You are on page 1of 20

Financial Management  Unit 9 

Unit 9  Risk Analysis in Capital Budgeting 

Structure 

9.1  Introduction 
9.2  Types and sources of Risk in capital Budgeting 
9.3  Risk Adjusted Discount Rate 
9.4  Certainty Equivalent 
9.5  Sensitivity Analysis 
9.6  Probability Distribution Approach: 
9.7  Decision – tree approach 
9.8  Summary: 
Terminal Questions 
Answer to SAQs and TQs 

9.1  Introduction 
In the previous chapter on capital budgeting the project appraisal techniques were applied on the 
assumption that the project will generate a given set of cash flows. 
It is quite obvious that one of the limitations of DCF techniques is the difficulty in estimating  cash 
flows with certain degree of certainty.  Certain projects when taken up by the firm will change the 
business risk complexion of the firm. 
This business risk complexion of the firm influences the required rate of return of the investors. 
Suppliers of capital to the firm tend to be risk averse and the acceptance of a project that changes 
the risk profile of the firm may change their perception of required rates of return for investing in 
firm’s project. 
Generally the projects that generate high returns are risky.  This will naturally alter the business 
risk  of  the firm.   Because of  this high  risk perception  associated  with  the  new  project  a  firm is 
forced  to  asses  the  impact  of  the  risk  on  the  firm’s  cash  flows  and  the  discount  factor  to  be 
employed in the process of evaluation. 
Definition of Risk:  Risk may be defined  as the variation of actual cash flows from  the expected 
cash flows.  The term risk in capital budgeting decisions may be defined as the variability that is 
likely to occur in future between the estimated and the actual returns.  Risk exists on account of 
the inability of the firm to make perfect forecasts of cash flows.

Sikkim Manipal University  147 
Financial Management  Unit 9 

Risk arises in project evaluation because the firm cannot predict the occurrence of possible future 
events  with  certainty  and  hence,  cannot  make  any  correct  forecast  about  the  cash  flows.  The 
uncertain economic conditions are the sources of uncertainty in the cash flows. 
For  example,  a  company  wants  to  produce  and  market  a  new  product  to  their  prospective 
customers.  The demand is affected by the general economic conditions.  Demand may be very 
high if the country experiences higher economic growth.  On the other hand economic events like 
weakening of US dollar, sub prime crises may trigger economic slow down.  This may create a 
pessimistic demand drastically bringing down the estimate of cash flows. 
Risk is associated with the variability of future returns of a project.  The greater the variability of 
the expected returns, the riskier the project. 
Every business decision involves risk.  Risk arises out of the uncertain conditions under which a 
firm has to operate its activities.  Because of the inability of firms to forecast accurately cash flows 
of  future  operations  the firms face the  risks  of  operations.  The  capital budgeting  proposals  are 
not based on perfect forecast of costs and  revenues because the assumptions about the future 
behaviour of costs and revenue may change.  Decisions have to be made in advance assuming 
certain future economic conditions. 
There are Many factors that affect forecasts of investment, cost and revenue. 
1)  The business is affected by changes in political situations, monetary policies, taxation, interest 
rates, policies of the central bank of the country on lending by banks etc. 
2)  Industry  specific  factors  influence  the  demand  for  the  products  of  the  industry  to  which  the 
firm belongs. 
3)  Company  specific  factors  like  change  in  management,  wage  negotiations  with  the  workers, 
strikes or lockouts affect company’s cost and revenue positions. 
Therefore,  risk  analysis  in  capital  budgeting  is  part  and  parcel  of  enterprise  risk  management. 
The best business decisions may not yield the desired results because the uncertain conditions 
likely to emerge in future can materially alter the fortunes of the company. 
Every  change  gives  birth  to  new  challenges.    New  challenges  are  the  source  of  new 
opportunities.  A proactive firm will convert every problem into successful enterprise opportunities. 
A firm which  avoids  new  opportunities for  the inherent  risk  associated with  it,  will  stagnate  and 
degenerate.  Successful firms have empirical history of successful management of risks. 
Therefore, analysing the risks of the project to reduce the element of uncertainty in execution has 
become an essential  aspect of today’s corporate project management.

