There are two tabs for VF, separated into DOI & NON-DOI land. The 16 miles (3 VF segements) are
highlighted orange: DV-6, DV-7, DV-8.
Call me with questions.
(b) (6)
Ops & Reporting Business Manager
Desk: (b) (6)
-----Original Message-----
From: (b) (6)
Sent: Monday, March 31, 2008 4:30 PM
To: (b) (6)
Subject: Re: Urgent VF miles
We can't simply lop off 27 to make it nice and clean.....segments are a group of operational miles they
were not intended to take bits and pieces so numbers fit nicely into a package.
Sorry...this is for VF. There are 187 Core CY08 VF miles, but we only need 160 to reach 300. Part of
the extra 27 buffer is to compensate for the 13 miles we are loosing to PF as part of the PF225 core
mileage. There's also a possibility that they may convert more VF for PF contingency miles (if they need
them) so this buffer is also to allow for that possibility.
(b) (6)
Ops & Reporting Business Manager
Desk: (b) (6)
-----Original Message-----
From: (b) (6)
Sent: Monday, March 31, 2008 4:24 PM
To: (b) (6) )
Subject: Re: Urgent VF miles
Ok.
I will also work on getting input from USACE on engineering or real estate constraints that may impact
the scheduling of the 187, while we wait for OBP's ID of the operational priority.
(b) (6)
Ops & Reporting Business Manager
Desk: (b) (6)
-----Original Message-----
From: GIDDENS, GREGORY
Sent: Monday, March 31, 2008 4:16 PM
To: (b) (6)
Cc: (b) (6) 'JEFFREY.Self@dhs.gov'
Subject: Re: Urgent VF miles
We have to ID the 27 less priority miles of the 187. We have 187 light green miles on the map that we
will try to build 160 miles. Which are the priority miles?
Greg G
Are you asking about the 27 miles of CY08 above 300? Or the 56 miles of CY09 miles for VF?? The 27
would be within the light green, but they are not separate from the rest of the CY08 miles. Would be
easier to point out the core PF retrofit that we are compensating for??
(b) (6)
Ops & Reporting Business Manager
Desk: (b) (6) 5
-----Original Message-----
From: GIDDENS, GREGORY
Sent: Monday, March 31, 2008 1:27 PM
To: (b) (6) )
Cc: (b) (6)
Subject: Urgent VF miles
I need to know the locations of the 24 FY09 miles that are in the waiver. I will get asked at 1230.
I need general locations of those miles. Can you point out some of them that are within the light green
on the map?
Greg G
1/2/2009
DOI-
Impacted
Total Land
(Alignment,
Congressi Continge Planne Access Rd, or
Non-DOI
USACE onal SBI ncy d Cum. Actual Fence Constr. Constr. Staging area on Impacted ESA Environmental
Map ID # State Sector Station District Location Project # Mileage Mileage Mileage Type Start Date End Date Updates and Issues DOI Land) Land Impacted Status
PV-1
Initial Assessments
Pack and Evaluations are
A-1 CA SDC BRF 51 Truck Trail 2001-1 3.58 4/15/08 7/13/08 underway 3.58 0 3.58 Draft FINAL EIS.
PV-1
Initial Assessments
W of and Evaluations are
A-2 CA SDC BRF 51 Tecate 2001-2 0.77 9/18/08 11/18/08 underway 0.77 0.77 Draft FINAL EIS.
