Item DESCRIPCION Parcial (S/.) 18 Oct - 31 Oct Nov Dic Ene Feb Mar Abr May
ESTRUCTURAS
1 OBRAS PROVISIONALES 10,214.27 10,214.27
3 TRABAJOS PRELIMINARES 29,255.94 13,739.12 15,516.82
5 MOVIMIENTO DE TIERRAS -
5.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 6,191.98 6,191.98
5.02 MODULO 02: COCINA Y COMEDOR 4,166.70 4,166.70
5.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 13,867.64 4,057.70 9,809.94
5.04 MODULO 04: BIBLIOTECA 6,669.90 6,669.90
5.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 13,867.64 13,867.64
5.06 MODULO 06: SS.HH. VARONES Y MUJERES 2,917.34 2,917.34
5.07 ESCALERAS: 02 UNIDADES 3,242.64 3,242.64
5.08 CERCO PERIMETRICO 4,229.03 2,600.12 1,628.91
5.09 MURO DE CONTENCION 45,580.65 45,580.65
5.1 GRADERIAS 610.86 610.86
5.11 VEREDAS Y LOSAS 43,837.77 29,903.22 13,934.55
7 CONCRETO SIMPLE -
7.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 9,293.44 7,050.58 2,242.86
7.02 MODULO 02: COCINA Y COMEDOR 5,493.49 2,624.94 2,868.55
7.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 15,322.50 6,305.10 9,017.40
7.04 MODULO 04: BIBLIOTECA 7,288.56 7,288.56
7.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 15,321.45 1,315.15 14,006.30
7.06 MODULO 06: SS.HH. VARONES Y MUJERES 4,654.29 3,753.26 901.03
7.07 ESCALERAS: 02 UNIDADES 6,598.06 6,598.06
7.08 CERCO PERIMETRICO 6,143.81 5,183.84 959.97
7.09 MURO DE CONTENCION 9,534.96 1,191.87 8,343.09
7.1 GRADERIAS 820.08 820.08
7.11 VEREDAS Y LOSAS 41,247.91 11,999.09 29,248.82
9 CONCRETO ARMADO -
9.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 48,088.54 39,053.24 9,035.30
9.02 MODULO 02: COCINA Y COMEDOR 27,764.91 21,421.65 6,343.26
9.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 147,741.74 38,625.35 74,150.70 34,965.69
9.04 MODULO 04: BIBLIOTECA 48,886.65 1,729.65 42,964.66 4,192.34
9.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 147,742.74 24,213.29 96,299.88 27,229.57
9.06 MODULO 06: SS.HH. VARONES Y MUJERES 15,602.85 13,310.81 2,292.04
9.07 ESCALERAS: 02 UNIDADES 43,233.69 15,019.18 28,214.51
9.08 CERCO PERIMETRICO 60,140.03 42,406.05 17,733.98
009.08.04 MURO DE CONTENCION 387,690.37 384,651.50 3,038.87
009.08.05 GRADERIAS 16,153.41 2,610.50 13,542.91
11 ESTRUCTURAS DE MADERA -
11.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 5,750.08 5,750.08
11.02 MODULO 02: COCINA Y COMEDOR 3,421.26 3,421.26
11.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 5,895.01 5,895.01
11.04 MODULO 04: BIBLIOTECA 5,184.66 5,184.66
11.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 5,895.01 5,895.01
11.06 MODULO 06: SS.HH. VARONES Y MUJERES 6,102.05 6,102.05
13 JUNTAS -
CRONOGRAMA VALORIZADO
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Item DESCRIPCION Parcial (S/.) 18 Oct - 31 Oct Nov Dic Ene Feb Mar Abr May
13.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 121.20 71.96 49.24
13.02 MODULO 02: COCINA Y COMEDOR 70.89 42.09 28.8
13.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 280.14 280.14
13.04 MODULO 04: BIBLIOTECA 96.05 96.05
13.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 280.14 280.14
13.06 CERCO PERIMETRICO 121.20 24.24 96.96
13.07 VEREDAS Y LOSAS 1,861.07 1,861.07
ARQUITECTURA -
15 ALBAILERIA -
15.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 9,744.26 9,744.26
15.02 MODULO 02: COCINA Y COMEDOR 5,718.60 5,718.60
15.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 22,076.28 9,205.35 12,870.93
15.04 MODULO 04: BIBLIOTECA 6,408.78 6,408.78
15.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 22,076.28 15,255.15 6,821.13
15.06 MODULO 06: SS.HH. VARONES Y MUJERES 7,451.59 7,451.59
15.07 ESCALERAS: 02 UNIDADES 10,987.63 2,295.81 8,691.82
15.08 CERCO PERIMETRICO -
17 REVOQUES ENLUCIDOS Y MOLDURAS 94,834.16 14,655.97 17,354.02 37,447.23 25,376.94
17.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 7,482.52 1,784.18 5,698.34
17.02 MODULO 02: COCINA Y COMEDOR 3,982.56 1,712.27 2,270.29
17.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 17,940.88 15,446.59 2,494.29
17.04 MODULO 04: BIBLIOTECA 6,193.55 5,697.94 495.61
17.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 20,311.69 18,724.42 1,587.27
17.06 MODULO 06: SS.HH. VARONES Y MUJERES 7,110.77 5,461.59 1,649.18
