Professional Documents
Culture Documents
An Introduction
60-499
Project Management
What is a plan?
A project plan is a network of dependent and
independent tasks
A plan may also contain descriptions of persona
A persona is a fictitious representation of a real person
The plan may also include assignments of tasks to various
persona
An important part of the project plan is the network
diagram, which shows task flow and task dependencies
60-499
Project Management
What is a schedule?
A schedule is a description of start and end times for all
the WBS’ tasks
The schedule accommodates the plan
The schedule specifies all dates in terms of offsets from the start
date
Ideally, the start date is a parameter which can be changed if the
project start is delayed
This way, real dates can be seen
However, dates are not hardcoded so they can be easily changed
An important part of the schedule is the Gantt chart
60-499: Project Management: Techniques & Tools
Planning
60-499
Project Management
Network Diagram
A network diagram shows task/activity flow
Flow from one task to another may indicate:
Dependencies between the tasks
Chronological ordering between the tasks
Parallel task flows indicate task independence
It is not necessarily the case that tasks may be done in parallel,
but it is possible
60-499
Project Management
Task/Activity Dependencies
Finish to start: One task/activity must finish before the other
task/activity can start
e.g. ‘Order PCs’ must finish before ‘Install IDE’ begins
Start to start: One task/activity must have started before the other
task/activity can start
e.g. ‘Design AI module’ must start before ‘Implement AI module’ begins
Schedules
60-499
Project Management
Schedules
A schedule is an implementation of the project plan
However, in industry lingo, a project plan document normally
includes the schedule
A common schedule representation is a Gantt chart
A Gantt chart is a graphical depiction of the task flow, with dates
Dates are shown as the x-axis, so questions about start/end
times can be answered
e.g. Relative start times of parallel tasks
e.g. Completion of all of an activity’s tasks
e.g. Chronological dependencies between tasks
However, other formats are possible:
A calendar, showing tasks started, active, and completing
A list of task descriptions, including start and expected end dates
60-499
Project Management
Gantt Charts
Visual representation can help when a project manager
needs an overview:
September October November December
User Interface
Prototype
Registration
Dialog
…etc…
Registration
Persistence
Code to Gen.
Password MD5
…etc…
60-499: Project Management: Techniques & Tools
A Practical Guide
60-499
Project Management
Creating a Schedule
In practice, a PM will use a project management tool to
do much of their work:
Microsoft Project
Gantt Project
Open Workbench
OmniPlan
All of these applications let you easily create:
Gantt charts
Task descriptions
Calendar views
60-499
Project Management
Using Microsoft Project
Using Microsoft Project to create a schedule is easy:
Step 1: Enter the tasks:
Enter the task name
Enter the start time
Enter either the duration or expected end time
Enter dependencies, if any
60-499
Project Management
Using Microsoft Project
MS Project generates the Gantt chart for you automatically, on the
right:
60-499
Project Management
Using Microsoft Project
MS Project allows you to change dates whenever you want
Thus, you can push back the start date if the project is delayed
The entire schedule is shifted over in response
You can add/change dependencies as you wish as well
Next to tasks is a space for resources
Here is one place where you could put in persona names
e.g. Java developer I
60-499
Project Management
Common Schedule Problems
Problems with estimates or deadlines:
Customer or upper management set deadline without team consultation
Schedule is based on ‘best case’ estimates
Target date moved up without re-adjustment to scope, resources, or schedule
Problems with requirements:
Schedule omits necessary tasks
Project size is impossible within allotted time
Project is larger than estimated
Effort is greater than estimated
Problems with schedule management:
Schedule was based on specific team members that will not be available
Schedule slips are ignored when schedule is re-evaluated (velocity)
Delays in tasks result in delays in dependent tasks
Unfamiliar territory causes unexpected delays
Problems with productivity:
Demotivated personnel (e.g. schedule pressure)
Weak personnel
Friction between team members