Professional Documents
Culture Documents
Sl.
Description Page Nos.
No.
1. Introduction 1-1
2. Contract 1-1
EXECUTIVE SUMMARY
0.1 INTRODUCTION
M/s Intercontinental Consultants and Technocrats Pvt. Ltd., New Delhi have been appointed
as Consultants to carryout the Feasibility Study and preparation of Detailed Project Report
(DPR) for 4/6-laning of Cherthalai to Thiruvananthapuram section of
NH-47 in Kerala State (Package No. NHDP Phase III/DL4/22). The work will be executed on
BOT basis.
0.2 CONTRACT
The Contract for Consultancy Services between M/s. ICT Pvt Ltd. and NHAI was entered
into on 08.09.2005 with the amount of consultancy contract being Rs. 2,21,69,400/-
(excluding service tax) for the entire length of proposed 4 laning in the Cherthalai-
Thiruvananthapuram section of NH-47 in the State of Kerala. Length has been divided in two
parts. Package II deals from Ochira (km 465.000) to Thiruvananthapuram
(km 551.900) section of NH-47.
0.3 PROJECT BACKGROUND
0.3.1 Earlier Stand
During the meeting taken by the Hon’ble Chief Minister of Kerala at Thiruvananthapuram on
08.11.2005, NHAI were asked by the State Govt. to carryout 4 laning within the existing 30m
width of Road (ROW) as acquisition of land was reported to be extremely difficult. M/s. ICT
were constrained to develop the x-sections of 4 laning accordingly. This had the following
inherent drawbacks:
i) Non availability of space for 4.5m wide Median as per Ministry’s / NHAI guidelines
ii) Non Provision of 1m wide earthen shoulders on both sides of the 4-lane road
iii) Only 5.5m width of service roads including 1.5m width for side drain and 0.5m for utility
services
iv) No space for stacking lane for turning traffic in medium opening for safety
v) Non availability of adequate space for utility services
vi) No space for bus bays, bus shelters, parking areas etc.
vii) No scope of future expansion
0.3.2 Reports Submitted
Feasibility report of the project was submitted to NHAI on 13.02.2006.
Draft Preliminary Project Report for Package II i.e. km 465.000 to km 551.900 was submitted
to NHAI on 12.01.2007. These reports were based on the earlier decision of 4 laning in the
existing 30m Right of way (ROW) width.
03.3 Later Developments
During the meeting taken by the Hon’ble Minister for Shipping, Road Transport &
Highways with the Chief Minister of Kerala at Thiruvananthapuram on 23rd May
2007, it was decided that 4-laning of NH-47 from Cherthalai to Thiruvananthapuram
will be carried out in 45m. Right of Way (ROW) width and NOT in 30m existing
ROW as desired by the State Govt. of Kerala. This has resulted in complete change of
design and drawings by the consultants.
Design CBR : 8%
Pavement Composition
New Pavement:
Bituminous Concrete : 50mm
Dense Bituminous Macadam (DBM) : 140mm
Wet Mix Macadam (WMM) : 250mm
Introduction
NPV (Rs.
Option EIRR %
Million)
Four lane carriageway 42.40 23652.86
configuration of existing 2-lane
carriageway of NH-47 (With
time saving)
Sensitivity Analysis
Condition – I : 15% increase in project cost, traffic remains unchanged
Condition – II : 15 % decrease in traffic, project cost remains unchanged
Condition – III: 15 % increase in project cost & 15% decrease in traffic
Post-
Equity
Sl Tax
Description FIRR NPV
No. FIRR
(%)
(%)
Concession Period: 25 Years
1 Base case with 15.00 12.98 95.50
no grant Crores
2 With 20% 25.94 18.96 611.53
equity support + Crores
20% O&M
support
•••
1. INTRODUCTION
M/s Intercontinental Consultants and Technocrats Pvt. Ltd., New Delhi have been appointed
as Consultants to carryout the Feasibility Study and preparation of Detailed Project Report
(DPR) for 4/6-laning of Cherthalai to Thiruvananthapuram section of NH-47 in Kerala State
(Package No. NHDP Phase III/DL4/22). The work will be executed on BOT basis.
2. CONTRACT
i) Amount of Consultancy Contract : Rs. 2,21,69,400.00 (Excluding service tax)
ii) Agreement Date : 08.09.2005
iii) Contract Period : 12 Months
iv) Length : 173 km
3. PROJECT BACKGROUND
National Highways Authority of India has decided to take up the development,
maintenance and management of various National Highway corridors / section under
NHDP Phase-III Programme of 4/6- laning of 10000 km on BOT basis where the
intensity of traffic has increased significantly and their is a requirement for
argumentation of capacity for safe and efficient movement of traffic. The Present
Project study concerned with Cherthalai- Thiruvananthapuram section of NH-47,
(length –172.8km) in Kerala state including the bypasses under construction i.e.
Alappuzha and Kollam and proposed new by pass in Attingal.
NHAI is employer and executing agency for the consultancy services and the
standards of output required from the appointed consultants are international level
both in the terms of quality and adherence of the agreed time schedule.
M/S Intercontinental Consultants & Technocrats Pvt. Ltd., A-8 Green Park, New
Delhi, India have been appointed as Consultants vide letter no NHAI/ BOT/
Monthly Progress Report
1 - 6
11012/67/20054 (Pt) ‘H’ /399 dated 18.08.2005 to carry out the Feasibility Study and
Detailed Project Report (DPR) for 4-laning of the section from Cherthalai (Km.
379.100) of NH-47 to Thiruvananthapuram (km 551.900) of NH-47 in the State of
Kerala. The scope and principal objectives of the consultancy services, shall be in
accordance with the Terms of Reference, which is part and parcel of the contract
agreement. The services were commenced with the effect from 23.09.05 and the date
of submission of Draft Detailed Project Report for this Project is 07.02.2006.
As per the directive of NHAI in conformity with the meeting held on dated 08.11.05
chaired by Chief Minister Govt. of Kerala. Consultant has carried out the Feasibility
Study, for the section of project road between km 379.100 to km 551.900.
The Quality Assurance Plan and Inception Report were submitted vide letter no.
ICT:436:WR:8503 dt. 27.09.05 and ICT:436:WR: 9268 dated 20.10.05, respectively.
Draft Feasibility Study report for Stage-II, from Km 431.000 (Purakkad) to km
551.900 (Kazakuttam Junction) of NH-47 was submitted vide letter no.
ICT:436:WR:1488 dated 13.02.2006.
Present submission Draft Preliminary Project Report (PPR) for Stage-II from Km.
465.000 to Km. 551.900 of NH-47, has been prepared in various chapters
incorporating the suggestions received from time to time from Member Technical
(BOT), CGM (BOT) and GM (BOT).
The total project road length is 168.950 km. It starts from km 379.100 i.e. 379.100 of
NH-47 at the junction of Thiurvoor and ends at Kazakuttam junction at km 551.900
i.e. 548.05. This stretch of road passes through populated areas such as Cherthalai,
Alappuzha, Kalavoor, Punnapra, Ambalapuzha, Haripad, Kayamkulam,
Krishnapuram, Ochira, Karunagapally, Chavara, Kollam, Umayanallore, Kottiyam,
Pariapally, Vavakavu, Puthiyakavu, Kavanadu, Attingal, Mamam, Pallipuram, and
Mangalpuram. The existing road is two lanes with paved shoulder on either side.
GM, BOT-II, NHAI, had informed that for this project nodal officer has been appointed i.e
Secretary PWD Kerala Govt. and the Consultant on visit to Thiruvananthapuram should meet
him.
The Team Leader of ICT for the subject project met Secretary PWD Kerala Govt., Nodal
Officer for the project on 30-9-2005 at his office. On 1.10.2005, meeting was organized in the
office of Secretary PWD Kerala Govt. where all the officers of National Highway Division
Kerala PWD and Mr. Abraham Zachariah Chief Engineer (Southern Region), Kerala Water
Authority, Thiruvananthapuram was present in the discussion about submission of Land Plan
and utility shifting. After the reconnaissance survey of the entire stretch by the ICT team
members, the Secretary PWD was again contacted on 4.10.2005.
The meeting was held again with CGM BOT-I, NHAI and Team Leader of ICT on 27.11.05.
The Inception Report was discussed in detail and certain changes were proposed by CGM,
BOT-I, NHAI and the same were complied by ICT on priority. The CGM, BOT-I, NHAI also
informed about the presentation to be given by ICT consultants to the chief minister of Kerala
and other officers of Kerala Govt. on 8.11.5005 based on the Inception Report submitted by
ICT on 20.10.05.
The CGM, BOT-I, NHAI, inspected the project site on 7th November 2005. The presentation
as per the direction of CGM, BOT-I, NHAI was given by the Team Leader for the above
project on 8.11.2005 in the CM’s conference hall at Thiruvananthapuram. The meeting held
on 08.11.05, was chaired by Honorable Chief Minster of Kerala Govt., presided by Minister
(Works) Kerala Govt., meeting was also attended by Minister (Revenue), Minister (Power),
Minister (Water Recourses and Forest), Vice Chairman (State Planning Board), CGM, BOT-I,
NHAI, Mr. Ashok Wasson; Secretaries of the various department of Kerala Govt. Inspector
General of Police and various Head of the departments of Kerala Govt.
The minutes of the above meetings has been issued by Kerala Govt. on dated 9th Nov. 2005,
wherein it was intimated that (NHAI) agreed to start the work of four laning for minimum one
stretch by Jan’ 06. Further in Continuation of the Minutes of the meetings on 8.11.2005 it was
communicated by Secretary PWD Kerala Govt. that the section from Km 379.100 to Km
431.000 will be taken up in first phase. Subsequently, during discussion on phone between
CGM, BOT-I, NHAI and Executive Director- III of ICT, it was intimated by CGM that
minimum stretch of 50 Km of the project road, i.e. Km 379.100 to Km 431.000, to be
considered by ICT as BOT package, in the first phase, for the preparation of feasibility study
and detailed project report.
