You are on page 1of 42

Department for Regional Development

Business Plan 2007-2008

CONTENTS
Page
1. Minister’s Foreword 2

2. Permanent Secretary’s Foreword 4

3. The Department’s Structure 7

4. The Department’s Aim, Objectives and Business Planning Context 10


The Department’s Overall Aim and Key Objectives
Planning Context
Priorities and Budget 2006-08
Investment Strategy NI 2005-15
DRD Public Service Agreement 2006-08
NICS Reform Framework 2006-08
NICS Efficiency Review 2005-08
DRD Business Plan 2007-08
Roads Service Business Plan 2007-08
Core Divisional Business Plans 2007-08
Government Strategies and Statutory Duties

5. Resources 15
Budget 2007-08 table

6. Corporate Governance 17
Responsibilities
Departmental Management Assurance System
Risk Management
Audit Committees

7. Business Plan 2007-08 19


Key Priorities and Targets for 2007-08


1. Minister’s Foreword

The Plan builds on the Priorities and Budget 2006-08,


published in December 2005, and is funded through the
budget agreed by Direct Rule Ministers for 2007-08.

Enormous progress has been achieved in recent times as a


result of power-sharing. The potential now exists to create a
base for sustainable economic growth and prosperity.

In a comparable effort, we must demonstrate how we can


meet the needs of a modern economy operating in a global
environment, as it is this which shall provide the basis for our
economic competitiveness.

The Department has a key role in facilitating this. An efficient


and balanced infrastructure is a major contribution and an
effective development strategy is fundamental.

As Minister for Regional In April 2007, Northern Ireland Water was established as the
Development, I am pleased water and sewerage undertaker. The Executive has taken the
to present my Department’s decision not to introduce domestic charges in 2007-08 and
business plan, actions and one of my key priorities now is to secure an acceptable and
targets for the period April 2007 sustainable way of funding water and sewerage services in
to March 2008. the longer term. With this objective in mind the Executive has
decided to conduct a comprehensive review to address the
longer term approach that should be adopted in relation to the
funding arrangements for these services. I expect this review
to be concluded by autumn 2007.

In the meantime, I will continue to support a major programme


of investment in our water and sewerage services.

Northern Ireland Water, with its key partners, will invest £780
million in these services over the next three years. This
means that £1.5 billion will have been invested in the six years
up to 2010. A further £232 million of capital investment will
be delivered in this period through Public Private Partnership
projects.

This investment programme will deliver benefits to customers


by further improving the quality of drinking water, by improving
the quality of our rivers and bathing waters and by reducing


the problems of sewer flooding and low water People became operational on 2 April 2007. In
pressure. The majority of this expenditure will addition, in January 2007, Peter Hain announced
be directed towards sewerage assets, reflecting a package of support for City of Derry Airport to
the priority of obtaining full compliance with be jointly funded by the Irish government. The
European standards of wastewater treatment as Department will carry out a public inquiry into a
soon as possible. request by Derry City Council for a vesting order
for works to allow maximum use of the existing
The first Roads Service Public Private runway.
Partnership (PPP) package started its operational
phase at the beginning of 2006-07. Procurement In 2007-08 the Department will continue to lead
of the second package has progressed during the implementation of the Regional Development
2006-07 and it is anticipated that this contract will Strategy (RDS) which seeks to achieve more
be awarded by the end of April 2007. Through sustainable patterns of development across the
the 2 PPP packages we will invest over £300 North. A Focused Assessment of the RDS will be
million in strategic road improvements over the completed in 2007. Work will also begin on the
next 4 years. mid-term review of the Regional Transportation
Strategy (RTS). The mid-term review will
In August 2006, the Government’s intentions examine progress to date in the implementation
for reforming the way that bus and rail public of the RTS, the budgetary position and the
transport services across the North are planned implications that other changes, such as the
and managed, was announced. The proposed publication of the Sustainable Development
arrangements will secure greater local control Strategy for Northern Ireland, have for the RTS.
over these services and will allow greater
transparency in the use of public money. Bus The targets that have been set in this plan
services here will continue to be regulated are challenging. I am confident we will deliver
and the Northern Ireland Transport Holding on these targets as well as meeting our other
Company’s subsidiaries operating as Translink objectives. Through these plans we will seek to
will continue to provide the majority of public deliver high quality services to the public whom
transport services. However, the arrangements we serve. I am pleased to publish this plan on
will allow greater private sector involvement in behalf of the Department.
the provision of services.

Significant developments in 2006-07 will allow


the Department to further develop access to
the region in 2007-08. In June 2006, the British
Secretary of State jointly with the Irish Foreign
Affairs Minister Dermot Ahern announced their
intention to introduce arrangements to allow free
bus and rail travel for senior citizens throughout
the island of Ireland. Following consultation, CONOR MURPHY MP, MLA
the all Ireland Free Travel Scheme for Older Minister for Regional Development


2. Permanent Secretary’s Foreword

The facilities are transport - road, rail, airport and harbour;


water and sewerage; and planning for long term development
of the region.

If we get this right, and provide effective and appropriate


facilities in a timely fashion, we provide an enormous “lift”
which will be to the benefit of everyone here.

We view our role as fundamentally important; as forward


looking; and as requiring strategic vision as well as immediate
technical excellence. Put broadly, we must judge the nature
and kind of facilities the region will need in future; and we
must ascertain and create them effectively.

This is challenging and important. We believe we have made


good progress to date; we are confident that we will carry
forward our task increasingly effectively in future.
The Department has a key role
in the creation of a prosperous I would like to draw attention to some key achievements of the
region, and one whose residents year just ended and to recognise the vital contributions from
live rich and fulfilled lives. staff throughout the Department.

The role relates to the creation Transport - Roads


of a framework of facilities which
encourage the achievement of Our overall aim is to increase the efficiency and safety of road
these objectives. transport. This means upgrading certain roads, revising safety
hazards and generally maintaining the network.

Within the past year Roads Service completed the


construction of 9 km of dual carriageway on the A1 between
Loughbrickland and Beech Hill (north of Newry) and a 2.4 km
single carriageway extension to Omagh throughpass.

The significant investment on the A1 will continue this year


through work on the Newry to Dundalk cross border link and
the commencement of work on a 12.1 km section of dual
carriageway between Beech Hill and Cloghogue. Completion
of these schemes will mean that the route from Belfast to the
border will be upgraded to at least dual carriageway standard
by the end of 2009.


