Professional Documents
Culture Documents
Japanese enjoyed measure of success in Western markets because they are superior in Operation management and
culture.
Operation management is seen to be a “Strategic Activity” in modern organizations. Comprising some key decision.
In 1893 Durkheim introduced the concept of anomie to describe the mismatch of collective guild labour to
evolving societal needs when the guild was homogeneous in its constituency. Durkheim's use of the term
anomie was about a phenomenon of industrialization—mass-regimentation that could not adapt due to its
own inertia—its resistance to change, which causes disruptive cycles of collective behaviour (e.g.
economics) due to the necessity of a prolonged build-up of sufficient force or momentum to overcome the
inertia.
The contemporary English understanding of the word anomie can accept greater flexibility in the word
“norm”, and some have used the idea of normlessness to reflect a similar situation to the idea of anarchy.
But, as used by Émile Durkheim and later theorists, anomie is a reaction against or a retreat from the
regulatory social controls of society, and is a completely separate concept from anarchy which is an absence of
effective rulers or leaders.
Capacity planning is relevant in both the long term and the short term.
The throughput (The throughput of an organization or system is the amount of things it can do or deal with
in a particular period of time) or number of products that an operation system can Manufacture, Store,
Hold or Process over a given period.
Capacity Demand
When demand is more,
If the capacity is more and increases production,
demand is less, then reduces quality, pressure
revenue does not cover of employees increases.
the cost Demand Capacity
Type A Type B
Managing Operation (MBA) sibichan.mungamakal@googlemail.com Page 2
FACTORS INFLUENCING CAPACITY DECISION
In the short term, capacity planning concerns issues of scheduling, labour shifts, and balancing resource
capacities. The goal of short-term capacity planning is to handle unexpected shifts in demand in an efficient
economic manner. The time frame for short-term planning is frequently only a few days but may run as long
as six months.
The easiest and most commonly-used method to increase capacity in the short term is working overtime. This is a
flexible and inexpensive alternative. While the firm has to pay one and one half times the normal labor rate, it
foregoes the expense of hiring, training, and paying additional benefits.
Short Term
20
18
16
14
Chase demand Flexi-Time shift
12
10
8 Demand
6 Capacity Number
Maximize 3 Es
4 1. Economy of
2
2. Efficiency Calls
3. Effectiveness
0
Example:
Linear programs
Queuing theory
Demand and capacity
Monte graph of a Call Centre
Carlo
Forecast demand
Quantitative
Example:
Time series
Reference &
co-relation
Actuarial curves
About forecasting:
Planning is what we
want to happen.
B. Technological Forecasting
Year
sibichan.mungamakal@googlemail.com
3 4
Forecasting is what
we think happen.
Actuarial Curve
5
?
Future
Page 4
Sony company build capacity ahead in advance during 1980s by building new production plant of CD Roam. As per
Porter “First mover advantage”.
“Irreversible strategy”. Example: Burning ships to show that we not came for battle.
Decision Trees
A mathematical method being up a complex decision in to measurable out comes and further decision
point using a tree with nodes and branches.
Capacity Decision
Remarks Small plant in town A Large plant in town B
Strong growth £300,000 profit £500,000 profit
Weak growth £50,000 profit £70,000 profit
Probability of strong to weak 50% / 50% 20% / 80%
LOCATION PLANNING
Identify a suitable geographical location for an operations system to maximise revenue or minimise cost.
What factors influence choice of location? Make five suggestions with examples.
6. Comparative wage rates: Cheap labour is intensive for business like clothing, toys, etc.
7. Government regulations: Example, In Europe amount of retail space was restricted by government.
Giving below the approximate details.
Category Area in million square meters Country
A 15 U.K and France
B 5 Germany
C 2 Spane
D 0.75 Switzerland
8 Taxation:
Managing Operation (MBA) sibichan.mungamakal@googlemail.com Page 8
Location planning technique
Breakeven
Factor rating
Centre of gravity
Location breakeven
Which is the best location of planned production of 1000 units and 2000 units? (Location B is best).
Factor rating
1. Identify location option C.S.F
X Y Containers
90 20 2,000
60 30 5,000
20 80 9,000
X = ∑Q1X1 Y = ∑Q1Y1
∑Q1 ∑Q1
Q = Quantity shifted to each store. X = X coordinate of each store Y = Y coordinate of each store
Conclusion:
PROJECT MANAGEMENT
A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start
and finish dates of the terminal elements and summary elements of a project. Terminal elements and
summary elements comprise the work breakdown structure of the project. Some Gantt charts also show the
dependency (i.e, precedence network) relationships between activities. Gantt charts can be used to show
current schedule status using percent-complete shadings and a vertical "TODAY" line as shown here.