17.07 ESCALERAS: 02 UNIDADES 7,240.60 7,240.60
17.08 CERCO PERIMETRICO 24,571.59 3,276.21 21,295.38
19 CIELORRASOS Y ALEROS -
19.01 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 6,387.65 6,387.65
19.02 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 6,404.21 6,404.21
19.03 ESCALERAS: 02 UNIDADES 502.03 502.03
21 PISOS Y PAVIMENTOS -
21.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 2,479.26 2,479.26
21.02 MODULO 02: COCINA Y COMEDOR 1,626.18 1,626.18
21.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 10,220.30 10,220.30
21.04 MODULO 04: BIBLIOTECA 3,431.91 3,431.91
21.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 10,220.30 10,220.30
21.06 MODULO 06: SS.HH. VARONES Y MUJERES 1,078.18 1,078.18
21.07 ESCALERAS: 02 UNIDADES 358.11 358.11
23 ZOCALOS Y CONTRAZOCALOS -
23.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 1,491.19 1,491.19
23.02 MODULO 02: COCINA Y COMEDOR 878.73 878.73
23.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 3,687.97 1,438.82 2,249.15
23.04 MODULO 04: BIBLIOTECA 1,385.89 1,385.89
23.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 3,687.97 1,438.82 2,249.15
23.06 MODULO 06: SS.HH. VARONES Y MUJERES 1,228.38 1,228.38
CRONOGRAMA VALORIZADO
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Item DESCRIPCION Parcial (S/.) 18 Oct - 31 Oct Nov Dic Ene Feb Mar Abr May
23.07 ESCALERAS: 02 UNIDADES 734.84 734.84
23.08 CERCO PERIMETRICO 7,409.81 7,409.81
25 CARPINTERIA DE MADERA -
25.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 7,202.53 7,202.53
25.02 MODULO 02: COCINA Y COMEDOR 4,503.26 4,503.26
25.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 15,824.86 15,824.86
25.04 MODULO 04: BIBLIOTECA 5,455.50 5,455.50
25.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 15,824.86 15,824.86
25.06 MODULO 06: SS.HH. VARONES Y MUJERES 2,573.93 2,573.93
25.07 ESCALERAS: 02 UNIDADES 1,470.35 1,400.33 70.02
27 CARPINTERIA METALICA -
27.01 ESCALERAS: 02 UNIDADES 4,005.75 4,005.75
27.02 CERCO PERIMETRICO 5,293.61 5,293.61
29 CERRAJERIA -
29.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 655.15 289.92 365.23
29.02 MODULO 02: COCINA Y COMEDOR 402.21 402.21
29.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 788.43 788.43
29.04 MODULO 04: BIBLIOTECA 374.89 374.89
29.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 788.43 788.43
29.06 MODULO 06: SS.HH. VARONES Y MUJERES 476.15 476.15
29.07 ESCALERAS: 02 UNIDADES 200.38 200.38
31 COBERTURA -
31.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 17,986.26 17,986.26
31.02 MODULO 02: COCINA Y COMEDOR 9,560.81 9,560.81
31.06 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 30,291.85 27,603.41 2,688.44
31.1 MODULO 04: BIBLIOTECA 17,085.11 1,468.86 15,616.25
31.14 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 30,290.67 14,588.77 15,701.90
31.18 MODULO 06: SS.HH. VARONES Y MUJERES 7,045.19 773.53 6,271.66
33 FALSO CIELORRASO -
33.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 6,116.21 6,116.21
33.02 MODULO 02: COCINA Y COMEDOR 3,681.27 3,681.27
33.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 12,809.11 12,809.11
33.04 MODULO 04: BIBLIOTECA 7,304.83 7,304.83
33.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 12,809.11 12,809.11
33.06 MODULO 06: SS.HH. VARONES Y MUJERES 2,540.53 2,540.53
35 VIDRIOS, CRISTALES Y SIMILARES -
35.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 1,094.49 1,094.49
35.02 MODULO 02: COCINA Y COMEDOR 790.25 790.25
35.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 3,317.67 3,317.67
35.04 MODULO 04: BIBLIOTECA 1,114.68 1,114.68
35.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 3,317.67 3,317.67
35.06 MODULO 06: SS.HH. VARONES Y MUJERES 101.81 101.81
35.07 ESCALERAS: 02 UNIDADES 120.88 120.88
37 PINTURA -
37.01 MODULO 01: ALMACEN - DIRECCION Y SALA DE PROFESORES 3,617.10 3,617.10
CRONOGRAMA VALORIZADO
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Item DESCRIPCION Parcial (S/.) 18 Oct - 31 Oct Nov Dic Ene Feb Mar Abr May
37.02 MODULO 02: COCINA Y COMEDOR 2,044.57 1,720.46 324.11
37.03 MODULO 03: 3 AULAS 1 PISO - 3 AULAS 2 PISO 9,487.16 6,867.10 2,620.06
37.04 MODULO 04: BIBLIOTECA 3,852.76 3,852.76
