You are on page 1of 13

Hornsea

Project One
Proposed Offshore Wind Farm
Project Update
March 2011– Issue 1
Who is SMart Wind and what
are we proposing in your area?
SMart Wind is a 50/50 joint As part of the UK’s commitment This project update,
venture between Mainstream to moving towards a low-carbon published in March 2011,
Renewable Power (UK) Ltd economy, the Government aims to:
and Siemens Project Ventures has set itself the ambitious
GmbH. The company has target of producing 15% of •P
 rovide an overview
been established to develop all energy from renewable of the project
the 4GW Hornsea Zone which sources by 2020. This translates
SMart Wind was awarded into a UK goal for renewable •D
 escribe the new
through The Crown Estate energy electricity generation of consenting process
Round 3 bid process. approximately 30% by 2020.
•P
 rovide a summary
The company is seeking Offshore wind power will play of progress so far
planning consent for Project a key part in achieving this
One, which consists of two target. In December 2007, the •D
 iscuss future consultation
offshore wind farm blocks Government announced the plans and public
and associated offshore and commencement of a Strategic involvement strategies
onshore infrastructure. Project Environmental Assessment to
One is located 103km off the examine 25 gigawatts (GW) of Project updates will now
East Riding of Yorkshire coast. additional UK offshore wind be published on a regular
The location of Project One is energy generation capacity basis to keep the local
shown in Figure 1 and consists by 2020. This follows the 8GW community and interested
of Subzone 1, the cable route planned for Rounds 1 and 2 parties informed on the
to shore and onshore grid which are well underway – with progress of Project One.
connection. several sites in operation and
more in construction. The
Subzone 1 Hornsea Zone is part of the
Hornsea Zone third round of offshore wind
International Boundary development.
Site & Area of Ancillary/Associated Development
Figure 1 – Location of Project One
Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 01
What are we planning to build? Round 3

Key
In 2009, following the Strategic Project One will comprise Turbines used for Project One The device will be fully
 Round 3 Wind Farm
Environmental Assessment, two wind farm blocks, each are likely to be a conventional commissioned at the end of Zone
The Crown Estate selected of approximately 600 megawatt 3-bladed design and will have March and provide the first International Boundary
nine offshore Zones around the (MW) capacity, plus offshore a maximum rotor diameter of accurate measurements of wind 12nm limit
1
UK (Figure 2) for a third round substations, a converter station 150m, maximum hub height of speed at the height of a wind
of wind farm development. and cable routes to shore. 120m, and maximum rotor tip turbine hub. Zone Developer
SMart Wind was awarded the height of 200m. 1. Moray Firth Moray Offshore
Hornsea Zone, also known as Onshore works will include a Works to identify the turbine Renewables Linited
Zone 4 which covers a total landfall site (with jointing pit), In order to provide information and foundation types, the 2. Firth of Forth Seagreen Wind Energy
Limited
area of 4735km2 and is shown a cable route from the coast on wind speed and direction, installation methodologies and 2
3. Dogger Bank Forewind Limited
in detail on Figure 1. to an onshore converter station, it is proposed to install an layout design is ongoing and 4. Hornsea SMart Wind Limited
and a short connection anemometry mast in 2011. The are reliant on more offshore Figure 3 – Windcube LiDAR installed
5. East Anglia East Anglia Offshore on the Schooner gas platform
By working in partnership between the converter station detailed information produced surveys and detailed modelling 3
Wind Limited
with The Crown Estate, local and substation, located in will help to calculate the most to better understand the seabed 6. Rampion E.ON Climate &
stakeholders, industry and Killingholme. efficient layout of individual conditions specific to each Renewable/UK
Government, SMart Wind are blocks of turbines within Project turbine location. 4
Southern Array Limited
planning to develop a number The two wind farm blocks will One. This will require a separate 9 7. West Isle of Eneco Round 3
White Development Limited
of offshore wind farms in the be situated within Subzone 1 planning application through Stakeholders will be consulted
8. Atlantic Array Bristol Channel Zone
Hornsea Zone that will have a located in the centre of the the Marine Management throughout the project design
Limited
combined capacity of 4GW Hornsea Zone, covering an area Organisation (MMO). phase in order to ensure that 5 9. Irish Sea Centrica Energy
by 2020. of 620km2 (Figure 1). Depending all realistic alternatives are Renewable Investment
on the rated capacity of the In addition to the proposed considered and any appropriate Limited
turbines, likely to be between anemometry mast, a Light mitigation measures can be put
3.6 and 8MW machines, the Detection and Ranging device in place at an early stage of the
8
estimated number of turbines is or Windcube LiDAR was project development.
between 124 and 332. The successfully installed on the
6
nearest turbine will be 103km Schooner gas platform at the 7
from the East Riding of end of January (Figure 3).
Yorkshire coast.
Figure 2 – The Crown Estate’s Round 3 Offshore Wind Farm Zones
Source: The Crown Estate 2010
smartwind.co.uk 02 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 03
What kind of grid connection will we need? Onshore infrastructure