PV-1
Initial Assessments
and Evaluations are
A-2 CA SDC ECJ 51 Ceti's Hill 2002-1 0.57 9/18/08 11/2/08 underway 0.57 0.57 Draft FINAL EA
PV-1
East
Brickyard
to Initial Assessments
Gunsight and Evaluations are
A-2 CA SDC ECJ 51 Drainage 2002-2 0.58 9/18/08 11/2/08 underway 0.58 0.58 Draft FINAL EA
PV-1
W. Initial Assessments
Horseshoe and Evaluations are
A-2 CA SDC ECJ 51 Canyon 2002-3 0.89 9/18/08 11/27/08 underway 0.89 0.89 Draft FINAL EA
PV-1
Initial Assessments
East Bell and Evaluations are
A-2 CA SDC ECJ 51 Valley 2002-4 0.12 9/18/08 10/5/08 underway 0.12 0.12 Draft FINAL EA
PV-1
Initial Assessments
and Evaluations are
A-2 CA SDC ECJ 51 Ag Loop 2002-5 1.02 9/18/08 12/8/08 underway 1.02 1.02 Draft FINAL EA
Soutwest PV-1
Rim of Initial Assessments
Smith and Evaluations are
A-2 CA SDC CAO 51 Canyon 2003-1 0.17 0.0 9/18/08 10/15/08 underway 0.17 0.17 Draft FINAL EA
PV-1
Rattlesnak
e Ridge to
Larry Initial Assessments
Pierce and Evaluations are
A-2 CA SDC CAO 51 Road 2003-2 1.06 0.0 9/18/08 12/11/08 underway 1.06 1.06 Draft FINAL EA
PV-1
West edge
of Initial Assessments
Boundary and Evaluations are
A-2 CA SDC CAO 51 Peak 2003-3 0.09 0.0 9/18/08 9/27/08 underway 0.09 0.09 Draft FINAL EA
PV-1
Initial Assessments
Willows and Evaluations are
A-2 CA SDC BLV 51 Access #1 2004-1 1.63 0.0 9/18/08 12/2/08 underway 1.63 1.63 Draft FINAL EA
PV-1
Initial Assessments
Willows and Evaluations are
A-2 CA SDC BLV 51 Access #2 2004-2 2.01 0.0 9/18/08 12/19/08 underway 2.01 2.01 Draft FINAL EA
PV-1
Initial Assessments
Airport and Evaluations are
A-2 CA SDC BLV 51 Mesa 2004-3 0.05 0.0 9/18/08 10/29/08 underway 0.05 0.05 Draft FINAL EA
O'Neil PV-1 and Evaluations are
A-2 CA SDC BLV 51 Valley 2004-4 1.47 0.0 9/18/08 11/25/08 underway 1.47 1.47 Draft FINAL EA
PV-1
Mon 224
to ELS Initial Assessments
West and Evaluations are
B-2 CA ELC ELS 51 Checks 2005-3 2.4 8/26/08 11/14/08 underway 2.4 2.4 Draft FINAL EA
PV-1
Initial Assessments
CAX East and Evaluations are
B-4 CA ELC CAX 51 Checks 2006-1 8.59 6/18/08 10/15/08 underway 8.59 8.59 Draft FINAL EA
PV-1
Initial Assessments
and Evaluations are
B-5A CA ELC CAX 51 2006-5 19.2 8/27/08 11/15/08 underway 19.2 19.2 Draft FINAL EA
Special and Evaluations are
B-5B CA ELC CAX 51 2006-2 2.85 Design 6/18/08 8/6/08 underway 2.85 2.85 Draft FINAL EA
Andrade PV-1 &
POE: Special
Imperial Design
sand Initial Assessments
CAX/YU dunes to and Evaluations are
C-1 CA YUM S 51 CA-AZ line 2007-1 10.28 7/24/08 1/4/09 underway 10.28 10.28 Draft FINAL EA
of PF70 PV-2 and Evaluations are
C-2B AZ YUM YUS 7 project to 2007-2 3.70 7/17/08 9/14/08 underway 3.70 0 Draft FINAL EA
Phase 1 Final Walkthrough
E-2B AZ TCA NCO 8 Naco 6.90 Design- Complete 20 Nov, 6.90 0 waiver
AJO 2mi Phase 1
east of Design-
D-2 AZ TCA AJO 7 POE 2008-1 3.10 Build 5/8/08 7/20/08 Est Const. Start date1/25/2008 3.10 3.10 FONSI 2008
1mi W to
3mi W of Phase 1 Const. Start 3 Dec
Mariposa Design- 07. Clearing and
D-5A AZ TCA NGL 7 POE 2010-1 2.08 Build 3/25/08 7/12/08 grubbing underway. 2.08 2.08 FONSI 2007
NCO
17.75mi W
to San Initial Assessments
Pedro and Evaluations are
E-2A AZ TCA NCO 8 River 2011-1 6.44 PV-1 7/6/08 10/23/08 underway 6.44 6.44 Initiating EA
NCO
3.4mi E to Phase 1 Feb 08 Pending Start
12.4mi E Design- Cultural &
E-3 AZ TCA NCO 8 of POE 2011-2 5.07 Build 3/29/08 6/26/2008 Environmental 5.07 5.07 FONSI 2008