Although now regarded as a common charting technique, Gantt charts were considered revolutionary when
they were introduced. In recognition of Henry Gantt's contributions, the Henry Laurence Gantt Medal is
awarded for distinguished achievement in management and in community service. This chart is used also in
Information Technology to represent data that has been collected.
The critical path method (CPM) or critical path analysis, is a mathematically based algorithm
for scheduling a set of project activities. It is an important tool for effective project management.
History
It was developed in 1950s by the DuPont Corporation at about the same time that Booz Allen Hamilton and
the US Navy were developing the Program Evaluation and Review Technique [1] Today, it is commonly used
with all forms of projects, including construction, software development, research projects, product
development, engineering, and plant maintenance, among others. Any project with interdependent activities
can apply this method of scheduling.
1. A list of all activities required to complete the project (typically categorized within a work breakdown
structure),
2. The time (duration) that each activity will take to completion, and
3. The dependencies between the activities
Using these values, CPM calculates the longest path of planned activities to the end of the project, and the
earliest and latest that each activity can start and finish without making the project longer. This process
determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be
delayed without making the project longer). In project management, a critical path is the sequence of
project network activities which add up to the longest overall duration. This determines the shortest time
possible to complete the project. Any delay of an activity on the critical path directly impacts the planned
project completion date (i.e. there is no float on the critical path). A project can have several, parallel, near
critical paths. An additional parallel path through the network with the total durations shorter than the
critical path is called a sub-critical or non-critical path.
These results allow managers to prioritize activities for the effective management of project completion, and
to shorten the planned critical path of a project by pruning critical path activities, by "fast tracking" (i.e.,
performing more activities in parallel), and/or by "crashing the critical path" (i.e., shortening the durations
of critical path activities by adding resources).
Expansion
Originally, the critical path method considered only logical dependencies between terminal elements. Since
then, it has been expanded to allow for the inclusion of resources related to each activity, through processes
called activity-based resource assignments and resource leveling. A resource-leveled schedule may include
delays due to resource bottlenecks (i.e., unavailability of a resource at the required time), and may cause a
previously shorter path to become the longest or most "resource critical" path. A related concept is called the
critical chain, which attempts to protect activity and project durations from unforeseen delays due to
resource constraints.
Since project schedules change on a regular basis, CPM allows continuous monitoring of the schedule,
allows the project manager to track the critical activities, and alerts the project manager to the possibility
that non-critical activities may be delayed beyond their total float, thus creating a new critical path and
delaying project completion. In addition, the method can easily incorporate the concepts of stochastic
predictions, using the Program Evaluation and Review Technique (PERT) and event chain methodology.
Currently, there are several software solutions available in industry that use the CPM method of scheduling,
see list of project management software. However, the method was developed and used without the aid of
computers.
Flexibility
A schedule generated using critical path techniques often is not realised precisely, as estimations are used to
calculate times: if one mistake is made, the results of the analysis may change. This could cause an upset in
the implementation of a project if the estimates are blindly believed, and if changes are not addressed
promptly. However, the structure of critical path analysis is such that the variance from the original schedule
caused by any change can be measured, and its impact either ameliorated or adjusted for. Indeed, an
important element of project postmortem analysis is the As Built Critical Path (ABCP), which analyzes the
specific causes and impacts of changes between the planned schedule and eventual schedule as actually
implemented.
B D G 5 weeks
3 weeks 4 weeks
Note: Critical Path was marked in red line with arrows. The total duration of critical path is the project
completion date.
ES A EF
ES (Earliest (Activity)
(Earliest
I Start) Finish)
LS LF
(Latest (Latest
S start) Finish)
fffffffffffffffffffffffff
(Activity
Duration)
5
ES
A EF
0 5
(0 + 5)
0 5
(5-5) 5
Start Mixing
LS LF ES
0 S 0 5 C 6 EF
(5+1)
(0 + 0)
ES EF
(6-1)
0 0 5 1 6
(0-0) 0
LS LF Find Everything
0 B 1 LS LF
ES EF
(5-1)
Backward pass begins from ‘end activity / last activity’ and moves backward to ‘start activity’ to find out
the value of Latest Start (LS).