In order to transfer the SMart Wind is proposing Converter stations will also be The onshore converter station Cables will be buried from The location and design are
electricity generated by the to transmit power from the required at both ends of the will be linked by either overhead a coastal landfall site (with not finalised but the area of land
wind turbines into the offshore turbines to shore via transmission circuit. An offshore lines or buried cables to jointing pit) to the converter required is estimated to be in
National Grid transmission High Voltage Direct Current station is required to convert National Grid’s substation. station. Various routes and the order of 200m length x 150m
system, SMart Wind has (HVDC) subsea cables. HVDC the High Voltage Alternating The use of overhead lines or landing points both north width and up to 35m height.
secured a 1GW grid connection systems have been successfully Current (HVAC) generated buried cables will be dependent and south of the Humber are
agreement at Killingholme installed for over 40 years and from the turbines to HVDC for on location of the converter currently being considered. Figure 6 shows an indicative
for Project One. Killingholme have a number of benefits transmission to shore. The station, feedback from public As shown in Figure 5, we are building form that could be
substation is an existing 400 including reduced transmission onshore converter station then consultation and environmental considering three onshore used for the onshore converter
kilovolt (kV) National Grid losses (Figure 4). They are the converts power back to HVAC and engineering constraints. cable corridor route options station.
substation located on the most economical and efficient for connection into the National It is currently proposed that for transmitting power to
south bank of the Humber method for the bulk transfer of Grid transmission system. all other offshore and onshore the converter station and At this stage in the development
Estuary. power over the long distances cables will be installed below substation at Killingholme. process, SMart Wind cannot
required by Project One. Each the surface. discount the possibility of future
wind farm ‘Block’ will also In order to select a preferred generation capacity of other
contain a series of inter-array cable route, consideration will projects within the Hornsea
cables between the turbines be given to feedback from Zone being connected at
and an offshore collector Onshore
the consultation events in Killingholme.
Existing Offshore Offshore
substation. National Grid Converter Converter Collector addition to ongoing onshore
Station Figure 5 – Onshore cable route corridor options
Substation Station Station environmental and engineering If you have any questions or
studies, and offshore cable route comments regarding the three Figure 6 – Visual
considerations. The onshore onshore proposed cable route representation of an
Figure 4 – Landfall North Sea converter station will be corridor options or the converter indicative converter
HVDC connection arrangement
30m constructed as close as possible station please let us know using station.
Source: SKM Enviros
to the existing substation. the contact details at the end of Source: RPS Group Plc.
the project update.
HVAC HVDC HVDC HVAC 33k AC
Cable Cable Subsea Subsea Subsea
Cable Cable Cable

