Dr Khairuddin Abdul Rashid

Session 5
PWD Form DB/T (2002)
Conditions of Contract
Clause 46 – 62

1
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 46 Procedure for Claims

 Cl. 46.1 if the contractor


intends to claim … he must
submit written notice together
with an estimate of the
amount within 60 days of the
occurrence of an event…
 Cl. 46.2 in relation to Cl. 46.1,
the contractor must submit
details within 90 days of CPC.
Amount to be added to the
contract sum

2
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 47 Testing and
Commissioning of M/E and
other Services

 The contractor shall arrange


for all necessary tests to be
carried out on the equipment
and installation, on
completion of the installation
work… the costs should have
been included in the contract

3
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 48 Defects After
Completion
 DLP = 24 months
 Contractor to repair at his own
cost upon instructed by the PD
 Schedules of Defects: 1st
within 14 days; and the final
schedule not later than 28
days after the DLP
 Contractor has up to 3 months
after receiving the final
schedule to make good any
defects, etc

4
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 48 Defects After
Completion

 Cl. 48.5 PD to issue the


Certificate of Completion of
Making Good Defects if the
contractor has fulfilled his
obligations under Cl. 48.1 and
48.2

5
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 49 Unfulfilled Obligations

 Notwithstanding the issue of


CCMGD as per Cl. 48.5, both
parties remain liable for the
fulfillment of any obligations
incurred under the contract

6
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Salient points (amendments) on
payments

 Schedule payment
 Payment based on valuation of
works
 Deferred payment

To be determined by the PD
before tender is called

7
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 50 Interim Payments

 Cl. 50 1(a) Payment Schedule


as Appendix 2. Prepared and
agreed mutually based upon
the approved programme of
works

 PD may pay according to


work done…

8
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 50 Interim Payments

 Cl. 50 1(b) Where there is no


Payment Schedule, interim
payment shall be made based
on PD’s monthly valuation of
work done

 Cl. 50.2 The contractor shall


submit to the PD written
application for interim
payments

9
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 50 Interim Payments

 The contractor’s application


shall show separately:

 based on schedule – amount


of variations (Cl. 28) and
amount of Provisional Sums
executed (Cl. 29)
 Not based on schedule – value
of goods or unfixed materials

10
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 50.3 (a) Schedule
Contractor’s application
14 days

OK?
Yes NO

PD issue PD issue notice


interim certificate and Govt. pays
pays within within 30 days
30 days (Cl. 50.3(c) (Cl. 50.3(c)

11
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 50.3 (b) No schedule
Contractor’s application
28 days

Valuation (work done + 90%


matls. on site) sum not less
than the sum stated in
Appendix 1

PD issue
interim certificate
pays within
30 days (Cl. 50.3(c)

12
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 50.3 (c) Honoring of
interim certificates = 30 days
from issue of the same

 Performance Bond – full value


as in the certificate

 Performance guarantee sum –


90% of the amount certified…
10% retained as the guarantee
sum until the total amount
retained is equivalent to 5% of
the contract sum

13
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 51 Final Account and Final
Certificate

 Cl. 51.1 The contractor to


submit a statement of the final
account with supporting
documents not later than 3
months from CCMGD or
CCM
 CL. 51.2 PD to issue the Final
Certificate within 3 months
after receiving the contractor’s
document as stated in Cl. 51.1

14
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 51 Final Account and Final
Certificate
CCMGD or CCM
3 months

Contractor’s documents (if none


3 months PD sends notice)
2 months
Final Certificate

15
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 51.6 Condition precedent
to Final Payment is deleted
(see Amendments note 7)

 A Statutory Declaration, or
 A Certificate signed by/or on
behalf of the DG of Labor
That all payments to workmen
have been paid

16
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 52 Effects of PD’s
Certificate

 PD’s certificate, any approval,


or payment… not considered
as conclusive evidence
 PD’s certificate shall be final
and binding if there is a
dispute brought before an
arbitrator or in the courts

17
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 53 Deduction from Money
Due to Contractor