The Draft Feasibility Study cum Preliminary Project Report, for Stage-I (km 379.100 to km
427.860) is submitted by the consultant, vide letter dated 29.12.05. The comments by the
Client, on the report is received on dated 05.01.06, during the discussion held on Feasibility
Study Cum Preliminary Project Report, at the office of CGM, BOT-I, NHAI. In accordance to
the said comments, Final Feasibility Study Report Cum Preliminary Project Report for Stage-
I (from Km 379.100 to 427.860) is modified, and submitted vide letter no ICT:436:WR:1363
dated 08.02.2006. For the preparation of Draft Feasibility Study report, for Stage-II, from km
431.000 to km 551.900, the comments received by Consultant, on Draft Feasibility Study
report for Stage-I is considered, as applicable and found relevant for Stage-II. The Feasibility
Report Study Report for the section km 431.000 to km 551.900 ICT:436:WR:1488 dated
13.02.2006.
A review meeting of all the National Highway Projects in Kerala State was conducted by
Honble Minister of Ministry of Shipping, Road Transport & Highways, Govt. of India at
Thiruvananthapura on 17.07.2006.
A meeting was conducted by Member (Technical) & CGM NHAI at
Thiruvananthapuram on 17.07.2006 for this project road and the final decision for
length of packages was taken, which are as follows:
Package-I : Km. 379.100 to Km. 465.000 (ch. 379.100 to ch. 462.700)
September to November North East monsoon which is weaker. Total average rainfall per
year is 3000 to 3500 mm.
As per the census of 2003 there are 27,45,948 vehicles. The highways are overloaded and
the present system is not able to adjust with the large number of vehicles. The statistics
indicate that the road accidents in Kerala is increasing day by day, more accidents occur
during April-May. About 33% of the total accidents were for the two wheelers. Out of total
137678Km National Highway Network in the country, Kerala State has 1560 kms National
Highways. At present there are 8 nos. National Highway in the State.
NH-47 : Walayar-Kaliyikkavila
NH-17 : Thalapadi-Edappally
NH-49 : Bodimettu-Kundannoor
NH-47A : Kundannoor-Willington Island
NH-208 : Kollam-Aryankavu
NH-212 : Kozikode-Muthanga
NH-213 : Palakkad-Kozikode
NH-202 : Kollam-Kumily
Out of 8 National Highways, NH-47 is the busiest highway in the State. NH-47 starts at
Salem in Tamilnadu and passes through Kerala and ends at Kanyakumari in Tamilnadu, the
southern most tip of the country. Important Industrial/Commercial Centre located at this NH-
47 are Salem, Erode. Coimbatore, Palaghat, Thrissur, Erunakulam, Alappuzha, Kollam,
Thiruvananthapuram, Nagarcoil and Kanyakumari. This portion of NH-47 in Kerala is
connected to other parts of the country through the following National Highways.
• NH-17 from Edappally passing through Calicut, Mangalore, Goa and terminating at
Bombay
• NH-49 from Ernakulam, passing through Moovattupuzha, Munnar, Madurai and
terminating at Rameswaram in Tamilnadu.
• NH-208 originates at Kollam and passing through Kundara, Kottarakara, Punaloor,
Thenmala, Aryankavu, Kottavasal, Chenkota and Thani.
3.5 Salient Features
The reconnaissance on the project road section from Cherthalai to Thiruvananthapuram was
carried out during 30th September 2005 to 6th October 2005. Subsequently detail survey has
been conducted for Stage-II (Km 465.000 to Km 551.900 ) in October 2005 to February 2006.
As per our survey, the observed salient features in km 465.000 to km 551.900 are as under.
1. The project road in Stage-II starts from km 465.000 in Ochira town, Alappuzha districts
and it ends at km 551.900 in Kazakuttam junction of Thiruvananthapuram districts.
2. The road passes through Ochira, Karunagapally, Chavara, Vettuthara, Kollam,
Umayanallore, Kottayam, Chatanoor, Karamkode, Pariapally, Karuvalam, Thotokiyad,
Attingal;, Mamam, Koram, Pallipuram, Mangalapuram and Alimode Town.
3. The construction of Kollam By Pass from km 488.972 km to km 502.804 of NH-47 is
being done, out of which 4.791 km is already constructed for 2-lane.
4. The project road crosses NH-208 at km 502.8000, where a flyover is proposed.
5. Ribbon development has been observed throughout the project road, including by pass
and the improvement of the existing road demands provision of service road for main
road, NH-47 and for by pass.
The land use along the existing NH is built-up area and commercial area in major portion of
project road, as a effect of ribbon development. In certain parts of project road, the land use
is Industrial area. The utilities are running along the NH through out its length. Utilities like
electricity, water supply lines etc are also crossing the NH. The data collected has been
furnished in Table 3.
Table 3 : Land Use
Coconut tree
139 542.000 542.500 BUA Thonnakkal
+ BUA
Height of Stretch
Embankment in
(m) LHS RHS
479.50-481.00, 481.50-482.50,
479.50-480.000, 480-481, 482- 484-486, 503-503.500, 504.50-
484, 485-486, 503-505.000, 505.00, 507.50-508.00,
507.50-508, 509.5-510.000, 511.50-512.00, 514-514.500,
511.50-513.00, 514-514.50, 516.00-516.50, 518.520.500,
< 1m
517.50-519.00, 519-520, 521- 522.500-523.000, 524.50-
521.50, 526-527, 538-538.50, 525.00, 526.00-527.00,
543.50-544.00, 546.547, 548- 541.50-542.00, 546.00-547.00,
548.50, 550-550.500 548.00-548.500, 550.00-
550.500
479-479.5, 481.0-481.5, 483-
479-479.35, 481-482, 484-485, 484, 486-489, 507-507.50,
486-487, 503-503.50, 507, 509- 513.5-514, 514.5-515.00,
>1m <2m
509.50, 516-517, 520-521, 516.500-517, 520.50-521.50,
521.50-522, 524.50-525 527-527.50, 539.50-540, 541-
541.50, 547-548
508.500-509.00, 515-515.500, 508.500-509.00, 513-513.50,
522-522.500, 523, 524-524.500, 515-515.500, 521.50-522.00,
>2m < 3m 537-537.500, 539-539.500, 540, 522.00-522.50, 524.00-
542.50-543, 544-544.500, 545- 524.500, 539-539.500,
546.000 542.500-543.000, 545-546.000
523.00-523.50, 537-537.50,
523-524, 538.500-539,
538.50-539, 540-540.50,
> 3m 540.500-541.00, 542-542.500,
540.50-541.00, 542.000-
544.50-545
542.50, 544.50-545.00
$ From km 486.600 to km 499.600 kollam by pass construction is under progress
$ from km 523.500 to km 534.300 attingal by pass is proposed.
3.10 Junctions
The details of existing junction are given in Table 5.
Table 5 : Existing Major Junctions
Sl. Design Description of Status of
Side Category Remarks
No. Chainage Road road
1 470.280 LHS Karumangappally MDR Underpass
Introduction
Kadavoor
Both Underpass
3 491.000 Junction to MDR
Side proposed
Amchalammod
Kollam
Both Junction
4 494.950 Shecottah NH- NH 208
Side proposed
208
Ayathil Junction
Kollam –
Both Junction
5 496.500 Kanmanalloor MDR
Side proposed
Road
Kollam bypass
Junction
6 499.500 RHS end junction NH-47
proposed
existing NH-47
Kottiyam
Both Junction to Underpass
7 502.600 MDR
Side Mayyanad to proposed
Kundara
Chattannur
Both junction to Underpass
8 507.710 MDR
Side Kannanalloor to proposed
Udayanad
Parippally
Both Junction to Underpass
9 515.200 MDR
Side Madathara to proposed
Paravoor
Kollambalam
Both Underpass
10 520.120 Junction to MDR
Side proposed
Varkala
Bypass
Attingal bypass
start
11 523.550 RHS start junction NH-47
junction
existing NH-47
proposed
Both Underpass
12 527.400 To Varkala MDR
side proposed
13 534.500 RHS Attingal bypass NH-47 Bypass end
Kanjirappally
Both
3 466.820 Makku, MDR
side
Tharaylkadavu
Pannama
Both ODR
8 475.600 Asramam,
side ODR
Godown
Edappally
Both Junction, MDR &
9 476.220 Sasthamkollaha,
side ODR
KMML Factory
Both Vakkatu Mukku, ODR
10 478.690
side IRE ODR
Introduction
Both
24 525.000 Village Road VR
Side
Both
25 526.475 MLA Road MDR
Side
Both Chianyam Begh
26 530.550 MDR
Side road
Both Chirayan beehu
27 531.650 MDR
Side road
Sl.
Design Chainage Remarks
No.
Low laying area water logging in rainy
1 462.900-463.000 (LHS)
season
2 471.820-471.900 (LHS & RHS) Natural canal connecting waters
3 473.900-473.950 (RHS) Low laying wet land dries in summer season
4 474.580-474.620 (LHS & RHS) Low laying paddy fields & drainage channel
5 475.060-475.120 (LHS & RHS) Low laying paddy fields & drainage channel
6 475.450-475.481 (LHS) Low laying paddy fields & drainage channel
7 476.200-477.500 (LHS) Low laying paddy fields & drainage channel
Navigational canal connecting back waters
8 480.110-480.160 (LHS & RHS)
rivers
9 482.130 (RHS) The Arabian sea is 50m away
Neendakara Harbour Canal connecting
10 484.680-485.080 (LHS & RHS)
Asthamudy lake to Arabian sea
11 487.300-487.820 (LHS & RHS) Branch of Ashtamudy lake
12 490.180-490.260 (LHS & RHS) Branch of Ashtamudy lake
13 491.900-492.720 (LHS & RHS) Branch of Ashtamudy lake
14 496.430-496.460 (LHS & RHS) Natural Drainage channel
15 497.150-497.170 (LHS & RHS) Natural Drainage channel
16 497.310-497.330 (LHS & RHS) Natural Drainage channel
17 504.430-504.450 (LHS & RHS) Natural Drainage channel
18 505.550-505.600 (LHS & RHS) Jthikkar River
19 517.600-517.615 (LHS & RHS) Natural Drainage Channel
20 519.460-517.470 (LHS & RHS) Natural Drainage Channel
21 520.730-520.740 (LHS & RHS) Natural Drainage Channel
22 529.300-529.400 (LHS) Vamarapuram River
23 530.300-530.400 (LHS & RHS) Low laying paddy field
24 534.100-534.120 (LHS & RHS) Mamam River
25 536.350-536.360 (LHS & RHS) Natural Drainage Channel
Introduction
Sl.