An important issue in relation to road transport Transport - Trains
efficiency is interruption by utility works. These
are, of course, inevitable but they need to be The use of trains is increasing. In 2006, overall
managed well, to minimise delay to road users. passenger numbers rose by 2.5%, with a notable
increase in local train services 13.8%. In order
In order to improve the position, we have, in the to improve the frequency of services, we also
past year, introduced new legislation to help recruited a number of train drivers during the
address the congestion and damage caused to year.
roads by utilities’ street works. We will continue
to work in partnership with the utility companies Transport - Harbours
in developing the regulations that will set out the
detailed operational controls for more effective In December 2006, a grant of almost £15
and safer management of street works. million was announced to support essential
developments at Warrenpoint harbour. The
Transport – Buses assistance to Warrenpoint harbour is being
provided through the establishment of a Service
Buses are, potentially, a particularly safe and of General Economic Interest. The grant will
efficient use of roads. But they will only be enable a major upgrade of the facilities at
widely used if the passenger experience is Warrenpoint which is now critical to meet the
acceptable. This requires safety, reliability and demands of modern vessels and to secure the
convenience. long term viability of the port and its contribution
to the local economy.
As part of our continued aim to improve the bus
service, the Department supported Translink Water Service (Northern Ireland Water)
in commissioning 150 new buses last year,
which will help generate improvements in the From 1 April 2007 Northern Ireland Water (NIW)
quality and frequency of services. In 2006-07 became responsible for the provision of water
passenger numbers on the Metro service rose by and sewerage services in Northern Ireland.
some 4.6%. The company is government owned, with the
Department as the sole shareholder.
Another important step forward is the introduction
of the new Door-2-Door service in November These arrangements were implemented by the
2006. These are local urban transport services Water and Sewerage Services (Northern Ireland)
for those with disabilities or who find it difficult to Order 2006 which came into effect on 1 April
use mainstream public transport. The service 2007. The Executive subsequently decided
began in Dungannon in September 2006, and will that the new annual charges for water supply
be extended to 27 towns and cities throughout and sewerage services would not be introduced
Northern Ireland by the end of May 2007. during 2007-08 and also decided to conduct
a review of existing arrangements with a view
to finding sustainable and acceptable funding
arrangements for water and sewerage services.


2. Permanent Secretary’s Foreword

NICS Reform and Efficiency

No organisation can remain the same, and


flourish. We have to be aware of the changing
surroundings, the impact of the global market
and technological advances. Given these
changes, we have to consider how we can
perform our tasks better; and whether we should
be re-defining the tasks we perform. This is not
easy but it offers the prospect of future success.
Our fundamental concern is to ensure we deliver
the right services and facilities in the years
ahead.

These programmes add short term pressure


on staff, and risk disruption; however, they are
justified by the benefits they promise and our
confidence in achieving the objectives we have
set. I am very grateful indeed for the resilience
and positive outlook shown by our staff in
implementing all these changes. This attitude
- as well as their hard work and competence
- are enormously encouraging for us all. I am
confident that the services we provide will be
increasingly effective, and will constitute a
framework for a genuine step change upwards in
the prosperity of the region and in improving the
lives of our residents.

GERRY McGINN
Permanent Secretary


3. The Department’s Structure

The Department comprises two Core Groups


and an Executive Agency. The Core Groups
are Resources and Management Services, and
Regional Planning and Transportation. The
Executive Agency is Roads Service.

The Department also plays an important role


in relation to a number of other organisations:
Northern Ireland Water, Northern Ireland
Transport Holding Company and Northern Ireland
Trust Ports.

The Department is headed by a Permanent


Secretary. Each of the Core Groups is managed
by a Deputy Secretary. Roads Service is Clarence Court, Belfast
managed by a Chief Executive.

The Permanent Secretary chairs the Executive Agency


Departmental Board. The Board also consists
of the two Deputy Secretaries, the Director of Roads Service: Responsible for ensuring
Finance, and the Chief Executive of Roads measures are taken to implement the roads
Service. Two Non-Executive Independent aspects of both the Regional Transportation
Board Members were appointed with effect from Strategy for Northern Ireland 2002-12 and the
January 2007. Investment Strategy for Northern Ireland and that
the public road network is managed, maintained
The Board provides collective leadership and and developed. Roads Service is responsible
corporate management of the Department within for just over 25,000 kilometres of public roads,
the strategic policy and resources framework set approximately 9,000 kilometres of footways,
by the Minister. 5,800 bridges, 257,700 streetlights and 370
public car parks.
Core Groups
The Department’s senior management structure
Resources and Management Services: is shown at Figure 1.1.
Responsible for personnel, finance, corporate
services, internal audit, central claims, water
policy and management of the Department’s
shareholder interest in Northern Ireland Water.

Regional Planning and Transportation:


Responsible for regional development and
transport planning, public transport, air and sea
ports and public transport performance.


3. The Department’s Structure

Figure 1.1.


3. The Department’s Structure

The Department’s Role in Relation Holding Company’s statutory duties are to


to Other Organisations manage public transport properties and to
oversee the activities of Translink.
The Department has an important role in relation
to each of these other separate organisations. The Department appoints the chairman and
members of the NITHCo board. They are
Northern Ireland Water: appointed following a public competition and
The Water and Sewerage Services (NI) Order serve for a defined period. The appointments
2006 made provision for the establishment of are made in line with guidance published
a Government owned company for the future by the Office of the Commissioner of Public
delivery of water and sewerage services. The Appointments (Northern Ireland).
Order transferred all the water and sewerage
functions previously conducted by the The Department is responsible for determining
Department’s Water Service Executive Agency to NITHCo’s performance framework against the
the new company, Northern Ireland Water (NIW), Department’s wider strategic aims and objectives
on 1 April 2007. NIW acts as the statutory water and for monitoring the extent to which targets are
and sewerage undertaker and operates under achieved. It is also responsible for ensuring that
licence. appropriate financial and management controls
are in place and that compliance with those
northern ireland controls is effectively monitored.
water

NIW is entirely owned by the Government. It


is established to operate at arms length from
central government structures. The non-
Executive members of Northern Ireland Water’s
Board are appointed by the Minister. While
the Department, as shareholder, sets strategic
objectives for the business, it is not intended
that it should become involved in day-to-day Northern Ireland Trust Ports: The Department
operational matters. appoints the chairmen and members of the
trust ports at Belfast, Derry and Warrenpoint.
Northern Ireland Transport Holding Company: They are appointed following a public
Northern Ireland Transport Holding Company competition and serve for a defined period. The
(NITHCo) is a public corporation and the appointments are made in line with guidance
parent company of the publicly owned bus and published by the office of the Commissioner of
rail companies in the North (Northern Ireland Public Appointments (Northern Ireland). The
Railways, Metro and Ulsterbus, all operating Department also appoints the Donaghadee
as Translink). The Northern Ireland Transport Harbour Commissioners.


