2020 T ransportation P lan 2010

Fairfax County Parkway (VA 7100) Corridor


1. Fairfax Co. Pkwy. (4 to 6 lanes) Sunrise
Capital Cost

Valley Drive to VA 123 . . . . . . . . . . . . . . . . .$55,000,000


2. Fairfax Co. Pkwy. (4 to 6 lanes)
VA 636 (Hooes) to VA 640 . . . . . . . . . . . . . .$10,000,000
3. Fairfax Co. Pkwy. (2 HOV lanes)
2020
1. 2 new interchanges (Lawyers Rd/
Fairfax Co. Pkwy, Franconia-Springfield
Capital Cost

Pkwy/Neuman St) . . . . . . . . . . . . . . . . . .$40,000,000

VA 640 to VA 7900 . . . . . . . . . . . . . . . . . . . .$10,000,000


Dulles/VA 7 Corridor 4. Fairfax Co. Pkwy. (0 to 6 lanes)
VA 7900 to Fullerton Rd . . . . . . . . . . . . . . . .$66,200,000
5. VA 7900 (2 HOV lanes) VA 7100 to
2010 Capital Cost 2020 Capital Cost Frontier Dr. . . . . . . . . . . . . . . . . . . . . . . . . .$10,000,000
1. Bus Rapid Transit (BRT) in 6. Fairfax Co. Pkwy. - Priority bus
Dulles Corridor . . . . . . . . . . . . . . . . . . . .$213,000,000 1. Dulles Greenway (4 + 2 HOV lanes) VA 772 (corridor-wide) . . . . . . . . . . . . . . . . . . . . . .$7,200,000
2. Metrorail - West Falls Church Station to to VA 28 . . . . . . . . . . . . . . . . . . . . . . . . .$13,800,000 7. 3 new interchanges (Monument Drive/Fair
VA 772 in Loudoun County . . . . . . . . . .$1,700,000,000 2. VA 7 - 2 New interchanges at Baron Cameron Lakes Pkwy, Rolling Road, Pohick Road) . .$60,000,000
3. VA 7 - 6 New Interchanges - VA 7/US 15 and Reston Parkway . . . . . . . . . . . . . . . .$40,000,000 8. Fairfax County Parkway Trail -
Bypass to VA 28 (Battlefield Parkway, River Cr. Pkwy, 3. VA 7 - Reconstruct 2 interchanges at Sunset Hills Road to VA 7 . . . . . . . . . . . . . .$1,000,000
Belmont Ridge Rd, Claiborne Parkway, Dulles Toll Road and VA 123 . . . . . . . . . .$20,000,000 9. Sugarland Run Trail - VA 7 to
Ashburn Village Blvd, Loudoun Pkwy) . . . .$60,000,000 W&OD Trail . . . . . . . . . . . . . . . . . . . . . . . . . .$700,000
4. VA 7/US 15 Bypass (4 to 6 lanes) __________ __________
VA 7 E to VA 7 W . . . . . . . . . . . . . . . . . . . .$6,000,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$220,100,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$40,000,000
5. 2 new interchanges on Greenway
(Battlefield Pkwy and Crosstrail Blvd) . . . . .$20,000,000 CORRIDOR TOTAL $260,100,000
6. Dulles Access Road (4 to 6 lanes) . . . . . . . .$40,000,000
7. VA 7 (4 to 6 lanes) Fairfax Co. Parkway
to Dulles Toll Road and (6 to 8 lanes)
Dulles Toll Road to I-495 . . . . . . . . . . . . . .$68,000,000
8. Battlefield Parkway (0/2 to 4/6 lanes) . . . . .$45,000,000
I-66/US 29/US 50 Corridor
9. Highway management system . . . . . . . . .$1,500,000 2010 Capital Cost 2020 Capital Cost
10. Transit traveler information systems . . .$10,300,000 1. I-66 (8 + 2 HOV-reversible lanes) and modify inter- 1. US 29 (4 to 6 lanes) I-495
11. Transit security systems . . . . . . . . . . . . . .$3,200,000 changes - Tri-County Parkway to I-495 . . .$535,000,000 to Graham Road . . . . . . . . . . . . . . . . . . .$15,000,000
12. Electronic payment system 2. Metrorail - Vienna Station to Centreville . .$657,000,000 2. US 29 (4 to 6 lanes) Fauquier County to
(transit and parking) . . . . . . . . . . . . . . .$11,400,000 3. I-66 - Express Bus (corridor-wide) . . . . . . . .$29,100,000 I-66 (Gainesville) . . . . . . . . . . . . . . . . . .$15,300,000
13. VA 7 Bikeway - Loudoun/Fairfax line 4. VRE service increase (20 minute headways) . . . .$5,000,000 3. US 50 (4 to 6 lanes) ECL of Fairfax to