37.05 MODULO 05: LABORATORIO, 2 AULAS 1 PISO - 3 AULAS 2 PISO 9,487.16 6,415.14 3,072.02
37.06 MODULO 06: SS.HH. VARONES Y MUJERES 1,805.63 1,805.63
37.07 ESCALERAS: 02 UNIDADES 1,402.25 1,402.25
37.08 CERCO PERIMETRICO 9,087.20 2,906.64 6,180.56
39 MOBILIARIO ESCOLAR 56,666.21 56,666.21
41 EQUIPAMIENTO DEPORTIVO Y JARDINERIA 4,201.68 4,201.68
43 FLETE DE MATERIALES 121,189.87 8,281.31 19,794.35 20,299.30 19,794.35 18,986.41 20,299.30 13,734.85
INSTALACIONES ELECTRICAS -
45 ACOMETIDA 10,597.16 231.27 10,365.89
47 INSTALACIONES ELECTRICAS INTERIORES 40,276.00 4,515.88 18,944.71 16,012.48 802.93
49 INSTALACIONES ELECTRICAS EXTERIORES 13,162.78 13,162.78
INSTALACIONES SANITARIAS -
51 RED EXTERIOR 52,781.74 52,781.74
53 RED INTERIOR 4,367.97 1,260.49 2,578.75 528.73
55 APARATOS Y ACCESORIOS SANITARIOS 6,558.37 3,925.68 2,632.69
COSTO DIRECTO 2,205,643.55 36,292.40 188,277.77 689,343.11 427,573.72 307,645.20 248,303.42 228,409.38 79,798.55
GASTOS GENERALES + UTILIDAD (18%)
SUB_TOTAL
IGV (18%)
TOTAL_PRESUPUESTO
AVANZE MENSUAL 100.00% 1.65% 8.54% 31.25% 19.39% 13.95% 11.26% 10.36% 3.62%
AVANZE ACUMULADO 1.65% 10.18% 41.44% 60.82% 74.77% 86.03% 96.38% 100.00%
CRONOGRAMA DE ADQUISICION DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7 mes 8
MATERIALES
ALAMBRE NEGRO RECOCIDO # 16 kg 2,969.64 3.36 9977.96 43.53 150.38 5,086.71 3,849.30 848.04
ALAMBRE NEGRO RECOCIDO # 8 kg 851.34 3.36 2859.98 1.34 149.94 1,290.67 1,203.75 214.28
CLAVOS PARA MADERA CON CABEZA DE 3" kg 122.80 3.54 435.14 416.45 18.69
CLAVOS PARA MADERA C/C PARA MADERA (PROMEDIO) kg 71.54 3.36 240.37 20.16 219.62 0.59
CLAVOS C/C PARA MADERA (PROMEDIO) kg 911.01 3.36 3062.15 1.68 92.27 497.6 1,073.67 561.27 153.52 536.61 145.53
CLAVOS PARA CEMENTO DE ACERO CON CABEZA DE 3/4" kg 11.21 3.52 39.43 24.03 15.4
ARANDELA PLANA 3/8" und 884.00 0.95 839.8 296.4 247 296.4
ARANDELA PLANA 1/2" pza 700.00 0.90 623.3 194.4 191.3 237.6
PERNOS DE 3/8" X 3" pza 132.00 1.68 221.76 221.76
PERNO AUTOROSCANTE 3/8" X 2" u 67.36 1.85 110.05 43.98 22.09 43.98
PERNOS 3/4" X 6 1/2" pza 2,278.00 2.84 6469.52 2,283.36 1,902.80 2,283.36
PERNOS 1/2" X 5" pza 371.01 3.41 1265.12 379.44 402.58 483.1
PERNOS AUTORROSCANTE 3/8" X 2" u 5,923.52 0.84 4975.76 87.7 2,240.78 1,588.37 1,058.91
PORTON METALICO 3.00X3.00m INC. CHAPA CANDADO ALDABAS Y PINTURA glb 1.00 3,361.34 3361.34 3,361.34
PUERTA METALICA 0.90X2.10m INC. CHAPA Y PINTURA glb 1.00 1,260.00 1260 1,260.00
GRAPAS METALICAS DE 1/16" u 34.00 4.85 164.9 58.2 48.5 58.2
ASTA DE BANDERA SEGUJN DETALLE. INC INSTALACION Y PINTURA glb 1.00 672.27 672.27 672.27
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 55,849.07 3.80 212226.38 647.28 98,121.30 92,933.20 20,524.60
ACERO CORRUGADO 3/8" kg 7,363.57 3.80 27981.49 2,992.29 24,989.20
ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 124.98 3.80 474.92 136.19 130.11 208.62
ARENA FINA m3 96.25 72.77 7005.17 20.96 749.69 1,357.76 1,953.84 2,922.92
TIERRA DE CHACRA O VEGETAL m3 9.80 32.80 321.44 109.06 120.54 45.92 45.92
PIEDRA CHANCADA DE 3/4" m3 179.84 140.00 25178.04 22,910.70 2,267.34
PIEDRA GRANDE DE 8" m3 61.50 52.06 3201.43 1,331.24 1,723.93 146.26
PIEDRA MEDIANA DE 4" m3 17.95 52.06 934.61 14.58 241.73 553.36 124.94
AFIRMADO m3 184.10 30.00 5523.07 421.45 5,008.99 92.63
ARENA GRUESA m3 517.93 72.77 37689.59 19.21 15,675.20 11,258.60 6,030.49 3,404.45 1,301.64
PIEDRA ZARANDEADA DE 3/4" m3 100.58 89.07 8959.19 993.55 4,315.05 1,111.99 2,538.60
PIEDRA ZARANDEADA DE 1/2" m3 395.74 89.07 35248.75 15,283.90 11,516.90 6,658.87 1,783.74 5.34
ADQUISICION DE PLANTAS PARA JARDINERIA PUESTA EN OBRA glb 1.00 840.34 840.34 840.34
CABLE TW # 14 AWG 2.5 mm2 m 1,056.00 1.27 1341.05 177.8 652.65 510.6
CABLE TW # 12 AWG - 4 mm2 m 74.40 1.65 122.77 31.68 55.28 35.81
CABLE TW # 2 AWG - 25 mm2 m 35.00 8.04 281.41 95.48 105.53 40.2 40.2
GANCHO GALVANIZADO DE 140 mm u 1,265.77 1.24 1569.56 24.49 659.34 664.3 221.43
INODORO TANQUE BAJO NORMAL BLANCO INCLUYE ACCESORIOS u 10.00 168.53 1685.3 1,685.30
LAVATORIO SONNET BLANCO COMERCIAL pza 10.00 92.02 920.21 345.08 575.13
PAPELERA CON EJE 15 X 15 cm BLANCA u 10.00 9.22 92.2 92.2
LLAVE PARA LAVATORIO CROMADA 1/2" u 10.00 20.03 200.3 75.11 125.19
LLAVE LAVADERO CROMADA CON PICO GIRATORIO pza 8.00 22.03 176.24 176.24
