Texas A&M University

Agriculture Headquarters
Weekly Report: 10/18/10-10/22/10

North View of AG HQ Millwork Throughout HQ Doors and Side Lights

Overview on Admin Cistern Canopy Deck


`
• Stone is being placed on the seat wall in between the HQ building and the VC.
• Metal panel installation at the VC fascia/soffit is 100% complete.
• Granite flooring is 90% completely laid on the first floor corridors.
• Doors are being hung throughout the HQ.
• Carpet is being installed on the 1st thru 3rd floors of the HQ.
• 75% of the SOCF has been poured at the Admin building.
• Slab over the crawlspace of the Admin building has been poured.
• The cistern canopy gutter and deck installation is ongoing.
• Installing RACO frames at the VC.
• Installed toilet partitions on the 4th floor.
• All 1st floor columns at the Admin have been poured.