to Tysons Corner . . . . . . . . . . . . . . . . . . . .$600,000 5. Additional Metrorail Station access Arlington County . . . . . . . . . . . . . . . . . . .$46,000,000
14. Extension of W&OD trail to Bluemont . . . .$400,000 (Rosslyn and Ballston) . . . . . . . . . . . . . . . . .$37,000,000 4. US 50 interchange at Waples Mill Road . .$20,000,000
___________ __________ 6. I-66 (4 to 6 lanes +2 HOV lanes) 5. US 29 interchange at Gallows Road . . . .$20,000,000
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . .$2,179,400,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$73,800,000 US 234 Bus. to US 29 (Gainesville) . . . . . . . . . .$64,000,000 6. Theodore Roosevelt Bridge - improved
7. I-66 - New interchange at US 29 (Gainesville) . .$70,000,000 bicycle connections . . . . . . . . . . . . . . . . .$2,500,000
CORRIDOR TOTAL $2,253,200,000 8. I-66 (4 + 2 HOV lanes) US 15 to US 29
(Gainesville) . . . . . . . . . . . . . . . . . . . . . . . . .$30,700,000
9. US 29 (4 to 6 lanes) WCL Fairfax
to ECL Fairfax . . . . . . . . . . . . . . . . . . . . . . .$27,000,000
Tri-County/Loudoun County Parkway & VA 234/VA 659 Corridor 10. US 29 (4 to 6 lanes) ECL Fairfax to I-495 . . . . .$22,000,000
11. US 50 - Priority bus from
2010 Capital Cost 2020 Capital Cost Eastern Loudoun to Arlington . . . . . . . . . . . .$2,500,000
1. Tri-County Parkway (0 to 4 lanes) 1. Tri-County Parkway (0 to 4 lanes) 12. Highway Management System
VA 234 Bus. to I-66 . . . . . . . . . . . . . . . . . .$33,000,000 I-66 to VA 620 . . . . . . . . . . . . . . . . . . . .$22,000,000 enhancement . . . . . . . . . . . . . . . . . . . . . . . .$1,000,000
2. Tri-County Parkway (0 to 4/6 lanes) 2. Loudoun Co. Parkway (0 to 4 lanes) 13. Traveler information on parking facilities . .$1,500,000
VA 620 to US 50 . . . . . . . . . . . . . . . . . . . . .$7,000,000 US 50 to Dulles Greenway . . . . . . . . . . .$20,000,000 14. Interstate Bicycle Route 50 . . . . . . . . . . . . . .$3,200,000
3. Loudoun Co. Parkway (0 to 4 lanes) 3. VA 659 (2 to 4 lanes) US 50 to PW County .$13,000,000 15. US 29 Trail - Fauquier Co. to City of Fairfax . . .$800,000
VA 7 to Gloucester Pkwy. . . . . . . . . . . . . . .$9,000,000 4. VA 234 Bypass north (0 to 4 lanes) 16. Rosslyn Circle - improved bicycle/
4. VA 234 Bypass north (0 to 4 lanes) VA 234 to VA 659 Relocated . . . . . . . . . . .$7,000,000 pedestrian crossings . . . . . . . . . . . . . . . . . .$1,000,000
I-66 to VA 234 . . . . . . . . . . . . . . . . . . . . .$14,000,000 5. VA 234 Bypass (4 to 6 lanes and upgrade) __________ __________
5. VA 234 (2 to 4 lanes) SCL Manassas to I-66 south to VA 234 . . . . . . . . . . . . . . . . .$23,000,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$1,486,800,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$118,800,000
VA 234 Bypass . . . . . . . . . . . . . . . . . . . . . .$6,000,000 6. 3 new interchanges at Tri-County Parkway/
6. VA 234 (2 to 4 lanes) VA 234 Bypass Lomond Dr., VA 234 Bypass/Liberia Ave. CORRIDOR TOTAL $1,605,600,000
South to Montclair . . . . . . . . . . . . . . . . . . .$55,000,000 and VA 234/Tri-County Parkway . . . . . .$60,000,000
7. VA 659 (2 to 4 lanes) VA 7 to US 50 . . . . . .$20,000,000
8. VA 234 Trail - I-66 via VA 234 Bypass
to I-95 . . . . . . . . . . . . . . . . .included in road projects
__________ __________
I-495 (Beltway) Corridor