Design Chainage Remarks
No.
26 544.150-544.160 Natural Drainage Channel
4.1 Corrugation
4.2 Rutting
Rutting is a longitudinal depression or groove in the wheel tracks. The ruts are usually
of the width of a wheel path. Swerving from a rutted wheel path at high speed can be
dangerous.
The depth of rut is measured by keeping the straight edge placing transversely across
the wheel tracks and using graduated measuring wedge. The mean value for the
wheel tracks is worked out.
Potholes are bowl shaped holes of varying sizes in a surface layer or extended into
base layer, caused by the localized disintegrations of the usually thin bituminous
surfacing material.
The area affected by major Pot holes was measured and the percentage area was
worked out.
4.4 Ravelling
4.5 Cracking
A common defect in bituminous surface is the formation of cracks. The area affected by
cracking was measured by encircling and the extent of cracking was assessed visually at
500m intervals or the places of defects.
4.6 Patching
During field inspection, patching was observed at the stretches.
4.7 Edge Breaking
Irregular breakage of pavement edge was noticed in some portion of road.
4.8 Edge Drop
The edge drop is the vertical difference in levels between the edge of the carriageway and
abutting shoulders.
4.9 Inventory of all Road Side Facilities
The details of the road side amenities and facilities like school, dhabas, telephone booths, bus
stop, hospital, hotel, repair shops etc. are given.
5. ROAD MEASUREMENT DATA ACQUISITION SYSTEM (ROMDAS)
5.1 Background
The roughness has been carried out for the whole length of the project road using Road
Measurement Data Acquisition System (ROMDAS). The calibration of the ROMDAS has
been done as per the procedure given in World Bank’s Technical Paper Number 46 (WTP-
46). The surveys have covered two runs along the wheel paths for each lane and results have
been expressed in the terms of IRI (m/km) and BI (mm/km) in tabular as well as graphical
forms. Further, whole stretch of 162 km has been delineated using Cumulative Difference
Approach and based on this homogeneous sections have been identified.
In addition video survey has also been conducted for digitisation of whole project road to
have a better in-house assessments and rectifications.
5.2 ROMDAS
Road Measurement Data Acquisition System (ROMDAS) has been developed as a
generic system for collecting a variety of information. The vehicle mounted
equipment includes: an axle mounted device called Bump Integrator for the
measurement of roughness; a Video camera and an IBM compatible notebook PC
which interacts with the instrumentation to store recorded data. The video camera is
used to record all pertinent information concerning the existing roadway and Right-
of-Way (though, whenever necessary, this information may also be verified by
physical inspection).
This is an indication of the surface irregularities influencing the riding quality and is a
major determinant of vehicle operating costs.
ROMDAS works as a response type road roughness measuring system. The system has been
calibrated by recording its response (RAW values) and comparing the same with that of a
ROMDAS Z-250 Reference Profiler. ROMDAS Z-250 reference Profiler has been developed
by Data Collection Ltd (DCL). The Calibration sections called standard sections have been
divided into a number of smaller subsections of 100m lengths each. A total of 12 such
“standard” points have been collected consisting of 400 lengths each. “Standard” sections
vary from “very smooth” to “very poor” and at each section the Z-250 has been run along the
selected lane and roughness has been noted in terms of IRI (m/km).
ROMDAS vehicle has been run at Constant Speed of 32+2 km/hr on the “standard” section
along the same selected lanes and ROMDAS response (RAW values) have been recorded.
Using the software-NLREG the calibration equation has been developed between ROMDAS
Response (RAW/km) and IRI (m/km).
Calibration equation at 32km/hr:
IRI Roughness values have been converted into Bump Integrator Index (BI) by means
of the equation given in HDM-III:
Field data collected and analyzed subsequently along each lane of the stretch have
been expressed in terms of IRI (m/km) and BI (mm/km) and have been presented in
both tabular and graphical forms in the following pages.
The following guidelines for road roughness in terms of IRI (m/km) and BI (mm/km)
for different surface types have been considered for assessing the road condition.
As per World Bank Technical Publication No. 46 the minimum and maximum
range of BI and IRI for new pavements is as follows, but the type of surface has
not been mentioned.
5.4 Observations
Based on the Roughness Measurement Studies the km-wise average roughness in IRI
and BI Units of various lanes. The detailed 100m-wise Roughness Measurement
Studies have been provided.
Due to constraint in available land width, the approach road towards the underpass shall be
restrained by providing RE wall on both side. The proposed vehicular underpass shall have
clear opening as 5.5m x 15.0m, and pedestrian underpass shall have clear opening as 3.5m x
15.0m in main road.
7.3 Median Opening
Median opening shall be provided at approximately 2km interval along the project highway.
Length of opening shall be 30m. On both sides of median opening, steel railing is proposed
to be provided on precast blocks. In between service road and main carriageway, to restrict
the pedestrian crossing through the designated road marking only. The details of median
opening are summarized in Table 9.
Table 9 : Details of Existing Median Opening
Sl. No. Design Chainage Sl. No. Design Chainage
1 464.000 21 511.500
2 466.000 22 513.200
3 471.000 23 518.200
4 472.600 24 520.000
5 474.200 25 521.700
6 475.500 26 523.500
7 476.600 27 525.200
8 478.800 28 527.400
9 481.000 29 528.500
9. HYDROLOGY OF BRIDGES
9.1 General
• This section deals with Hydrological and Hydraulic study of Bridges from Existing Km
465.000 to km 551.900 of NH-47.
Introduction
• There are 14 existing Bridges in the existing road stretch. Two number bypass has been
proposed to be bypass Kollam and Attingal towns. 3 number new bridges are proposed in
Attingal bypass and 6 number new bridges are proposed in Kollam bypass. Other 5 nos
existing bridges of NH-47 are of 2 lane and are required to be widened to 4 lanes except
the AS Canal Bridge at existing Km 482.
• The hydrological study, computations and methodology adopted for discharge and other
hydrological computations have been discussed in this report.
• List of proposed culverts are included for bypasses.
9.2 Study Objective
These investigations are primarily intended for evaluating the adequacy of waterways of the
existing bridges for the design flood flow. The hydrological study has been done based on the
field investigations and survey data. This report describes the method of evaluation of
performance of existing bridges on the existing highways for widening proposals, and design
discharges, waterway required, scour depth and afflux etc for the new bridges.
9.3 Hydrological Investigation Pertaining to Bridges
There are total 14 bridges on existing main road out of which 9 bridges are proposed to be
bypassed. Major rivers, Canals and lakes crossing the proposed alignment are outlined below:
• Among Existing bridges 2 number bridges are on defined river Ithikkara at design
chainage 505+300 and Pallipuram at chainage 544+155 .One bridge is on famous
Ashtamudi Lake at chainage 484+900. Other 2 number bridges are on canal at chainage
471+880(Pallikal) and other is at 480+150 (TS canal).
• 6 number bridges are proposed on Kollam bypass among which 3 no bridges are proposed
on the lakes and other 3 number bridges are on the different branches of Churanga thodu
river.
• Total 3 number bridges are proposed on Attingal bypass among which Two bridges are
proposed on the major river Vannapuram at chainage 529+300 and Mammon at
chainage 534+110 river of Periyer Basin. One minor bridge is proposed on Thotakadu
river at chainage 529+600.
• Bridges are found to be of varying span of 8 m to 423 m ( on lake)
• River slope in the bypass are generally found to be varies from 1 in 250 to 1 in 1000.
• General ground are varring from RL 60 on the waterdivide to RL 0 on bridge site.
Vannapuram river generates at Ranges of Sayhadri hills of elevation 1100 .
9.4 Hydrological Data
The Hydrological Data collected for calculation of bridges are as follows:
Various data such as terrain, soil and cover condition, nature and size of bed material, river
bed and plan forms etc. are collected from field through local inquiry made during site
inspection by engineer based upon designed format for the same. Table 12 shows the
hydrological features such as bed level and HFL of Channels.
Toposheet Number 58C/12, 58C/16, 58D/9, 58 D/13, 58D/14, 58 H/2 of has been taken from
Survey of India and catchments of streams has been demarcated. Equivalent Slope of stream ,
terrain slope and land uses are also studied in the toposheet.
Rainfall/runoff data published in the Flood Estimation Reports for West Coast Region Sub
zone 5a & 5b, prepared jointly by Central Water Commission (CWC), Indian Meteorological
Department (IMD), Research Designs Standards Organisation (RDSO) and Ministry of
Shipping Road Transport & Highways (MOSRT&H) are used for information regarding
stream flow and rainfall. From Isopluvial maps in Flood Estimation Report, 24 hour rainfall
of 50 year return period is found to be 280 mm for this stretch of road. The rainfall data has
been given in Table 13.
For rain fall of shorter duration less than 24 hrs a conversion ratio has been adopted from
same CWC report. Mean average Time distribution curves of storms of various duration are
also adopted from CWC report subzone 5a and 5 b Aerial to point rainfall ratio for various
duration over different catchment is adopted from CWC report of Subzone 5 a and 5 b. The
general land use data and Soil Data are also adopted from the same report.
