Kewajipan Interchange

Existing Condition
Conventional Diamond
Interchange
4 - Phase Conflicts
Congestion especially during peak
hours due to high traffic volume
and delay in 4 – Phase traffic lights
Traffic Configuration
Overall
Traffic Configuration
Phase 1
Traffic Configuration
Phase 2
Traffic Configuration
Phase 3
Traffic Configuration
Phase 4
Proposal on Improvement to
Interchange
Convert to Diverging Diamond
Interchange
Reduce to 3 – Phase traffic light
hence increase capacity of
interchange
Video clip 1
Video Clip 2
Traffic Configuration
Overall
Traffic Configuration
Phase 1
Traffic Configuration
Phase 2
Traffic Configuration
Phase 3
Overall Layout Plan
Modification Works
Modification to kerbs and traffic
islands
Widening of bridge approach
Widening of slip roads
Re-arrangement of traffic lights
Advantages
Reduced conflict points
Increase capacity
Reduce backup to main line
Disadvantages
Drivers unfamiliar with configuration
(Solution : Signage to educate drivers)
 No cross over for motorcyclist on
interchange
(Solution : To exit into main line before
interchange)