smartwind.co.uk 04 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 05
Offshore infrastructure What other developments
are planned for the area?
Offshore infrastructure is SMart Wind is currently in There are several Round 2 Lincs and Sheringham Shoal
currently planned to include the process of selecting offshore wind farms planned offshore wind farms have been
turbines and inter-array the optimal offshore export or under construction off the successfully consented and are
cabling, offshore collector cable route corridor, based East coast of England now under construction.
substations, an offshore on various engineering and (Figure 8). Westermost
High Voltage Direct Current environmental desk studies Rough owned by DONG The Round 3 Dogger Bank
(HVDC) converter substation including nature conservation, Energy and the recently Zone (Figure 2) being developed
and export cables to shore. navigational features, oil & gas consented Humber Gateway by the Forewind consortium, is
Depending on the rated subsea & surface infrastructure, owned by E.ON are both located 70km north of Project
capacity of the turbines, likely aggregate dredging, marine located less than 10km from One. The East Anglia Zone
to be between 3.6 and 8MW archaeology and seabed the Holderness Coast and (Figure 2) awarded to Scottish
machines, the estimated conditions. Onshore approximately 95km west of Power Renewables and
number of turbines is between considerations will also be Project One. Vattenfall AB, is located 44km
124 and 332. taken into account. south of Project One.
Westermost Rough submitted
The HVDC converter substation Feedback from consultation a planning application in 2009 The Hornsea, Dogger Bank
along with up to four marine with the local community, key and is awaiting a final decision and East Anglia developers
export cables connecting to statutory stakeholders and from the Department for are collaborating on studies to
a landfall point will form an commercial fisheries will form These options have now been Figure 7 – Energy and Climate Change assess the potential cumulative Figure 8 – Location of Hornsea Zone in relation to other Round 1, 2 and 3 zones.
Offshore Transmission Operator an essential part of the offshore narrowed down to the three Offshore cable route corridor options (DECC). Triton Knoll, Race impacts of the east coast Source: EMU Limited
(OFTO) asset. It is envisaged cable route selection. Initially, corridor options shown in Bank, Dudgeon and Docking Round 3 offshore wind farm
that all submarine cables will be five potential routes were Figure 7. If you have any Shoal offshore wind farms are developments.
installed below the seabed to a identified, three routes north of questions or comments also located in the ‘The Greater
depth appropriate to the ground the Humber estuary and two regarding the proposed Wash’ area (Figure 8) are still in
conditions. routes to the south. offshore cable route corridors development.
please let us know using the
contact details at the end of the
project update.

smartwind.co.uk 06 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 07
What have SMart Wind done so far? SMart Futures

The Scoping Report for In addition, SMart Wind SMart Wind is conducting a During 2010 and 2011, various SMart Wind has joined Technical workshops were
the offshore and onshore published a Zone Characterisation comprehensive consultation offshore surveys and desk forces with STEMNET and hosted, where students built
elements of Project One was (ZoC) document in January exercise that will continue based studies have been Humberside Engineering a small wind system to learn
submitted to the Infrastructure 2011 that provides a broad throughout the whole project. carried out to better understand Training Association (HETA) about extracting energy from
Planning Commission (IPC) description of the physical, the existing biological, physical to launch ‘SMart Futures’. The the wind and held a creative
and published on the project biological, socio-economic Anyone who wishes to learn and human conditions across four-year initiative is aimed naming competition to name
website in November 2010. and cultural heritage more about the project, both the Hornsea Zone and at engaging up to 56 local the first and second Hornsea
characteristics of the Zone comment on the information also Project One. These studies schools, in and around the Offshore wind farm blocks.
The IPC collated all responses and a Zone Assessment including the Scoping Report, will further inform the baseline Humber Area, in a fun and
from the statutory and non- Methodology (ZAM) document or raise specific concerns description of the EIA. Further educational programme to From the sixteen schools
statutory stakeholders into which describes the proposed are welcome to get in touch. details of the data gathered so name each of the offshore engaged in the first year, the five
a formal Scoping Opinion methods to be used in assessing Contact details for the project far and plans for future work are wind farms.  finalists to reach the creative
which outlined aspects which impacts across the Zone. are provided at the end of this described later in this project naming competition were South
should be assessed during project update. update. The initiative is aimed at Year Axholme Science & Arts School,
the Environmental Impact Both of these documents, as 8 and 9 Pupils (13-14 year- Beverley High School, Hessle
Assessment (EIA) stage. This well as the Scoping Report, are olds) to encourage them to High School, Malet Lambert
was received on December 24th available on the SMart Wind consider Science, Technology, Specialist Language College and
2010 and is also available on website. Engineering & Maths (STEM) Hornsea School & Language
the IPC website. subjects and inform their career College. The overall winner was Figure 9 – SMart Futures schools’ Technical Workshop
choices toward renewables and South Axholme School, resulting
offshore wind. The programme in the first wind farm block
consists of three phases, being named “Heron Ventus”.
including an awareness-raising The runners-up were Hessle
presentation to pupils and High School, with their name of
teachers in order to highlight “Njord” being assigned to the
the global Climate Change second wind farm block. These
challenge (Figure 9). two schools receive a trophy
each and all pupils receive a
CREST Award for their effort.

smartwind.co.uk 08 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 09
The Consenting process explained

