If the pile starts to walk (move around) during

INSPECTORS DUTIES (contd)


F Call the Bridge Construction Office if an

driving, inform the Contractor immediately so he/she can make adjustments to keep the pile within tolerance. Contractor shall never pull the pile back within tolerance. F Instruct the Contractor to discontinue

obstruction is encountered. n Document obstructions


n object n time

driving if; n ultimate bearing has been achieved n grade has been reached n if practical refusal is encountered.
Pile Driving Process

hit needed to remove the object n bottom elevation of the disturbed soil n pertinent conversations or remarks n steps taken by the Contractor or directed by the Engineer.
Pile Driving Process

INSPECTORS DUTIES (contd)


F If

INSPECTORS DUTIES (contd)


F If

practical refusal is reached before reaching grade; n inform the RCE n call the Bridge Construction Office.

Note: Do not stop driving after only 5 blows of practical refusal. We may have hit a thin layer that will break through. However, do not pound on the pile for one hundred blows of practical refusal. (See Boring Logs for judgement call.)
Pile Driving Process

pile is within 1 of cutcut- off elevation without achieving bearing, n leave the pile 6 above grade n inform the RCE n call the Bridge Construction Office. F For restrikes, check to ensure the hammer has been warmed up on another pile per the specs before starting. See Section 711.21 of the Std. Specs for additional restrike requirements.

Pile Driving Process

INSPECTORS DUTIES (contd)


F Ensure

INSPECTORS DUTIES (contd)


F Record on the Pile Driving Log the location and type of

that all buildups comply with the plans & specs. F Ensure that any steel pile splices or pile point splices comply with specs or approved details. F Ensure that welding follows the procedure that has been previously submitted by the Contractor to the RCE and Research & Mat. Lab and that splice welding is performed by a SCDOT certified welder

splices or buildups.
F Fax the completed Pile Driving Log to the Bridge

Construction Office.
F If no PDA is required, complete an index pile information

sheet similar to the one shown on the following page and fax it to the Bridge Construction Office.
F Ensure any pile encasements, pile painting, or touch -up

painting has been preformed in accordance with the plans and specs.

Pile Driving Process

Pile Driving Process

INDEX PILE - FILE NO. __ 99.999 ______BENT N0. _ 4______PILE NO.__ 2_____
- 70' 18" PRESTR. C O N C R E T E WITH HP 10X 57 POINT AND REINFORCED TIPS HAMMERICE 42-S SINGLE ACTING D I E S E L RAM WT.= 4088 LBS.

INDEX PILES WITH PDA TESTING (PG 92)


F Pile

Driving Analyzer (PDA) Process is a portable computer

60'

CO ELEV.= 67.265' WATER ELEV. = 61.91' O.G. ELEV.= 60.71'

Boring 4' Lt.' of

Sta. 84 + 35.0

F PDA F PDA

11-

Medium to very dense dark gray silty fine sand

50' EXPOSED PILE POINT = 5' 40' STEEL TIP ELEV. = 41.90 NOTE: Crack Appeared in pile at top pick-up point when Steel Tip Elev. = 43.0' REINF. TIP 5530' 40 in 0.4'Very hard dense Dark gray silty Clayey fine sand 40 in 0.3'-

uses specially designed strain transducers and accelerometer gauges for data acquisition. are attached near the pile top (generally two pile diameters down from the top) to concrete, steel, or timber piles. driving, the PDA computer analyzes data in real time for each hammer blow.
Pile Driving Process

40 in 0.3'28-

F Gauges

4120' 51Boring Terminated 10' 0 60 80 100 120 140 160 180 200 220 240

F During

FROM WEAP CHART ULTIMATE BEARING CAPACITY (TONS) WITHOUT PDA

Pile Driving Process

91

PILE DRIVING ANALYZER (PDA) RESULTS


F Ultimate F Driving
n n n

PILE DRIVING ANALYZER (PDA) RESULTS


continued

Bearing Capacity

F Pile
n

Stresses

Tension Compression Bending Performance Transfer Energy Transfer Efficiency

F Hammer
n n

Integrity Extent n Location F Aspects of Soil Resistance n End Bearing n Skin Friction F Soil Strength Changes with Time n End of Initial Driving n Beginning of Restrike
Pile Driving Process

Pile Driving Process

LOAD TESTS (94)


F Are

TYPICAL ARRANGEMENT FOR LOAD TESTING A PILE (Not in Manual)

seldom used on SCDOT projects


F The

F Vary from project to project. F When called for, plans and specs. must be read

and followed closely. sample spec is on pages 3737- 42 of this manual. F The Inspector must ensure n that the reaction frame is properly installed n that proper coordination is maintained with Contractor and all SCDOT consultant firms and other interested parties.
FA
Pile Driving Process

following pictures were taken of the Pile Load Testing performed on the Conway Bypass Project. F This project had both a vertical and horizontal Load Test.