The value of Latest Finish (LF) of the last activity is always the EF value of that activity.
Use formula to find out the value of LS (LS = LF – Activity Duration)
LF value of an activity is the LS value of immediate predecessor. If there are more than one
predecessors, take the lowest value of LS.
If the LS value of ‘start activity / first activity’ is 0, then your calculation is correct.
B D G 5 weeks
3 weeks 4 weeks
Use the backward pass and forward pass to identify ES, EF, LS and LF from the above diagram.
A C F
0 2 2 4 4 7
10 13
0 2 2 4 3
2 2
H
S
E 13 15
0 0
4 8
13 15
0 0 2
0 4 8
4
S D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Note: If you total the duration of critical path will be equal to the value of Earliest Finish (EF).
Find out the spare time (slack) of each activity and check there is any spare time on critical path.
The following represents a software project that should be scheduled using CPM.
Time / Days
Activity Immediate predecessor A M B
A --- 8 10 12
B A 18 22 34
C A 14 21 27
D A 17 30 42
E B 31 42 57
F C,D 33 40 53
G D,E 33 40 62
H F,G 22 40 53
Where A = Optimistic, B = Pessimistic and C = Most likely.
The normal and crash data for this software project are as follows:
Required:
1. Draw a network diagram and identify the critical path using the most likely (M) data. Use the
backward pass and forward pass to identify ES, EF, LS and LF. Explain the significance of your result.
(15 marks).
2. Using the Beta Probability Distribution identify the variance for each activity. (5 marks).
3. Determine the least cost of reducing the project completion date. (5 marks)
a)
B E
Managing Operation (MBA) 10 32 32
sibichan.mungamakal@googlemail.com 74 Page 17
10 32 32 74
A D G
0 10 10 10 74 114
0 10 44 74 74 114
10 30 40
C F H
10 31 40 80 114 154
b)
There are several spare days are available on non-critical activities which is not helpful to reduce the
project completion date of 154 days because all the critical path shows zero slacks.
c)
Normal
Normal Crash Crash Per day Least
Activity -crash Normal (£) Crash (£)
days days -Normal crash exp. crash cost
day
A 10 8 2 22000 24000 2000 1000 2000
B 22 20 2 30000 32000 2000 1000 2000
C 21 20 1 21000 25000 4000 4000
D 30 28 2 45000 56000 11000 5500
E 42 40 2 20000 22000 2000 1000 2000
F 40 38 2 30000 34000 4000 2000
G 40 38 2 35000 38000 3000 1500 3000
H 40 38 2 30000 38000 8000 4000 8000
10 days 17000
We can finish the project in 144 days by crashing 10 days with the additional cost of 17000.
Example:
4. All above challenged the respective industries recipe for success. Developed a unit paradigm. ( A
paradigm is a model for something which explains it or shows how it can be produced).
However these firms face a major danger ‘imitation’.
5. Imitation: things are not genuine but are made to look as if they are.
6. Protection: Imitation can be protected by copy right, legal right, IPR’s and patent. But one
firm can not protect:
Demand for cinema declined since II world war because it was replaced by CD, DVD, Cable
Connection and Internet.
Cinema operators attempted to liberate assets.
Restructure the cinema.
In earlier days people consumed or purchased what the manufacturers had produced. Their only concern
was the price of the product. But thing have changed, people are beware of the ‘quality’ of the products or
services which they are going to consume. The consumers are giving more importance to the quality of the
products or services rather than their price.
The evolution of the concepts and practices of TQM has taken several years of trials and tribulations in
many organizations all over the world. According to Feigenbanum, “in the increasing competitive world
the quality is no longer an optional extra, it is essentially a business strategy”. Without quality, an
organization cannot survive. The creation of quality products and services demands total commitment
from the entire organization and hence it requires TQM.
Definition
The British Quality Association defined TQM as “management philosophy and company practices that aim
to harness the human and material resources of an organization in the most effective way to achieve the
objectives of the organization.”
Shop Floor
Raw materials (R.M) Work in progress (W.I.P) Finished Goods
(Quality checkers & sampling)
Principles of TQM
1. Customers’ needs must be met in time, regularly and fully.
2. Employees must strive to do error-free work.
3. Employees must strive to do error-free work.
4. Management should aim at preventing the occurrence of errors and not at correcting them
after they occur.