1. Notify IPC 2. Identify Interested 3. Seek input and 4. Continue to


The Planning Act 2008 has Although this will change In addition to a DCO, other SMart Wind will produce an Groups and comment communicate
made significant changes the body responsible for consents may be required, Environmental Statement Stakeholders Scoping Report – Distribute to Invite stakeholders to meetings,
to the planning system administering DCO applications, including a Marine Licence for all offshore and onshore consultees and provide a method of presentations and consultation
Record stakeholder and interest
applicable to offshore it is unlikely to impact on the (which will replace the current works associated with Project group contact details and provide
feedback events
wind farm development.   grounds for making application requirement for separate Food One – this will form one part a record of communication Statement of Community Invite interest groups and local
decisions.   and Environment Protection of the documentation required consultation (SoCC) – distribute community to consultation events
Project One will be classified Act and Coast Protection to support an application to Local Authorities and publish in
Provide updates to consultees
local press
as a Nationally Significant Decisions on DCO applications Act licences). The Marine for a DCO and set out through website updates and emails.
Infrastructure Project because will be taken in accordance Management Organisation will how SMart Wind will minimise
the development has a with National Policy Statements be responsible for issuing Project One’s impact on the
generating capacity of greater (NPSs) which set out planning Marine Licences but the IPC/ environment. 
than 100MW. Therefore SMart policy in relation to energy MIPU has special powers
Wind will apply for permission infrastructure, including offshore to include a Marine Licence SMart Wind will also provide
in the form of a Development wind. NPSs are currently at within a DCO. This avoids an overview of how pre-
Consent Order (DCO) from a final draft stage following the need for developers to application consultation has
the Infrastructure Planning public consultations. The final apply separately for multiple been carried out throughout the 5. Provide 6. Statutory 7. Ongoing 8. Examination
Commission (IPC).  decision to grant consent for consents. If a Marine Licence is pre-application period and how feedback Consultation Consultation and decision
Project One will be made by the included in a DCO, the Marine comments from stakeholders by the IPC
Meetings and presentations Issue draft Environmental Submit Environmental
The IPC was created in 2009 Secretary of State with regard Management Organisation have been addressed. before first draft of Environmental Statement – Distribute to Statement, Consultation
to make the process for to recommendations by the will be a statutory consultee of Statement to feedback on consultees Report and draft Development
deciding Nationally Significant IPC/MIPU. the IPC/MIPU and give advice consultation and EIA process
Issue draft Consultation Report –
Consent Order
Infrastructure Project consents and input to the consenting Distribute to consultees Develop a commitments register
more streamlined. Current process. In the same way as Statutory public consultation period
and include commitments made
Government proposals indicate NPSs inform decisions on during consultation
of 28 days
the IPC will be replaced by the DCO, Marine Licences will be Work through issues raised during
Incorporate recommendations
Major Infrastructure Planning decided in accordance with a from the Environmental Statement
public consultation with statutory
within an Environmental
Unit (MIPU) in spring 2012. Marine Policy Statement which consultees
Management Plan
is currently being finalised by
Ongoing consultation post ES
the Government.   approval as required

smartwind.co.uk 10 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 11
When will the project be built? What Information did we gather in 2010?

The first step is to achieve Proposed project timeline Prior to, and during the Bird and marine mammal In addition, surveys and studies
planning consent for Project Scoping Phase, specialist studies commenced in required to inform the onshore
One through three extensive Project One Timeline 2010 2011 2012 2013 2014 2015 2016 studies (including benthic, March 2010 and will continue components of Project One
phases of stakeholder geophysical, marine mammals, for two years. (such as habitat and protected
consultation.
Scoping
birds, navigation and metocean species surveys) will be carried
surveys) were undertaken to The benthic, geophysical, out in 2011.
The onshore and offshore
Phase 1
better inform the understanding navigation and metocean
Environmental Impact
Consultation Events
of the environmental and surveys commenced in 2010
Assessments and
Phase 2
physical constraints of the and additional studies such as
Environmental Statement
Consultation Events
Project One site. underwater noise and socio-
are due to be completed by
Phase 3 economic assessments are
the summer of 2012. SMart
Consultation Events planned to be carried out during
Wind aims to submit its DCO
Environmental both the baseline and the
application for Project One in
Impact Assessment assessment phases of the EIA
July 2012. Subject to approval,
Draft of Environmental process.
Statement and DCO
construction on Project One
Submission
is likely to commence in 2014,
of DCO
with final commissioning and
Decision by IPC
energisation of the offshore
wind farms proposed for 2016.
Pre-construction