Pile Driving Process

Pile Driving Process

Pile Driving Process

Pile Driving Process

Pile Driving Process

Pile Driving Process

Pile Driving Process

Pile Driving Process

Pile Driving Process

PRODUCTION PILE DRIVING (PG 95)

F OVERVIEW:
n

Production piles are those to be incorporated into the project. Production pile driving is set to begin when:
n Pile

lengths have been set criteria is in hand, and checklists have been completed

n Driving

n Pre Pre- driving

Pile Driving Process

Pile Driving Process

PRODUCTION PILE DRIVING (PG 95)


F This

Inspectors Duties
F Never instruct the Contractor in how to correct his/her

segment contains n Inspectors duties n Detailed information and instructions to help the Inspector in the performance of those duties. F Remember, the Inspector is to keep the Contractor and RCE informed when the construction is not following the plans or specs.

problem.
F Check for:
n n n n n

correct pile (length, size, etc.) is being used driving head is up (stenciled end) pile tips have been installed as per the plans and specs (when required). pile is in the proper location before driving

batter or plumbness of the pile and the pile orientation. F Record preliminary information on the Pile Driving Log (such as File #, Bent #, Pile #, template elevation, etc.).
Pile Driving Process

Pile Driving Process

INSPECTORS DUTIES (contd)


Record on the Pile Driving Log:
F Preliminary information (e.g., file #, bent #, pile #,

INSPECTORS DUTIES (contd)


Record on the Pile Driving Log: (continued)
F Any significant rebound (over 1/2) F Location and severity of any pile cracking or damage

template elevation, etc.).


F Placement data including jetting or predrilling prior to

including the time and driving depth.


F If damage occurs, record it and, instruct the Contractor

driving (e.g., auger diameter and depth of drilling or jetting). F Hammer blows and blows per foot
F Average stroke height (or bounce chamber pressure)

to discontinue driving and inform the RCE, and the Bridge Construction Office; Office;
n

for each corresponding foot of driving


F General notes of observations (e.g., changed from fuel

CONCRETE: multiple horizontal hairline cracks, open horizontal cracks (dust flies out during driving), vertical cracks, diagonal cracks, significant spalling; STEEL: any cracks, twisting, significant bending

2-o to fuel 33-o at 31 feet or pile driving stopped at 1:10 pm for 10 minutes at 35 to move template, etc.)
Pile Driving Process

Pile Driving Process

INSPECTORS DUTIES (contd)


F If the pile starts to walk (move around) during driving,

INSPECTORS DUTIES (contd)


F Call the Bridge Construction Office if an obstruction is

inform the Contractor immediately so he/she can make adjustments to keep the pile within tolerance. Contractor shall never pull the pile back within tolerance. F Instruct the Contractor to discontinue driving if; n ultimate bearing has been achieved n grade has been reached n if practical refusal is encountered. n minimum tip elevation has been obtained (or is within 5 of grade if there is no minimum tip elevation requirement) n minimum penetration has been obtained Note: Contractor is required to drive 2 past the elevation at which required bearing was first obtained unless cut off elevation is reached or practical refusal is obtained.
Pile Driving Process

encountered.
n

Document obstructions
n object n time

hit

needed to remove the object elevation of the disturbed soil conversations or remarks

n bottom

n pertinent n steps

taken by the Contractor or directed by the Engineer.

Pile Driving Process

INSPECTORS DUTIES (contd)


F If practical refusal is reached before reaching grade;
n n

INSPECTORS DUTIES (contd)


F If pile is within 1 of cutcut-off elevation without achieving

inform the RCE call the Bridge Construction Office.

bearing,
n n n

leave the pile 6 above grade inform the RCE call the Bridge Construction Office.