ACCESORIO COMPLETO BRONCE TANQUE BAJO u 10.00 25.00 250 250
TAPON DE JEBE PARA TIRAFON u 899.40 0.80 719.52 48.15 373.29 298.08
REGISTRO DE BRONCE DE 4" u 5.00 9.50 47.5 47.5
GRIFO DE RIEGO 1/2" u 3.00 12.61 37.83 12.61 25.22
ARTEFACTO DE ALUMBRADO EXTERIOR TIPO FAROLA DE 250 W u 20.00 168.61 3372.2 3,372.20
FLUORESCENTE CIRCULAR 32 W u 27.00 25.16 679.32 478.04 50.32 150.96
TABLERO DE DISTRIBUCION DE 4 CIRCUITOS u 6.00 25.40 152.41 50.8 60.33 41.28
TABLERO GABINETE METAL BARRA BRONCE 12 POLOS pza 1.00 63.03 63.03 63.03
TOMACORRIENTE BIPOLAR DOBLE + TOMA TIERRA u 62.00 10.92 677.04 174.72 304.85 197.47
INTERRUPTOR TERMOMAGNETICO DE 2 X 15A u 14.00 25.21 352.94 176.47 173.32 3.15
INTERRUPTOR TERMOMAGNETICO DE 2 X 20A u 8.00 36.15 289.2 31.63 112.97 144.6
INTERRUPTOR DE BAKELITA u 1,125.00 8.40 9450 1,209.60 4,611.60 3,628.80
CAJA RECTANGULAR GALVANIZADA LIVIANA DE 4" X 2 1/8" u 124.50 1.31 163.1 31.44 76.53 55.13
CAJA DE PASO ALIMENTADORES 100 mm X 100 mm u 20.00 10.08 201.6 201.6
CAJA OCTOGONAL GALVANIZADA LIVIANA 4" X 2 1/8 " u 140.53 1.21 170 24.2 82.25 63.55
CAJA DE PASO ALIMENTADOR 100 mm X 150 mm u 8.00 15.73 125.84 29.49 33.43 31.46 31.46
FLUORESCENTE RECTO ISPE 2X40 W C/EQ + PANTALLA u 56.00 94.39 5285.84 2,265.36 3,020.48
DURACION: 210 DIAS CALENDARIOS
pag. 6 de 12
CRONOGRAMA DE ADQUISICION DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7 mes 8
DURACION: 210 DIAS CALENDARIOS
FLUORESCENTE RECTO ISPE 2X20 W C/EQ + PANTALLA u 42.00 40.90 1717.8 899.8 736.2 81.8
INTERRUPTOR TERMOMAGNETICO MONOFASICA 2 X 30 A und 8.00 50.61 404.88 50.61 50.61 101.22 202.44
INTERRUPTOR TERMOMAGNETICO MONOFASICA 2 X 280A pza 1.00 126.05 126.05 126.05
INTERRUPTOR TERMOMAGNETICO MONOFASICA 2 X 75 A pza 4.00 80.03 320.12 80.03 80.03 160.06
ASFALTO RC-250 gal 55.03 9.47 520.98 520.98
LADRILLO KING KONG DE ARCILLA 9 X 14 X 24 cm u 456.00 0.76 346.56 346.56
LADRILLO KK DE ARCILLA 9 X 14 X 24 cm u 81,425.36 0.76 61883.12 16,560.50 19,720.30 24,010.80 1,591.52
LADRILLO PARA TECHO 15 X 30 X 30 cm 8 HUECOS REX u 107.10 2.10 224.91 224.91
LADRILLO PARA TECHO 15 X 30 X 30 cm 8 HUECOS u 3,563.70 2.10 7483.77 701.6 6,782.17
CUMBRERA INFERIOR TEJA ANDINA und 217.35 11.76 2556.09 171.05 1,326.11 1,058.93
CUMBRERA SUPERIOR TEJA ANDINA pza 217.35 11.76 2556.09 171.05 1,326.11 1,058.93
CABLE NYY 2 - 1 X 150 mm2 m 11.03 102.24 1127.2 1,127.20
CABLE NYY 2 - 1 X 25 mm2 m 105.53 21.08 2224.47 2,224.47
CABLE NYY 2 - 1 X 6 mm2 m 502.02 4.11 2063.22 1,237.11 826.11
CEMENTO PORTLAND TIPO I (42.5 kg) bls 10,861.21 17.48 189853.06 262.2 6,726.66 85,251.30 47,417.60 24,815.10 13,509.00 11,871.20
TAPA DE CONCRETO DE D=0.50M X 0.10M u 7.00 42.02 294.14 99.8 110.3 42.02 42.02
MAYOLICA 20 X 20 cm COLOR m2 34.46 21.00 723.66 723.66
MAYOLICA 20 X 30 cm COLOR m2 6.18 21.00 129.78 129.78
CERRADURA EXTERIOR DE DOS GOLPES u 23.00 58.98 1356.54 412.86 235.92 707.76
CERROJO DE 3" ALUMINIZADO pza 6.00 3.37 20.22 20.22
BISAGRA BRONCEADA CAPUCHINA # 555 1 1/2" X 1 1/2" u 22.00 5.04 110.88 110.88
JALADOR DE PERILLA u 33.00 2.21 72.93 72.93
BISAGRA CAPUCHINA PLOMA 2 1/2" X 2 1/2" u 24.00 3.37 80.88 80.88
BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" par 112.00 9.24 888.7 416.63 28.55 443.52
CERRADURA DE PERILLA pza 5.00 23.66 118.3 23.66 94.64
YESO DE 28 Kg bls 85.82 7.73 661.68 312.46 349.22
VARILLA DE COBRE 5/8" X 2.50 m und 7.00 42.98 300.86 102.08 112.82 42.98 42.98
OCRE ROJO kg 330.82 9.23 3053.41 930.09 2,123.32
FRAGUA kg 20.66 7.19 148.55 18.41 130.14
SOLDADURA CELLOCORD 1/8" kg 0.31 11.76 3.61 3.61
GIGANTOGRAFIA und 2.00 300.00 600 600
ARCOS DE FG 2" INC/TABLERO BASQUET Y PINTURA glb 2.00 1,260.50 2521 2,521.00
POSTES DE FGDE 3.50M und 20.00 98.04 1960.8 1,960.80
SELLADOR gal 54.27 15.13 822.71 30.58 470.81 321.32
FIBROCEMENTO DE 1.20 X 2.40 X 4MM m2 1,097.62 7.29 8001.1 3,471.32 4,529.78
LAVADERO ACERO INOXIDABLE 19"X37" CON ESC. P. SAT.CON ACCES. u 4.00 105.67 422.68 422.68
PEGAMENTO PARA PVC AGUA FORDUIT gal 2.16 18.02 39.04 3.08 1.17 12.37 22.42
SILICONA u 3.00 12.64 37.92 37.92
PEGAMENTO PARA PVC 1/4 gl u 4.57 18.02 82.35 6.67 3.6 18.58 53.5
CINTA TEFLON u 12.90 1.00 12.91 0.75 6.88 5.28
SOLDADURA ELECT. MONOF. ALTERNA 225 AMP hm 39.29 8.40 330.07 88.7 94.08 147.29
