STV Construction, Inc.

DAILY CONSTRUCTION REPORT


Project

Atlantic Yards

Date

8/15/2014

B2

Weekday

Friday

Location
Client
Contract #
Project #
STV Representative:
Work hours

ESD
6717
2114659

Report #
Weather
Temp. L/H
Wind Speed

William King

381
Sunny, Dry
70's
Slight

Precip

8:00-4:00

297
930

175
0.319

1.7

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably working on 12th floor mods with a workforce in the low 160's.
Tower Crane - Inactive
Module Transportation - No mods delivered
Module Installation - 0 mods installed. Completion % at 31.9% from 31.4% - 297 out of 930 mods installed in 175 work days since mod
installation began = an avg. of 1.7 mods per day. Complete through 10th floor.
MEP - Some minor work left in main electrical switching room and then will be ready for Con Ed to turn on permanent power - waiting for a
greater power load in building before Con Ed will allow use of permanent power.
Other - Hoist is in operation to 5th floor.
Various mateline connection work principally on lower floors. No drywall replacement work yet.

Additional New Observations:

New Information received:

New Information requested:


Information previously requested: Read Skanska ec's report no. 2, sent by FCR on 6/17. In 6/19 email response to FCR's SS, who
sent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to measure potentially
high mold spore counts in a unit where any mold is not vis ble, i.e in upper or inner layer of wallboard in ceiling/wall. Cited leak day on 6/13,
after e.c's most recent site visit, when subsequent leak damage was not that evident. On 7/16 sent FCR's Scott Stutman a 2nd request for
response to 6/19/14 STV questions concerning leaks/mold remediation/testing. On 8/13, sent 3rd request.
Requested warranty duration for faade of FCR on 7/16. Will look up in specs.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
On 5/1/14

Information to be requested:
Previous Information received: 7/31 - Will be bringing in hanging scaffold soon to fix flap doors on faades. As of 8/14 no scaffold.
7/31 - Waiting for approval by DOB of crane permit amendments for jumping crane (which won't do until shortly before mod installation
recommences) and tieing in crane to building at 8th floor.
7/29 - Informed that mods won't resume until Sept. 15. Want to fill the yard outside of Bldg 292 at the Navy Yard before resume bringing
them over.
7/15 - New 3rd worst water leaks, especially affecting the 7th floor even though 1-2 floors below the top of the bldg. 7/3/14 - 3rd biggest water
leaks in center and west of building. Skanska/MG McGrath totally at a loss as to cause.
Tolerances for doors between side panels are 1-1/4" to 2-1/4". Several doors on south and east facades out of tolerance and won't close.
Water penetration not an issue as gaskets behind them determine whether water penetrating or not - not seen as a water leak problem.
Doors on east side wired open so won't blow/bang in the wind.

1 of 2

STV Construction, Inc.


Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
4/8 - Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
3/21 - Paper documenting DOB's approval (signed 2/2/14) of no sidewa k shed on Dean received.
10/16/13 - At Navy Yard FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog of
30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep ahead
of erection so there would be no downtime during mod erection at the B2 site.

Previous observations: Front faade is now less than 33-35' from the ped wa kway due to the 6th floor Dean St. transfer beam facade
protruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush faade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.

Special instruction(s) given:

Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

20-25

Navillus

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

Stearns
J Supor Trucking
MEP trades

15-20

Other

5-10

Equip. Arr./ Departure-Observed

Manpower figure is rough approximation by STV.

Materials Delivered other than Mods (Observed)

William King

8/15/2014

Prepared by William King