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$144,000,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$145,000,000
2010 Capital Cost 2020 Capital Cost
CORRIDOR TOTAL $289,000,000 1. I-495 (8 general purpose + 2 HOV lanes and 1. I-495 (10 general purpose lanes +
modify interchanges) I-395 to 2 HOV lanes and modify interchanges)
Dulles Toll Road . . . . . . . . . . . . . . . . . . .$323,000,000 Woodrow Wilson Bridge to
2. Reconstruct Woodrow Wilson Bridge approaches American Legion Bridge . . . . . . . . . . .$1,677,000,000
VA 28 Corridor and interchanges, including bicycle/pedestrian
improvements . . . . . . . . . . . . . . . . . . . .$200,000,000
2. Metrorail - Dunn Loring Metrorail
Station to Maryland via
3. I-495 - Express Bus (corridor-wide) . . . .$14,000,000 Tysons Corner . . . . . . . . . . . . . . . . . . .$740,000,000
2010 Capital Cost 2020 Capital Cost 4. Traffic management and safety
1. VA 28 (4 to 6 lanes) NCL Manassas Park 1. VA 28 (6 to 8 lanes) with 4 new interchanges, enhancement . . . . . . . . . . . . . . . . . . . . .$12,800,000
to US 29 . . . . . . . . . . . . . . . . . . . . . . . . . .$16,300,000 I-66 to Dulles Toll Road* . . . . . . . . . . . . .$32,000,000 5. Enhanced incident management systems .$3,700,000
2. VA 28 (2 to 4 lanes) Fauquier Line to 2. VA 28 (6 to 8 lanes) Dulles Toll Road __________ __________
VA 234 Bypass . . . . . . . . . . . . . . . . . . . . . .$19,300,000 to VA 606 . . . . . . . . . . . . . . . . . . . . . . . . .$4,000,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$553,500,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . .$2,417,000,000
3. New interchanges at VA 28/VA 625 and 3. Light rail (Manassas to Dulles Airport) .$790,000,000
VA 28/Smithsonian Museum . . . . . . . . . . . . .$37,000,000 4. 3 new interchanges at VA 28/VA 606,
4. New interchange at VA 28/US 29 . . . . . . . . .$37,000,000 VA 28/Sterling Blvd., and VA 28/New CORRIDOR TOTAL $2,970,500,000
5. Route 28 trail extension - US 29 to Braddock Road . . . . . . . . . . . . . . . . . . . .$40,000,000
Fauquier County . . . . . . . . . . . . . . . . . . . . . .$900,000 *assumes right-of-way available
__________ __________
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$110,500,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$866,000,000
I-95/I-395/US 1 Corridor
CORRIDOR TOTAL $976,500,000 2010 Capital Cost 2020 Capital Cost
1. Interchange at I-95/I-395/I-495 . . . . . . . . . .$392,000,000 1. Metrorail - Franconia/Springfield Station
2. I-95 (6 to 8 lanes) Newington to VA 123 . . . .$18,900,000 to Lorton/Fort Belvoir . . . . . . . . . . . .$640,000,000
3. I-95 [HOV peak (2 lanes)] Stafford Co/ 2. Metrorail - Lorton/Fort Belvoir
PW line to Quantico Creek . . . . . . . . . . . . .$24,900,000 to Potomac Mills Mall Area
Prince William Parkway (VA 3000) Corridor 4. Interchange improvement at
I-95/Van Dorn . . . . . . . . . . . . . . . . . . . . .$20,000,000
in Prince William County . . . . . . . . . . .$700,000,000
3. Light rail - US 1 Corridor -
5. I-95/Franconia-Springfield Pkwy Alexandria to Arlington to Pentagon . .$330,000,000
2010 Capital Cost 2020 Capital Cost SOV access . . . . . . . . . . . . . . . . . . . . . . . .$40,000,000 4. Eastern Potomac River crossing
6. I-395 - 3 HOV lanes from I-495 to DC . . . . . .$20,000,000 (I-95 bypass) to Route 301
(No major improvements) 1. VA 3000 (4 to 6 lanes) Liberia Avenue to 7. Interchange improvement at in Maryland . . . . . . . . . . . . . . . . . . . .$1,000,000,000