9.5 Stream Data
For all the bridges, the longitudinal section of the river extending from about 100m to 500m
on the U/S and 100m to 500 m on the D/S (depending on stream size) has been drawn on the
basis of actual survey data at site. Several river cross-sections, one at the bridge site, others
both U/s and D/S of the bridge are drawn on the basis of field survey data. Longitudinal
section of the stream along deep channel is plotted for each stream to find the longitudinal bed
slope and compared with terrain slope found from toposheets. Manning’s roughness
coefficient (n), cross section area of flow (A), wetted perimeter (P) and conveyance (K) etc.
are found for each of the stream.
9.6 Hydrological Computations Pertaining to Bridges
The adequacy of the existing bridges has been determined on the basis of design discharge /
flow. The detailed hydrological computations for all bridges on existing main road and
bridges on bypasses have been done. The discharge has been computed by various methods
and then finally, design discharge has been adopted as recommended in IRC:SP – 13 and
IRC : 5. The computed discharge is given in Table 14. It also gives other details e.g. names
of streams, existing clear waterway, skew angle, effective waterway, design discharge and
HFL as obtained from local enquiry. The adequacy of the existing bridge is determined by
taking into consideration of Lacey’s Regime waterway and actual waterway (at HFL) of the
channel and is given in Table 15 & Table 16 gives the abstract of hydraulic parameters e.g.
design HFL, maximum scour levels for piers and abutments, recommended waterway,
fluming ratio, afflux etc.
9.7 Methodology Adopted For Discharge Computation
Design discharge is computed by using various methods (i.e. Empirical Formula, Rational
method, Slope Area method, and Weir / Orifice method), as recommended in IRC-SP-13 and
IRC 5 – 1998 are briefed below. Methods adopted in any particular case may vary depending
on availability of data.
Dicken’s Formula:
Dicken’s formula is commonly used for computation of flood discharge based on
catchment area of the stream.
Q = C1A0.75 (1)
Where:
A = Catchment area in Sq. km.
C1 = Run-off coefficient which depends on the topography, Rainfall, type of soil, vegetation,
ground slope, climate of the region, etc
Rational Formula
Q= 0.028 PfAIC (2)
Introduction
Where:
Q = Maximum runoff in cumecs
A = Catchment area in hectares
Ic = Critical intensity of rainfall in cm/ hr.
P = Coefficient of run off for the given catchment characteristics.
F = Spread factor for converting point rainfall into area mean rainfall.
Table 14
Table 2.16
Q = KS1/2 (3)
1/n
Ke = Equivalent conveyance rate = (K1, K2…Kn)
1
Kn = N n * An Rn 2/3 (n = 1, 2, 3…n) (4)
Where:
Q = Discharge in m3/sec.
A = Cross-sectional area of flow in sq. m.
R = Hydraulic mean depth in m = A/P
P = Wetted perimeter in m.
S = Mean longitudinal slope of the channel.
K = Conveyance factor and n refers no. of cross-section
N = Rugosity coefficient as per IRC: SP –13
n = nos. of cross-sections
This method has been used only for those bridges, which are having defined channel in
toposheet. Those bridges, where there is no defined channel and slope, Area-velocity method
has been used by assuming a velocity of 2 ms-1
Weir/Orifice Formula
Weir formula
3/2
Q = 1.706CW L D + u2 (5)
u
2g
Introduction
Q= Discharge in cumecs
L= Linear effective clear waterway in meter under the bridge normal to channel axis.
Du = Average depth of flow at upstream in meter measured above a datum usually taken as
reduced invert level of bridge
u= Velocity of approach in m/sec.
g= Acceleration due to gravity = 9.81 m/sec2.
Cw = Coefficient of discharge over weir, which may be taken as under as per IRC: SP-13
as follows:
Type of Bridge opening Value of Cw
Narrow bridge opening with or without floors: 0.94
Wide bridge opening without floor: 0.96
Wide bridge opening with no bed floor: 0.98
u has been calculated using the relation
u = Q/(Du *W) = Q/Au (6)
Where,
W = Width of channel at upstream section and Au is the cross section of flow upstream.
The above formula is valid when the weir flows freely depending on afflux (h) given by
h = (Du- Dd) = (U/S H.F.L. – D/S HFL) (7)
Where Du and Dd are the depths of flow upstream and d/s of the bridge measured above a
given datum usually taken as the bed level of the stream. Weir equation is applicable only
when h/Dd ≥ 0.25 .
Orifice formula
2 ½
u
Q =C
o 2gLD d h + (1 + e ) (8)
g
2
h = Afflux = (Du – Dd)
Co and e are coefficients to account for losses of head and recovery respectively
Values of e and Co are taken from IRC-SP13 respectively. In all the cases, energy head in
terms of recovery has been neglected.
The above formula is valid for h < ¼ Dd
This method can not be used for the bridges on totally new alignment or on bypass.
Synthetic Unit Hydrograph
TB = 7.3801 (tp)0.7343
(19)
Tm = tp +tr /2 (20)
QP = qp xA (21)
Where,
Tm = Time from the start of rise to the peak of the U.G. (hr)
tp = Time from the centre of effective rainfall duration to the U.G. peak (hr)
W50 = Width of the U.G. measured at 50% of peak discharge ordinate (hr)
WR50 = Width of the rising limb of U.G. measured at 50% of peak discharge ordinate
(hr)
WR75 = Width of the rising limb of U.G. measured at 75% of peak discharge ordinate
(hr)
Qi = 2.78 A/tr
Where
Steps to Estimate the Critical Distribution of Storm Rainfall and Design Flood
Hydrograph
Where R is the Lacey’s regime scour depth, measured below HFL, q is the design discharge
intensity under bridge in cumecs per meter and f is silt factor given by the equation
f= 1.76 (d50)1/2
Where d50 is the mean sediment size in mm. Normal scour depth based on Lacey’s equation
and the actual observed depth (equal to the difference between HFL and LBL)/1.27 are
compared as per code. Higher of the two values is adopted for design. Silt factor ‘f’ is found
from Lacey’s equation corresponding to d50 size of bed materials. Maximum scour level for
pier and abutment are calculated using a factor of safety of 2 and 1.27 respectively as per
IRC: Code-5. For computing scour depth, design discharge is enhanced by 30% to provide for
Introduction
adequate margin of safety as per provision of IRC: 78 - 2000. As the borehole data is awaited,
the preliminary calculations for scour depth has been done by taking silt factor obtained from
d50 of the surface bed material.
Computation of Afflux
Afflux is due to constriction in normal waterway under the bridge. It is computed using Weir–
Orifice formula and Molesworth formula (IRC-SP:89)
Molesworth formula:
Afflux = ((v2/17.88)+0.015)*((A/A1)2-1)
Weir / Orifice formula has already been discussed above. The afflux computed based on both
the methods will be taken into considerations for the final value
Proposed Culverts
Total 14 numbers culverts are provided in Kollam Bypass among which 6 numbers are pipe
culverts and 8 number culverts are RCC Box culvert. Total 19 number culverts have been
provided along the Attingle Bypass for free movement of run off . New culverts of adequate
size have been provided wherever
There is a sag in the ground.
The length of drains becomes excessively long, for disposal of drain water at intervals
in order to limit the drain size.
Most of the culverts in this stretch are balancing type. As there is no defined channel,
the catchment for such culverts could not be demarcated in the toposheet. The size
and type of culverts has been decided according to the visual observation of
catchment at site itself and assessment of discharge likely to pass through these cross
drainage structures.
Year of
Nos. Name of Bridge Length (m)
Construction
Fifties 1 Chavara Bridge (483/1) 44
Kanettil bridge (475/2) 80
Sixties 2
ROB in approaches of Kanettil bridge (475/1) 7.7
Seventies 3 Neendakara (488/1) 422
Poovampara (533/1) 79.5
Ithikkara (509/1) 64
Eighties 2 531/1 8
538/1 49
Nineties 4 3 bridges & 1 ROB on Kollam Bypass 65 (total)
Date Not known 1 Pallipuram bridge (548/1) 13.5
type and the horizontal and vertical clearances available under the bridge fall short of
those laid down by Inland Waterway Authority of India. In view of this, Chavara
bridge (bridge no. 483/1) having 44m length is recommended for replacement.
Generally, all of the bridges have deck level at considerable height above ground.
There is no report of any submergence. Further the bridges are across lakes, canals
and rivers having very little velocity due to being near to sea. Therefore, no adverse
effect of water current has been noted and the bridges appear to have adequate
waterway. Thus from hydraulic consideration all of the existing bridges are in
satisfactory condition.
Apart from bypass to Kollam town (km 489 to km 503) under construction, it is
proposed to provide a bypass to Attingal town also from km 528 to km 537.4.
Bridge no. 533/1 Bridge across Vamanpuram river near Poovampara, length – 80m
For 4-laning of the road, additional 2-lane bridges, ROBs, underpasses are proposed
by the side of existing 2-lane bridges / structures proposed to be retained. Thus
following additional 2-lane bridges / ROBs are proposed.
Additional 2-lane bridges : 475/2, 488/1, 509/1, Minor bridges 10/1, 11/1 &
11/2 on Kollam bypass and 548/1
Existing 44m long bow string girder bridge being old and narrow, is proposed to be
replaced by a new 4-lane bridge.
Underpass
Proposed alignment of Attingal bypasses crosses an MDR at ch. 531+650. The MDR
is proposed to be taken under NH 47 after regarding. Accordingly, an underpass with
12m opening and vertical clearance 5m is proposed at this location.
Flyover
National Highway no. 47 crosses National Highway no. 208 near Kollam town. A 4-
lane flyover is proposed over NH no. 208.
