You are on page 1of 24

mg2066

Supply Management,
MRP 1 & Just-in-time

1
mg2066

Issues

Resource Usage
Performance objectives

Market competitiveness
Quality make or buy (contract out
Speed market-based purchasing?
Reliabiity supply partnerships?
Flexibility
Supply network
Cost relationships Process

Capacity technology

Decisions

2
mg2066

On being a supply network manager

Strategy

Concepts

Supply Network Relationships Supply Network Behaviour

Vertical
Partnerships Market Network Network
Integration
trading dynamics Management
Quantitative Coordinate
Qualitative Differentiate
Reconfigure

3
mg2066

What are Supply Networks?

 supply networks vs. supply chains


 buyer-supplier relationship
 aserver-client
supply network is a system of organisations connected by
links - upstream/downstream - that service
processes & activities (operations) bringing added value to
each client and ultimately the end customer.

4
mg2066

Flows of products, services & information


Supply side Demand side
second-tier first-tier first-tier second-tier
suppliers suppliers customers customers

Company B

Down stream
Up stream

Company C X

X
X X For Company A
Internal supply network
Immediate supply network
5
Total supply network
mg2066

Measuring Supply Chain Performance

 Delivery
 Quality
 Time
 Cost

6
mg2066

Structural Improvement

Basic Ways to Improve Supply Chain Structure:


 Change structure
 Capacity, Facilities, Process technology, vertical
integration
 Change infrastructure
 People, Information systems, Organization, Production
and inventory control, Quality control systems

7
mg2066

Forms of Structural Change

 Forward and Backward Integration


 Major process simplification
 Changing the configuration of factories, warehouses, or
retail locations
 Major product redesign
 Outsourcing logistics to a third party.

8
mg2066

Supply relationships

 a company can trade with first tier and second tier customers at
the same time - but consider the % balance of each
 immediate suppliers vs suppliers of suppliers in the total network
 relationships between companies in the network need not be
exclusive - multi-sourcing.
 Company C - seems to single source (exclusive supply) item X
 Types of relationship:
 close and intimate? Make or contract in (outsource)? What items:
strategic, trivial? Many suppliers or a few. Keiretsu? Transactional
(arms-length only) or collaborative? Loyalty in buyers and sellers
markets?

9
10
mg2066

From Aggregate to MPS to MRP1

Aggregate
MRP2
Plan (product groups)

Firm Forecast
orders random
Master orders
production
schedule
Design Time-phased plan
(MPS)
changes how many + when we will
build each end item.

Bill of Inventory
material MRP1
record

Reports Stock
movements
10
mg2066

Material Requirements Planning

 dependent demand
 info. system to determine
 No. of parts, components, materials needed
for a product order
 scheduling information - dates when
 orders for materials should be released,
based on lead times.
 batches of materials, parts, components
should be ordered/produced
 based on a master production schedule (MPS)

11
mg2066

Inventory Records Data

Bill of Materials
 complete product description
 materials
 parts
 components
 production sequence
 modular BOM
 subassemblies
 planning BOM
 fractional options
Inventory record
 status according to “time windows or buckets”
 identify each parent item that created demand

12
mg2066

Product Structure Tree

No. of components for each product + when needed.

Lead Times
A 1 week
B 2 wks
A C 1 wk
D 3 wks
E 4 wks
F 1 wk
B(4) C(2)
Demand
wk 10 50 A
D(2) E(1) D(3) F(2) wk 8
wk 6
20 B (Spares)
15 D (Spares)
Product Structure Tree for Assembly A
from bill of materials

13
mg2066

Material Requirements Planning

1. Schedule no. of units of “A” backwards to allow for lead time.


2. place order for 50 of “A” at week 8 to receive in week 10

Week: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50

Lot sizing
 Lot-for-lot (L4L)
 Economic order quantity (EOQ)
LT = 1 week
 Least total cost (LTC)
 Least unit cost (LUC)

14
mg2066

MRP

Week: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
B Required 20 200
Order Placement 20 200

LT = 2
surplus
schedule components of “A”.
4 B’s in each A (50x4) = 200Bs. A
back the schedule up for 2
weeks lead time.
B(4) C(2)

D(2) E(1) D(3) F(2)