Sikkim Manipal University  148 
Financial Management  Unit 9 

Learning Objectives: 

After studying this unit, you should be able to understand the following. 
1.  Define risk in capital budgeting. 
2.  Examine the importance of risk analysis in capital budgeting. 
3.  Methods of incorporating the risk factor in capital budgeting decision. 
4.  Understand the types and sources of risk in capital budgeting descision 

9.2 Types and sources of Risk in capital Budgeting 
Risks in a project are many.  It is possible to identify three separate and distinct types of risk in 
any project. 
1)  Stand – alone risk:  it is measured by the variability of expected returns of the project. 
2)  Portfolio risk:  A firm can be viewed as portfolio of projects having as certain degree of risk. 
When new project added to the existing portfolio of project the risk profile the firm  will alter. 
The degree of the change in the risk depend on the covariance of return from the new project 
and the return from the existing portfolio of the projects. If the return from the new project is 
negatively correlated with the return from portfolio, the risk of the firm will be further diversified 
away. 
3)  Market or beta risk:  It is measured by the effect of the project on the beta of the firm.  The 
market risk for a project is difficult to estimate. 
Stand alone risk is the risk of a project when the project is considered in isolation.  Corporate 
risk is the projects risks to the risk of the firm.  Market risk is systematic risk.  The market risk 
is the most important risk because of the direct influence it has on stock prices. 
Sources of risk:  The sources of risks are 
1.  Project – specific risk 
2.  Competitive or Competition risk 
3.  Industry – specific risk 
4.  International risk 
5.  Market risk 
1.  Project – specific risk:  The sources of this risk could be traced to something quite specific 
to  the  project.    Managerial  deficiencies  or  error  in  estimation of  cash flows  or  discount  rate 
may lead to a situation of actual cash flows realised being less than that projected. 
2.  Competitive  risk  or  Competition  risk:  unanticipated  actions  of  a  firm’s  competitors  will 
materially  affect  the  cash  flows  expected  from  a  project.    Because  of  this  the actual  cash 
flows from a project will be less than that of the forecast.

Sikkim Manipal University  149 
Financial Management  Unit 9 

3.  Industry – specific:  industry – specific risks are those that affect all the firms in the industry. 
It could be again grouped into technological risk, commodity risk and legal risk.  All these risks 
will affect the earnings and cash flows of the project.  The changes in technology affect all the 
firms not capable of adapting themselves to emerging new technology. 
The  best  example  is  the  case  of  firms  manufacturing  motor  cycles  with  two  strokes  engines. 
When technological innovations replaced the two stroke engines by the four stroke engines those 
firms which could not adapt to new technology had to shut down their operations. 
Commodity  risk  is  the  risk  arising  from  the  effect  of  price  –  changes  on  goods  produced  and 
marketed. 
Legal risk arises from changes in laws and regulations applicable to the industry to which the firm 
belongs.  The best example is the imposition of service tax on apartments by the Government of 
India  when  the  total  number  of  apartments  built  by  a  firm  engaged  in  that  industry  exceeds  a 
prescribed limit.  Similarly changes in Import – Export policy of the Government of India have led 
to the closure of some firms or sickness of some firms. 
4.  International Risk:  these types of risks are faced by firms whose business consists mainly 
of  exports  or  those  who  procure  their  main  raw  material  from  international  markets.    For 
example, rupee – dollar crisis affected the software and BPOs because it drastically reduced 
their  profitability.    Another  best  example  is  that  of  the  textile  units  in  Tirupur  in  Tamilnadu, 
exporting  their  major  part  of  the  garments  produced.  Rupee  gaining  and  dollar  Weakening 
reduced  their  competitiveness  in  the  global  markets.    The  surging  Crude  oil  prices  coupled 
with  the  governments  delay  in  taking  decision  on  pricing  of  petro  products  eroded  the 
profitability of oil marketing Companies in public sector like Hindustan Petroleum Corporation 
Limited.  Another example is the impact of US sub prime crisis on certain segments of Indian 
economy. 
The changes in international political scenario also affect the operations of certain firms. 
5.  Market Risk:  Factors like inflation, changes in interest rates, and changing general economic 
conditions affect all firms and all industries. 
Firms cannot diversify this risk in the normal course of business. 
Techniques used for incorporation of risk factor in capital budgeting decisions 
There  are  many  techniques  of  incorporation  of  risk  perceived  in  the  evaluation  of  capital 
budgeting  proposals.    They  differ  in  their  approach  and  methodology  so  far as incorporation of 
risk in the evaluation process is concerned. 
Conventional techniques 
Pay Back Period