Note: Do not stop driving after only 5 blows of practical refusal. We may have hit a thin layer that will break through. However, do not pound on the pile for one hundred blows of practical refusal. (See Boring Logs for judgement call.)

F For restrikes, check to ensure the hammer has been

warmed up on another pile per the specs before starting. See Section 711.21 of the Std. Specs for additional restrike requirements.

Pile Driving Process

Pile Driving Process

INSPECTORS DUTIES (contd)


F Ensure that all buildups comply with the plans &

INSPECTORS DUTIES (contd)


F Record on the Pile Driving Log the location and type of

specs.
F Ensure that any steel pile splices or pile point splices

splices or buildups.
F Fax the completed Pile Driving Log to the Bridge

Construction Office.
F If no PDA is required, complete an index pile information

comply with specs or approved details.


F Ensure that welding follows the procedure that has

been previously submitted by the Contractor to the RCE and Research & Mat. Lab and that splice welding is performed by a SCDOT certified welder

sheet similar to the one shown on the following page and fax it to the Bridge Construction Office.
F Ensure any pile encasements, pile painting, or touch -up

painting has been preformed in accordance with the plans and specs.

Pile Driving Process

Pile Driving Process

DRIVING SEQUENCE: (PG 97)


F Driving sequence of piles in a pier or bent cap can be

Driving Sequence

important.
F Contractor needs to provide the proposed driving

SEQUENCE 3

< ------------------------------------------------- < ----------------------------------------------- >


SEQUENCE 1

SEQUENCE 2

sequence in his Pile Installation Plan.


F Driving sequence can affect the way piles drive and can

17 18 19 20 21

16 5 6 7 22 FIGURE 14

15 4 1 8 23

14 3 2 9 24

13 12 11 10 25

affect near -by structures.


n n

especially true for displacement piles nonnon -displacement piles, not as critical.

F Driving sequence of displacement pile groups should be

from the center of the group outward or from one side to the other side (See Figure 14 PG 97).
Pile Driving Process Pile Driving Process

DRIVING SEQUENCE

Driving Sequence Example


F Driving sequence of group in Fig. 14 :
n n

Driving Sequence continued


F Pile groups should not be driven from the outside to the

By the pile number as shown. By driving each row starting with the center of row & working outward as shown in sequence 2.

center (the reverse of sequence 1 or 2). Such sequencing will cause displaced soil to become trapped and compacted in the center of the pile group.
F Work away from existing structures. F For example, if a structure is located to the right side of

By driving each row starting on one side of the group and working to the other side as shown in sequence 3.

pile group shown in Fig. 14, piles should be driven by sequence 3. This reduces amount of soil displaced toward the existing structure.
F May be critical next to a bascule bridge where small

movements can hinder the locking mechanism.

Pile Driving Process

Pile Driving Process

DETERMINING PILE TIP ELEVATION EXERCISE (PG 116116- 127)

PILE DRIVING LOG (PG 128)


PILE DRIVING LOG DATA ON FORM Blanks F Fill in every blank on the form. If it does not apply, put N/A in the blank. Use a pencil, but never erase. erase. If you need to change something, strike a single line through the item and insert the correct information above it. If there is insufficient room to make an entry, footnote the item and go to the bottom or to the back of the page. Fill in the heading before driving starts.

Slides for exercise

Pile Driving Process

Pile Driving Process

PILE DRIVING LOG (PG 128)


PILE DRIVING LOG DATA ON FORM Blows F Count usually in oneone-foot increments. ReRe-taps use 1/4", 1/2", 1", 2", 3", 4", & 6" increments. F Always convert driving criteria to blows per 1, 2, 3, 4, 5, 6, etc. in case pile refusal is obtained prior to pile reaching cutcut-off elevation.

PILE DRIVING LOG (PG 128)


REMARKS F Intermediate stops and starts. F Example reason for stops. (Pile cushion change, hammer breakdown, template in the way, etc.) F Blows per minute (BPM). See Manufacturer's Brochure. F Stroke or Bounce Chamber Pressure (BCP). F Pile damage. F Clarification of Blow Count Increment. F Rebound. F Reason for acceptance. F Attachment or detachment of PDA Equipment. F Show Splice. F Other relevant information such as warnings/recommendations to the Contractor.
Pile Driving Process

Pile Driving Process

PILE DRIVING LOG (PG 128)


INSTRUCTIONS FOR COMPLETING THE PILE DRIVING LOG
F File No. -The Departments File Number F Date - The date that the pile driving begins. F Sheet No. - This sheet number of the total sheets. F Bent No. - Bent No. (from plans) that the pile is being

PILE DRIVING LOG (PG 128)


F Pile Type -Type of pile being driven. It is usually a

Square Prestressed , Steel H or Steel Pipe Pile.