Thus in all following. 29 nos. new structures are proposed as per Table 19 given
below:
Addition
Sl. Design Span Overall
Bridge No. 2-lane or
No. Chainage Arrangement length
4-lane
Introduction
Addition
Sl. Design Span Overall
Bridge No. 2-lane or
No. Chainage Arrangement length
4-lane
ROB 475/1
1. (Now 471.735 1 x 7.70 7.70 2-lane
underpass)
475/2
2. (Kanettil 471.88 4 x 20 80.0 2-lane
bridge)
483/1
3. (Chavra 480.145 1 x 60 60.0 4-lane
Bridge)
488/1 2 x 8.75 +
4. 484.900 422.50 2-lane
(Neendkara) 15 x 27
Bridge on 9 x 43.5 +
5. Ashtmudi 487.60 2 x 43.9 + 569.75 4-lane
lake 2 x 45.2
Bridge over
6. Kandachira 490.230 2 x 43.5 87.0 4-lane
lake
Bridge over
7. 492.31 20 x 43.5 870.0 4-lane
Aravila lake
Flyover over
8. 494.960 11 x 31.5 346.50 4-lane
NH No. 208
ROB on
9. Kollam 495.168 1 x 37.7 37.7 2-lane
bypass
Churanga
10. 496.450 1 x 14.5 14.50 2-lane
Thodu
Churanga
11. 497.175 1 x 13.24 13.24 2-lane
Thodu
Churanga
12. 497.340 1 x 13 13.0 2-lane
Thodu
Ithikkara
13. 505.90 3 x 21.3 63.9 2-lane
509/1
Attingal bypass
Thotakadu
14. 526.570 1 x 15.8 15.8 4-lane
bridge
Vamanpuran
15. 529.340 3 x 27.5 82.5 4-lane
river bridge
Underpass
16. 531.650 1 x 12 12.0 4-lane
for an MDR
Mamon
17. 534.140 3 x 27.5 82.5 4-lane
bridge
Pallipuram
18. 544.155 1 x 13.5 13.5 2-lane
bridge 548/1
19
Underpasses
to 1 x 16 16.5 4-lane
(11 nos.)
29
*The ROB in the approach of Kanettil bridge no. 475/2 is over a railway line leading
to an abandoned jetty. As such though no structure is now required at this location
an underpass of same size as that of existing i.e. 6.1m clear width has been proposed.
For passing MDR under National Highway 47 at ch. 531 + 650 a box structure is
proposed.
Thus in the project stretch in all 30 bridges / structures having 2/4 lane capacity will
have to be constructed.
Location
Median
Because of habitation developed all along the National Highway, there is scarcity of
land. Hence only 0.5m wide median has been proposed on the main NH.
Accordingly the new bridges are proposed to be constructed adjacent to existing
bridges. In case of bridges on bypasses 4.5m wide median is proposed. In view of
this 4.5m wide open median has been proposed over bridges on bypasses.
Span Arrangement
In case of additional two lane bridges proposed to be constructed by the side of the
existing bridges span lengths have been proposed equal to or in multiples of those of
existing bridge so that the new piers are inline with the existing ones to achieve
streamline flow. Where altogether new bridges are proposed span lengths have been
chosen from practical considerations.
There is only 30m land width available for widening the road. In this width 4-lane
road alongwith service roads on either side have been proposed with reduced widths.
In view of this there is no possibility of widening the road to 6-lane. Since traffic
projections indicate need for 6-laning of road within 10 years of completion of 4-
laning, the bridges have been proposed with deck configuration shown in NHAI’s
Type of Superstructure
Types of superstructure have been proposed as per site requirement and ease of
construction. Normally following types of superstructure have been adopted :-
RCC Wall type abutments and RCC Wall / circular type piers have been proposed.
Type of Foundations
Depending upon hydraulic data, type of substrata likely to be available and span
length etc open/pile type foundations have been proposed.
Loading
Since the proposed deck configuration for each 2-lane bridge unit has scope for widening to
3-lane capacity in future, each unit shall be designed for 3-lanes of IRC Class “A” or one lane
of IRC class 70R +one lane of IRC Class-A loading.
Seismic Force
As per modified seismic map of India the project road lies in Seismic Zone - III. According to
modified clause 222.1, of IRC 6-2000, in Seismic Zone - III, only those bridges having span
length more than 15m or bridge length more than 60m are to be designed for seismic force.
Therefore seismic force shall be considered in the design of bridges according to their overall
length / span length.
Bearings
Crash barriers have been proposed for all new bridges as per provision of IRC:5-1998.
Expansion Joints
65mm thick wearing course comprising of 50mm thick bituminous concrete (laid in 2 layers
of 25mm thick each) laid over 15mm thick layer of mastic asphalt, has been proposed in
accordance with section 500 of MOSRTH specifications.
Design Concrete Strength
Severe exposure condition
For Foundations M-35
considered as Arabian Sea is
For RCC Substructure M-35 very near.
For RCC superstructure M-35
For PSC superstructure M-40, M-45
Untensioned Reinforcement
Inland waterways authority of India have declared west coast canal from Kottapuram
to Kollam as National Waterway no. 3 of class-III type. As per draft regulations of
IWAI following clearances are to be provided in case of new structures over this
waterway
Horizontal Clearance
- Foundations 2.5m
Protective Coating
Since the proposed bridges / structures are in proximity of Arabian sea it is proposed
to provide protective coating to all exposed concrete surfaces.
Design Standards
Designs for various components of bridges shall be carried out as per following IRC
codes of practice:
IRC:SP:64-2005
Bearings
IRC:83-1987 (Part-II) for Elasomeric bearings (with amendments in 2000)
IRC:83-2000 (Part-III) for POT/PTFE bearings
Expansion Joints
IRC: SP-69
Protection Works
IRC: 89-1997
Based on the above stipulations General Arrangement Drawings for all of the bridges
and structures in Package-II have been prepared and are contained in Volume-III.
• Due to change in ROW width from 30m to 45m new cross-sections for 4-laning
were developed and sent to NHAI for approval on 31.05.2007 and 06.07.2007.
• Approval in principle for the modified 4-lane cross-section has been received
from NHAI vide their letter no. NHAI/BOT/11012/67/2005 dated 15.11.2007.
• Extension of Time (EOT) upto 31st Jan 2008 has been approved by NHAI vide
their letter of 15.11.2007 referred to above.
• Approval for additional cost as variation is awaited from NHAI.
14. SITE VISIT
A site visit was undertaken by Team Leader accompanied by Senior Surveyor from
4th December 2007 to 10th December 2007. After the approval of the modified X-
sections of 4 laning by NHAI, widening schedule was finalized keeping in view the
ground situation. The abstract of widening is indicated as under:
Package
30.910 28.980 1.680 24.000 85.570
II
Based on above, the modified alignment plans have been prepared and sent to NHAI
vide letter no. ICT: 436: TL:1523 dated 18.02.2008.
15. PACKAGING
The entire length from Cherthalai to Thiruvananthapuram of NH-47 in Kerala has
been divided into two sections. The present report deals with Package-II from Ochira
to Thiruvananthapuram in Km 465.000 to Km 551.900.
16. TRAFFIC
16.1 General
The following necessary traffic surveys have been carried out as stipulated in the terms of
reference in order to obtain data for efficient design, reliable economic analysis and to depict
the reality scenarios.
Introduction
To get consequence, to the above requirements, the project road was considered for:
1. The influence and location of major intersecting/feeder roads
These features facilitate a framework for carrying out the necessary count surveys in
accordance with the guidelines specified in IRC codes of practice. The various survey
locations have been selected with careful assessment of the traffic characteristics including
entry and exit point along the NH 47 corridor. These points were further refined jointly at site
with the NHAI. The final locations of various surveys were carried out are furnished in Fig. 1.
The approach and methodology employed for carrying out the traffic surveys in the project is
described in the following paragraphs.
Manual traffic counts have been conducted between November 8, 2005 and December 3,
2005.The counts have been carried out in both directions, for successive 15-minute periods,
24 hours a day for 7 consecutive days. Various types of vehicles counted were converted into
PCU using the respective PCU factors. The summary of Average Daily Traffic (ADT) is
given in Table 20.
Location of Survey
Non Motorized
Chainage (km)
With Trailer
ADT (PCU)
3-Wheelere
Station No.
2-Wheeler
Vehicle
Trucks
Car
167 592 220 111 134
VC1 485 Neendakara 6570 60 971 23890
5 2 9 2 6
278 745 211 145 100
VC2 511 Chathanoor 8200 66 607 27068
0 4 9 8 1
2
Kall 1
amb 197 384 177 115 5
VC3 7692 946 18 346
5 2 8 4
alam 0
1
Che
2
mpa
0
ka
119 385 186 1
VC4 8410 843 953 35 72
man 3 9 0
3
gala
5
m
The diminished commercial traffic at km 526, in comparison with at km 511 volume count
location is due to the diversion of the traffic to Paravoor and Kottarakara which are of
commercial importance. The ADT percentage composition of the traffic Volume counts at
each location is given in Table 21.
Table 21: Average Percentage Composition of Traffic
Percentage Composition
Chainage (Km)
Motorized Two
Goods Vehicles
or Commercial
Three Wheeler
Mini Bus)
Wheeler
Vehicles
Vehicles
Buses/
Car
The surveys have been carried out on one working day for 24 hours on a random sampling
basis. All categories of motorized vehicles (e.g. Cars, Jeeps, Buses, light as well as heavy
goods vehicles), have been surveyed for its trip origin, destination, trip purpose, occupancy
and weight of commodity carried. The survey crew was organized into 3 groups by 8-hour
shifts with sufficient enumerators in each traffic direction as well as in groups. Classroom
training were given to the enumerators in order to get acquainted the work and in the use of
standard interview sheets. Police help was sought to ensure smooth flow of traffic and for
stoppage of randomly selected vehicles. Engineers supervised the whole survey activities. The
locations of OD survey conducted are given in Table 24.
