This paper presents a case study of a retaining sys-
tem for a deep basement excavation in Kenny Hill Formation of Kuala Lumpur. The office building consists of 7 storeys and 4 levels of basement and is founded on a raft foundation. The depth of the basement excavation varied from 14 m to 17 m. Two sides of the excavation were adjacent to the existing buildings while the other sides were facing public roads. Owing to the variation in subsoil condition and cost consideration, a combined retaining system was adopted. The combined retaining system in- cluded tie back anchors, internal horizontal strutting and inclined-struts-and-berm systems to support the earth retaining walls consisting of contiguous bored piles of size 600 mm to 900 mm diameters. Figure 1. Borehore location and instrumentation layout plan. 2 DESCRIPTION OF PROJECT The site was originally a gently hilly terrain with re- duced levels vary from about RL88m to RL118m. The site had been flatten into platforms during the development of the adjacent properties by cut and fill. The level of the site was in the range of RL97m to RL100m after earthworks. Figure 1 shows the site layout and survey level of the site. Two rows of 4-storey shop offices are adjacent to the site at the western and northern sides.These shop lots are supported by pile foundation. The shop lots and the proposed building are divided by side lanes of about 8 m wide. The vacant land in between the shop lots at the north-western direction was being developed at the time of detailed design for the pro- posed building. The development consisted of single to two levels of basements. 3 GEOLOGICAL SETTING AND SUBSOIL CONDITIONS The site is underlain by metasedimentary residual soils of the Kenny Hill Formation and granitic rocks. The granitic rock boundary is about 0.6 km away, running in a north-west direction to the site. The Kenny Hill Formation belongs to Carboniferous Age, originally formed of interbedded sedimentary rocks, namely shale, mudstone and sandstone. During the intrusion of magma, in the process of forming granitic rock, these sedimentary rock were A basement excavation using tie back, internal horizontal strutting and inclined-struts-and-berm system C.S. Lim, S.M. Tan & L.C. Hiew SSP Geotechnics Sdn Bhd, Selangor, Malaysia ABSTRACT: This paper presents a scheme of a retaining system with a combination of tie back anchors, in- ternal horizontal strutting and inclined-struts-and-berm systems for the basement excavation of an office building located in Kuala Lumpur, Malaysia. The difficulties encountered in design and construction as well as the performances of the retaining system are presented. The subsoil was mainly residual soil of the Kenny Hill Formation. The building consists of 7 storeys and 4 levels of basement, supported by a raft foundation. The area of the excavation was about 3240 m 2 . The depth of the excavation varied from 14 m to 17 m below the existing ground level. The performance of the retaining systems has been monitored by instrumentation. metamorphosed to metasedimentary rocks namely phyllite and schist. The residual soils formed in-situ from the parent rock, mainly consist of sandy Silt/Clay. In between these materials are layers of clayey silty Sand and Gravel. A total of 34 exploratory boreholes were sunk over the adjacent development site in 1983. In line with the proposed office block, an additional soil in- vestigation consisting of 4 boreholes was conducted. The locations of the additional boreholes are shown in Figure 1. Figure 2 shows the soil profile obtained from the four boreholes. Stiff and medium dense overburden soil with SPT N values of 15 to 20 was found within the first 5 m in boreholes BHA1 and BHA2. Underlying the overburden soil was hard material having N value generally greater than 100. Hard material was ex- posed at ground surface for borehole BHA4. Pres- ence of backfill material was suspected in borehole BHA3 as the original ground level at this area was found to be around RL98m to RL90m. The exis- tence of some decayed wood at 11 m to 13 m deep in BHA3 substantiated this finding. The total thick- ness of backfill material including residual soil was about 13 m. Figure 2. Subsoil borehole profile. Quartzite and sandstone were encountered in boreholes BHA1 and BHA4 at 11 m and 15 m depth respectively. Rocks were not found in boreholes BHA2 and BHA3 within termination depth of 18 m. Based on the groundwater monitoring results, the recommended ground water levels used for design were minimum of RL90m and maximum of RL92.5m. The basement excavation level was RL84.0m. 4 CONTIGUOUS BORED PILE RETAINING WALL Contiguous bored piles (CBP) were designed as the permanent wall for the basement excavation. CBP is cost effective compared to other type of wall such as diaphragm wall and scant pile wall. The construction sequence was excavation in stages with the successively installation of ground anchor or propping system until the lowest level. The basement raft was then cast followed by others basement structure components. The layout plan of the proposed retaining system for the project is shown in Figure 3. Figure 3. Layout plan of retaining system. 