Professional Documents
Culture Documents
Supply Management,
MRP 1 & Just-in-time
1
mg2066
Issues
Resource Usage
Performance objectives
Market competitiveness
Quality make or buy (contract out
Speed market-based purchasing?
Reliabiity supply partnerships?
Flexibility
Supply network
Cost relationships Process
Capacity technology
Decisions
2
mg2066
Strategy
Concepts
Vertical
Partnerships Market Network Network
Integration
trading dynamics Management
Quantitative Coordinate
Qualitative Differentiate
Reconfigure
3
mg2066
4
mg2066
Company B
Down stream
Up stream
Company C X
X
X X For Company A
Internal supply network
Immediate supply network
5
Total supply network
mg2066
Delivery
Quality
Time
Cost
6
mg2066
Structural Improvement
7
mg2066
8
mg2066
Supply relationships
a company can trade with first tier and second tier customers at
the same time - but consider the % balance of each
immediate suppliers vs suppliers of suppliers in the total network
relationships between companies in the network need not be
exclusive - multi-sourcing.
Company C - seems to single source (exclusive supply) item X
Types of relationship:
close and intimate? Make or contract in (outsource)? What items:
strategic, trivial? Many suppliers or a few. Keiretsu? Transactional
(arms-length only) or collaborative? Loyalty in buyers and sellers
markets?
9
10
mg2066
Aggregate
MRP2
Plan (product groups)
Firm Forecast
orders random
Master orders
production
schedule
Design Time-phased plan
(MPS)
changes how many + when we will
build each end item.
Bill of Inventory
material MRP1
record
Reports Stock
movements
10
mg2066
dependent demand
info. system to determine
No. of parts, components, materials needed
for a product order
scheduling information - dates when
orders for materials should be released,
based on lead times.
batches of materials, parts, components
should be ordered/produced
based on a master production schedule (MPS)
11
mg2066
Bill of Materials
complete product description
materials
parts
components
production sequence
modular BOM
subassemblies
planning BOM
fractional options
Inventory record
status according to “time windows or buckets”
identify each parent item that created demand
12
mg2066
Lead Times
A 1 week
B 2 wks
A C 1 wk
D 3 wks
E 4 wks
F 1 wk
B(4) C(2)
Demand
wk 10 50 A
D(2) E(1) D(3) F(2) wk 8
wk 6
20 B (Spares)
15 D (Spares)
Product Structure Tree for Assembly A
from bill of materials
13
mg2066
Week: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
Lot sizing
Lot-for-lot (L4L)
Economic order quantity (EOQ)
LT = 1 week
Least total cost (LTC)
Least unit cost (LUC)
14
mg2066
MRP
Week: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
B Required 20 200
Order Placement 20 200
LT = 2
surplus
schedule components of “A”.
4 B’s in each A (50x4) = 200Bs. A
back the schedule up for 2
weeks lead time.
B(4) C(2)
MRP
Week: 1 2 3 4 5 6 7 8 9 10
A Required 50
LT=1 Order Placement 50
B Required 20 200
LT=2 Order Placement 20 200
C Required 100
LT=1 Order Placement 100
D Required 55 400 300
LT=3 Order Placement 55 400 300
E Required 20 200
LT=4 Order Placement 20 200
F Required 200
LT=1 Order Placement 200
A Part D: Wk 6
40 + 15 spares
Time Fencing
Frozen
No schedule changes allowed within the time frame
Moderately Firm
Specific changes allowed within product groups as long
as parts are available.
Flexible
Significant variation allowed as long as overall capacity
requirements remain at the same levels.
17
mg2066
Primary
Planned orders - to release at a future time.
Order release notices - execute planned orders
Changes in due dates of open orders due to
rescheduling Gross
GrossRequirements
Requirements
Secondary
Planning reports e.g. forecasting inventory
receipt
Planned
Plannedorder
order
release
release
requirements over time.
Performance reports e.g. actual vs. planned
usage and costs.
Exception reports e.g. serious discrepancies,
late/overdue orders.
18
mg2066
MRP Example
Spares 1 2 3 4 5 6 7 8 9 10
A 12
B 7
C 10
D 15
19
mg2066
MRP Example
C Gross Requirements 45 36 64
LT=2 On-Hand=10 10
Net Requirements 35 36 64
Planned Order Receipt 35 36 64
Planner Order Release 35 36 64
D Gross Requirements 15 135
LT=2 On-Hand=20 15 5
Net Requirements 130
Planned Order Receipt 130
Planner Order Release 130
A(2) B(1)
Day: 1 2 3 4 5 6 7 8 9 10
X Gross Requirements 95
LT=2 On-Hand=50 50
Net Requirements 45
Planned Order Receipt 45
Planner Order Release 45
A Gross Requirements 90 12
LT=3 On-Hand=75 75
Net Requirements 15 12
Planned Order Receipt 15 12
Planner Order Release 15 12
B Gross Requirements 7 45
LT=1 On-Hand=25 7 18
Net Requirements 27
Planned Order Receipt 27
Planner Order Release 27
C Gross Requirements 45 36 54 10
LT=2 On-Hand=10 10
Net Requirements 35 36 54 10
Planned Order Receipt 35 36 54 10
Planner Order Release 35 36 54 10
D Gross Requirements 15 135
LT=2 On-Hand=20 15 5
Net Requirements 130
Planned Order Receipt 130 21
Planner Order Release 130
mg2066
22
mg2066
R P
E
23
mg2066
JIT Requirements
24