Minnieville Road . . . . . . . . . . . . . . . . . . .$38,000,000 I-95/Lorton Road . . . . . . . . . . . . . . . . . . .$10,000,000 5. I-395 - Additional lane on
8. VRE service increase (20 minute 14th Street Bridge . . . . . . . . . . . . . . . . .$100,000,000
__________ __________ headways) . . . . . . . . . . . . . . . . . . . . . . . . . .$5,000,000 6. 4 new interchanges on US 1
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$0 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$38,000,000 9. Metrorail station entrance enhancement (Huntington Ave, Kings Hwy, Fairfax
(Crystal City and Pentagon City) . . . . . . . .$46,400,000 County Pkwy, Rippon Blvd/Dale Blvd) . .$80,000,000
CORRIDOR TOTAL $38,000,000 10. US 1 (6 + 2 peak HOV lanes) VA 235
North to Capital Beltway . . . . . . . . . . . . . .$49,000,000
11. US 1 (4 to 6 lanes) Stafford County line
to VA 235 North . . . . . . . . . . . . . . . . . . . .$335,000,000
12. 2 new interchanges on US 1
Notes: (Russell Rd and VA 234) . . . . . . . . . . . . . .$40,000,000
1. Corridor boxes show major improvements. A complete list can be viewed in supporting documentation. 13. Interchange at US 1/VA 123 . . . . . . . . . . . . .$31,000,000
2. Projects in bold are not in current regional constrained long range plan (CLRP - FY99 - 2004). 14. US 1 - Priority bus (corridor-wide
3. Cost estimates will be updated as projects move toward implementation. south of the Beltway) . . . . . . . . . . . . . . . .$2,000,000
4. Improvements on a new location are conceptual and require additional detailed study. 15. US 1 - Priority bus to bus rapid transit
5. WTC = Western Transportation Corridor (1 mile wide) that was recommended for additional study. to light rail (north of the Beltway) . . . . . .$2,000,000
6. ECL = eastern city limits, WCL = western city limits, SCL = southern city limits, and NCL = northern city limits 16. Highway management system
enhancement . . . . . . . . . . . . . . . . . . . . . . .$1,100,000
17. Traveler information on parking facilities .$1,500,000
18. US 1 Trail -Beltway to
Stafford County . . . . . . . . . . .included in road projects

Selected Improvements and 2020 Plan Strategies 19. Potomac Yard Trail . . . . . . . . . . . . . . . . . . . .$200,000
__________
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . .$1,039,000,000
__________
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . .$2,850,000,000
Strategy Strategy Strategy Strategy Strategy Strategy CORRIDOR TOTAL $3,889,000,000
Enhance access Maintain Promote Target Operate Secure funding
between activity existing HOV/transit congested system for improvements
centers and infrastructure solutions corridors more by timeframe
urban core (to include efficiently Legend Other Major Improvements (outside corridors)
2010 Improvements Metrorail) 2010 Capital Cost 2020 Capital Cost
Metrorail extension – Dulles Corridor to VA 772 in Loudoun County • • • •
Metrorail extension – Vienna to Centreville • • • • 1. VA 123 (2/4 to 6 lanes) Fairfax County 1. Light Rail - VA 7 - Tysons Corner to
Pkwy to Prince William County . . . . . . . . .$96,000,000 Baileys Crossroads . . . . . . . . . . . . . . . .$325,000,000
New or expanded express bus – Beltway, I-66, I-95, and Dulles Corridors • • • • • 2. VA 236 - Priority bus (corridor-wide) . . . .$2,000,000 2. Light Rail - Columbia Pike corridor -
