You are on page 1of 2

WORKING ADVANCE REPORT

Project Name :
Date :
Week :
NO. DESCRIPTION UNIT VOL WEIGHT TOTAL
I PREPARATION WORK
1 Cleaning the project location Ls
2 Breaking off the old building roof construction Ls
3 Breaking off the old concrete wall Ls
4 Breaking off the old floor Ls
5 Breaking off the foundation structure Ls
6 Measuring dan constructing the bouwplank
0.50
II GROUND WORK
1 Ground foundation digging m³ 78.52 0.90
2 Ground refilling m³ 19.63 0.23
3 Piling up the ground to the floor m³ 66.70 2.93
4.06
III ROCK, CONCRETE AND PLASTER WORK
1 Piling the rock to the floor…….. m³ 6.88 0.94
2 Foundation rock filling 1:4 m³ 44.15 10.60
3 Veined concrete filling 1:2:3 for column m³ 1.89 2.40
4 Veined concrete filling 1:2:3 for sloof balk m³ 2.58 2.90
5 Veined concrete filling 1:2:3 for ringbalk m³ 1.24 1.48
6 Floor foundry 5 cm 1:2:3, plastered m³ 333.50 9.45
7 Concrete brick wall filling 1:4 m³ 7.91 3.76
8 Concrete wall plastering 1:4 m³ 131.84 1.90
9 Concrete plastering 1:2 m³ 71.68 0.95

IV   WOODEN WORK
1 Supplying and doing the causen, well planed. m³ 4.96 9.86
2 Supplying and doing wooden wall, well planed m³ 110.02 4.26
3 Supplying and doing ……….., not planed m³ 5.33 8.21
4 Doing the ceilling frame, not planed m³ 2.60 3.33
5 Supplying and doing the ceilling 0,8×0,8 m m³ 324.00 9.50
6 Supplying and doing board lisplank, planed well 2x20 cm m³ 18.28 0.66
7 Doing straight bits panel door m³ 6.48 1.34
8 Supplying and wiring the aluminium wire m³ 62.64 4.02
9 Supplying armature, bolt and key m³ 1.00 0.31
41.49
V ROOF WORK
1 Supplying and constructing the sago palm roof 468.10 11.50
2 Constructing the ridge of sago palm roof m 2
30.20 0.31
11.81
VI PAINTING WORK
1 Supplying the …….frame and theceilling frame m2 541.24 2.15
2 Plastering m 2
309.60 4.71
6.86
VII ELECTRIC INSTALLATION WORK
1 Supplying lamp
·        TL 40 watt bh 6.00
·        TL 20 watt bh 6.00
2 Supplying meter, cable, electric switch, etc. Ls 1.00
0.70
VIII    KEY AND HANGER WORK
1 Doing ……..key merc Angker 8” bh 3.00
2 Constructing the big hinge bh 12.00
3 Constructing the big door bolt bh 6.00
4 Constructing the big handle bh 3.00
0.20
100.00