From Initial Assessments
F-1 AZ TCA NCO 8 existing 2012-1 0.97 PV-1 7/1/08 8/19/2008 and Evaluations are 0.00
17 miles
2
West of
COL POE
beginning
3 miles Initial Assessments
West of and Evaluations are
H-2A NM EPT DNM COL POE 2013-3 14.1 PV-2 7/24/08 10/12/08 underway 14.1 5.07 Final Draft EA
2
DNM
1.5mi E to Phase 1 Est. const. start 24
3mi E of Design- Jan 08 (Mods pending
I-1A NM EPT DNM POE 2013-2 2.56 Build 7/27/08 10/14/08 for fence gauge) 2.56 0 FONSI 2007
2
3mi E of
POE to
Luna Initial Assessments
DNM/ST County and Evaluations are
I-1B NM EPT N Line 2013-4 9.9 PV-2 7/16/08 10/4/08 underway 9.9 0 Draft Final EA
2
Initial Assessments
Neely's and Evaluations are
L-1 TX MAR SBT 23 Crossing 2019-1 4.63 P-3A-15 9/18/08 12/7/08 underway 4.63 0 Draft FINAL EA
Presidio
POE to Conc. Initial Assessments
3.2mi E of Retaining and Evaluations are
L-1A TX MAR PRS 23 POE 2020-1 3.28 Wall 9/24/08 12/7/08 underway 3.28 0 Draft FINAL EA
L-1B TX MAR PRS 23 POE to 2020-2 2.87 Retaining 9/24/08 11/12/08 and Evaluations are 2.87 0 Draft FINAL EA
DRS San
Felipe &
Rio
Grande to
Cienegas
Creek & Initial Assessments
Rio and Evaluations are
M-1 TX DRT DRS 23 Grande 2021-1 2.36 Ameristar 6/27/08 9/25/08 underway 2.36 0 Draft FINAL EA
EGT 2.3mi
upstream Initial Assessments
to 1mi No and Evaluations are
M-2A TX DRT EGT 23 of POE 2022-1 0.75 Ameristar 9/12/08 10/21/08 underway 0.75 0 Draft FINAL EA
M-2B TX DRT EGT 23 to North of 2022-2 1.06 Ameristar 9/12/08 10/31/08 and Evaluations are 1.06 0 Draft FINAL EA
28
Initial Assessments
Hidalgo P-2 and P- and Evaluations are
O-6 TX RGV MCS POE 2024-4 3.86 3B-15 9/20/08 11/24/08 underway 3.86 3.86 Draft FINAL EA
15
Initial Assessments
Retamal and Evaluations are
O-8 TX RGV MER Dam 2024-6 3.24 P-1, P-2 9/20/08 11/19/08 underway 3.24 3.24 Draft FINAL EA
15
Initial Assessments
Progresso and Evaluations are
O-9 TX RGV MER POE 2025-1 3.86 P-1, P-2 9/20/08 11/24/08 underway 3.86 3.86 Draft FINAL EA
15
Initial Assessments
Progresso and Evaluations are
O-10 TX RGV MER POE 2025-2 2.33 P-1, P-2 9/19/08 12/18/08 underway 2.33 2.33 Draft FINAL EA
27
Initial Assessments
Weaver's P-2 and P- and Evaluations are
O-12 TX RGV HRL Mountain 2025-4 0.96 3B-15 9/19/08 11/3/08 underway 0.96 0.96 Draft FINAL EA
27
Initial Assessments
Triangle - and Evaluations are
O-15 TX RGV HRL La Paloma 2026-2 1.93 P-2 9/19/08 12/3/08 underway 1.93 1.93 Draft FINAL EA
27
River Post on
CV-1a 2201-1 YUM/YUM YUM YUM Corridor AZ 7 5.00 0.00 5.00 Rail Moralas Dam south 7 miles F no fonsi 5 0.00 5 5
Cabeza Post on Eastern edge of BMGR, East 14
CV-2 1053-4 YUM/WEL YUM WEL Prieta AZ 7 10.62 0.00 10.62 Rail miles F no fonsi 10.62 0 10.62 10.62
Project runs 2.18 miles west of B
Pima 138 and runs east in segments for a F
DV-6 TBD TCA County AZ 2.33 2.33 total of 2.32 miles no fonsi 2.33 2.33
EV-2A TCA/NCO TCA NCO SPNWR AZ 8 0.25 0.25 NF Waiver 0.25 Waiver
Starting at 0.07 miles west of
Border Monument 83. FV-1A runs
for 2.35 miles east along the border
to Monument 81. FV-1B runs from
Border Monument 81 east along the
Post on border for 21.41 miles, through the F / NF
Rail/ San Bernardino National Wildlife (State, BLM,
FV-1b 2203-2 TCA/DGL TCA DGL Douglas AZ 8 15.73 0.00 15.73 Normandy Refuge, to the Ne Private) no fonsi 15.73 15.73
EA compl 2007.