Construction

Commissioning

smartwind.co.uk 12 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 13
The physical environment The offshore biological environment

SMart Wind has commissioned A high resolution geophysical Hornsea Round 3 Zone. Understanding the biological In addition, an acoustic Most importantly it will allow us
studies to assess the offshore survey of the ground conditions This data is being made environment of the Project hydrophone is towed during to estimate collision risk to birds
wind resource, sea state and of Project One was carried out available to interested parties One site is important in order daylight hours to detect any and any potential effects due to
weather conditions, as well as from April to December 2010, free of charge as part of a to assess the potential effects marine mammals in the vicinity habitat loss and displacement
the geology of the seabed. to gain a better understanding twelve month measurement the development may have on of the vessel. Data has been or ‘barrier effects’ created
of the surface features of the programme divided into two its surrounding environment. analysed up to and including by the presence of the wind
SMart Wind is proposing to seabed and subsurface sets of observations. In June November 2010. turbines.
install a meteorological mast in geology (Figure 11). 2010, oceanographic moorings
Subzone 1 during 2011, which A geotechnical survey, including and met buoys (Figure 12) were Approximately 30 species of Six species of marine mammals Figure 13 – Surveyors on boat
will provide site-specific data on preliminary borehole sampling deployed at three locations, Figure 10 – Geophysical survey vessel Birds and seabird were identified in the were positively identified
meteorological conditions such to investigate the subsurface with planned installation marine mammals Hornsea study area between during surveys in the Hornsea
as wind speed and direction. geology and its engineering period of twelve months. In March and November 2010, study area between March
This will require a separate constraints, was carried out October 2010, these were with approximatey 29 species and November 2010. Harbour
planning application through in September 2010. Further augmented with oceanographic Monthly boat based bird
recorded in the Hornsea Zone porpoise was the most
the Marine Management geophysical surveys of the and meteorological buoys and marine mammal surveys
and 28 species in Subzone 1 frequently recorded species
Organisation. cable route study area are at a further three sites, plus across both the Hornsea Zone
over the nine months period followed by minke whale, white-
planned for 2011. a wave buoy. These three and the Project One study
(Figure 13). The most common beaked dolphin and grey seal
oceanographic/meteorological area began in March 2010
species were kittiwake, (Figure 15). Harbour porpoise
A comprehensive geotechnical buoy moorings will be deployed and surveys will continue for Figure 14 – Gannet
Figure 11 – Example side scan sonar guillemot and fulmar, with abundance in the Hornsea
survey is proposed to be carried for six months over the winter two years. The Southern Star Source: Mike Bailey – Emu Ltd.
image from geophysical survey razorbill and gannet (Figure 14) study area was low between
out across the site in summer period, while the wave buoy will survey vessel has completed
also occurring in high numbers. March and May 2010, but
2011. By registering on be deployed for a full year. 6km transect survey lines of
Analysis of the bird data increased in June.
www.smartwind.co.uk, the Hornsea Zone and 2km
will provide estimates of the
visitors can now access real transects in Subzone 1, using
numbers of birds in Subzone Statistical analyses will
time data for meteorology (wind visual observation for birds
1 and surrounding waters be conducted on the data
speed, mean wind direction, and marine mammals.
throughout the year. It will also collected from site and used
air temperature & air pressure) tell us how the birds are using to inform the Environmental
and waves (wave height, wave the area (e.g. for migration, Impact Assessment.
period & wave direction) from feeding or breeding) and their Figure 15 – Grey seal
the seven locations within the distribution. Source: Mike Bailey – Emu Ltd.
Figure 12 – Metocean buoy

smartwind.co.uk 14 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 15
What about creatures on the seabed? Fish ecology studies