Benefits of TQM
TQM offers a wide range of advantages or benefits to both consumers and the manufacturers. These
can be classified into tangible benefits and intangible benefits. The tangible benefits are:
1. Associated with Japanees management (Ishikawa, Taguchi) but originated from USA (Deming,
Crosby, Juran)
2. Total = quality everything.
3. Suppliers Workers Customers Users
Quality is recognize an important reserves by senior executives. Why?
Protection of the company, image and brand.
Premium price.
Customer Preference or Loyalty. (eg. Cigarette)
Cost reduction. Volume makes lower cost.
Market power.
4. Quality is built in to the product at the design stage. Built on principles of redundancy. (When there are
redundancies, an organization tells some of its employees to leave because their jobs are no longer necessary or because the
organization can no longer afford to pay them. (BRIT BUSINESS; in AM, use dismissals, layoffs) Faults arise without
putting unfair committee.
Managing Operation (MBA) sibichan.mungamakal@googlemail.com Page 23
5. Different level of quality.
Perfect Quality
Design quality
Production quality
Online service
Scope – variety of products (eg. Dell)
Accuracy (eg. Motorolla)
Skills: careful recruitment, selection, training and development of personality of staff.
(Honda takes 6 interviews before taking an employee in production department and gives
training).
Management development. Charls Hany (1990) conducted a study about management
development in 5 countries.
9. Culture:
Quality Circle
Six-Sigma : Six Sigma is a business management strategy originally developed by Motorola, USA in 1981.[1]
As of 2010, it enjoys widespread application in many sectors of industry, although its application is not
without controversy.
Maslow's Theory Z should not be confused with the book by William Ouchi bearing the same name.
Theory Z, was presented by William Ouchi, in his 1981 book 'Theory Z: How American management can
Meet the Japanese Challenge'. William Ouchi is professor of management at UCLA, Los Angeles, and a
board member of several large US organisations.
Theory Z is a name applied to two distinctly different psychological theories. One was developed by
Abraham H. Maslow in his paper Theory Z and the other is Dr. William Ouchi's so-called "Japanese
Management" style popularized during the Asian economic boom of the 1980s.
Maslow's Theory Z' In contrast to Theory X, which stated that workers inherently dislike and avoid work
and must be driven to it, and Theory Y, which stated that work is natural and can be a source of satisfaction
when aimed at higher order human psychological needs.
For Ouchi, Theory Z focused on increasing employee loyalty to the company by providing a job for life with
a strong focus on the well-being of the employee, both on and off the job. According to Ouchi, Theory Z
management tends to promote stable employment, high productivity, and high employee morale and
satisfaction.
Ironically, "Japanese Management" and Theory Z itself were based on Dr. W. Edwards Deming's famous
"14 points". Deming, an American scholar whose management and motivation theories were rejected in the
United States, went on to help lay the foundation of Japanese organizational development during their
expansion in the world economy in the 1980s.
A quality circle is a volunteer group composed of workers (or even students), usually under the leadership
of their supervisor (but they can elect a team leader), who are trained to identify, analyse and solve work-
related problems and present their solutions to management in order to improve the performance of the
Quality circles are an alternative to the dehumanising concept of the division of labour, where workers or
individuals are treated like robots. They bring back the concept of craftsmanship, which when operated on
an individual basis is uneconomic, but when used in group form (as is the case with quality circles), it can be
devastatingly powerful and enables the enrichment of the lives of the workers or students and creates
harmony and high performance in the workplace. Typical topics are improving occupational safety and
health, improving product design, and improvement in the workplace and manufacturing processes.
The term quality circles derives from the concept of PDCA (Plan, Do, check, Act) circles developed by Dr.
W. Edward Deming.
They are formal groups. They meet at least once a week on company time and are trained by competent persons
(usually designated as facilitators) who may be personnel and industrial relations specialists trained in human factors
and the basic skills of problem identification, information gathering and analysis, basic statistics, and solution
generation.[1] Quality circles are generally free to select any topic they wish (other than those related to salary and
terms and conditions of work, as there are other channels through which these issues are usually considered)
Quality circles were first established in Japan in 1962; Kaoru Ishikawa has been credited with their creation. The
movement in Japan was coordinated by the Japanese Union of Scientists and Engineers (JUSE). The first circles were
established at the Nippon Wireless and Telegraph Company but then spread to more than 35 other companies in the
first year.[5] By 1978 it was claimed that there were more than one million Quality Circles involving some 10 million
Japanese workers.[citation needed] There are now Quality Circles in most East Asian countries; it was recently claimed that
there were more than 20 million Quality Circles in China. [ Quality circles have been implemented even in educational
sectors in India, and QCFI (Quality Circle Forum of India) is promoting such activities. However this was not successful
in the United States, as it (was not properly understood and) turned out to be a fault-finding exercise although some
circles do still exist.