Table 24: OD survey locations
S.No. Chainage (Km) Location
1 485.000 Neendakara
2 530.000 Alamcode
The traffic census and the axle load surveys have been conducted simultaneously. In traffic
census surveys, all types of vehicles traveling in both directions have been counted
throughout the axle load survey period to provide the actual break down of the traffic
composition at the particular location. It was not possible to weigh all the commercial
vehicles because of the requirement of stopping a vehicle for weighing, nevertheless, a
attempt was made to capture large amount of commercial vehicles passing through survey site
to know the pattern of loading. About 10% of commercial vehicles have been weighed in the
24 hours duration.
The major proportion of the total number of vehicles selected in this survey comprised of two
axle trucks and light goods vehicles because of its presence in high percentage in the total
traffic flow. The Vehicle Damage Factor (VDF) is an important index factor in characterizing
the traffic loading for a road. It is a multiplier for converting the number of commercial
vehicles of different axle loads, to the number of standard Axle load repetitions. The VDF,
calculated for all commercial vehicles on the basis of Axle load survey carried out on the
project road is given in Table 26.
Table 26: Vehicle Damage Factor (VDF) for Commercial Vehicles
Chainage
Location Type of Vehicle VDF
(Km)
2 - Axle truck 5.021
Neendakara 485.10
3 - Axle truck 4.453
Chainage Type of
Location Total Flow Samples
(km) Traffic
Passenger 8524 730
485.00 Neendagara
Goods 2686 240
Passenger 9470 835
530.00 Alamcaud
Goods 2115 205
Introduction
The interviewees were first briefed about the proposed project road covering nearly
175 kms, along with the benefits, which are expected to accrue from it to the users.
Thereafter, they were asked of their view on the project, followed by their willingness
to pay and the reason for the same. In case a respondent declined to pay the toll,
attempt has been to understand their reaction in case tolls were anyway imposed to
use of the study corridor.
The data was analysed to determine how the highway users react to tolls. For this purpose,
goods vehicles and passenger vehicles were analysed separately.
Passenger Vehicles (Cars)
Willingness To Pay
Of all the respondents, approximately 19% are not willing to pay the toll. For those who are
willing to pay, nearly 17% respondents would not pay more than Rs. 50 per trip. A toll of Rs.
75 is acceptable to 13% of respondents whereas 26% are ready to pay a toll of Rs. 100 and
25% of total respondent are ready to pay toll more than Rs. 100.
Reasons for Paying the Tolls
Maximum number of people (33%) are willing to pay toll due to expected reduction in
transport costs. While 20% and 18% people are willing to pay because of increased safety and
better riding quality respectively, only 10% would pay because of higher speeds. Rest would
pay as they feel it is a legal enforcement. Thus safety and vehicle operating costs are the two
crucial factors according to the perception of car owners.
Reaction to Higher Tolls
In case the respondents are not willing to pay tolls to the extent fixed by the NHAI,
then their reactions to the situation that they will not be allowed on the facility, has
been recorded. If the users are charged higher toll than acceptable to them, nearly
21% responded by saying that they would change their mode of travels. 24% would
reduce their frequency of travel and 55% of the respondents said that they would pay
because of legal enforcement, as they have no other alternative.
Willingness to Pay
The Bus operators’ survey has been conducted at major bus transport centers in Trivandrum,
Attingal, Kollam and Allapuzha. Of the total number of bus operators surveyed, some
operators have denied paying toll. More than 66% of operators are ready to pay the toll up to
Rs. 300 and only 19% of operators are ready to pay more than Rs. 300.
Reasons for Paying the Tolls
The main reason for paying tolls has been cited by 38% of respondents as ‘better riding
quality’. Rest of them is willing to pay due to expected reduction in transport costs and
increase in speed and time saving. Thus, good pavement quality leading to a comfortable ride
is the main reasons for paying the toll by bus operators.
Truck Operators’ Interview
Speed has emerged as the unanimous reason for paying tolls, for most of the truck
operators. This helps in completing their trips in shorter time and hence higher vehicle
utilization.
For the passenger vehicles, however, it was found that if the users are charged higher
toll than acceptable to them, nearly 21% would change their mode of travel, 24%
(approx.) would reduce their frequency and 55% would pay as forces by law, as they
have no other alternative.
Cross-pedestrian counts at the following five major intersections have been carried
out at designated locations as required along the project road.
Introduction
The OD survey analyses and survey of truck parking facilities did not reveal the
requirements of truck parking terminal on the section of the project road.
Road accident statistics of the project road section have been collected from pertinent
police stations in Alappuzha, Kollam and Thiruvananthapuram districts. The details
collected are summarised and the same is furnished in Table 29.
2005
(up to 1024 899 70
September)
The less number of road accident in Thiruvananthapuram district is due to less length
of project road as well less number of big urban stretches involved in comparison with
Alappuzha and Kollam districts. Of the total project road length, 48% and 34 % falls
in Alappuzha and Kollam districts respectively and the rest 18% fall in
Thiruvananthapuram district.
General
The returns from transport sector depend on the agricultural and industries economy of the
country. This is especially true in the case of developing nations where transport is the
catalyst for all round development and also one of the basic infrastructures. When the capital
Year
Mode
2007 2012 2017 2022 Beyond 2022
Cars 1.20 1.35 1.22 1.10 0.99
Buses 1.50 1.67 1.50 1.35 1.22
Trucks 0.80 0.86 0.77 0.70 0.63
Motorized two wheelers 1.80 1.97 1.77 1.59 1.43
3 wheeler 1.10 1.26 1.19 1.02 0.92
Growth in population and per-capita income are the principal parameters for forecasting
future passenger traffic demands. The following formula combines these parameters to get
the passenger vehicle elasticity:
Annual growth rate = [(1 + P/100) (1 + I/100) – 1] x 100 x E
Where:
P = annual population growth rate
I = annual per-capita income growth rate
E = elasticity coefficient.
For goods vehicles, the principal parameters are agriculture, mining, industry, trade and
commerce, which are combined and averaged before applying the elasticity coefficient to
obtain the growth rate.
Future patterns of change in various parameters such as population, NSDP, primary and
secondary industries, trade and commerce, fuel consumption and etc could only be estimated
with limited accuracy. Three scenarios related to future socio-economic trends in the form of
‘most probable’, ‘pessimistic’ and ‘optimistic’ are thus adopted for comparison with the
growth rates determined from the analyses of category wise growth of motor vehicles in
Kerala state. The growth rate obtained from elasticity method is named as ‘most probable’.
Other two considerations of 10% lower and 10% higher growth rates in comparison with most
probable case are named as ‘pessimistic’ and ‘optimistic’ respectively. The growth rates
developed for each of these scenarios are summarised in Table 32.
Mode Year
Beyond
2007 2012 2017 2022 2027
2027
Trucks 4.5 4.9 4.5 4.0 3.6 3.6
Motorised Two-
10.3 11.3 10.2 9.2 8.3 8.3
wheelers
3 wheeler 6.6 7.3 6.5 5.9 5.3 5.3
Scenario-2: Projected Pessimistic Traffic Growth Rate
Cars 6.4 7.0 6.3 5.7 5.1 5.1
Buses 7.9 8.7 7.8 7.0 6.3 6.3
Trucks 4.0 4.5 4.0 3.6 3.2 3.2
Motorised Two-
9.3 10.2 9.2 8.3 7.4 7.4
wheelers
3 wheeler 5.9 6.5 5.9 5.3 4.8 4.8
Scenario-3: Projected Optimistic Traffic Growth Rate
Cars 7.8 8.6 7.7 6.9 6.2 6.2
Buses 9.6 10.6 9.5 8.6 7.7 7.7
Trucks 4.9 5.4 4.9 4.4 4.0 4.0
Motorised Two-
11.3 12.5 11.2 10.1 9.1 9.1
wheelers
3 wheeler 7.3 8.0 7.2 6.5 5.8 5.8
These growth rates have been calculated with detailed study of economic indicators of Kerala
state and from the guidelines of World Bank for the calculation of elasticity for different
vehicles.
16.13 Traffic Forecast
Historical growth of vehicle registration
The traffic projections based on category wise growth of motor vehicles in Kerala state have
been computed.
Elasticity of Transport Demand
This method of long-term traffic forecasting incorporates analyses of some of the key socio
economic characteristics in the road influence area and its anticipated rates of change during
the study period. These characteristics are taken as indicators for the future growth of traffic.
The growth rates for normal traffic obtained from this approach take some account of the
following factors, which affect future traffic levels
• The prospective growth in the economy,
• The estimated elasticity of demand for transport
• Change in the structure of the vehicle fleet, for example vehicle productivity and changes
in the inter-modal share of passenger and freight demand.
The traffic forecasts computed based on the growth rates estimate for ‘most probable’,
‘pessimistic’ and ‘optimistic’ scenarios from elasticity of transport demand.
16.14 Comparison of Different Method Of Forecast
Monthly Progress Report
1 - 68
The traffic fore cast comparison of different method is given in Table 2.53. The elasticity
demand takes into account of different socio – economic profile factors and thus the future
growth may not perfectly depict. Of the 3 scenarios developed by the Elasticity of transport
demand approach, the most probable scenario give the closest comparison with the
projections computed by historical growth of vehicle registration method. The traffic forecast
computed by most probable method has been adopted for design and economic analysis.
16.15 Inference
Two scenarios were examined here namely
• Do nothing option
• Widening the existing road to four/ six lane capacity
The impact of speed for various links is considered in this option. The speed flow analysis
using the following Road User Cost Study equations is carried out. Substituting the normal
growth of traffic for the required period the average speed of different modes with base year
flow are computed.
Two lane carriageway speed equations (with earthen shoulders)
Vc = 85.45 – 0.017Q
Vb = 66.79 – 0.013Q
Vt = 58.96 – 0.008Q
Vtw = 51.58 – 0.007Q
Four lane carriageway speed equations (with paved shoulders)
Vc = 92.79 – 0.0075Q
Vb = 74.48 – 0.0042Q
Vt = 63.25 – 0.0047Q
Vtw = 57.21 – 0.0062Q
Where,
Q: Traffic flow in PCU
Vc, Vb, Vt, and Vtw: Speeds of cars, buses, trucks and motorized two wheelers respectively.