Benthic studies were carried SMart Wind is currently The potential impact on
out between April and carrying out a desk study of migratory fish species such
December 2010 to identify the fish and shellfish ecology and as Atlantic salmon (Salmo
existing species and habitat commercial fishing practices salar), sea trout (Salmo trutta),
distribution. Surveys were in the area. The European eel (Anguilla
carried out over the Hornsea anguilla), Sea lamprey
Zone and more intensively Offshore surveys will begin in (Petromyzon marinus) and River
within Subzone 1 (Figure spring 2011. These are likely to lamprey (Lampetra fluviatilis)
16). Grab samples to collect include trawling surveys, potting will also be assessed within
seabed sediment and species surveys and intertidal fish the Environmental Impact
living within the sediment surveys. Survey methodology Assessment, including effects
were undertaken from the MV and sampling frequency is on migration. Data collected
Shannon survey vessel. Figure 17 – Seabed sediment showing being drafted with input from during biannual fisheries Figure 19 – Example of marine samples
small sand waves. Source: EMU Limited local fisheries organisations surveys, desk based literature obtained from a benthic trawl (includes
Seabed digital photography and the Centre for Environment, searches and catch and fish crabs, fish, star fish). Source: EMU
and video was also used to Fisheries and Aquaculture pass data from nearby estuaries Limited
collect data on habitats and Science (CEFAS). and tributaries, will be used to
associated species living on Figure 16 – Benthic survey sampling locations.
inform the assessment.
the sea bed (Figures 17 – 18). Source: EMU Limited
Scientific beam trawling for
information on species such as
fish, crabs, shrimps and prawns
was also carried out (Figure
19). A report on the results
of the benthic surveys will be
completed by the end of March to
inform the Environmental Impact
Assessment. Figure 18 – Gravelly sediment with
benthic organisms including star fish
and flat fish. Source: EMU Limited

smartwind.co.uk 16 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 17
How are we making our final decisions? The human environment