4. The Department’s Aim: Objectives and Business Planning Context

The Department’s Overall Aim and


Key Objectives

The Department’s overall aim and key objectives • Contributing to the health and well being
are set out in the Secretary of State’s “Priorities of the community and the protection
and Budget 2006-08”. They are stated in the of the environment by developing and
following terms: maintaining the policy and regulatory
environment which provides modern, high
The overall aim of the Department is to improve quality water and sewerage services, at
the quality of life for everyone in Northern the lowest possible cost.
Ireland by maintaining and enhancing a range of
essential infrastructure services and by shaping
the region’s long-term strategic development. Planning context

In pursuing this aim the key objectives of the The Business Plan sets out how the Department
Department are: plans to meet its requirements within relevant
constraints. These requirements and constraints
• Supporting the economy by maintaining come from a number of sources as set out in
and developing safe transportation Fig. 1.2. Some are stated in general terms;
networks, promoting airport and others are more specific; some only apply to
harbour services, shaping the long-term the Department; others give the Department a
development of the region and providing role in NICS wide programmes. The following
other services to the public and other commentary gives more detail on these services.
Departments; and

Figure 1.2.

10
4. The Department’s Aim: Objectives and Business Planning Context

Priorities and Budget 2006-08

This is the fundamental document for the With regard to the road network, this would
Department. It was published on 14 December progress the objectives established in the
20051 and sets out the context within which the Regional Transportation Strategy 2002-12
Department operates. and the associated Transport Plans. The
Investment Strategy would also enable further
Investment Strategy NI 2005-15 progress to be made with regard to the public
transport objectives established in the Regional
The Investment Strategy for Northern Ireland Transportation Strategy. This would facilitate
2005-152 was published by the Secretary of the development of the public transport
State on 14 December 2005. The Strategy network system and support the Government’s
sets out a long-term high-level view of planned commitment to sustainable development.
investment over the next 10 years. Potentially,
up to £14.4 billion worth of projects could The Department is currently engaging with
be supported over the 10 years to 2014- the Strategic Investment Board (SIB) and
15, a number of which would be within the the Department of Finance and Personnel in
Department’s sphere of operation. All investment developing ISNI 2. This will build on the plans
proposals envisaged by the Investment Strategy envisaged in the first ISNI and will set out the
will be subject to economic appraisal, statutory capital investment plans for the North for the 10
processes and the availability of resources at years to 2017-18.
future budget rounds.
DRD Public Service Agreement
The Department’s proposed investment totals 2006-08
£4.1 billion overall. In the field of water services,
this would enable Northern Ireland Water to Public Service Agreements are set by Ministers
progress compliance with European Union to ensure the delivery of public services to
Directives, achieve substantial progress towards agreed standards of service, performance
the completion of the 20 year capital investment and quality. The Department for Regional
programme for Water infrastructure as set out Development’s Public Service Agreement
in the second NI Asset Management Plan, and for 2006-08 sets out the key outcomes that
enhance its capacity to respond to the increasing it is seeking to provide for the citizen. The
demand for water and sewerage services in the Department has identified the ways in which it
North. will achieve these outcomes. The Public Service
Agreement for 2006-08 for the Department is
published on its website3.

1
Priorities & Budget 2006-08: http://www.pfgni.gov.uk/fulldoc0608.pdf
2
Investment Strategy for Northern Ireland (2005-2015):
http://www.sibni.org.uk/index/information/sibpublications/investment-strategy.htm
3
DRD Public Service Agreement: http://www.drdni.gov.uk/publications-details.htm?docid=2747

11
4. The Department’s Aim: Objectives and Business Planning Context

NICS Reform Framework 2006-08 NICS wide Reform initiatives


This is the detailed implementation of the reform • Records NI (formerly known as Electronic
aims set out in the Priorities and Budget 2006-08. Documents Record Management);
There are three principal elements affecting the
Department specifically and five which are NICS • HR Connect (formerly known as e-HR);
wide but which involve the Department.
• Account NI (formerly known as Accounting
Departmental Reform Plans Services Programme);

• Water Reform – to support the Executive’s • Information & Communications Technology;


review of the existing arrangements for the and
funding of water and sewerage services.
• Workplace 2010.
Northern Ireland Water (NIW), established
in April 2007 as the water and sewerage
The key targets for the delivery of these reforms
undertaker, is responsible for the cost-
in 2007-08 are outlined in Section 7.
effective delivery of high quality services
for the people of Northern Ireland, at the NICS Efficiency Review 2005-08
lowest possible cost.
The Priorities and Budget 2005-08 summarised
• Public Transport Reform – to improve the work involved in identifying efficiencies
the planning, delivery and governance of within NICS departments. It quantifies the
bus and rail public transport, optimising total financial efficiency gains to be delivered
the involvement of the private sector in by departments by 2007-08. By 2007-08, the
terms of its expertise and investment, and Department will realise total annual efficiencies
improving the quality and efficiency of of at least £48.5 million. At least £39.4 million of
public transport services. these efficiencies will be resource releasing.

• Construction Procurement – to improve


The Department has prepared an Efficiency
value for money and increase efficiency in
Technical Note (ETN)4 which provides details
Roads Service, thereby delivering better
on its financial efficiency targets. These are
services to the public.
summarised by budget period in Table 1.1.

Table 1.1

2005-06 2006-07 2007-08


(£ millions) (£ millions) (£ millions)

Of which Of which Of which


Total Total Total
Resource Resource Resource
Efficiencies Efficiencies Efficiencies
Releasing Releasing Releasing

24.1 17.8 39.1 30.3 48.5 39.4


4
Efficiency Technical Note: http://www.drdni.gov.uk/DRDwww_FOISearch/details.asp?docid=1775

12
4. The Department’s Aim: Objectives and Business Planning Context

These efficiencies are being achieved through a a Divisional Business Plan. These plans
number of measures including: are managed by Directors to ensure that the
performance of their business areas throughout
• improvements in procurement processes the year support the achievement of the
and by reducing construction costs on Department’s objectives and targets.
contracts;
Government Strategies and
• rationalising office accommodation and Statutory Duties
associated costs;
The Department also, of course, operates within
• simplifying and standardising processes the context of Government Strategies and
through improved systems and Statutory Duties. These are wide ranging but the
centralisation; and following in particular are worth noting:

• maintaining productivity with fewer Equality of Opportunity, Lifetime


resources. Opportunities and Human Rights

DRD Business Plan 2007-08 The Department’s policies and practices are
underpinned by arrangements to promote
The Department has identified a number of
equality of opportunity and good relations.
Business Plan targets. These are set out in
They also take account of the Government’s
tabular form at Section 7. The intention is to
Anti-Poverty and Social Inclusion Strategy for
operate to specific and measurable targets
Northern Ireland - Lifetime Opportunities.
in order to fulfil our more general aims and
objectives. The table outlines these performance In accordance with Section 75 of the Northern
targets and associated activities and budgets for Ireland Act 1998, the Department has screened
each spending area within the Department. all its policies to identify any differential impacts
on the nine Section 75 groups. It is carrying out
Roads Service Business Plan a programme of Equality Impact Assessments
2007-08 on those policies which might have a significant
The Minister has agreed 11 Key Performance impact on the promotion of equality of opportunity
Targets to reflect the Agency’s Key Objectives and good relations. In addition, all new policies
from April 2007 to March 2008. To further and legislation are screened for equality of
develop challenging business commitments, the opportunity and good relations impacts, with
Minister has also agreed 21 Supporting Business equality impact assessments carried out where
Targets. The full Roads Service Business Plan for appropriate. The human rights implications
2007-08 can be found on the Agency’s website5. of all policies are assessed in line with the
requirements of the Human Rights Act 1998.
Core Divisional Business Plans
The Department will continue to implement its
2007-08
Equality Scheme and address the improvements
To deliver the Department’s Business Plan and good practice issues emerging from the
Targets for 2007-08, each Core Division has current Review of the Effectiveness of Section 75
by the Equality Commission.
5
http://www.roadsni.gov.uk/

13
4. The Department’s Aim: Objectives and Business Planning Context

With effect from 1 January 2007, an amendment Civil Contingencies


to the Disability Discrimination Act 1995 requires
public authorities, when carrying out their Emergency preparedness and response is an
functions, to have due regard to the need to: important issue for the Department. Planning
is developed in accordance with the Civil
• Promote positive attitudes towards disabled Contingencies Framework produced by the Office
people; and of the First Minister and Deputy First Minister. A
rolling emergency planning activity programme,
• Encourage participation by disabled people the Emergency Management Development Plan,
in public life. is reviewed and updated at bi-annual meetings of
the Department’s Emergency Planning Steering
To this end the Department will prepare a Group.
Disability Action Plan, in accordance with
guidance prepared by the Equality Commission, A Major Emergency Response Plan has
by 30 June 2007. been developed for the Department. This is
supplemented by a range of emergency and
business continuity plans developed by individual
business areas. An annual report detailing
progress on emergency planning is submitted to
the Departmental Board in June each year.

Better Regulation

The Northern Ireland Better Regulation Strategy


aims to minimise the burden of bureaucracy
on businesses. The Department of Enterprise
Trade and Investment (DETI) has reviewed
the strategy to take account of developments
elsewhere in the United Kingdom and to address
concerns raised by business representative
organisations. The review identified a number
of actions that need to be taken to strengthen
the strategy. The Department is committed to
encouraging Better Regulation and will take
forward relevant recommendations from the
review in collaboration with the DETI Better
Regulation Unit. Progress will be reflected in the
Department’s input to a Better Regulation Annual
Report.

Door-2-Door transport

14
5. Resources

Expenditure Plans 2007-08


Summary Tables

The Budget provides the Department with a Table 1.2 below sets out the budget allocations
total allocation of £811.8 million in 2007-08. agreed by Direct Rule Ministers for 2007-08.
The Department will provide the resources for
Northern Ireland Water to further improve water Table 1.3 on page 16 provides details of the
and sewerage services in the region, and its Department’s budget allocations for both 2006-07
transportation infrastructure. and 2007-08.

Table 1.2
Key Objective 1: Supporting the economy by maintaining and developing safe transportation
networks, promoting airports and harbour services, shaping the long-term development of the region
and providing other services to the public and other Departments.

Spending Area: Current Investment Total


2007-08 (£m) (£m) (£m)

Roads 198.4 103.7 302.1


Transport 80.1 124.2 204.3
Other 0.2 - 0.2

Total Objective 1 278.7 227.9 506.6

Key Objective 2: Contributing to the health and well being of the community and the protection of
the environment by developing and maintaining the policy and regulatory environment which provides
modern, high quality water and sewerage services at the lowest possible cost.

Current Investment Total


Spending Area: (£m) (£m) (£m)
Water and Sewerage (NIW) 160.0 145.2 305.2
Total Objective 2 160.0 145.2 305.2

Total Departmental Expenditure Limit allocation 438.7 373.1 811.8

15
5. Resources

Table 1.3:

Building On Progress Budget 2006-2008


Summary Table For DRD

2006-07 2007-08
OBJECTIVE (£m) (£m)
AND
SPENDING Resource Resource
AREA Cap Sum Cap Sum
Admin Other Admin Other

Roads 81.6 90.1 110.5 282.2 83.2 115.2 103.7 302.1

Transport 11.9 66.1 26.1 104.1 11.1 69.0 124.2 204.3

Water and 79.9 44.0 234.1 358.0 5.6 154.4 145.2 305.2
Sewerage

Other 0.2 0.2 0.2 0.2

TOTAL DRD 173.4 200.4 370.7 744.5 99.9 338.8 373.1 811.8

16
6. Corporate Governance

Responsibilities addition, the annual Resource Accounts of the


Department and Roads Service are scrutinised
The Permanent Secretary of the Department, as by the Comptroller and Auditor General.
Accounting Officer, is responsible for maintaining
a system of internal control. This system Risk Management
safeguards the public funds and departmental
assets in accordance with the responsibilities set The system of internal control within the
out in Government Accounting (NI). The system Department is based on an on-going risk
includes the appointment of the Chief Executive management process. This identifies the
of Roads Service as Agency Accounting Officer. principal risks that threaten the achievement of
The Chief Executive accordingly has similar departmental policies, aims and objectives. It
responsibilities in relation to the funds and assets also identifies the controls in place to manage
of Roads Service. Now that Northern Ireland those risks at four key levels:
Water is a separate legal entity, its Board is
collectively responsible for its operations. • Corporate – high level risks for the
Department managed by the Departmental
The Departmental Board supports the head of Board;
the Department. It contributes to the corporate
management of the Department within the • Agency/Core Group – key risks identified
strategic and policy resources framework set by and managed by the Senior management
Ministers. The Departmental Board operates team of each of the Department’s
within Terms of Reference which comply with the Executive Agencies and Core Groups
Code of Good Practice on Corporate Governance under Deputy Secretaries;
in Central Government Departments. The Board
includes two independent members to ensure • Division/Directorate Level – key risks
that executive members are supported and identified and managed by Directors and
constructively challenged in their role. They were their management teams; and
appointed in January 2007 for a two year period.
• Branch/Functional Area – key risks at
Departmental Management this level are identified by all staff and
Assurance System managed by the Head of Branch and feed
into the Agency/Divisional level risks as
In preparing the annual Statement on Internal
appropriate.
Control for the Department, the Accounting
Officer will place reliance on information
and assurances provided by the executive
members of the Departmental Board. The
work of the Internal Audit Branch also provides
the Accounting Officer with an independent
assurance on the effectiveness of the
Department’s system of internal control. In

17
6. Corporate Governance

Figure 1.3

The risk management cycle is a “top-down” and


“bottom-up” exercise. This allows risks to be
identified and managed at all the levels outlined
above and to be escalated as appropriate.