FLETE TRANSPORTE LOCAL kg 77,518.84 2.50 193796.8 178,376.00 15,420.80
FLETE TERRESTRE glb 1.00 121,189.87 121189.71 8,281.31 19,794.30 20,299.30 19,794.30 18,986.40 20,299.30 13,734.80
HORMIGON m3 344.32 44.88 15453.17 75.85 5,097.76 9,641.44 229.26 408.86
COLA SINTETICA FULLER gal 53.99 14.63 789.8 318.29 1.39 452.1 18.02
LIJA PARA MADERA u 726.64 1.30 944.64 114.69 9.69 347.88 472.38
TEKNOPOR DE 1" X 4' X 8' pln 13.86 14.00 194.04 41.27 15.33 118.04 19.4
LIJA N 80 u 624.01 1.30 811.2 29.99 457.32 323.89
AGUA m3 323.78 1.50 483.83 1.69 112.58 182.8 89.41 45.39 25.78 26.18
ESTERA DE 2.00 X 3.00 m u 77.74 9.03 701.98 701.98
OFICINA glb 1.00 1,000.00 1000 1,000.00
ALMACEN Y/O DEPOSITO glb 1.00 800.00 800 800
GUARDIANIA glb 1.00 400.00 400 400
BAO PORTATIL (ALQUILER) INC. MANTENIMIENTO mes 1.00 500.00 500 500
TRANSPORTE DE EQUIPO Y HERRAMIENTAS glb 1.00 3,361.34 3361.34 3,361.34
FIERRO DE D=1/2 kg 33.17 2.55 84.51 84.51
FIERRO LISO DE D=1/2 kg 45.02 2.94 132.36 40.38 41.81 50.17
MADERA TORNILLO p2 416.16 4.85 2018.34 1,229.93 788.41
pag. 7 de 12
CRONOGRAMA DE ADQUISICION DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7 mes 8
DURACION: 210 DIAS CALENDARIOS
REGLA DE MADERA p2 333.10 1.50 499.65 12.97 486.68
MADERA TORNILLO CEPILLADA p2 5,933.31 4.39 26047.03 1,553.80 1,294.83 1,553.80 21,644.60
MADERA DE TORNILLO CEPILLADA p2 13,186.26 4.39 57887.24 1,917.64 24,902.20 12,059.40 19,008.00
MADERA DE CEDRO PARA CARPINTERIA p2 4,124.96 6.34 26152.15 10,296.20 30.05 15,825.90
MADERA PINO PARA ANDAMIOS p2 749.80 1.50 1124.69 149.96 974.73
MADERA PINO (REGLAS) p2 120.70 3.50 420.06 63.55 79.57 160.18 116.76
ANDAMIO DE MADERA p2 3,194.50 1.50 4791.75 956.35 1,195.41 2,016.76 623.23
MADERA EUCALIPTO ROLLIZO (p2) p2 1,064.85 2.47 2630.18 2,630.18
TRIPLAY DE 4 mm m2 186.34 9.48 1766.53 699.92 9.84 1,056.77
MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 20,879.64 3.17 66189.01 508.89 1,340.20 30,204.00 21,793.00 2,626.99 9,715.93
TAPA PARA CAJA DE DESAGUE DE FIERRO FUNDIDO DE 12" X 24" u 11.00 31.93 351.23 351.23
TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 11.00 50.42 554.62 554.62
ANGULO DE FIERRO DE 2" X 2" X 3/16" ml 113.40 11.20 1270.08 1,270.08
ANGULO METALICO DE 3" X 3" X 3/16" kg 74.04 3.62 268.03 4.72 120.71 85.56 57.04
ANGULO DE 3/4" X 3/4" X 1/8" m 575.04 2.81 1615.86 1,615.86
PLATINA DE FIERRO 3/8" X 1" X 6 m pza 40.80 54.62 2228.5 2,228.50
PLATINA DE FIERRO 1/2" X 1/4" m 1,811.38 2.10 3803.89 3,803.89
PINTURA ESMALTE SINTETICO gal 3.00 25.21 75.63 75.63
PINTURA LATEX gal 207.92 25.21 5243.73 193.87 2,956.19 2,093.67
PINTURA ANTICORROSIVA gal 0.48 31.54 15.14 15.14
TAPAPOROS DE MADERA ACABADA CON BARNIZ O LACA gal 42.07 29.41 1237.15 57.33 640.69 539.13
BARNIZ MARINO gal 135.09 25.21 3405.09 42.24 465.61 2,897.24
IMPRIMANTE gal 67.75 15.12 1022.12 37.79 576.23 408.1
PINTURA ESMALTE gal 19.01 25.21 479.14 19.91 363.44 95.79
PINTURA PARA PIZARRA gal 6.72 33.61 225.86 225.86
PLANCHA 3/16" kg 850.00 4.10 3485 1,230.00 1,025.00 1,230.00
PLANCHAS DE ACERO DE 1/4" kg 371.28 4.20 1559.38 550.37 458.64 550.37
TEJA ANDINA DE 1.14m X0.72m pza 1,772.08 18.50 32783.34 511.45 13,771.60 13,875.20 4,625.09
PLANCHA GALVANIZADA DE 1/27" pln 86.88 28.45 2471.74 2,471.74
POSTE DE FG Y NET P/VOLEY INC. PINTURA glb 1.00 840.34 840.34 840.34
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 3/4" u 12.00 3.55 42.6 35.5 7.1
NIPLE DE F G DE 1/2" X 1 1/2" u 1.25 1.63 2.04 2.04
TUBO DE FIERRO GALVANIZADO DE 2" m 25.30 14.01 354.41 354.41
TIRAFON 4" u 299.80 1.10 329.78 22.07 171.09 136.62
TIRAFON 5" u 3,797.31 1.26 4784.6 74.64 2,009.91 2,025.04 675.01
CODO DE 90 C/R PVC SAP P/AGUA DE 1/2" u 4.00 1.18 4.72 4.72
CODO DE 90 PVC SAL DE 2" u 31.00 1.70 52.7 35.7 17
CODO DE 90 PVC SAL DE 4" u 15.00 3.39 50.85 50.85
ADAPTADOR DE COBRE DE 3/4" u 12.00 1.03 12.36 10.3 2.06
SUMIDERO DE BRONCE DE 2" u 10.00 12.66 126.6 126.6
ABRAZADERA DE FF DE E=1/8" u 120.00 7.63 915.6 915.6
ABRAZADERA DE FF DE 4"" u 287.70 12.61 3627.9 3,627.90
TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 1/2" m 34.51 1.47 50.71 23.24 27.47
TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 3/4" m 91.51 1.85 169.27 77.58 91.69
TUBERIA PVC SAP A-10 DE 1/2" m 4.80 1.47 7.06 7.06