4.1 Temporary anchor tie back system Ground anchors was provided for excavation sides that faced the roads and the shop offices at the West side as shown in Figure 3. For the excavation adja- cent to existing buildings, the horizontal length of ground anchor was limited to not more than 11.8 m to prevent hitting the foundation piles of the adjacent buildings. Four to five rows of anchors were in- stalled for excavation depths of 14 m to 16 m. 4.1.1 Removable Ground Anchors Since all ground anchors encroached into adjacent land, a non-conventional removable ground anchor system was used to facilitate the removal of anchors after completion of excavation. The details of the anchor system, namely non-explosive loop system, are shown in Figure 4. The difference between the loop system anchors and conventional anchors is that the entire length of the prestressed strand is not in contact with the grout column. The strands are separated with the grout column by poly-ethlene (PE) tube fill with grease for the purpose of removal. The load transfer of the anchor is not through the bonding between strands and the grout, but through a loading transfer body to the surrounding ground. The load is transferred from the tendon to the load- ing body, from which the load is transmitted to the surrounding by means of compressive action. With this system, high anchor retrieval rate was reported. Detailed load transfer mechanism and description of the non-explosive loop system ground anchors were reported elsewhere (Chua & Prasanthee 1997). Figure 4. Composition of temporary loop system anchor. 4.2 Internal diagonal strutting Taking advantage of the shape of the excavation, internal strutting was installed at the northern corner of the excavation as shown in Figure 3. Internal strutting was proposed due to the limited space be- tween the excavation and the adjacent building. In addition, the backfill material, as revealed in BHA3, could not provide sufficient anchorage for ground anchors with length limited by the existing building. The strutting consisted of four levels for the excava- tion depth of 14 m as shown in Figure 5a and 5b. 4.3 Inclined-struts-and-berm-system Inclined-struts-and-berm system was introduced where the space between the excavation and the ex- isting building was insufficient for ground anchors installation. Furthermore, the use of internal strut- ting was not suitable due to long distance to the op- posite wall. Three rows of inclined strutting were proposed. The site was first excavated with a temporary berm to foundation level for the construction of raft foun- dation. After completion of the raft foundation, the first row of inclined prop was installed followed by partial excavation at the earth berm for the installa- tion of the second level strutting. The last part of the earth was removed upon the installation of the low- est row props. Plate 1 shows the construction of in- clined-struts-and-bem-system. 5 THE PERFORMANCE OF THE RETAINING WALL SYSTEM An instrumentation scheme was proposed around the excavation to monitor movements and settlements of ground and adjacent buildings, deflection of the re- taining wall and variation of ground water table. The layout of the instrumentation is shown in Figure 1. Initial readings were taken before the ex- cavation work. Subsequently, readings were taken once a week during basement excavation. The excavation started in June 1997. The total volume of excavation was about 50,000m 3 . Raft slab was cast in October 1998. Figures 5a and 5b show the deflection of the wall as revealed from the incli- nometers I1 & I2 respectively. I1 and I3 represent the deflection of wall as braced by internal strutting system. Only I1 is pre- sented. At completion of basement structure, the maximum deflection behind the wall as revealed from I1 is about 103 mm at ground level and gradu- ally reduced to 4.5 mm at final excavation level. However, the excessive wall deflection in the top 2m was due to extra loading contributed by stock piling of construction material and traffic of construction trucks in the vicinity of inclinometer and thus not representative. The maximum deflection of the CBP wall should be about 60 mm at the ground surface. On the other hand, I2, represented the deflection of wall retained by anchor tie back system. It indi- cated deflection behind the wall of 13 mm at 2 m below ground level and 5 mm at final excavation level on completion of basement construction. The deflection of wall was remarkably reduced by the anchor tie back system as compared to the internal diagonal strutting system. This finding suggests that anchor tie back system, with the use of preloading, is more effective in preventing wall lateral movement compared to unpreloaded internal strutting system. The lateral movement of wall braced by inclined- struts-and-berm system is not available. Figure 5a. Lateral ground movement behind wall (I1). It is worth to note that, the movement behind wall notably increased from the date the excavation reached final level up to the day prior to the casting of raft slab although the construction activity was virtually stagnant at adjacent area. This suggests that the wall movement is time dependent. Figure 5b. Lateral ground movement behind wall (I2). The settlement profiles of the two sets of settle- ment markers