TERMITE PROOFING

TERMITE PROOFING (TRENCHES) SFT 976.20


HEPTACHLORE LTS 7.81
Lean Concrete (1:4:8) Ravi Sand & B.Ballast
Lean Concrete (1:4:8) Ravi Sand & B.Ballast CFT 100.00
CEMENT OPC BAGS 9.48
SAND RAVI CFT 47.38
BRICK BALLAST CFT 94.77
Lean Concrete (1:2:4) Ravi Sand & B.Ballast CFT 100.00
CEMENT OPC BAGS 17.60
SAND RAVI CFT 44.00
BRICK BALLAST CFT 88.00
Damp proof Course.
2" Horizontal D.P.C. (1:2:4) SFT 100.00
CEMENT OPC BAGS 2.94
SAND RAVI CFT 7.35
AGGREGATE CFT 14.70
BITUMEN KG 20.42
KEROSENE OIL LTRS 15.00
Polythene Sheet 1.13
VERTICAL D.P.C SFT 100.00
CEMENT OPC BAGS 1.56
SAND RAVI CFT 5.86
BITUMEN KG 20.42
KEROSENE OIL LTRS 15.00
WASTE WOOD Kgs 20.42
BRICK WORK IN SUB STRUCTURE ( G.Floor )
13 1/2" thick (1:6) CFT 100.00
CEMENT OPC BAGS 3.43
SAND RAVI CFT 25.71
BRICKS IST CLASS THOU 1.35
R.C.C (1:2:4) using chenab sand crush.
Footing CFT 100.00
CEMENT OPC BAGS 17.60
SAND CHENAB CFT 44.00
AGGREGATE CFT 88.00
Steel Kg 272.23
2 Masonary up to slab level ( G.Floor ) 15%
BRICK WORK IN SUPER STRUCTURE
9" & 13 1/2" thick (1:6) (G.F) CFT 100.00
CEMENT OPC BAGS 4.00
SAND RAVI CFT 25.00
BRICKS IST CLASS THOU 1.35