Figure 1.3 shows the relationship between the


various levels of risk management within the
Department.

Audit Committees

Audit Committees operate within the Department


and Roads Service. The Committees meet
up to four times per annum and their role is to
support the Accounting Officers in monitoring
the corporate governance and control systems
across the Department and Roads Service. The
Departmental Audit Committee is chaired by
a non-executive independent member of the
Departmental Board.

18
7. Business Plan 2007-08

Key Objective 1:

Supporting the economy by maintaining and Ireland. This represents a significant increase
developing safe transportation networks, over current investment levels and those levels
promoting airport and harbour services, and envisaged in the Regional Transportation
shaping the long-term development of the Strategy 2002-12.
region and providing other services to the
public and other Departments. The Investment Strategy for Northern Ireland,
along with conventionally procured schemes,
Better maintained road network currently includes two Public Private Partnership
packages with an estimated combined value
In 2007-08, the Department will ensure that of some £370 million. These packages will
structural maintenance of roads is undertaken in further enhance the roads infrastructure and
a timely fashion with a focus on optimising safety assist in achieving reductions in journey times
and value for money. on Key Transport Corridors. It commenced in
February 2006 and will include flyovers at the
More efficient transportation Grosvenor Road and Broadway roundabouts on
infrastructure the Westlink. It will also widen the M2 between
Sandyknowes and Greencastle and create new
In December 2005 the Secretary of State on-slips from Antrim Hospital to the M2.
announced total capital investment proposals
for the road network in excess of £1.9 billion,
as part of the Investment Strategy for Northern

Work ongoing A1 Newry to Dundalk Dual Carriageway

19
7. Business Plan 2007-08

The Department will continue to carry forward the range of measures will be undertaken. These
Accessible Transport Strategy. The Department’s include road safety engineering and traffic
Mobility Inclusion Unit will consult with key calming schemes and further enhancement of
stakeholders on a revised Accessible Transport the pedestrian and cycling infrastructure will also
Strategy Action Plan for 2007-09. Consultation improve road safety and facilitate an increase in
with the Inclusive Mobility Transport Advisory travel using these more sustainable modes of
Committee suggested that the Action Plan focus transport. These included significant cycleway
on ensuring that information is provided in ways and footway improvements on the Hospital Road,
which are accessible to people with disabilities Crevenagh Road and Irishtown Road in Omagh,
and older people to allow them to plan and make completed in conjunction with stage 3 of the
journeys independently and on training both for Omagh Throughpass, and at Westland Road in
transport providers on the needs of users and Cookstown.
for those users to enable them to overcome the
psychological barriers which inhibit their use of Improved air and sea port services
the accessible services which exist. and gateway facilities

Safer Roads In June 2006, the Department published a


consultation paper on ports policy issues, in
In partnership with the Department of the particular those relating to the powers, status
Environment and the Police Service of Northern and governance of public trust ports. The
Ireland, the Department is committed to reducing consultation paper was published in parallel
the number of people killed or seriously injured with “Ports Policy – your views invited”, the
on our roads. In support of this aim, a wide Department for Transport’s discussion paper

Traffic calming scheme Strabane

20
7. Business Plan 2007-08

for the United Kingdom ports policy review, In December 2006, a grant of almost £15
which was published in May 2006. Consultation million was announced to support essential
ended in September 2006. Subsequently the developments at Warrenpoint harbour. The grant
Department has been developing a range of will enable a major upgrade of the facilities at
options for consideration by Ministers. Warrenpoint to meet the demands of modern
vessels. This will secure the long term viability of
In January 2007, the Secretary of State the port and its contribution to the local economy.
announced the details of a package of support
for City of Derry Airport to be jointly funded Improved public transport services
with the Irish government. The British and and infrastructure
Irish governments are contributing equally to a
grant of £14 million to Derry City Council, the The Department will continue to support Translink
airport owner. Derry City Council is carrying in improving public transport in the region. The
out works to allow maximum use of the existing Department has carried out a strategic review
runway. The proposed safety works include the of future options for railways in the region. The
installation of new equipment and the purchase Department will report to Minister in light of the
of lands to remove obstacles. In February 2007 Review on a range of options for the size and
the Department announced a public inquiry into a level of rail services. The Department will also
request by Derry City Council for a vesting order examine the feasibility of potential Rapid Transit
relating to those lands. pilot routes in the Belfast Metropolitan Area.

Warrenpoint Harbour

21
7. Business Plan 2007-08

The Department has approved proposals for a finalisation of the policy. The Department is also
£50 million investment in additional new buses. reviewing planning policy Housing in Settlements
This will facilitate further development of the in response to the growing affordability problems
Metro service and help reduce the age of the identified in the Semple Review.
Ulsterbus fleet. It will also enable the elimination
of 3 for 2 seating and standing on school Enhancing Service Delivery and the
transport services. In addition the Department NICS Reform Framework
will fund a major programme of railway station
refurbishment to ensure compliance with the During 2007-08, the Department will begin to
Disability Discrimination Act 1995. implement HR Connect. This is a major reform
programme relating to Human Resource services
A sustainable approach to throughout the NICS. The reform programme
development and land use envisages extensive online services, timely
management reporting and consistency across
In 2007-08 the Department will continue to lead the whole of NICS. The aim is to provide more
the implementation of the Regional Development effective HR services with fewer resources
Strategy 2025 (RDS) through its work with other – allowing resources to be allocated to services
Departments, Councils and other key groups provided to the public.
at a sub-regional level. The Department will
complete the first five year review of the Regional There are significant accommodation challenges
Development Strategy by 30 June 2007. The ahead for the Department given its participation
review will consider in-course adjustments to the in Workplace 2010. The aim is to provide more
Strategy and will confirm adjustments to sections efficient accommodation for the Department.
on Rural Northern Ireland, the Environment and We will also ensure there is minimal disruption
the Economy. It will also set out anticipated to Departmental activities and service delivery.
figures for housing needs which were confirmed The challenge will be to use this project as an
following a Public Examination in February 2006. opportunity to consider, and where appropriate
introduce, new and more effective working
The Department has also prepared a series of practices.
Planning Policy Statements to implement the
Regional Development Strategy. These deal with The implementation and effective use of NICS
Development in the Countryside, Retailing and Records will provide the means for a more
town Centres, Housing in Settlements and The efficient management of documents and records
Coast. There is considerable public interest in held by the Department. The move from
these Statements. Consultation on ’Development personal document ownership to file sharing will
in the Countryside’ which was published in ensure duplication of information is reduced.
March 2006 elicited over 8,500 responses. All This in turn will improve the storage and
of these were considered by the Department accessibility of information and make for more
in preparing its final Statement. During 2007- efficient working practices.
08 the Department hopes to move forward the