The entire project road stretch passes through plain terrain barring about 15 km stretch which
is between plain and rolling. Thus Plain terrain with curvature (degree/kilometer) 0 to 50 is
considered. Design service volume as reveal in IRC 64: 1990, recommend for two-lane road
that has 7 m wide blacktop carriageway with reasonably good earthen shoulders with peak
hour traffic in the range of 8% and level of service ‘B’ is 15000 PCU/day and for four lane
dual roads is 40000 PCU/day. From the projected traffic different carriageway requirement
options are considered. The carriageway options are given in Table 33.
Introduction
Table 33
It is obvious that the project road is already exceeded the capacity requirements of two lane.
The peak hour factors obtained from all the seven count stations are in a range between
6.290% and 6.947%, which are comparatively lower than the peak hour factors of 8% that are
referred in the IRC guidelines. So, about 20% capacity may be increased. Accordingly the
requirement and go beyond of four laning facilities are calculated
It is evident from the traffic studies that the entire project road stretch from km 379.100 to km
551.900 is already exceed its capacity and warrant four lane facilities right at the moment.
Table 34: Carriageway Option
Highway grade separators are envisaged at intersection of divided rural road if the ADT (fast
vehicles only) on the cross road within the next 5 years is likely to exceed 5000 and otherwise
the need for such facilities could be kept in view for future consideration/construction. An
interchange may be justified when an at-grade intersection fails to handle the volume of
traffic resulting in serious congestion and frequent choking of the intersection. This situation
may arise when the total traffic capacity of all the arms of the intersection is in excess of
10,000 PCU/ hours. Based on these considerations the following conclusion is arrived. The
type of intersections proposed are given in Table 36.
Table 36: Types of intersections proposed.
Warrant of interchange arise in Kollam city (km 495.90) Paripally (km 518.00) and
Kallambalam (km 527.00) at-grade junctions in the year 2017. In the year 2027, the at- grade
junctions in X ray hospital (km 392.10), Power house bridge junction (km 411.20),
Nangairkulangara (km 447.40), Kayamkulam (km 458.00), Kottiyam (km 506.00), Attingal
(km 534.00) and Mamoa (km 536.00) exceed its traffic capacity limit. The project road is
proposed to detour Alappuzha, Kollam and Attingal towns and thus the junctions at Power
house bridge (km 411.20), Kollam city (km 495.90), Attingal (km 534.00) and Mamoa (km
536.00) which lie in these tows may not consider for up-graded interchange facilities. Based
on the peak hour flow all the existing junctions of the project road from km 379.100 to km
551.900 will be considered for ‘at grade junction design’ as per MoSRT &H standards.
17 BYPASS
The project road starts from km 465.000 Ochira and ends at km 551.900 (Kazakuttam
Junction) of NH-47 in Thiruvananthapuram district. There are two number bypass in this
project road length (Stage-II) namely Kollam bypass and a new Attingal bypass to bypass the
Attingal town where the RoW is too less in view of constructed held up.
17.1 Kollam Bypass
The alignment of this bypass starts in Allharamamad at km 488.972 of NH-47 and passes
through Thrikkadavoor, Kallumthazham and Ayathil and ends at km 502.540 of NH-47
Since proposed alignment of NH-47 in Kollam bypass is crossing NH-208, it is proposed to
provide a flyover at this location.
There is an ROB on Kollam bypass. An additional 2-lane ROB is proposed by its side 3 nos.
additional minor bridges for the exiting bridges on existing portion of 2-lane road and 3 nos.
4-lane new bridges and one underpass.
17.2 Attingal Bypass
There is a town Attingal from km 530.400 to km 536.600 (municipal limit) on National
Highway 47 in Kerala. Due to heavy builtup commercial area and right of way (ROW) being
less than 30m, construction of four lane (divided carriageway) with service road is not
possible. Construction of bypass from km 528.400 to km 537.400) or flyover in 536.500.
Length of bypass comes to 10.8 km. Length of flyover is about 6.5 km. The cost of flyover
shall be about Rs. 390 crores, while cost of bypass shall be about Rs. 150 crores.
Moreover for flyover a four lane with 1.5m footpath on both side the width of structure is
20m, if no improvement is geometric is taken into account at least one metre clearance shall
be required on both side. There are upto three stories building (10m height) on both side of
the road, hence we require 22m wide space for to 536.500 (Table 37 & Table 38) is less than
22m. At places it is 13m only. Hence construction of four lane flyover is not possible at
Attingal.
In brief advantage of bypass over flyover are as follows;
• Bypass is less costly
• Bypass shall help city to develop & expand
• Kizhattingal village
• Attingal Municipality village
• Kizhuvallam village
There are four villages coming under the Chirayinkil Taluk and Trivandrum District.
Alignment Details
Proposed bypass is starting from Manamboor junction places are near Deviapura
Nagar temple after the Thottakkhade, Valakottumala, paddy field region, Puthencode
region, Perumkulam region, MLA palam near palamkonam jn. Mosque region –
Meleattingal. Thottavaram-paddy field area, cutting of Kunnuvaram road-build up
area. Then reaching the Ramachanvila region-build up area then coming the paddy
field area. Kaduvayil Ela-Kavanasseri Ela in Kizhuvallam village-Chittanttinkara
Desam reaching the Mamom bridge into the NH-47 road.
G5 = 5 cm
G6 = 3 cm
(e) Tarmaric Trees = 11 nos.
Details of girth is as follows:
G2 = 11 cm
(f) Cashew Trees = 21 nos.
Details of girth is as follows:
G1 = 21 cm
(g) Palm Trees = 1 no
Details of girth is as follows:
G1 = 1 cm
(h) Other Trees = 5 nos.
Details of girth is as follows:
G1 = 2 cm
G3 = 3 cm
Total number of trees to be cut on Attingal Bypass = 2887 nos.
Hence for bypass RHS alignment is recommended for final adoption. Tentative length of the
bypass is 12 km.
18. DESIGN OF PAVEMENT
Design Life : 20 Years (Flexible)
Design Traffic : 100 msa for main carriageway; 10msa for service road
Design CBR : 8%
Pavement Composition
New Pavement:
Bituminous Concrete : 50mm
Dense Bituminous Macadam (DBM) : 140mm
Wet Mix Macadam (WMM) : 250mm
Granular Subbase (GSB) : 200mm
Overlay:
Bituminous Concrete : 50mm
Dense Bituminous Macadam (DBM) : 140mm
Profile Correction with DBM : 50mm
Service Road:
Bituminous Concrete : 40mm
Dense Bituminous Macadam (DBM) : 60mm
Wet Mix Macadam (WMM) : 250mm
Granular Subbase (GSB) : 200mm
19.1 General
Improvement of surface connectivity through construction of new roads or strengthening/
upgradation of existing roads is generally undertaken to improve the economic and social
welfare of those using the road or served by it. The need for faster growth in the economic
and social sectors has propelled the Government of India to invest liberally in infrastructure
development program and strengthening the road network of the country has got a focus.
There is a realization that improved connectivity goes a long way in integrating the markets in
the country and providing a level playing field for the manufacturers and producers located in
different regions. The project of 4-laning of Cherthalai Thiruvananthapuram section (km
379.10 to km551.90) of National Highway NO. 47 in the state of Kerala is a part of the
National Highway Development Program. The project involves rehabilitation and upgrading
of the existing 2-lane road and widening it to 4-lane dual carriageway. The project road has
been divided into two packages. Package-II starts at Ochira (km 465.000) and ends at
Thiruvananthapuram
(km 551.000). This package starts in the Kollam district and is confined within the boundaries
of the districts of Kollam and Thiruvananthapuram. Kollam is a center for cashew processing
industries. Kollam has also the second largest estuary of Kerala in Ashtamudi lake which in
the recent past has been declared as a Ramsar site.
19.2 Description of the Project
The package of NH 47 – the busiest highway in the state of Kerala covers the stretch between
km 465.000 and km 551.900. It primarily runs through the district of Kollam and
Thiruvananthapuram. This stretch passes through settlements of Karunagapally, Chavra,
Attingal, Pallipuram and Mangalpuram etc. Quite a few of these settlements are thickly
populated. To avoid large scale dislocation of people and property, it has been proposed to
construct a bypass at Attingal and elevated roads at some of the thickly populated towns.
The carriageway of the existing road on an average varies between 10m and 13m except in
few patches where the carriageway is narrower. The package has some stretches where the
divided 4-lane carriageway has already been constructed. Built up areas occupy the bulk of
the land along the project corridor. A large number of junctions punctuate the road
Roadside plantations of varying densities and species composition line almost the entire
stretch of the road. Some locations have the Arabian sea close by. The project road also
crosses backwaters at a few locations.
19.3 Environmental Management Plan
Environmental Management Plan (EMP) is the means to ensure that the environmental
quality of the zone dos not get adversely impacted beyond acceptable level due to the
construction and operation of the project. The plan lays down measures for three distinct
phases - (a) design phase (b) construction phase and (c) the operational phase. This plan
suggests mitigation measures against all identified impacts. Environmental management
matrix provides detailed management measures for specified anticipated impacts and defines
responsibilities of each participating organization. Mitigation and management measures have
been detailed out for impacts on water bodies, roadside vegetation, water /air/sound quality,
road safety, drainage as well as sanitation of labour camps.
Introduction
Monitoring of environmental quality during construction and during operation reflects the
success of implementation of the mitigation measures. Monitoring will be conducted by the
project authority with the help of an independent monitoring organisation Monitoring
parameters, locations and frequency for air, water, noise quality have been suggested.
Monitoring of survival rates of plantations also has been suggested.
A budgetary estimate of Rs. 750.00 lacs for environmental management activities has been
prepared. This includes cost of mitigation measures, enhancement and monitoring.