Consultation with local Phase 2 Phase 3 The human environment Shipping surveys will continue The archaeology and cultural
communities, businesses, encompasses the recreational for two years to ensure accurate heritage of the Zone and
and organisations is a vital Following analysis of the Phase 3 will be the final and commercial use and the characterisation of the Zone. AIS Subzone is also being
part of the planning process feedback from Phase 1, a consultation on the whole of visual amenity of the site. equipment is installed on two of investigated, with the offshore
and all feedback from local preferred onshore cable route Project One prior to finalising Offshore surveys and desk our survey vessels with radar archaeology divided into two
consultation and statutory will be selected which will and submitting our application based studies have been data also being collected for main disciplines: maritime
consultees will help to inform trigger a targeted Phase 2 for development consent. Our complemented by extensive fishing and recreational vessels. archaeology on the seabed,
the design of the project. So consultation with those near draft Environmental Statement consultation with all existing users which includes shipwrecks
being involved can influence the chosen cable route corridor Figure 20 – will be made available at that of the Project One study area. Consultation has commenced (Figure 21) and aircraft losses;
Mainstream Consultation Event
the final design of Project One. and other associated onshore time. Phase 3 will consist of a with local fishermen and their and submerged prehistoric
Consultation will be managed development. Phase 2 will Assessments and consideration number of consultation events These studies and consultations representatives along the east archaeology, which considers
in three phases: consist of questionnaires and of engineering constraints to along the chosen onshore cable will help to determine key issues coast of Yorkshire and will the potential inhabitation of
information leaflets distributed produce a robust alternatives route and other associated such as shipping and navigation continue throughout the humans on land which is now
by post to the parties with study, which will justify a final onshore development. routes and the level of fishing Environmental Impact Assessment submerged.
Phase 1 postcodes within 400m of the selection. activity and methods used within and consenting process.
preferred onshore cable route Confirmation of the venues and and around the Hornsea site. SMart Wind is working with local
A series of consultation events
corridor, landing point, and A smaller number of Phase 2 dates for Phase 3 consultation Visual amenity and the recreational fishermen to ensure that disruption
in March and April 2011 will
converter station. Offshore consultation events will be events will be publicised when use of the study site are also to local fishing activity is minimised.
consult on the overall project
stakeholders will also be held at those venues used in known but we anticipate that this being investigated.
and the broad onshore and
consulted during this phase. Phase 1, in closest proximity will be early 2012. Oil and gas is also a major
offshore cable route study areas.
to the preferred onshore Preliminary findings from consideration within the Hornsea
The information and feedback
The preferred onshore cable cable route corridor and An Explanatory Note which Automatic Information System Zone, with 17 offshore platforms
provided through these events
route will be strongly influenced other associated onshore details how the consultation (AIS) shipping data shows how and associated maintenance
will help to define the preferred
by the feedback we receive from development. Confirmation programme and the the Hornsea Zone and Subzone vessel and helicopter movements
cable route options north and Figure 21 – Image from the geophysical
our Phase 1 consultation events. of the venues and dates for geographical extent of our 1 are currently being used. located in the Zone. SMart Wind survey showing a ship wreck within the
south of the Humber and the
the Phase 2 consultation events consultation has been defined Preliminary data shows that there will be consulting with oil and Hornsea Zone. Source: EMU Limited
design of the rest of the project.
The options will be narrowed will be published closer to the and is also available on the are several routes regularly used gas operators to ensure both
further by a series of onshore time and we anticipate that these SMart Wind website: by vessels to the west of the Zone, parties are aware of project
Environmental Impact will be in summer 2011. www.smartwind.co.uk with the majority of vessels headed progress and and opportunities
to UK ports in the north-east. for cooperation.
smartwind.co.uk 18 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 19
How does the development of the What happens next?
Hornsea Zone benefit me and my local community?
On the 20th January 2011 It is important to note the SMart There are a number of Phase 1 However, throughout the Phase 1 Consultation Events
Siemens and Associated Wind partnership between consultation events happening Phase 1 and Phase 2
Venue Date Opening hours
British Ports (ABP) have Mainstream Renewable Power in and around the region over consultation periods
signed a Memorandum and Siemens Project Ventures March and April 2011. These stakeholders can send North Cotes Village Hall 15 March 2pm – 8pm
of Understanding for the GmbH, is not linked with the events provide an opportunity SMart Wind comments or Lock Road, North Cotes DN36 5UP
development and construction proposed manufacturing to learn more about Hornsea questions through the contact Immingham Civic Centre - Lyndsey Suite 16 March 2pm – 8pm
of a new Siemens offshore facility. The development is in Project One and have the options identified overleaf. Pelham Road, Immingham. DN40 1QF
wind turbine manufacturing association with a separate opportunity to contribute
and export facility at the Green arm of the Siemens global their views on the alternative Please note that we must Laceby Community Centre 17 March 2pm – 8pm
Port Hull development at engineering and technology offshore and onshore cable receive your comments High Street. DN37 7AA
Alexandra Dock. services company, However the route options presented at the in response to Phase 1 North Killingholme Village Hall 22 March 2pm – 8pm
construction of the Siemens consultation events. consultation by Village Green, North Killingholme. DN40 3LX
The development would place manufacturing facility is 30th April 2011 to ensure
Hull at the centre of UK’s dependent on Round 3 offshore Feel free to ask questions of that they are taken into Holton le Clay Church Hall 23 March 2pm – 8pm
wind turbine production and wind farm projects such as the the staff at the event, provide consideration. Church Lane, Holten le Clay. DN36 5AL
could create thousands of Hornsea Zone gaining consent feedback through filling in one of Albrough Youth Club 24 March 2pm – 8pm
new skilled and well paid jobs to construct and operate the questionnaires, or submit your Comments received by Hornsea Road, Aldbrough
in the region. The Siemens offshore wind farms. own questions and comments SMart Wind will be recorded
Figure 22 – ABP provisional concept design of the port facilities. Patrington Village Hall 30 March 2pm – 8pm
announcement has been met through the forms provided. for the purposes of preparing
with overwhelming support SMart Wind are working our Consultation Report and Church Lane, Patrington. HU12 0RJ
across the Humber region and with the supply chain, local We recognise that not everyone may be made public. Burton Pidsea Memorial Hall 31 March 2pm – 8pm
SMart Wind also fully backs the Government, schools and will have the opportunity to attend Back Lane, Burton Pidsea. HU12 9AN
development. education groups to ensure the Phase 1 or 2 consultation
that the local community and events however your feedback Keyingham Village Hall 5 April 2pm – 8pm
businesses are prepared for is important to us and you can Station Road, Keyingham. HU12 9SX
the future opportunities and send your comments to SMart Withernsea Pavillion Leisure Centre 6 April 2pm – 2pm
investment in areas of predicted Wind through the contact options Queen Street, Withernsea. HU12 2QA
skill shortages. identified overleaf.
Hedon Methadist Church 15 April 2pm – 8pm
Church Lane, Hedon. HU12 8EL

smartwind.co.uk 20 Hornsea Project One Proposed Offshore Wind Farm Project Update March 2011 – Issue 1 21
SMart Wind Limited
11th Floor, 140 London Wall, London
EC2Y 5DN

Tel: +44 (0) 20 7776 5500 


Email: info@smartwind.co.uk
Website: www.smartwind.co.uk

By registering on our
website, you can select to receive
project updates by email or by
post if requested.

You might also like