22
7. Business Plan 2007-08

The Records-NI reform project incorporating The Construction Procurement Reform


the TRIM electronic document and records programme builds on the achievement of Roads
management system will be fully implemented Service in being recognised in 2007 as a Centre
in DRD between March and July 2007. This of Procurement Expertise. The Department will
will involve the training of some 2,500 users. progress actions in relation to design quality,
There will inevitably be some disruption during sustainability, project management, procurement
the implementation phase, but the benefits routes and health and safety. In particular it is
envisaged from use of the system are very proposed to:
significant, and long lasting.
• move to the New Engineering Contract
Account NI (ACNI) is being introduced to (NEC) Version 3 (Conditions of Contract)
modernise financial accounting processes. It from Version 2 presently being used.
aims to improve financial management across The Office of Government Commerce
all NICS departments. During 2007-08 the recommends the use of NEC3 by public
Department will continue to liaise with the ACNI sector construction procurers;
central team in establishing key requirements
and develop internal business processes • deliver the remaining nine Street Lighting
to enable the efficient linkage with a newly Term Contracts to complete the revised
established Shared Service Centre. strategy adopted for maintenance and
minor improvement works by March 2008;

Lagan bridge Belfast

23
7. Business Plan 2007-08

• review procurement strategies for capital • The Northern Ireland Transport Holding
schemes in line with Best Practice and Company’s subsidiaries will continue to
Achieving Excellence principles and provide the majority of public transport
produce revised policies and procedures services. However, the new public
by April 2008; and transport authority will be able to secure
services from private operators; and
• consider additional use of Public Private
Partnership to supplement packages I & II • Currently Government supports bus public
already in place. transport primarily through capital grant for
the purchase of new buses. It is intended
The Public Transport Reform programme will to shift support for buses away from capital
implement the statement relating to bus and to revenue, building on existing revenue
rail transport made on 22 August 2006. The support mechanisms.
announcement contained five main points:
Subject to legislation, the new arrangements will
• The new local authorities envisaged in the be in place from 2010. A major implementation
Review of Public Administration will have programme is being developed which will include
responsibility for planning, designing and work to set up the public transport authority.
securing public transport services, both
bus and rail. This is a development of the The various elements of Equality Reform will
commitment made as part of the Review continue to be progressed by the Department. It
of Public Administration that the new will continue to implement the Equality Scheme
local authorities would be involved in the and address issues emerging from the current
planning of bus services; Review of the Effectiveness of Section 75 by
the Equality Commission. With effect from 1
• Arrangements will be made for the January 2007, an amendment to the Disability
local authorities to discharge these Discrimination Act 1995 required public
responsibilities acting together in the authorities, when carrying out their functions, to
form of a public transport authority. The have due regard to the need to:
authority would comprise district councillors
drawn from the new local authorities. • Promote positive attitudes towards disabled
This is intended to ensure that within the people; and
region there is a unified approach to public
transport development; • Encourage participation by disabled people
in public life.
• Bus services will continue to be regulated.
There will not be “on the road” competition To this end the Department will prepare a
by bus operators as in Great Britain. This Disability Action Plan, in accordance with
is consistent with the intention that there is guidance prepared by the Equality Commission,
an integrated approach to public transport by 30 June 2007.
development;

24
7. Business Plan 2007-08

Key Objective 2:

Contributing to the health and well being to 82.5% of population served by compliant
of the community and the protection of the works in 2007-08, compared to 76% in 2006-07.
environment by developing and maintaining
the policy and regulatory environment which Reform of Water and Sewerage
provides modern, high quality water and Services
sewerage services at the lowest possible
cost. A major change programme carried through by
the Department has been the establishment
High quality drinking water and of Northern Ireland Water (NIW). This is an
high standard of Wastewater independent company whose shares are owned
treatment by the Department. All the region’s water and
sewerage assets, facilities and operations were
Investment in the region’s water and wastewater transferred to it on 1 April 2007.
infrastructure is essential to meet key
environmental standards and to deliver good
quality services to customers. The investment
in upgrading the water infrastructure will raise
the compliance with Drinking Water Standards
to 99.72% taking into account Authorised
Departures, and 99.60% not taking into account
Authorised Departures by 31 December 2007.

The drive to achieve wastewater compliance


standards remains the single largest asset
spend. The additional investment will raise the
total number of compliant works6 to 84%. The
population equivalent served by compliant works
will also be raised to 82.5% by 31 December
2007.

The target of 84% is below the original Public


Service Agreement target for waste water
compliance set in 2005. This is partly due to re-
definition of standards. The population served
by compliant works has however, increased, due
to some relatively large works being completed.
This has led to an increase in the target outturn Banbridge storm tanks

6
This target includes a small number of wastewater treatment works with <250 population equivalent and an Environment and Heritage
Service numeric discharge standard.

25
7. Business Plan 2007-08

The intended introduction of new domestic


charges for water and sewerage services was
deferred by the Executive for 2007-08. It also
announced a review of existing arrangements
with a view to finding sustainable and acceptable
funding arrangements for water and sewerage
services.

During 2007-08 work will focus on the Review of


funding arrangements for water and sewerage
services, the implementation of a regulatory
framework and supporting the achievement of
compliance with EU and legislative requirements.

On 1 April 2007, the Department assumed the


role and responsibilities of shareholder in the
company. This role includes the implementation
of the governance framework and setting
objectives for the company. The Department
will monitor and analyse the performance of the
company, as well as developing dividend and
remuneration policies.

26
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks,
promoting airport and harbour services, shaping the long-term development of the region and providing
other services to the public and other Departments
Planned Citizen Spending Area
7.