TUBERIA PVC SAP A-10 DE 3/4" m 176.44 1.85 326.35 112.67 213.68
CODO PVC SAP PARA AGUA CON ROSCA DE 3/4" X 90 u 120.00 1.52 182.4 83.6 98.8
TUBERIA PVC SAL PARA DESAGUE DE 2" m 10.00 2.73 27.3 27.3
TUBERIA PVC SAL PARA DESAGUE DE 4" m 342.90 4.66 1597.84 137.47 1,460.37
TUBERIA PVC SAL PARA DESAGUE DE 6" m 26.16 13.31 348.22 348.22
TUB. FO. GO. PESADO DE 1/2" X 1 1/2" m 1.00 7.00 7 7
RAMAL TEE SIMPLE PVC SAL DE 2" u 16.00 2.76 44.16 44.16
RAMAL TEE DOBLE CON REDUCCION PVC SAL 4" A 2" u 10.00 8.41 84.1 84.1
TEE SANITARIA SIMPLE PVC SAL DE 4" u 25.00 7.74 193.5 193.5
TEE SANITARIA SIMPLE C/REDUC. PVC SAL 4"A 2" u 16.00 12.76 204.16 204.16
REDUCCION PVC 3/4" A 1/2" pza 32.00 1.28 40.96 17.6 20.8 2.56
SOMBRERO DE VENTILACION PVC SAL 2" pza 5.00 3.22 16.1 16.1
TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 3/4" pza 498.00 9.40 4681.2 902.4 2,196.47 1,582.33
pag. 8 de 12
CRONOGRAMA DE ADQUISICION DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7 mes 8
DURACION: 210 DIAS CALENDARIOS
TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 1" m 230.01 11.89 2734.7 2,734.70
TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 3" m 11.02 15.36 169.34 169.34
TUBERIA PVC SEL PARA INSTALACIONES ELECTRICAS DE 1 1/4" m 315.00 12.61 3972.15 3,972.15
TUB. PVC SAP P/ INST. ELEC. DE 1" m 35.00 4.27 149.45 50.71 56.04 21.35 21.35
TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 1" 1/4 m 115.58 12.61 1457.4 1,457.40
TUB. PVC SAL P/DESAGUE DE 2" m 53.10 2.73 144.96 144.96
TUB. PVC SAL P/DESAGUE DE 4" m 4.80 4.66 22.37 22.37
CURVA PVC SAP PESADO PARA INSTALACIONES ELECTRICAS DE 3/4" u 187.00 1.26 235.63 40.32 112.04 83.27
CURVA PVC SAP PESADO PARA INSTALACIONES ELECTRICAS DE 1" u 7.00 2.10 14.7 4.99 5.51 2.1 2.1
CONEXION A CAJA PVC SAP PARA INSTALACIONES ELECTRICAS 3/4" u 374.00 1.68 602.45 107.52 272.89 222.04
VALVULA COMPUERTA DE BRONCE DE 3/4" u 6.00 17.53 105.18 87.65 17.53
VIDRIO TRANSPARENTE INCOLORO CRUDOSEMIDOBLE p2 3,068.79 1.70 5216.95 5,216.95
MANO DE OBRA
OPERADOR DE EQUIPO LIVIANO hh 676.35 14.37 9719.39 192.22 3,396.77 2,730.94 1,638.25 981.09 780.12
OPERADOR DE EQUIPO PESADO hh 458.07 14.37 6581.66 414.24 1,194.73 3,980.28 911.84 80.57
TOPOGRAFO hh 68.49 12.06 825.87 389.99 435.88
CAPATAZ hh 2,528.84 14.98 37881.33 591.76 7,311.15 5,312.04 5,656.68 4,870.03 5,548.80 6,060.57 2,530.30
OPERARIO hh 19,859.49 14.37 285624.94 1,066.58 3,393.26 46,798.90 54,717.50 46,713.40 50,395.00 58,223.60 24,316.70
OFICIAL hh 8,007.62 12.61 98680.17 2,296.49 39,252.00 30,291.30 9,825.48 1,784.82 6,260.02 8,970.06
PEON hh 25,234.75 11.40 287723.51 8,186.26 105,109.00 53,036.50 32,450.30 30,312.50 35,384.90 22,361.10 882.95
EQUIPOS
WINCHA DE 50 m he 68.48 0.50 34.24 16.17 18.07
MEZCLADORA DE CONCRETO DE 9 -11p3 hm 680.32 25.03 17028.61 1,386.66 8,312.06 4,262.17 1,708.89 1,358.83
CAMION VOLQUETE 4 X 2 210-280 HP 8 m3 hm 98.56 126.05 12422.28 794.3 6,985.75 4,171.06 471.17
ANDAMIO METAL TABLAS ALQUILER est 194.70 0.00 0 0 0
SIERRA CIRCULAR hm 301.43 12.00 3617 357.87 628.09 2,631.04
COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP d 18.39 23.56 433.19 69.27 287.4 76.52
COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP hm 186.03 23.56 4384.01 176.61 4,166.75 40.65
CARGADOR S/ LLANTAS 80-95 HP 1.5-1.75 yd3 hm 75.67 134.45 10171.88 3,113.27 4,087.66 2,669.41 301.54
VIBRADOR DE CONCRETO 3/4" - 2" hm 369.99 6.59 2438.12 1,432.51 712.4 293.21
TORNILLO DE FIJACION 1 1/2" C/TARUGO DE PLASTICO 3" u 480.00 3.00 1440 1,440.00
ESTACION TOTAL hm 68.48 12.50 856 404.22 451.78
CEPILLADORA ELECTRICA hm 350.93 14.00 4913.05 639.12 1,204.39 3,069.54
Herramientas manuales % MO 24416.43 340.3 3,707.65 4,642.99 4,151.01 3,101.74 2,919.36 3,794.45 1,758.93
COSTO DIRECTO 2,162,200.05 36,292.38 188,276.81 689,342.49 412,917.38 297,883.03 249,985.12 207,704.36 79,798.48
GASTOS GENERALES + UTILIDAD (18%) 389,196.01 6,532.63 33,889.83 124,081.65 74,325.13 53,618.95 44,997.32 37,386.78 14,363.73
SUB_TOTAL 2,551,396.06 42,825.01 222,166.64 813,424.14 487,242.51 351,501.98 294,982.44 245,091.14 94,162.21
IGV (18%) 459,251.29 7,708.50 39,989.99 146,416.34 87,703.65 63,270.36 53,096.84 44,116.41 16,949.20
