PROJECT TITLE: CROWNE PLAZA MUTIARA KL REAR ENTRANCE RENOVATION COLUMN STRENGTHENING WORKS

Nature of Problem Circular RC column of 8.5m high was required to be enlarged due to misalignment of the column. The Solution The column was enlarged by formwork grouting with shrinkage com ensated high strength grout mi!ed with chi ing with additional reinforcement in accordance to the Consultant"s design.
Year 2005