PSA Targets
Outcomes Actions SMART Targets
SERVICE PROVIDER: Spending Area 1 Resource £192.1 m
ROADS SERVICE Capital £103.1 m
Total £295.2 m
Better maintained road Maintain the road Implement Strategic Road Network By 31 March 2008, we will maintain
network network to the following structural maintenance programme. the motorway network so that at
defined levels of least 81% is in satisfactory1 structural
structural condition: condition.
Business Plan 2007-08

Carry out Annual Deflectograph By 31 March 2008, we will maintain


• 85% of the Motorway
Survey. the trunk road network so that at
network and
least 70% is in satisfactory structural
70% of the trunk

27
condition.
road network in
satisfactory7 structural Implement Local Road Structural By 31 March 2008, the remainder
condition Maintenance Programme. of the road network will receive
resurfacing treatment – 20% of
• “Other” roads to that recommended in Best Practice
receive resurfacing Guidelines.
treatment of 10% of
that recommended
in National Best
Practice Guidelines

7
“Satisfactory” means having a residual life of over 5 years.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks,
promoting airport and harbour services, shaping the long-term development of the region and providing
other services to the public and other Departments
Planned Citizen Spending Area
7.

PSA Targets
Outcomes Actions SMART Targets
More efficient By 2015 reduce journey Implement the major Capital Works By 31 March 2008, we will achieve
transportation times on the Key Programme. 85% of Roads Service’s major works
infrastructure Transport Corridors by milestones.
2.5% compared to 2001.
Safer Roads Reduce the number of Implement We will reduce, by at least 50%,
people/children killed • defect repair programme; the total number of target collisions
or seriously injured in • proactive maintenance occurring at treated sites over the
road traffic collisions programmes; and three years following completion of
Business Plan 2007-08

by 33/50% by 2012 • LTSM programme. the collision remedial works.


compared to 1996-2000
average.

28
Customer Service and Monitor and review performance on During 2007-08, we will respond
Service Improvements monthly basis. substantively to 90% of written
enquiries from customers within 15
working days.
Monitor and review performance on During 2007-08, we will issue
monthly basis. substantive replies to 95% of written
complaints from customers within 15
working days.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Spending Area
Planned Citizen
PSA Targets
Outcomes Actions SMART Targets

SERVICE PROVIDER: Spending Area 2 Resource £14.7 m


PORTS & PUBLIC Capital £14.5 m
TRANSPORT DIVISION Total £29.2 m
Improved air and sea Maintain annual Translink Complete Ports Policy Review. By 30 June 2007, detailed options will
port services and passenger numbers at have been presented to the Minister.
gateway facilities over 70 million in the face
of downward trends.
Business Plan 2007-08

Monitor Warrenpoint Harbour By 30 September 2007, we will appoint


Authority performance in relation consultants to review the port charging
to compliance with conditions regime and methodology.

29
set out under the Services of
General Economic Interest (SGEI) By 31 December 2007, we will
regulations as agreed through the implement full SGEI monitoring
Entrustment Contract between arrangements.
the Department and Warrenpoint
Harbour Authority.

Project financial monitoring. During 2007-08, we will monitor


Warrenpoint Harbour Authority and the
Department’s contributions to project
costs on a monthly basis.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
Facilitate effective port and harbour By 1 October 2007, we will
operations. reconstitute Warrenpoint Harbour
Authority.

By 1 January 2008, we will


reconstitute Belfast Harbour
Commissioners.
Provide grant to City of Derry Airport We will process valid grant claims
Business Plan 2007-08

for runway safety works. within 30 calendar days of receipt.

30
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Spending Area
Planned Citizen
PSA Targets
Outcomes Actions SMART Targets

SERVICE PROVIDER: Spending Area 3 Resource £55.5 m


PUBLIC TRANSPORT PERFORMANCE Capital £108.8 m
DIVISION Total £164.3 m
Improved public Maintain annual Translink Determine appropriate targets During 2007-08, we will monitor
transport services and passenger numbers at aimed at enhancing public transport Translink’s performance against a
facilities over 70 million in the face services and increasing passenger basket of key targets covering value
of downward trends. numbers. for money, operating efficiency, quality
Business Plan 2007-08

of service and safety.

By 31 December 2007, we will issue

31
a report benchmarking Translink’s
performance for 2007-08.

By 31 March 2008, we will set agreed


targets, main KPI measures in respect
of 2008-09.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
Ensure public funding of public By 30 September 2007, we
transport services is subject to will undertake a review of the
proper controls. Management Statement and Financial
Memorandum to ensure that they
provide an effective governance
framework between the Department
and NITHC.

During 2007-08, we will fully


Business Plan 2007-08

implement a financial memorandum


for the Public Service Obligation for
the railways.

32
Ensure plans for public transport By 31 May 2007, we will produce an
provision have a sound basis and appraisal report setting out options for
are aligned with departmental future railway services.
objectives.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Spending Area
Planned Citizen
PSA Targets
Outcomes Actions SMART Targets

SERVICE PROVIDER: Spending Area 4 Resource £1.4 m


REGIONAL PLANNING & TRANSPORTATION Capital £0.0 m
DIVISION Total £1.4 m
A sustainable Achieve more sustainable Continue current Regional By 31 December 2007, we will publish
approach to patterns of development Development Strategy (RDS) the Regional Development Strategy
development and land as outlined in Regional monitoring arrangements. Monitoring report, which will include
use Development Strategy. monitoring of the Brownfield target of
60%.
Business Plan 2007-08

Determine if Area Plans received We will issue statements within 28


from the Department of the calendar days of receipt of plans.

33
Environment are in general
conformity with the RDS.

Complete the 5 year review of the By 30 June 2007, we will publish


Regional Development Strategy. a final report on the review of the
Regional Development Strategy.

Prepare Planning Policy Statements By 31 March 2008, we will revise the


(PPS) to guide the implementation PPS on Housing to facilitate the supply
of the RDS. of housing land, especially social and
affordable.

By 31 March 2008, we will publish the


draft PPS on the Coast.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
Initial work on the mid-term review By 30 September 2007, we will
of the Regional Transportation undertake the review by critically
Strategy (RTS). assessing progress towards the RTS
key outcomes.

By 31 March 2008, we will consider


the need for any adjustments to the
Strategy.
Business Plan 2007-08

Rapid Transit feasibility studies. By 30 September 2007, we will


determine the preferred option to pilot
a scheme(s) in Belfast.

34
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Spending Area
Planned Citizen
PSA Targets
Outcomes Actions SMART Targets

SERVICE PROVIDER: Spending Area 5 Resource £15.0 m


RESOURCES AND MANAGEMENT SERVICES Capital £1.5 m
(DEPARTMENT FUNCTIONS NOT COVERED Total £16.5 m
BY PSA TARGETS)
Enhancing Service Implement over period of rollout (in We will implement the phased rollout
Delivery and the NICS liaison with CPG, HR Project Team of HR Connect between May 2007 and
Reform Framework and Provider) Change Strategy, September 2008.
Stakeholder Strategy, Deployment
Business Plan 2007-08

Strategy and Communication


Strategy.