F Pile Size The side dimension in inches of a square pile.

place in.
F Pile No. The Pile No. within the bent or footing (number

pile from left to right and in direction of stationing).

For Steel HH-piles, the HH-pile shape dimensions should be used and for steel pipe piles the outside pipe diameter should be used. F Length The original length of the pile in feet/meters. (Excluding pile points on composite pile) F Pile Pt. Exp. Ln./Size The exposed length and size of pile point. F Hammer Type Make and model number of the hammer being used. Refer to accepted Pile Driving Equipment Data Form for this information. Verify that data in PDED Form matches hammer on the project.
Pile Driving Process

Pile Driving Process

PILE DRIVING LOG (PG 128)


F Serial No. manufacturers Serial No. shown on the pile

PILE DRIVING LOG (PG 128)


F Pile Cushion Type & Thickness Thickness in inches /

hammer. F Energy/Blow This value is the rated energy and is found on the PDED Form. F Operating Rate Manufacturers rated hammer speed in blows/minute. F Design Bearing design bearing required for the pile that is shown in the plans.
F Ultimate Bearing ultimate bearing required for the pile

F F F F F

that is shown in the plans.


F Driving Criteria Inspector can write down this

information or have a copy of the original pile driving criteria letter.


Pile Driving Process

millimeters and type of material being used. Check before driving begins and compare actual versus data on PDED Form. Common material is plywood. Req. Min Pen. Required minimum penetration below groundline or scourline. Actual Pen. Actual penetration below groundline or scourline. Start Time Time initial driving begins or driving resumes after interruptions. Stop Time Time driving stops or is interrupted. Template Elevation Elevation of the reference used to count blows/foot during driving. This reference must be a nonnon -moving point (stationary). Usually some part of the pile template can be used.
Pile Driving Process

PILE DRIVING LOG (PG 128)


F Water Elevation elevation of water at time of driving. F Final Elevation Steel tip elevation of steel tip at end of

PILE DRIVING LOG (PG 128)


F Pile Rebound amount of pile rebound if or greater F Min. Conc. Tip Elev. required minimum concrete tip

elevation.
F Min. Steel Tip Elev. required minimum steel tip

driving.
F Final Elevation Concrete Tip elevation of concrete tip at

elevation.
F Soil Type soil type from soil borings in plans or in

end of driving.
F Pile CutCut -off Elevation This elevation is shown on plans. F Original Ground Elev. Record original ground elevation

Special Provisions.
F Mark Ft./m pile length in increments used in feet or

at pile.
F PG Hose Length pressure gage hose length. F Pile CutCut -off length of concrete pile cut off.
Pile Driving Process

meters.
F Steel Tip/Conc. Tip Elev. actual steel tip and concrete

tip elevations.
F Blows number of blows required to move pile one foot

or one meter.
Pile Driving Process

PILE DRIVING LOG (PG 128)


PILE DRIVING LOG

F Stroke/Pressure stroke for open -end diesels or

F F F

air/steam hammers. For closed -end diesel hammers record the bounce chamber pressure. Remarks any information related to driving. i.e., pile rebound, pile cushion changes, pile cracking and spalling or any unusual problems. Stop and start times during driving should also be recorded in this space if driving is temporarily halted. Pile Fabricator name of prestress supplier. Date Pile Cast date the pile was cast. This date is etched into pile near driving head. Signature Signature of Inspector monitoring the pile driving. Print your name immediately below your signature.
Pile Driving Process