PVB Zone VF From 0.25 Miles East of BM39 Some 404 work
IV-2 EPT/DNM EPT DNM 9 AZ 2 12.79 12.79 Normandy East Past BM 33 - 12.8 Miles required 12.79 LOC
Post on
Cabeza Rail/ International Border and Yuma
CV-3 1053-3 YUM/WEL YUM WEL Prieta AZ 7 22.48 0 00 18.79 Normandy County Line 22 miles west F fonsi 2005 22.48 0 0 18.79
West Edge of Organ Pipe 15.5
Cabeza Post on miles to Yuma County Line
DV-1 2202-1 TCA/AJO TCA AJO Prieta AZ 7 12.99 0 00 0 00 Rail (Yuma PDT) fonsi 2005 0 0.00
Star ing at .87 miles east of
Border Monument 160.
Con inuing east along the
border for 1.29 miles. On the
Tohono O'odham Indian
Sierra De Post on Reservation, between the Sierra
La Nariz Rail/ la Nariz Mountains and the
DV-2 2205-1 TCA/AJO TCA AJO Mtn. AZ 7 1 52 0 00 1 52 Normandy Santa Rosa Mountains. no fonsi 12 99 0 0 0 0 1.52
Star ing at 1.52 miles east of
Border Monument 159.
Con inuing east along the
border for 15 26 miles, On the
Tohono O'odham Indian
Reservation, between the Santa
Papago Rosa Mountains and the La
DV-3a 1023-4 TCA/AJO TCA AJO Farms AZ 7 15.48 0 00 10.69 Bollard Lesna Mountains. F fonsi 2006 0 1.52 0 1.52 0 10.69
La Lesna Mountain Drive
Through Area EA done on
0.41 miles,
need envir
Normandy
work done
Papago / Post on for 0.08 mile
DV-3b 1023-5 TCA/AJO TCA AJO Farms AZ 7 0.49 0.49 0.0 Rail NF section. 0 15 36 0 10.57 0 0.49
Star ing at 0.37 miles east of
Border Monument 153.
Con inuing east along the
border for 20.84 miles, On the
Tohono O'odham Indian
Reservation between the La
Tohono Post on Lesna Mountains and the
O'Odham Rail/ eastern edge of Morena
DV-4a 1024-3 TCA/CAG TCA CAG Nation AZ 7 19.36 0 00 19.36 Normandy Mountain. NF fonsi 2006 0 0.49 0 0.49 0 19 36
Star ing at 0.29 miles west of
Border Monument 145.
Con inuing east along the
border for 11.55 miles, On the
Tohono Post on Tohono O'odham Indian
O'Odham Rail/ Reservation between corral and
DV-4b 1024-4 TCA/CAG TCA CAG Nation AZ 7 11.02 2.73 0 00 Normandy the Presumido Canyon. NF fonsi 2006 0 19 36 0 19.36 0 2.73
Tohono
O'Odham
DV-4C TCA/CAG TCA CAG Nation AZ 7 0.40 0.40 0 00 F no fonsi 0 11 02 0 2.73 0 0.40
Printed:4/12/2010 page 11 of 13
PV-VF Master Data DOI vs NON-DOI by segment 3-28-08 0015 EDT.xls
Jersey
Barrier Jersey 180 LF VF Under Ysleta POE CATEX
KV-1 1052-2 EPT/YST EPT YST POE TX 16 0 04 0 04 Barrier Bridge F 2006 0 no
110 60 51 107
Printed:4/12/2010 page 12 of 13
PV-VF Master Data DOI vs NON-DOI by segment 3-28-08 0015 EDT.xls
Mileage in
Mileage in Waiver NEPA No NEPA Waiver xls -
xls - Column I Coverage Coverage Column J
Printed:4/12/2010 page 13 of 13