35
Plan, manage and implement the By 31 January 2008, we will complete
roll out of Workplace 2010. the successful decant of all DRD
business areas to other city centre
locations (this date is subject to
change following central agreement of
WP2010 timescales).

Agree implementation timetable and By 31 March 2008, we will assess


requirements with Account NI. Departmental readiness for migration
to Account NI service.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
See that the NICS Common During 2007-08 we will monitor the
Infrastructure reform projects level of service provided by the
are implemented in a way that is NICS ICT Shared Service Centre
consistent with DRD’s corporate (SSC) to ensure that it is consistent
objectives for its people, resources with the commitments and agreed
and processes. levels as defined in the Service Level
Agreements and Operational Level
Agreements between the SSC and
the Department.
Business Plan 2007-08

Implement the Department’s By 31 March 2008, we will realise


Efficiency Technical Note and any total annual efficiencies of at least

36
additional agreed procurement £48.5 million and any additional
targets. procurement targets.

Emergency Management We will review Emergency


Development Plan and Major Management Development Plan
Emergency Response Plan objectives in April and October 2007.
reviewed and updated biannually.
By 30 June 2007, we will provide an
annual report to Departmental Board
on contingency planning.

By 31 December 2007, we will


have emergency plans in place and
reviewed.
Key Objective 1: Supporting the economy by maintaining and developing safe transportation networks, promoting
airport and harbour services, shaping the long-term development of the region and providing other services to the
public and other Departments 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
Implement relevant By 31 August 2007, we will report on
recommendations from the Review progress in the Department’s input to
of Better Regulation in collaboration the Better Regulation Annual report.
with DETI Better Regulation Unit.
Submit Quarterly progress reports By 31 August 2007, we will submit
on equality issues to the Minister Annual Progress Report to the
and Departmental Board. Equality Commission.
Business Plan 2007-08

Develop a Disability Action Plan. By 30 June 2007, we will submit


Disability Action Plan to Equality
Commission.

37
Raise awareness prior to roll-out of By 1 July 2007, we will implement
Records NI and ensure training is Records NI in the Department.
fully attended according to the roll-
out schedule.

Resource £278.7 m
TOTAL BUDGET FOR OBJECTIVE 1 Capital £227.9 m
Total £506.6 m
Key Objective 2: Contributing to the health and well being of the community and the protection of the environment by
developing and maintaining the policy and regulatory environment to provide modern, high quality water and sewerage
services, at the lowest possible cost. 7.

Spending Area
Planned Citizen
PSA Targets
Outcomes Actions SMART Targets

SERVICE PROVIDER: Spending Area 1 Resource £156.1 m


WATER POLICY DIVISION / SHAREHOLDER Capital £144.6 m
UNIT Total £300.7 m
High quality To increase compliance Monitor Northern Ireland Water In 2007-08 we will review Northern
drinking water and with the drinking water compliance with Key Performance Ireland Water’s performance against
high standard of standards set in the Indicators agreed in Strategic the following Key Performance
wastewater treatment. Water Supply (Water Business Plan on a quarterly basis. Indicators agreed in Strategic Business
Quality) Regulations Plan:
Business Plan 2007-08

(NI) 2002 to 99.72% by


December 2007. Seek corrective measures where • 99.72% taking account of
targets are not being met. authorised departure limits.

38
• 99.60% not taking account of
authorised departure limits.

To increase compliance Monitor, via NIAUR, NIW During 2007-08, for all wastewater
with Wastewater compliance with Key Performance treatment works serving greater than
Treatment Works Indicators agreed in Strategic 250 population equivalent we will
Registered Discharge Business Plan on a quarterly basis. monitor, via NIAUR, performance
Standards set by the on registered discharge compliance
Environment and against agreed Key Performance
Heritage Service to 84% Indicators as follows:
by December 2007.
(i) 84% of works;
(ii) 82.5% of the population
equivalent.
Key Objective 2: Contributing to the health and well being of the community and the protection of the environment by
developing and maintaining the policy and regulatory environment to provide modern, high quality water and sewerage
services, at the lowest possible cost. 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
High quality drinking To implement a Make relevant regulations and other By 1 April 2008, we will have a
water and high programme of reform of arrangements; prepare relevant comprehensive framework in place to
standard of wastewater the arrangements for the documents and to consult with include:
treatment. provision of water and stakeholders.
sewerage services in By 30 September 2007, we will make
Northern Ireland penalty regulations;
designed to secure self-
financing arrangements By 31 October 2007, we will
for these services by commence a review of the Water
Business Plan 2007-08

2009-10. Quality regulations.

By 31 January 2008, we will make

39
water fittings regulations;

By 31 March 2008, we will make


insolvency regulations.

During 2007-08, we will make


miscellaneous commencements as
required.

Draft Social and Environmental By autumn 2007, we will


guidance, under Article 7 of the draft Guidance on Social and
Water and Sewerage Services (NI) Environmental issues;
Order 2006 prioritising the need
for improvement and agree with
Regulators.
Key Objective 2: Contributing to the health and well being of the community and the protection of the environment by
developing and maintaining the policy and regulatory environment to provide modern, high quality water and sewerage
services, at the lowest possible cost. 7.

Planned Citizen Spending Area
PSA Targets
Outcomes Actions SMART Targets
Establish liaison arrangements with By 31 December 2007, we will have in
regulatory bodies. place Memorandum of Understanding
with regulatory bodies;

Payment and monitoring of By 30 June 2007, we will put in place


subsidies to NIW. arrangements for payment of subsidy.

Securing Effectiveness Active management of value of By 1 April 2007, we will have in place
and Value for Money shareholding through quarterly Northern Ireland Water’s governance
monitoring of company performance. arrangements.
Business Plan 2007-08

By 31 July 2007, we will commence


quarterly performance monitoring.

40
By 31 July 2007, we will agree with
Northern Ireland Water the process
for completing Key Performance
Indicators.

The Dividend for 2007-08 will be


paid as planned for in the Strategic
Business Plan.
Development and Support the Executive’s Review Meet Ministerial and Executive
maintenance of of funding of water and sewerage deadlines for Review;
effective policy and services;
regulatory environment
to provide high quality Handling of infraction proceedings Produce briefing as required.
water and sewerage within stipulated time frames;
services.
Development of implementation Contribute to Government policy as
policy on Water Framework Directive required.
and NI Sustainable Development
Plan.
Spending Area 2 Resource £3.9 m
DEPARTMENT FUNCTIONS NOT COVERED BY
Capital £0.6 m
PSA TARGETS
Total £4.5 m 7.

Resource £160.0 m
TOTAL BUDGET FOR OBJECTIVE 2 Spending Areas 3 Capital £145.2 m
Total £305.2 m
Business Plan 2007-08

41