FILE NO.______________ DATE__________________ SHEET _____ OF _______ BENT NO._______PILE NO._______ PILE TYPE/SIZE ________________________ LENGTH (EXCL. PT.)____________ _ PILE PT. EXP. LN./SIZE ________________ HAMMER TYPE____________________ SERIAL NO.________________________ ENERGY/BLOW____________________ OPERATING RATE__________________ DESIGN BEARING__________________ ULTIMATE BEARING_______________ DRIVING CRITERIA_____________________________________________________ PILE CUSHION TYPE & THICKNESS______________________________________ REQD. MIN. PEN ._________________ ACTUAL PEN._______________________ START TIME_______________________ STOP TIME_________________________ TEMPLATE ELEV.__________________ WATER ELEV.______________________ FINAL ELEV. STEEL TIP__________ _ FINAL ELEV. CONC. TIP_____________ PILE CUT-OFF ELEVATION ________ _ ORIGINAL GROUND ELEV.___________ PG HOSE LENGTH ________PILE CUT-OFF__________ PILE REBOUND ________ MIN. CONC. TIP ELEV.______________ MIN. STEEL TIP ELEV. ______________ PG 130

Pile Driving Process

SOIL TYPE

MARK FT/m

STEEL TIP ELEV.

CONC. TIP ELEV.

BLOWS / FOOT

STROKE / PRESSURE

PILE DRIVING LOG CONTINUATION SHEET FILE NO.________________DATE__________________ SHEET ______ OF _______ BENT NO._______________PILE NO._______________ PILE TYPE______________ SOIL TYPE MARK FT/m STEEL TIP ELEV. CONC. TIP ELEV. BLOWS / FOOT STROKE / PRESSURE

REMARKS______________________________________________________________ ________________________________________________________________________ BOT. ELEV. PREDRILLED HOLE/JETTING _________________________________ PILE FABRICATOR_______________________ DATE PILE CAST______________
RECORDER _______________________________ SIGNATURE_______________________________

REMARKS_________________________________________________ ___________________________________________________________ ___________________________________________________________ RECORDER______________________SIGNATURE_______________ 131

Pile Driving Process

Pile Driving Process

FINAL PLANS PILE RECORD (PG 132)


< For P S C >
ENGLISH RAM WEIGHT ___________LBS.

P G LENGTH

Original Length (1)

Date

Bent NO. Footing

Pile NO. Type Pile

Size

Theoretic Design al Factor Bearing of Safety

Build-up Size Of Pay Reinf. Pile or Splice Pile Length of Point Length Points Pile Point

Total Length (1)

Length C.O. (1)

Net Length (1)

Pile Driving Process

Pile Driving Process

10

PILE RECORD ON FILE NO. ____________

GROUP NO. ___________

Elevation Of Tip Pay When Elev. Pile Elevation Length Ultimate Tip C. O. (1) Bearing (2) Value is Obtained

Pen. In Pen. Exposed Ground or Stroke or Blows Per Pile Pt. Bottom of Pressure Foot Length Footing (3)

From WEAP Analysis From PDA Analysis Est. Ultimate Estimated Actual Measured Est. Ult. Actual Bearing Hammer Factor of Hammer Bearing Bearing Value Efficiency Safety Efficiency Value Value <from chart>

Pile Driving Process

Pile Driving Process

FED. RD. DIV. NO.

STATE

FILE NO. ROUTE NO. SHEET NO 1

TOTAL SHEETS
NOTES: PAY LENGTH SHOULD INCLUDE ALLOWANCES FOR SPLICING STEEL PILES AND ANY OTHER AUTHORIZED ALLOWANCES. A SKETCH OF BENT OR FOOTING TO BE DRAWN ON THIS SHEET AND PILES TO BE NUMBERED, ALSO FLOW OF STREAM TO BE SHOWN. PENETRATION PER BLOW: GIVE THIS INFORMATION IN DECIMALS OF AN INCH. 1) CONCRETE LENGTH ON COMPOSITE PILE

Notes Concerning any Unusual Foundation Conditions

Bent NO. Footing Pile No.

Remarks

2) CONCRETE TIP ON COMPOSITE PILE 3) OR FRACTION OF A FOOT IF REFUSAL IS OBTAINED

Pile Driving Process

Pile Driving Process

COMPLETE THE PILE & DRIVING EQUIPMENT DATA FORM

NOTE: COMPLETE THE PILE REPORT AS SOON AS POSSIBLE AND SUBMIT A COPY TO THE GEOTECHNICAL SECTION OF THE BRIDGE DESIGN OFFICE IN COLUMBIA. THE ORIGINAL SHOULD BE SUBMITTED WITH THE FINAL PLANS FOR THE PROJECT.