TOTAL_PRESUPUESTO 3,010,647.35 50,533.51 262,156.63 959,840.48 574,946.16 414,772.33 348,079.28 289,207.55 111,111.40
pag. 9 de 12
CRONOGRAMA DE ADELANTO DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5
MATERIALES
ALAMBRE NEGRO RECOCIDO # 16 kg 2,717.24 3.36 9,129.92 43.53 150.38 5,086.71 3,849.30
ALAMBRE NEGRO RECOCIDO # 8 kg 787.41 3.36 2,645.70 1.34 149.94 1,290.67 1,203.75
CLAVOS PARA MADERA CON CABEZA DE 3" kg 122.92 3.54 435.14 416.45 18.69
CLAVOS PARA MADERA C/C PARA MADERA (PROMEDIO) kg 71.54 3.36 240.37 20.16 219.62 0.59
CLAVOS C/C PARA MADERA (PROMEDIO) kg 495.60 3.36 1,665.22 1.68 92.27 497.6 1,073.67
CLAVOS PARA CEMENTO DE ACERO CON CABEZA DE 3/4" kg 11.20 3.52 39.43 24.03 15.4
ARANDELA PLANA 3/8" und 312.00 0.95 296.40 296.4
ARANDELA PLANA 1/2" pza 216.00 0.90 194.40 194.4
PERNO AUTOROSCANTE 3/8" X 2" u 23.77 1.85 43.98 43.98
PERNOS 3/4" X 6 1/2" pza 803.43 2.84 2,283.36 2,283.36
PERNOS 1/2" X 5" pza 111.40 3.41 379.44 379.44
PERNOS AUTORROSCANTE 3/8" X 2" u 104.40 0.84 87.70 87.7
GRAPAS METALICAS DE 1/16" u 12.00 4.85 58.20 58.2
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 51,844.99 3.80 197,010.95 647.28 98,121.30 92,933.20 5,309.17
ACERO CORRUGADO 3/8" kg 7,363.55 3.80 27,981.49 2,992.29 24,989.20
ACERO DE REFUERZO fy=4200 kg/cm2 GRADO 60 kg 70.08 3.80 266.30 136.19 130.11
ARENA FINA m3 10.59 72.77 770.65 20.96 749.69
TIERRA DE CHACRA O VEGETAL m3 3.33 32.80 109.06 109.06
PIEDRA CHANCADA DE 3/4" m3 179.84 140.00 25,178.04 22,910.70 2,267.34
PIEDRA GRANDE DE 8" m3 61.50 52.06 3,201.43 1,331.24 1,723.93 146.26
PIEDRA MEDIANA DE 4" m3 15.55 52.06 809.67 14.58 241.73 553.36
AFIRMADO m3 184.10 30.00 5,523.07 421.45 5,008.99 92.63
ARENA GRUESA m3 370.39 72.77 26,953.01 19.21 15,675.20 11,258.60
PIEDRA ZARANDEADA DE 3/4" m3 59.60 89.07 5,308.60 993.55 4,315.05
PIEDRA ZARANDEADA DE 1/2" m3 300.90 89.07 26,800.80 15,283.90 11,516.90
CABLE TW # 14 AWG 2.5 mm2 m 653.90 1.27 830.45 177.8 652.65
CABLE TW # 12 AWG - 4 mm2 m 52.70 1.65 86.96 31.68 55.28
CABLE TW # 2 AWG - 25 mm2 m 11.88 8.04 95.48 95.48
GANCHO GALVANIZADO DE 140 mm u 19.75 1.24 24.49 24.49
TAPON DE JEBE PARA TIRAFON u 60.19 0.80 48.15 48.15
REGISTRO DE BRONCE DE 4" u 5.00 9.50 47.50 47.5
GRIFO DE RIEGO 1/2" u 1.00 12.61 12.61 12.61
FLUORESCENTE CIRCULAR 32 W u 19.00 25.16 478.04 478.04
TABLERO DE DISTRIBUCION DE 4 CIRCUITOS u 4.38 25.40 111.13 50.8 60.33
TOMACORRIENTE BIPOLAR DOBLE + TOMA TIERRA u 43.92 10.92 479.57 174.72 304.85
INTERRUPTOR TERMOMAGNETICO DE 2 X 15A u 7.00 25.21 176.47 176.47
INTERRUPTOR TERMOMAGNETICO DE 2 X 20A u 4.00 36.15 144.60 31.63 112.97
INTERRUPTOR DE BAKELITA u 693.00 8.40 5,821.20 1,209.60 4,611.60
CAJA RECTANGULAR GALVANIZADA LIVIANA DE 4" X 2 1/8" u 82.42 1.31 107.97 31.44 76.53
CAJA OCTOGONAL GALVANIZADA LIVIANA 4" X 2 1/8 " u 87.98 1.21 106.45 24.2 82.25
CAJA DE PASO ALIMENTADOR 100 mm X 150 mm u 4.00 15.73 62.92 29.49 33.43
FLUORESCENTE RECTO ISPE 2X40 W C/EQ + PANTALLA u 24.00 94.39 2,265.36 2,265.36
FLUORESCENTE RECTO ISPE 2X20 W C/EQ + PANTALLA u 22.00 40.90 899.80 899.8
INTERRUPTOR TERMOMAGNETICO MONOFASICA 2 X 30 A und 2.00 50.61 101.22 50.61 50.61
INTERRUPTOR TERMOMAGNETICO MONOFASICA 2 X 75 A pza 1.00 80.03 80.03 80.03
ASFALTO RC-250 gal 55.01 9.47 520.98 520.98
LADRILLO KING KONG DE ARCILLA 9 X 14 X 24 cm u 456.00 0.76 346.56 346.56
LADRILLO KK DE ARCILLA 9 X 14 X 24 cm u 21,790.13 0.76 16,560.50 16,560.50
LADRILLO PARA TECHO 15 X 30 X 30 cm 8 HUECOS REX u 107.10 2.10 224.91 224.91
LADRILLO PARA TECHO 15 X 30 X 30 cm 8 HUECOS u 334.10 2.10 701.60 701.6
CUMBRERA INFERIOR TEJA ANDINA und 14.55 11.76 171.05 171.05
CUMBRERA SUPERIOR TEJA ANDINA pza 14.55 11.76 171.05 171.05
CEMENTO PORTLAND TIPO I (42.5 kg) bls 7,989.57 17.48 139,657.76 262.2 6,726.66 85,251.30 47,417.60
TAPA DE CONCRETO DE D=0.50M X 0.10M u 2.38 42.02 99.80 99.8
MAYOLICA 20 X 30 cm COLOR m2 6.18 21.00 129.78 129.78
YESO DE 28 Kg bls 85.60 7.73 661.68 312.46 349.22
pag. 10 de 12
CRONOGRAMA DE ADELANTO DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5
VARILLA DE COBRE 5/8" X 2.50 m und 2.38 42.98 102.08 102.08
FRAGUA kg 2.56 7.19 18.41 18.41
GIGANTOGRAFIA und 2.00 300.00 600.00 600
PEGAMENTO PARA PVC AGUA FORDUIT gal 0.17 18.02 3.08 3.08
PEGAMENTO PARA PVC 1/4 gl u 0.57 18.02 10.27 6.67 3.6
