QA/QC Inspection Checklist

design coordinates, inc. CP No. __________________


La Vie Flats
Parkway Ave.Filivest Corporate City
Alabang,Muntilupa City

Building Element/System: D20 – Plumbing Systems


Category: D2020.15060 – Domestic Water Distribution / Hot Water Distribution
Items to be Inspected: Pipes and Pipe Fittings
Date Inspected:
Supplier:
Location:

Non - Not Not Due


ITEM / REQUIREMENT Conform.
Conform. Avail. Applic.
Remarks / Corrective Actions
Date
Open Close

A SUBMITTALS:
A.1 Materials
a.1.1 Type : XLPE
a.1.2 Brand :
a.1.3 Origin :
a.1.4 Type of Joint :
a.1.5 Conformance to ASTM or other
standards
a.1.6 Installation procedure
a.1.7 Mill Certificate
A.2 Shopdrawings

B INSTALLATIONS:

B.1 Plumbness
B.2 Alignment
B.3 Right sleeves
B.4 Right type of fire topping
B.5 Filler between pipe sleeve and pipe
b.5.1 fire rated
b. 5.2 non-fire rated

DCI-QIC rev. 00 Page 1 of 3


QA/QC Inspection Checklist
design coordinates, inc. CP No.: ______________________
La Vie Flats
Parkway Ave.Filivest Corporate City
Alabang,Muntilupa City

Non - Not Not Due


ITEM / REQUIREMENT Conform.
Conform. Avail. Applic.
Remarks / Corrective Actions
Date
Open Close

b.5.3 in accordance/approved
submittal
Correct spacing and installation of
B.6 brackets, hangers, sway braces and
supports
B.7 Approve insulation
B.8 Joints:
b.8.1. mechanical joint
b.8.2 brazed
b.8.3 threaded
b.8.4 soldered
B.9 Types:
b.9.1. K
b.9.2. L
b.9.3. M
b.9.4. DWV
B.10 Correct pipe size
B.11 Pipe labels
B.12 Valve labels
Valve flow marks on the direction of
B.13
the flow
B.14 Correct location of installed valve
Proper heat temperature for brazing
B.15
and soldering
B.16 Lead free flux and solder
B.17 Installed relief valve
B.18 Installed balancing valve
Die electric fitting in between
B.19
copper and galvanized iron.
B.20 Installed water hammer arrestor

DCI-QIC rev. 00 Page 2 of 3


QA/QC Inspection Checklist
design coordinates, inc. CP No.: ______________________
La Vie Flats
Parkway Ave.Filivest Corporate City
Alabang,Muntilupa City

Non - Not Not Due


ITEM / REQUIREMENT Conform.
Conform. Avail. Applic.
Remarks / Corrective Actions
Date
Open Close

Well clean pipes and fittings prior to


B.21
installation
B.22 Flushing (cleaning)
B.23 Disinfected
C TESTING PROCEDURES:
C.1 Calibrated instruments
C.2 Joints exposed
C.3 Caulking on joints
C.4 With pressure drop
C.5 Cracks on fittings
C.6 Leakage
C.7 Air pressure
C.8 Hydrostatic pressure
a. initial pressure reading, _____psi
b. final pressure reading, ____ psi

General Notes, Comments and Recommendations:

Inspected by : Noted by : Concurred by :

ROY JOHN BORNILLA ARCH. RODERICK DENNIS M. CALLUENG RONALD ANDY PUNSALAN
_____________________________________ _____________________________________ __________________________________________
Construction Project Engineer / Architect Construction Project Manager Supplier
Distribution:

Supplier Customer / Developer DCI File


DCI-QIC rev. 00 Page 3 of 3
QA/QC Inspection Checklist
design coordinates, inc. CP No.: ______________________
La Vie Flats
Parkway Ave.Filivest Corporate City
Alabang,Muntilupa City

Non - Not Not Due


ITEM / REQUIREMENT Conform.
Conform. Avail. Applic.
Remarks / Corrective Actions
Date
Open Close

Note : A separate Non-Conformance & Corrective Action Report (DCI-NCR) should be prepared for each and every non-conforming item identified in this checklist.