Priority bus – several corridors including Fairfax Co. Parkway, VA 7, VA 236, US 50, & Columbia Pike • • • • • 3. VA 7 and Columbia Pike - Priority bus/bus Baileys Crossroads to Pentagon . . . . . .$325,000,000
I-66 – 8 + 2 HOV reversible lanes from the Beltway to Tri-County Parkway • • • • rapid transit to light rail . . . . . . . . . . . . .$4,000,000 3. Western Transportation Corridor --
4. Columbia Pike to Pentagon Trail . . . . . . . .$200,000 I-95 to I-270 in Maryland with
I-495 – 2 HOV lanes from I-395 to Dulles Toll Road • • • • 5. Springfield to Tysons Corner Bikeway . . .$1,500,000 Potomac River crossing . . . . . . . . . . .$1,625,000,000
US 29 – 4 to 6 lanes from WCL Fairfax to ECL Fairfax • • 6. Connection from W&OD trail in Leesburg 4. US 15 (2 to 4 lanes) US 29 to
Tri-County Parkway – 4 lanes from VA 234 (bus.) to I-66 • • • to Whites Ferry/C&O Canal . . . . . . . . . . . .$800,000 Loudoun/Prince William line . . . . . . . . . . .$28,000,000
7. Hunter Mill Road bikeway - VA 123 to VA 7 .$400,000 5. US 50 (4 to 6 lanes) Loudoun/Fairfax line
Maintenance and Rehabilitation Program • • • 8. Alternative detection for signal to Lee Rd. . . . . . . . . . . . . . . . . . . . . . . . . .$8,000,000
Bicycle/Pedestrian improvements • • • operation . . . . . . . . . . . . . . . . . . . . . . . .$12,500,000 6. US 50 (4 to 6 lanes) Route 659
Intelligent Transportation Systems/Telecommuting • • • 9. Video surveillance installation (relocated) to Loudoun/Fairfax line . . . .$17,000,000
on arterials . . . . . . . . . . . . . . . . . . . . . . .$10,000,000 7. VA 7 (4 to 6 lanes) Seven Corners to
2020 Improvements 10. Regional signal operation Baileys Crossroads . . . . . . . . . . . . . . . . . .$32,000,000
Metrorail – Dunn Loring to Tysons Corner to MD • • • • improvement . . . . . . . . . . . . . . . . . . . . .$23,600,000 8. VA 236 (4 to 6 lanes) Pickett Rd. to I-395 . .$55,000,000
Metrorail extension – Franconia/Springfield transportation center to Prince William County • • • • 11. Incident management and safety . . . . . . .$4,200,000 9. VA 620 (4 to 6 lanes) Fairfax County
12. Transit vehicle tracking system . . . . . . .$10,800,000 Parkway to VA 123 . . . . . . . . . . . . . . . . . .$17,000,000
Light rail in VA 28 corridor – Manassas to Dulles Airport • • • • 13. Traveler information for transit systems .$6,300,000 10. Mount Vernon Trail Extension
Light rail in US 1 corridor – Alexandria to the Pentagon • • • • 14. Security system for transit services . . . . .$3,200,000 to the north . . . . . . . . . . . . . . . . . . . . . . . .$700,000
I-495 – 10 + 2 HOV lanes from Woodrow Wilson Bridge to American Legion Bridge • • • • 15. Integrated electronic payment system . . .$4,000,000
16. Enhance and support transportation
Dulles Greenway – 4 + 2 HOV lanes from VA 28 to VA 772 • • • • planning programs . . . . . . . . . . . . . . . . .$3,200,000
VA 28 – 6 to 8 lanes (with interchanges) from I-66 to Dulles Toll Road • • • __________ __________
US 29 – 4 to 6 lanes from Fauquier line to I-66; 4 to 6 lanes from I-495 to Graham Road • • • TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$182,700,000 TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . .$2,432,700,000
Maintenance and Rehabilitation Program • • • Other Major Improvements TOTAL $2,615,400,000
Bicycle/Pedestrian improvements • • •
Intelligent Transportation Systems/Telecommuting • • TOTAL FOR MAJOR PROJECTS TOTAL FOR MAJOR PROJECTS
COMPLETED BY 2010 $5,916,000,000 COMPLETED BY 2020 $8,981,300,000