Definitions

Metric Abbrev. Description Formula/Value


Budget at Completion BAC Baseline cost for 100% of project. N/A

Actual Cost of Work Performed ACWP Total costs actually incurred so far. N/A
Budgeted Cost of Work Amount of budget earned so far based on physical work
Performed BCWP accomplished, without reference to actual costs. N/A
Budgeted Cost of Work The budget for the physical work scheduled to be completed by
Scheduled BCWS the end of the time period. N/A

Budgeted Cost of Work Performed–


Measure of cost overrun. The difference between the budget for Actual Cost of Work Performed
Cost Variance CV the work actually done so far and the actual costs so far. BCWP/ACWP

Budgeted Cost of Work Performed/


Cost efficiency ratio. A CPI of 1.00 means that the costs so far Actual Cost of Work Performed
Cost Performance Index CPI are exactly the same as the budget for work actually done so far. BCWP/ACWP

Measure of schedule slippage. The difference between the Budgeted Cost of Work Performed–
budget for the work actually done so far and the budgeted cost Budgeted Cost of Work Sceduled
Schedule Variance SV of work scheduled. BCWP–BCWS
The schedule efficiency ratio. An SPI of 1.0 means that the
Schedule Performance Index SPI project is exactly on schedule. BCWP/BCWS
Estimate at Completion–Actual Cost
Work Performed
Estimate to Completion ETC The expected additional cost to complete. EAC–ACWP
Budget at Completion/Cost Performance
Index
Estimate at Completion EAC Expected total cost based on the current cost efficiency ratio. BAC/CPI
Budget at Completion–Estimate at
Completion
Variance at Completion VAC Estimated cost overrun at the end of project. BAC–EAC
(Cost Performance Index+Schedule
Performance Index)/2
Status Average of CPI & SPI. (CPI+SPI)/2
GREEN = On track >1.0
YELLOW = Slightly behind schedule or budget >0.85
RED = Needs immediate attention >0.65
BLACK = Killed or Restore <0.65

Page 1 of 4
Analysis

Project Earned Value Analysis


<ProjectName>

EVA Review Dates >>>>>>>>>>>>> Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Budget at Completion (BAC) £1,230 £1,320 £1,320 £1,320 £1,500 £1,500 £1,500 £1,500 £1,500 £1,500
BCWP - Budgeted Cost of Work Performed £100 £300 £400 £550 £850 £900 £1,200 £1,300 £1,450 £1,300
ACWP - Actual Cost of Work Performed £100 £250 £400 £700 £900 £1,100 £1,300 £1,400 £1,600 £1,700
BCWS - Budgeted Cost of Work Scheduled £100 £300 £425 £700 £900 £925 £1,300 £1,600 £1,450 £1,500
Cost Variance (CV) £0 £50 £0 -£150 -£50 -£200 -£100 -£100 -£150 -£400
CV % 0% 17% 0% -27% -6% -22% -8% -8% -10% -31%
Schedule Variance (SV) £0 £0 -£25 -£150 -£50 -£25 -£100 -£300 £0 -£200
SV % 0% 0% -6% -21% -6% -3% -8% -19% 0% -13%
Cost Performance Index (CPI) 1.00 1.20 1.00 0.79 0.94 0.82 0.92 0.93 0.91 0.76
Schedule Performance Index (SPI) 1.00 1.00 0.94 0.79 0.94 0.97 0.92 0.81 1.00 0.87
Estimate to Completion (ETC) £1,130 £850 £920 £980 £688 £733 £325 £215 £55 £262
Estimate at Completion (EAC) £1,230 £1,100 £1,320 £1,680 £1,588 £1,833 £1,625 £1,615 £1,655 £1,962
Variance at Completion (VAC) £0 £220 £0 -£360 -£88 -£333 -£125 -£115 -£155 -£462
Status based on Average Performance Index GREEN GREEN YELLOW RED YELLOW YELLOW YELLOW YELLOW YELLOW RED

Status Update New


baseline set

Page 2 of 4
Performance Graphs

Earned Value Analysis


£1,800

£1,600

£1,400

£1,200

£1,000
$ (000)

£800

£600

£400

£200

£0
Jan Feb Budget
Marat Completion
Apr ACWP - Actual
May Jun Cost of
Jul BCWPAug- Budgeted
Sep BCWS
Oct - Budgeted
(BAC) Work Performed Cost of Work Cost of Work
Period Performed Scheduled

Performance Index
1.30

1.20

1.10

1.00
Efficiency

0.90

0.80

0.70

0.60

0.50
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Cost Performance Schedule Performance
Index (CPI) Period
Index (SPI)

Page 3 of 4
Performance Graphs

Variance Analysis
£300

£200

£100

£0
$ (000)

-£100

-£200

-£300

-£400

-£500
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Cost Variance (CV) Schedule Variance Variance at
(SV) Period
Completion (VAC)

Estimate at Completion
£2,100

£2,000

£1,900

£1,800

£1,700

£1,600
$(000)

£1,500

£1,400

£1,300

£1,200

£1,100

£1,000
JanBudget Feb Mar
at Completion Apr at May
Estimate Jun Jul Aug Sep Oct
(BAC) Completion (EAC)
Period

Page 4 of 4