QC
1,000,000 QCs
Research by Bradley and Hill in 1990 on effectiveness of Qc’s in US and UK firm observations:
Economic game
Improve industrial relations
But Trade Unions are against this concept.
Line managers are suspicious QCs.
Another definition is provided by the APICS Dictionary when it defines SCM as the "design, planning,
execution, control, and monitoring of supply chain activities with the objective of creating net value,
building a competitive infrastructure, leveraging worldwide logistics, synchronizing supply with demand,
and measuring performance globally."
A supply chain, as opposed to supply chain management, is a set of organizations directly linked by one or more of
the upstream and downstream flows of products, services, finances, and information from a source to a customer.
Managing a supply chain is 'supply chain management' (Mentzer et)
1. Management of activities that purchase material and service, transforming them into intermediate and final
goods and delivering the final product into a distribution system.
2. Volkwagen’s Radical experiment in supply-chain Management. In its new Brazilian truck factory introduced
new supply chain management to reduce defective parts, labour costs, and improve efficiency. There are
1000 workers in that factory out of that 800 works for sub-contractors and 200 for Volkswagen. These 200
workers are responsible for TQM. The VW employees are responsible for overall quality, marketing,
research and design. Sub-contractors do the entire assembling jobs including materials. VW is buying not
only the materials but also labour and related services. Volkswagen manufacturing nothing and all the
assemble works are done by sub-contractors.
1. Q = Quality
2. F = Flexibility
3. D = Dependability
4. C = Cost
5. S = Speed
Government Driver
Liberalization of trade helps the Supply chain’s span across many territories. Example: 40 years ago
GNP of South Korea and Ghana were at par (same). South Korea followed liberal economy and GNP
increase a great extent whereas Ghana followed closed economy and present GNP is too low if we
compare with South Korea.
By signing WTO agreement, the government harmonise traffic of goods and services and it cause
longer and broader supply chain.
Managing Operation (MBA) sibichan.mungamakal@googlemail.com Page 28
)
G
.
(
C
F
M
,
I
:
x
E
b
s
p
m
S
t
u
d
r
P
w
N
a
i
g
l
o
n
h
c
e
T
Technological
Cost
Cost is powerful competitive weapon (Porter). Even perishable products sources overseas.
Example: In US markets flowers arrives from Colombia. Flowers must be delivered within 8 hours in
90C – 130C to keep the freshness.
Market
Convergence (The
become more similar)
argument.
convergence of different ideas, groups, or societies is the process by which they stop being different and
In middle class economy there is a large homogenous market and supply chain will be deeper and
broader.
Firm grows in size. Hierarchy is expensive because the use of market. Make Vs Buy. Make is cheaper
and buy is expensive. Historically firms ‘made’ many things in house. When they grow the size
concentrated on supply chain.
Transaction
cost
Cost saving
TC 1
TC 2
TC 1 TC 2
Sales 100 100
Cost of sales 70 65
Gross profit 30 35
Example:
Hierarchical business
More problems. Higher management costs.
A1
Agency A2
cost
Cost saving
Outsourced problems
Validity of transactions
Agency theory
Many more but efficient suppliers.
Example: Volkswagen use of market will less expensive.
NASH Equilibrium
In game theory, Nash equilibrium (named after John Forbes Nash, who proposed it) is a solution concept of
a game involving two or more players, in which each player is assumed to know the equilibrium strategies of
the other players, and no player has anything to gain by changing only his or her own strategy unilaterally. If
each player has chosen a strategy and no player can benefit by changing his or her strategy while the other
players keep theirs unchanged, then the current set of strategy choices and the corresponding payoffs
constitute a Nash equilibrium.
The Nash equilibrium concept is used to analyze the outcome of the strategic interaction of several decision
makers. In other words, it is a way of predicting what will happen if several people or several institutions are
making decisions at the same time, and if the decision of each one depends on the decisions of the others.
The simple insight underlying John Nash's idea is that we cannot predict the result of the choices of multiple
decision makers if we analyze those decisions in isolation. Instead, we must ask what each player would
do, taking into account the decision-making of the others.