Environmental mitigation measures, which are part of engineering activities such as slope
stabilization, sediment/ silt control, provision of cross-drainage etc. have not been included in
this estimate.
20. INITIAL SOCIAL ASSESSMENT
20.1 General
The Resettlement Action Plan (RAP) is based on social impact assessment of the
potentially affected owners of houses, shops, hotels, tea stalls, business and
agricultural land including impact on local community infrastructures due to widening
of National Highway – 47. In view of the human involved, the possible social
impacts have been integrated into the improved alternative engineering designs to
minimize resettlement and forced displacement. This task has been achieved by
adopting road engineering techniques in terms of the provision of Alappuzha bypass,
realignment, widening and reduction in median width at congested settlements. The
RAP provides details to implement provisions of the policy framework, including
institutional arrangements and budgets based on enumeration of project-affected
people with entitlements under the framework.
20.2 Budget
The estimated budget for R&R is Rs.384.44 crores including land acquisition. The
item wise detailed indicative budget of the R&R component of the project will be
The estimated cost (civil cost) of this package based on 2006-07 rates works out to
Rs. 912.75 crores. This has been updated to Rs. 1006.31 crores after adding
escalation for 2 years @ 5 % per annum i.e. Rs. 11.76 crores per km (Total Length =
85.57 km). After adding contingency and supervision charges and cost of shifting
utility services, environmental mitigation measures, land acquisition and resettlement
and rehabilitation charges, the cost comes to Rs. 1564.90 crores i.e. Rs. 18.29 crores
per km.
Introduction
This chapter presents the economic analysis for the project road section from km 465.000 to
km 551.900 of NH-47 in the state of Kerala. The economic analysis is carried out within the
broad framework of social cost-benefit analysis. The appraisal compares the total transport
costs in situations of “with” the project and “without” the project alternatively called the
“base case” or the “do minimum case” for the project highway.
The underlying objective of economic analysis is to maximize the returns on the investment.
The concept behind the economic appraisal of the project is that if it is implemented, the
resulting benefits will be the decreased road users costs when compared to the costs of the
‘base’ situation.
The total transport costs comprise two basic components, viz. road supplier costs and road
user costs.(Table 39)
Table 39: Total Transport Costs
Methodology
All costs considered in the analysis are valued in money terms at the market prices. For
economic analysis, these are expressed as economic costs for avoiding distortions in the
prices of inputs such as labour, materials, equipment, and machinery i.e. market prices net of
transfer payments such as taxes and subsidies arising due to market imperfections. The
transport costs are estimated for the ‘Do nothing’ and ‘With Project’ scenarios. The reduction
in these costs under ‘With Project’ scenario, alternatively called the savings, are treated as
economic benefits corresponding to the incremental investment estimated over the life of
project.
Introduction
The economic appraisal is carried out by using the ‘Highway Development and Management
(HDM 4) Model’. The model is used to generate cash flow streams of VOCs and travel time
costs to compute the net economic benefits, as inputs for the estimation of the IRRs and NPVs
for project evaluation.
Project Option
Economic evaluation for the project road from km 465.000 to 551.900 has been carried out.
The project option considered is:
Widening and strengthening of existing 2-lane (partly 4-lane) National Highway to four lane
carriageway configuration with 7.0m wide service lane on either side.
Basic Input Data
The basic input data used for the application of HDM-4 have been grouped into following
categories:
General
Traffic
Road Condition and Pavement design
General Data
Pavement Option : Flexible Pavement has been considered for proposed four
lane carriageway configuration of existing 2-lane highway
Construction Period : Construction period for the section from km 465.000 to km
551.900 has been assumed as 30 months i.e. from April
2009 to Sept 2011.
Investment Schedule : For construction period, the distribution of cost for each
year is given as below:
1st Year - 30 %
2nd Year – 40 %
3rd Year – 30 %
Analysis Period : 20 years
Discount rate : 12%
Solvage Value : 15%
Project Cost
Estimated cost for project option is as given in below Table 40
Table 40 : Estimated cost for Construction
Construction Cost
Option
(Rs. in million)
New four lane carriageway configuration of existing 2-
10063.10
lane highway
The foreign exchange component in the total capital cost is insignificant and has been
considered to be zero, as all material, machinery and labour are available in India. Standard
Conversion factor of 0.90 has been used for converting market prices of road construction and
maintenance inputs into economic costs.
Traffic Volume and Composition
Two Wheelers
Car/Jeep/Van
(Passenger)
in Nos.
LGV
Bus
485.00 19062 34.47 2.14 9.45 8.79 31.07 7.06 5.83 0.89 0.30
511.00 23161 35.40 2.21 6.94 12.00 32.18 4.32 6.30 0.36 0.28
526.00 17577 43.76 2.94 8.17 11.24 21.86 6.55 4.90 0.48 0.10
540.00 17513 49.03 4.41 6.43 6.96 22.50 5.56 4.44 0.48 0.20
Estimated growth rates used for projection of traffic to horizon years are given in Table 41.
Table 41: Estimated Traffic Growth Rates (%)
Year
Mode 2005 - 2008 - 2013 - 2018 - 2023 - 2027
2007 2012 2017 2022 2027 onwards
Cars 7.1 7.8 7.0 6.3 5.7 5.7
Buses 8.7 9.6 8.7 7.8 7.0 7.0
Trucks 4.5 4.9 4.5 4.0 3.6 3.6
Motorized two
10.3 11.3 10.2 9.2 8.3 8.3
wheelers
3 wheeler 6.6 7.3 6.5 5.9 5.3 5.3
Existing Road Condition: Other parameters like pavement condition data, roughness
Pavement Deflection (BBD) of various sections have been taken from respective chapter and
are summarized in the Table 42 and Table 43.
Table 42: Existing Roughness (m/Km) of various sections
Chainage (km.)
Sl. No. Length (km) Roughness (m/km)
From To
1 465 490 25 3.15
2 490 517 27 3.09
Introduction
Chainage (km.)
Sl. No. Length (km) Roughness (m/km)
From To
3 517 530 13 3.47
4 530 551.900 21.90 2.98
The base objective of the financial analysis is to determine whether the Build Operate
and Transfer (BOT) model is workable for the stretch Ochira to Thiruvananthapuram
(km 465.000 to km. 551.000) and if so, under what conditions.
Financial Analysis has been carried out for the following scenarios.
With 20%
equity support 611.53
2 25.94 18.96
+ 20% O&M Crores
support
23.2 The memorandum for Public Private Partnership Appraisal Committee (for ‘Final’
approval) has also been prepared and is sent herewith as Annex III together with brief
particulars of the Concession Agreement (Annex III-Appendix ‘A’).
The economic with sensitivity analysis and financial analysis results show that the
project is economically and financially viable even without any grant from NHAI.
The project is therefore recommended to be taken up on priority for 4 laning under
BOT (Toll).
•••
2005 23892 23892 23892 23892 27068 27068 27068 27068 21533 21533 21533 21533
2006 25754 27477 27300 27653 29241 31261 31053 31466 23203 25673 25514 25831
2007 27778 29417 29035 29800 31604 33526 33079 33973 25013 27408 27065 27751
2008 29979 31520 30902 32144 34173 35981 35258 36711 26974 29283 28730 29841
2009 32373 33801 32910 34706 36969 38645 37603 39703 29100 31309 30515 32116
2010 34978 36274 35072 37506 40010 41534 40127 42975 31405 33499 32431 34593
2011 37812 38956 37399 40568 43321 44668 42845 46552 33905 35867 34487 37293
2012 40898 42154 40152 44264 46927 48405 46059 50872 36618 38680 36911 40538
2013 44259 45651 43138 48345 50853 52493 49546 55641 39561 41747 39532 44107
2014 47920 49478 46377 52851 55132 56967 53328 60910 42756 45090 42365 48032
2015 51909 53668 49892 57830 59794 61866 57434 66731 46225 48736 45429 52351
2016 56257 58255 53707 63333 64877 67230 61890 73166 49993 52714 48743 57105
2017 60997 62786 57436 68789 70419 72526 66249 79546 54087 56625 51972 61798
2018 66167 67706 61452 74761 76464 78279 70945 86533 58535 60854 55435 66913
2019 71808 73056 65785 81308 83060 84532 76010 94190 63370 65443 59165 72505
2020 77962 78867 70451 88477 90258 91327 81467 102578 68628 70403 63164 78600
2021 84680 85188 75487 96339 98116 98718 87354 111775 74345 75787 67472 85264
2022 92015 91374 80380 104099 106696 105955 93079 120856 80566 81030 71640 91808
2023 100026 98050 85623 112538 116068 113767 99211 130731 87334 86675 76096 98903
2024 108777 105256 91238 121714 126306 122198 105781 141470 94701 92748 80855 10659
2025 118339 113034 97254 131696 137495 131300 112819 153152 102722 99282 85938 11492
2026 128790 121431 103701 142555 149726 141128 120362 165862 111457 106314 91369 12395
2027 140216 129610 109877 153185 163099 150701 127589 178304 120972 113142 96562 13276
2028 152711 138379 116449 164661 177724 160966 135281 191738 131339 120442 102073 14224
2029 166378 147783 123445 177052 193722 171976 143468 206244 142638 128247 107925 15245
2030 181331 157870 130891 190434 211227 183785 152184 221911 154955 136596 114137 16343
2031 197694 168690 138818 204889 230386 196455 161463 238836 168386 145525 120734 17526
2032 215606 180298 147258 220506 251358 210049 171344 257122 183035 155078 127740 18800
2033 235217 192755 156246 237380 274323 224637 181866 276883 199017 165300 135181 20172
2034 256693 206124 165818 255617 299474 240295 193073 298241 216457 176239 143086 21650
2035 280216 220474 176013 275330 327026 257103 205010 321329 235492 187947 151484 23243
Note: In this section of the project road the growth rate of traffic is about 6% and
so considering the traffic in the various years the project road can safely
cater the traffic of 4-lane upto the year 2016.