 The Government or the PD is


entitled to deduct any money
owing from the contractor to
the Government under the
contract which may become
due or payable to the
contractor under the
contract…

18
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 54.1 Determination of
Contractor’s Employment
Determination if the contractor
shall make default in any one
or more:
 Suspends the design or
construction
 Fails to proceed regularly and
diligently
 Failed to follow contract
 Refuses to comply with PD’s
instruction
 Fails to comply with Cl. 31

19
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 54.2 Determination of
Contractor’s Employment
Determination if the contractor:

 Is bankrupt
 Becomes insolvent
 Company winding up
 Having a provisional
liquidator

20
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract

Clause 54.3 Post determination

 Procedures as per Cl. 54.3(a)


– (f)

Clause 55 War or Earthquake

 To continue? To suspend? To
terminate?... Settled by mutual
agreement or Arbitration

21
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract

Clause 56 Arbitration

 Any dispute… refer to the


person named in Appendix 1
 The officer decides (within 45
days, in writing) and is
binding to the parties until
after the completion of the
works
 If the above fails… refer to
Arbitration … see Cl. 56.3
and Cl. 56.4-56.9

22
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract

Clause 57 Law Governing the


Contract

 Malaysian Law and Malaysian


Courts

Clause 58 Stamp Duty

 To be borne by the Contractor

23
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Special Conditions
Clause 59 Maintenance

 Cl. 59.1 The contractor shall


maintain the whole works and
services for 24 months from
CPC (for scope refer to the
Government’s Requirements)

 Cl. 59.4 PD to issue


Certificate of Completion of
maintenance upon completion
of all maintenance

24
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Special Conditions
Clause 60 Direct Payments and
Consultancy Agreement with
Contractor’s Consultants
 Cl. 60.1 -60.2 agreement with
consultants must follow the
JKR Standard Form of
Agreement For Consultancy
Services
 The contractor recommends to
the PD for payments… the
Government pays direct to the
respective consultants

25
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Special Conditions
Clause 61 Bills of Quantities

 Only provisional quantities.


Firm quantities shall not form
part of the contract.

 Rates in the BQs shall be used


as basis from valuation of
variations (Cl. 28)

26
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Special Conditions
Clause 62 Advance Payment

 Cl. 62.1 The contractor is


entitled – 15% of the Builder’s
Work or maximum of RM5.0
million. Condition precedent:

 LA duly signed, with


Performance Bond, Insurances
and SOCSO, with all receipts
 Advance payment guarantee

27
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Special Conditions
Clause 62 Advance Payment

Treasury Letter 10/02:

 25% of builder’s work,


maximum RM10.0 million
 20% of NSC’s work,
maximum RM5.0 million

28
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Special Conditions
Clause 62 Advance Payment

 For recoupment see Cl. 62.2

 Liability under advance


payment is terminated once
the Government realized the
full sum of advance paid

29
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Deferred payment [Amendments]
Cl. 50 Interim Valuations and
Interim Payments
Cl. 63 Loan Disbursement by the
Lender
Cl. 64 Direct Payment to the
Contractor’s Bumiputera
Organizations and or
Professionals
Cl. 65 Financing Cost
Delete Cl. 62 Advance Payment

30
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Deferred payment [Amendments]
 Monthly interim payments are
deferred until CPC
 Contract Sum = Construction
cost + Financing cost
 Lender – BPIMB (Bank
Pembangunan)
 Deed of Assignment between
the contractor and the Bank
 Financing cost = actual cost of
fund + 1%

31
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract

Deferred payment
 There will be monthly interim
valuation & payments
 Direct payments to Bumi
organizations
 Direct payments to
consultants
 Contractor to submit claims
for payments
 PD issue interim valuation
certificate within 28 days

32
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract

Deferred payment
 Lender (the bank) will
disburse payment based on
PD’s certificate
 Govt. pays interim payment
no 1 on CPC = 50% work
done + 50% financing cost
 Govt. pays interim payment
no 2 one year after CPC for
the balance.

33
Dr Khairuddin Abdul Rashid

End of Session 5

34