are shown in Figures 6a to 6b. The comparison of ground settlement at all settlement markers revealed that the maximum settlement was about 2.8 mm at Marker S10. The settlement is neg- ligible as compared to deflection of walls. The set- tlement also suggested that the ground settlement due to lowering of ground water through the perme- able CBP wall was insignificant. Figure 6a. Settlement marker S4 to S6. Figure 7 presents the ground water variation as revealed from the water standpipe, namely P1, dur- ing the course of basement excavation. The water level was initially about 9.1 m below ground level and gradually reduced to 13.5 m when excavation depth reached 14.1 m. The level was 10.6 m at completion of basement construction. The compari- son between the excavation level and the ground water level suggested that the CBP wall was not ef- fective to maintain ground water level for the soil encountered at the site. However, since the soil was rather impermeable, the problem of ground water seepage was not serious and manageable without carrying out any grouting treatment to the CBP walls. The water level at water standpipe was some 0.5 m above the final excavation level. The water level started to raise after the raft slab had been cast. The raise in ground water level was assisted by casting of skin wall on the CBP wall which made the wall wa- ter tight. The water level after casting of the skin wall of the lowest level of the basement was about 9.7 m below the ground level which was about the same level as the top of skin wall. However, ground water table again reduced to a steady water table of about 11.0 m below ground level few weeks after casting of skin wall. This phenomenon may due to the flow of ground water into the adjacent wall at which raft slab or skin wall had not been con- structed. Figure 6b. Settlement marker S7 to S10. Figure 7. Ground water variation from P1. -16.000 -14.000 -12.000 -10.000 -8.000 -6.000 -4.000 -2.000 0.000 5 - J u n - 9 7 1 2 - J u n - 9 7 1 9 - J u n - 9 7 2 6 - J u n - 9 7 3 - J u l- 9 7 1 0 - J u l- 9 7 1 7 - J u l- 9 7 2 4 - J u l- 9 7 3 1 - J u l- 9 7 7 - A u g - 9 7 1 4 - A u g - 9 7 2 1 - A u g - 9 7 2 8 - A u g - 9 7 4 - S e p - 9 7 1 1 - S e p - 9 7 1 8 - S e p - 9 7 2 5 - S e p - 9 7 2 - O c t - 9 7 9 - O c t - 9 7 1 6 - O c t - 9 7 2 3 - O c t - 9 7 3 0 - O c t - 9 7 6 - N o v - 9 7 1 3 - N o v - 9 7 2 0 - N o v - 9 7 2 7 - N o v - 9 7 4 - D e c - 9 7 1 1 - D e c - 9 7 1 8 - D e c - 9 7 2 5 - D e c - 9 7 1 - J a n - 9 8 8 - J a n - 9 8 1 5 - J a n - 9 8 2 2 - J a n - 9 8 2 9 - J a n - 9 8 5 - F e b - 9 8 1 2 - F e b - 9 8 1 9 - F e b - 9 8 2 6 - F e b - 9 8 5 - M a r - 9 8 1 2 - M a r - 9 8 1 9 - M a r - 9 8 2 6 - M a r - 9 8 2 - A p r - 9 8 9 - A p r - 9 8 1 6 - A p r - 9 8 Date D e p t h
B e l o w
G r o u n d
L e v e l
( m ) P1 Excavation Level Casting of Skin Wall at 4th basement To 9.3 mbgl Casting Of Raft Slab -3.00 -2.50 -2.00 -1.50 -1.00 -0.50 0.00 0 5 10 15 20 25 30 35 40 45 50 Distance From Wall (m) S e t t le m e n t ( m m ) 09/04/1997 11/05/1997 26/11/1997 12/09/1997 30/12/1997 27/1/1998 17/03/1998 (Completion of Basement) S4 S5 S6 -3.00 -2.50 -2.00 -1.50 -1.00 -0.50 0.00 0 5 10 15 20 25 30 35 40 45 50 Distance From Wall (m) S e t t le m e n t ( m )
09/04/97 11/05/97 26/11/1997 12/09/97 30/12/1997 27/1/1998 17/03/1998 (Completion of Basement) S7 S9 S8 S10 6 CONCLUSIONS In view of the site constraints, a scheme of a com- bined retaining system, consisting of contiguous bored pile walls braced by a combination of tie back anchors, internal diagonal strutting and inclined- struts-and-berm system, was presented for the 14 m to 16 m deep basement excavation in Kenny Hill formation of Kuala Lumpur. The performance of the retaining system was sat- isfactory as confirmed by the ground settlement be- hind the wall during basement excavation. Only negligible settlement of a few mm was observed. The deflection of the wall as revealed from incli- nometers suggests that tie back system by means of pre-stressed anchors has been effective in reducing lateral wall movement. During basement excavation, the ground water level behind the wall was drawn down to about 0.5m above the corresponding excavation level for that stage. This is probably due to the flow of ground water into basement during excavation. This shows that CBP wall is not water tight. As the adjacent buildings are supported by piles and the subsoil is relatively strong in most part of the site, ground settlement was negligible even though the ground water table was lowered during excavation. Plate1. The construction of the inclined strutting REFERENCES Chua T.S. & Prasanthee R. 1997. Performance of temporary removable U-Turn ground anchors in Singapore, Proceed- ings of 3YGEC, Singapore. CIRIA report 104. 1984. Design of retaining walls embedded in stiff clay. London, United Kingdom. Geotechnical control office publication No. 1/90. 1991. Review of design methods for excavation. Hong Kong. L&M Geotechnic Sdn Bhd. 1997. Technical report on design and analysis of retaining wall system for development of 7- storey building of Damansara Height, Kuala Lumpur. SSP Geotechnics Sdn Bhd 1996. Geotechnical design report for development of 7-storey building at Damansara Height, Kuala Lumpur.