CINTA TEFLON u 0.75 1.00 0.75 0.75
SOLDADURA ELECT. MONOF. ALTERNA 225 AMP hm 10.56 8.40 88.70 88.7
FLETE TRANSPORTE LOCAL kg 77,518.72 2.50 193,796.80 178,376.00 15,420.80
FLETE TERRESTRE glb 0.56 121,189.87 68,169.21 8,281.31 19,794.30 20,299.30 19,794.30
HORMIGON m3 335.21 44.88 15,044.31 75.85 5,097.76 9,641.44 229.26
TEKNOPOR DE 1" X 4' X 8' pln 2.95 14.00 41.27 41.27
AGUA m3 257.65 1.50 386.48 1.69 112.58 182.8 89.41
ESTERA DE 2.00 X 3.00 m u 77.74 9.03 701.98 701.98
OFICINA glb 1.00 1,000.00 1,000.00 1,000.00
ALMACEN Y/O DEPOSITO glb 1.00 800.00 800.00 800
GUARDIANIA glb 1.00 400.00 400.00 400
BAO PORTATIL (ALQUILER) INC. MANTENIMIENTO mes 1.00 500.00 500.00 500
TRANSPORTE DE EQUIPO Y HERRAMIENTAS glb 1.00 3,361.34 3,361.34 3,361.34
FIERRO LISO DE D=1/2 kg 13.73 2.94 40.38 40.38
MADERA TORNILLO p2 416.15 4.85 2,018.34 1,229.93 788.41
REGLA DE MADERA p2 333.10 1.50 499.65 12.97 486.68
MADERA TORNILLO CEPILLADA p2 353.94 4.39 1,553.80 1,553.80
MADERA DE TORNILLO CEPILLADA p2 436.82 4.39 1,917.64 1,917.64
MADERA PINO (REGLAS) p2 18.16 3.50 63.55 63.55
ANDAMIO DE MADERA p2 637.57 1.50 956.35 956.35
MADERA EUCALIPTO ROLLIZO (p2) p2 1,064.85 2.47 2,630.18 2,630.18
MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 16,986.15 3.17 53,846.09 508.89 1,340.20 30,204.00 21,793.00
ANGULO METALICO DE 3" X 3" X 3/16" kg 1.30 3.62 4.72 4.72
PINTURA ESMALTE SINTETICO gal 3.00 25.21 75.63 75.63
PLANCHA 3/16" kg 300.00 4.10 1,230.00 1,230.00
PLANCHAS DE ACERO DE 1/4" kg 131.04 4.20 550.37 550.37
TEJA ANDINA DE 1.14m X0.72m pza 27.65 18.50 511.45 511.45
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 3/4" u 10.00 3.55 35.50 35.5
NIPLE DE F G DE 1/2" X 1 1/2" u 1.25 1.63 2.04 2.04
TIRAFON 4" u 20.06 1.10 22.07 22.07
TIRAFON 5" u 59.24 1.26 74.64 74.64
CODO DE 90 PVC SAL DE 2" u 31.00 1.70 52.70 35.7 17
CODO DE 90 PVC SAL DE 4" u 15.00 3.39 50.85 50.85
ADAPTADOR DE COBRE DE 3/4" u 10.00 1.03 10.30 10.3
SUMIDERO DE BRONCE DE 2" u 10.00 12.66 126.60 126.6
TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 1/2" m 15.81 1.47 23.24 23.24
TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 3/4" m 41.94 1.85 77.58 77.58
TUBERIA PVC SAP A-10 DE 3/4" m 60.90 1.85 112.67 112.67
CODO PVC SAP PARA AGUA CON ROSCA DE 3/4" X 90 u 55.00 1.52 83.60 83.6
TUBERIA PVC SAL PARA DESAGUE DE 2" m 10.00 2.73 27.30 27.3
TUBERIA PVC SAL PARA DESAGUE DE 4" m 29.50 4.66 137.47 137.47
TUB. FO. GO. PESADO DE 1/2" X 1 1/2" m 1.00 7.00 7.00 7
RAMAL TEE SIMPLE PVC SAL DE 2" u 16.00 2.76 44.16 44.16
RAMAL TEE DOBLE CON REDUCCION PVC SAL 4" A 2" u 10.00 8.41 84.10 84.1
TEE SANITARIA SIMPLE PVC SAL DE 4" u 25.00 7.74 193.50 193.5
TEE SANITARIA SIMPLE C/REDUC. PVC SAL 4"A 2" u 16.00 12.76 204.16 204.16
REDUCCION PVC 3/4" A 1/2" pza 13.75 1.28 17.60 17.6
SOMBRERO DE VENTILACION PVC SAL 2" pza 5.00 3.22 16.10 16.1
TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 3/4" pza 329.67 9.40 3,098.87 902.4 2,196.47
TUB. PVC SAP P/ INST. ELEC. DE 1" m 11.88 4.27 50.71 50.71
TUB. PVC SAL P/DESAGUE DE 2" m 53.10 2.73 144.96 144.96
TUB. PVC SAL P/DESAGUE DE 4" m 4.80 4.66 22.37 22.37
pag. 11 de 12
CRONOGRAMA DE ADELANTO DE MATERIALES
Obra CONSTRUCCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. JOSE CARLOS MARIATEGUI N 86629 DE HUASHCAO, DISTRITO DE MANCOS, PROVINCIA DE YUNGAY - REGION ANCASH
Fecha:
10/18/2011
Lugar: ANCASH - YUNGAY - MANCOS
Nombre del recurso Und Cant. P.U. (S/.) TOTAL mes 1 mes 2 mes 3 mes 4 mes 5
CURVA PVC SAP PESADO PARA INSTALACIONES ELECTRICAS DE 3/4" u 120.92 1.26 152.36 40.32 112.04
CURVA PVC SAP PESADO PARA INSTALACIONES ELECTRICAS DE 1" u 2.38 2.10 4.99 4.99
CONEXION A CAJA PVC SAP PARA INSTALACIONES ELECTRICAS 3/4" u 226.43 1.68 380.41 107.52 272.89
VALVULA COMPUERTA DE BRONCE DE 3/4" u 5.00 17.53 87.65 87.65
COSTO DIRECTO 864,906.73 20,537.19 44,047.81 516,886.63 278,125.93 5,309.17
GASTOS GENERALES + UTILIDAD (18%) 155,683.21 3,696.69 7,928.61 93,039.59 50,062.67 955.65
SUB_TOTAL 1,020,589.94 24,233.88 51,976.42 609,926.22 328,188.60 6,264.82
IGV (18%) 183,706.19 4,362.10 9,355.75 109,786.72 59,073.95 1,127.67
TOTAL_PRESUPUESTO 1,204,296.13 28,595.98 61,332.17 719,712.94 387,262.54 7,392.49
pag. 12 de 12

You might also like