PILE AND DRIVING EQUIPMENT DATA FILE NO._____________ COUNTY DESCRIPTION CONTRACTOR: PROJECT NO. __________________ ROUTE

Pile Driving Process

Pile Driving Process

11

PILE DRIVING LOG (INDEX PILE SAMPLE) FILE NO._21.963________ DATE_ 10-21-98_________ SHEET __1___ OF __1____ BENT NO._4___PILE NO._7 ____PILE TYPE/SIZE 18 Sq. Prestressed _____________ LENGTH (EXCL. PT .)_30 Concrete PILE PT. EXP. LENGTH/SIZE_10' _W8x58 HAMMER TYPE_Kobe K-25__________ SERIAL NO._ 10-2986________________ ENERGY/BLOW_41,325 Ft-Lbs._____ OPERATING RATE_UNK .____________ DESIGN BEARING_65 Tons__________ ULTIMATE BEARING_ 162.5 Tons_____ DRIVING CRITERIA_ 42 Blows/Ft. @ 7' Stroke________________________________ PILE CUSHION TYPE & THICKNESS_- Plywood @ 4" Thickness________________ REQD. MIN. PEN._10____________ ACTUAL PEN.__ 16.005 FT.______________ START TIME_ 8:50 am _______________ STOP TIME_ 9:35 am_________________ TEMPLATE ELEV._93.945__________ WATER ELEV._77.510_______________ FINAL ELEV. STEEL TIP_50.945_____ FINAL ELEV. CONC. TIP_60.945_______ PILE CUT-OFF ELEVATION 89.941___ ORIGINAL GROUND ELEV._76.95____ PG HOSE LENGTH N/A __PILE CUT-OFF_1.0 _____ PILE REBOUND __ 0 ______ MIN. CONC. TIP ELEV._66.0 _______ _ MIN. STEEL TIP ELEV. _56.0________ PG 133
Pile Driving Process

SOIL TYPE MARK STEEL TIP CONC. TIP BLOWS / FT/m ELEV. ELEV. FOOT Grey Silty 22 71.945 Sand 23 70.945 24 69.945 25 68.945 26 67.945 27 66.945 28 65.945 29 64.945 30 63.945 31 62.945 72.945 30 32 61.945 71.945 112 33 60.945 70.945 65 34 59.945 69.945 32 35 58.945 68.945 50 36 57.945 67.945 55
Pile Driving Process

STROKE / PRESSURE

4.50 5.25 5.50 5.75 5.75 5.75

SOIL TYPE MARK STEEL TIP CONC. BLOWS / FT/m ELEV. TIP ELEV. FOOT

STROKE/ PRESSURE

FINAL PLANS PILE DRIVING RECORD SAMPLE (PG 134)

37* 56.945 66.945 66 6.25 37.42** 56.525 66.525 72/.42' 6.25 38.42 55.525 65.525 130 6.25 39.525 54.525 64.525 122 6.5 40.525 53.525 63.525 76 6.5 41.525 52.525 62.525 88 6.5 42.525 51.525 61.525 137 6.75 43.105 50.945 60.945 150/.58' 7.25 REMARKS:_*Stopped _Driving_to_move_template. _**Ultimate Bearing first obtained. _Refusal obtained at Conc. Tip Elev. = 60.945'.________________ BOT. ELEV. PREDRILLED HOLE/JETTING _N/A____________________ PILE FABRICATOR-Standard Conc. Products DATE PILE CAST_10-15-98 RECORDER__John Q. Doe__SIGNATURE__________________________

ENGLISH

RAM WEIGHT __5510 LBS.

Date

Bent NO. Footing

Pile NO. Type Pile

Size

Theoretic Design al Factor Bearing of Safety

10/21/98

N/A

SPC

18"

65 TONS

2.5

Pile Driving Process

Pile Driving Process

< For P S C > Original Length (1) Build-up Size Of Pay Reinf. Pile or Splice Pile Length of Point Length Points Pile Point Total Length (1) Length C.O. (1) Net Length (1)

PILE RECORD ON FILE NO. 21.963

30.0'

W8X58

16.0'

NO

N/A

30.0'

1.0'

29.0'

Elevation Of Tip Pay When Elev. Pile Elevation Length Ultimate Tip C. O. (1) (2) Bearing Value is Obtained 89.94 30.0' 66.53' 60.95'

Pen. In Pen. Exposed Ground or Stroke or Blows Per Pile Pt. Bottom of Pressure Foot Length Footing (3)

16.0'

7.25'

10.0'

150/0.58'

Pile Driving Process

Pile Driving Process

12

GROUP NO. ________________

FED. RD. DIV. NO.