15
16
mg2066

MRP
Week: 1 2 3 4 5 6 7 8 9 10
A Required 50
LT=1 Order Placement 50
B Required 20 200
LT=2 Order Placement 20 200
C Required 100
LT=1 Order Placement 100
D Required 55 400 300
LT=3 Order Placement 55 400 300
E Required 20 200
LT=4 Order Placement 20 200
F Required 200
LT=1 Order Placement 200

A Part D: Wk 6
40 + 15 spares

B(4) C(2) Repeat for all


components
==> final MRP
D(2) E(1) D(3) F(2) 16
mg2066

Time Fencing

 Frozen
 No schedule changes allowed within the time frame
 Moderately Firm
 Specific changes allowed within product groups as long
as parts are available.
 Flexible
 Significant variation allowed as long as overall capacity
requirements remain at the same levels.

17
mg2066

MRP Reports & Information

 Primary
 Planned orders - to release at a future time.
 Order release notices - execute planned orders
 Changes in due dates of open orders due to
rescheduling  Gross
GrossRequirements
Requirements

 Cancellations or suspensions of open orders  On-hand


On-hand
due to cancellation or suspension in the MPS.  Net
Netrequirements
requirements
 Stock status data  Planned
Plannedorder
receipt
order

 Secondary
 Planning reports e.g. forecasting inventory
receipt
 Planned
Plannedorder
order
release
release
requirements over time.
 Performance reports e.g. actual vs. planned
usage and costs.
 Exception reports e.g. serious discrepancies,
late/overdue orders.

18
mg2066

MRP Example

Item On-Hand Lead Time (Weeks)


X X 50 2
A 75 3
B 25 1
A(2) B(1) C 10 2
D 20 2

Requirements include 95 units (80


C(3) C(2) D(5) firm orders and 15 forecast) of X
in wk 10 plus the following spares:

Spares 1 2 3 4 5 6 7 8 9 10
A 12
B 7
C 10
D 15

19
mg2066

MRP Example

C Gross Requirements 45 36 64
LT=2 On-Hand=10 10
Net Requirements 35 36 64
Planned Order Receipt 35 36 64
Planner Order Release 35 36 64
D Gross Requirements 15 135
LT=2 On-Hand=20 15 5
Net Requirements 130
Planned Order Receipt 130
Planner Order Release 130

A(2) B(1)

C(3) C(2) D(5) 20


mg2066

Day: 1 2 3 4 5 6 7 8 9 10
X Gross Requirements 95
LT=2 On-Hand=50 50
Net Requirements 45
Planned Order Receipt 45
Planner Order Release 45
A Gross Requirements 90 12
LT=3 On-Hand=75 75
Net Requirements 15 12
Planned Order Receipt 15 12
Planner Order Release 15 12
B Gross Requirements 7 45
LT=1 On-Hand=25 7 18
Net Requirements 27
Planned Order Receipt 27
Planner Order Release 27
C Gross Requirements 45 36 54 10
LT=2 On-Hand=10 10
Net Requirements 35 36 54 10
Planned Order Receipt 35 36 54 10
Planner Order Release 35 36 54 10
D Gross Requirements 15 135
LT=2 On-Hand=20 15 5
Net Requirements 130
Planned Order Receipt 130 21
Planner Order Release 130
mg2066

Operating an MRP System

 Should MRP carry “safety stock”?


 How much “safety stock” should be carried?
 Issue of “safety lead time”
 Danger of “informal” system driving out the “formal” system
 Expansion of MRP to other functions (finance, HRM, etc.)
of business

22
mg2066

Manufacturing Resource Planning - MRP 2

 Goal: Plan & monitor all resources of a manufacturing firm


(closed loop):
 manufacturing
 marketing
 finance
 engineering
 Simulate the manufacturing system

R P
E
23
mg2066

JIT Requirements

Work with suppliers Reduce inventory


 reduce lead times  including
 frequent deliveries  stores
 project usage requirements  WIP + W in transit
 quality standards
 carousels & conveyors
Problem-solving
Problem-solving
 Rootproblem
Root problem
 Long-termsolution
Long-term solution
 Teamcontribution
Team contribution
Product Design Improvement
 Line-specialistcooperation
Line-specialist cooperation
 DFM & process design
 Learning
Learning
 Modules & fewer parts
 Measureperformance
Measure performance
 Quality standards
 CQI
CQI
 Monitor&&report
Monitor report

24

You might also like