STATE

FILE NO. ROUTE NO. SHEET NO 1

TOTAL SHEETS

From WEAP Analysis From PDA Analysis Est. Ultimate Estimated Actual Measured Est. Ult. Actual Bearing Hammer Factor of Hammer Bearing Bearing Value Efficiency Safety Efficiency Value Value <from chart> UNK UNK UNK UNK UNK UNK

Notes Concerning any Unusual Foundation Conditions

Bent NO. Footing Pile No. 4 N/A


Pile Driving Process

Remarks Stopped driving at 37' mark to move template. Pile refusal obtained at Conc. Pile Tip Elev. = 60.945

Pile Driving Process

PILE DRIVING LOG HOMEWORK 1. Fill out the Pile Driving Log (page 136) provided for the following data. Most of the top portion of the log has been filled in for you, just complete the form including the table portion. The pile was marked off in one-foot increments from the toe (bottom) end of the concrete. The template elevation is 100.0. When the 20 mark on the pile is at the template elevation, the driving data for the next 3.5 feet is as follows: a. b. c. d. Hammer stroke of 4.5 for 25 blows in 1 in brown silt. Hammer stroke of 5.0 for 40 blows in 1 in medium dense silty sand. Hammer stroke of 6.0 for 60 blows in 1 in medium dense silty sand. Hammer stroke of 7.5 for 150 blows in 6 inches in dense silty sand PG 135

FINAL PLANS PILE DRIVING RECORD HOMEWORK 1. Use the information from the Pile Driving Log Problem above to fill out the Final Plans Pile Driving Record Sheet provided on page 132 in the manual.

Pile Driving Process

Pile Driving Process

PILE DRIVING LOG (HOMEWORK) FILE NO._55.555______ DATE__1-31-2000 _____ SHEET __1__ OF ___1___ BENT NO.__2___PILE NO.__ 3___PILE TYPE/SIZE 18 Square Prestressed ________ LENGTH (EXCL. PT.)_30 ______PILE PT. EXP. LN/SIZE 15 W8x58____________ HAMMER TYPE_Kobe K-25__________ SERIAL NO.__11-1111________________ ENERGY/BLOW__41,325 Ft-Lbs.____ OPERATING RATE__N/A _____________ DESIGN BEARING___70 Tons________ ULTIMATE BEARING_175 Tons_______ DRIVING CRITERIA__55 Blows/Ft. @ 7 Stroke_______________________________ PILE CUSHION TYPE & THICKNESS_- Plywood @ 4 Thickness________________ REQD. MIN. PEN._10_____________ ACTUAL PEN.__ ? ____________________ START TIME__8:45 am______________ STOP TIME___9:15___________________ TEMPLATE ELEV._100.0___________ WATER ELEV.__N/A_________________ FINAL ELEV. STEEL TIP__?_________ FINAL ELEV. CONC. TIP_?_____________ PILE CUT-OFF ELEVATION _105.0___ ORIGINAL GROUND ELEV._92.5______ PG HOSE LENGTH _N/A_____ PILE CUT-OFF_ ? ________ PILE REBOUND _1 ___ MIN. CONC. TIP ELEV.__75.0 _______ MIN. STEEL TIP ELEV. _60__________
PG 136
Pile Driving Process

SOIL TYPE

MARK FT/m

STEEL TIP ELEV.

CONC. TIP ELEV.

BLOWS / FOOT

STROKE / PRESSURE

REMARKS_________________________________________________ ___________________________________________________________ BOT. ELEV. PREDRILLED HOLE/JETTING _N/A________________ PILE FABRICATOR__ ABC Prestress__DATE PILE CAST_1-20-2000_ RECORDER _______________SIGNATURE_____________________
Pile Driving Process

13

Pile Driving Process - Recap Session


Segment has presented:
F INDEX PILING F PRODUCTION PILING F INSPECTORS DUTIES F PDA F DRIVING SEQUENCE F DETERMINING PILE TIP ELEVATION F PILE DRIVING LOG FORM

your questions?

END OF SESSION
Pile Driving Process

14

You might also like