Sikkim Manipal University  150 
Financial Management  Unit 9 

The  oldest  and  commonly used  method  of  recognising risk  associated  with  a  capital  budgeting 
proposal is pay back period.  Under this method, shorter pay back period is given preference to 
longer  ones.    Firms  establish  guidelines  for  acceptance  or  rejections  of  projects  based  on 
standards of pay back periods. 
Payback period prefers projects of short – term pay backs to that of long – term pay backs.  The 
emphasis is on the liquidity of the firm through recovery of capital.  Traditionally Indian business 
community employs this technique in evaluating projects with very high level of uncertainty. The 
changing trends in fashion make the fashion business, one of high risk and therefore, pay back 
period  has  been  endorsed  by  tradition  in  India  to  take  decisions  on  acceptance  or  rejection of 
such projects.  The usual risk in business is more concerned with the fore cast of cash flows.  It is 
the down side risk of lower cash flows arising from lower sales and higher costs of operation that 
matters in formulating standards of pay back. 
Pay back period ignores time value of many (cash flows).  For example, the following details are 
available in respect of two projects. 

Particulars  Project A (Rs)  Project B (Rs) 


Initial cash outlay  10 lakhs  10 lakhs 
Cash flows 
Year 1  5 lakhs  2 lakhs 
Year 2  3 lakhs  2 lakhs 
Year 3  1 lakhs  3 lakhs 
Year 4  1 lakhs  3 lakhs 

Both the projects have a pay back period of 4 years.  The project B is riskier than the Project A 
because Project A recovers 80% of initial cash outlay in the first two years of its operation where 
as  Project  B  generates  higher  Cash  inflows  only  in  the  latter  half  of  the  payback  period.    This 
undermines the utility of payback period as a technique of incorporating risk in project evaluation. 
This  method  considers  only  time  related  risks  and  ignores  all  other  risks  of  the  project  under 
consideration. 

Self Assessment Questions 2 
1.  _____________ is measured by the variability of expected returns of the project. 
2.  Market risk is measured by the effect of the project on the ____ of the firm. 
3.  Firms cannot ____ market risk in the normal course of business. 
4.  Impact  of  U.S  sub  prime  crisis  on  certain  segments  of  Indian  economy  is  and  example  of 
_______________________.

Sikkim Manipal University  151 
Financial Management  Unit 9 

9.3 Risk Adjusted Discount Rate 
The basis of this approach is that there should be adequate reward in the form of return to firms 
which decide to execute risky business projects. Man by nature is risk­averse and tries to avoid 
risk.  To motivate firms to take up risky projects returns expected from the project shall have to be 
adequate, keeping in view the expectations of the investors. Therefore risk premium need to be 
incorporated in discount rate in the evaluation of risky project proposals. 
Therefore the discount rate for appraisal of projects has two components. 
Those components are 
1.  Risk – free rate and risk premium 
Risk Adjusted Discount rate = Risk free rate + Risk premium 
Risk free rate is computed based on the return on government securities. 
Risk  premium  is  the  additional  return  that  investors  require  as  compensation  for  assuming  the 
additional risk associated with the project to be taken up for execution. 
The  more  uncertain  the  returns  of  the  project  the  higher  the  risk.  Higher  the  risk  greater  the 
premium.    Therefore,  risk  adjusted  Discount  rate  is  a  composite  rate  of  risk  free  rate  and  risk 
premium of the project. 
Example:  An investment will have an initial outlay of Rs 100,000. It is expected to generate cash 
inflows as under: 
Year  Cash in flows 
1  40,000 
2  50,000 
3  15,000 
4  30,000 

Risk free rate of interest is 10%.  Risk premium is 10% (the risk characterising the project) 
(a)  compute the NPV using risk free rate 
(b)  Compute NPV using risk – adjusted discount rate 
Solutions = (a) using risk – free rate 

Year  Cash flows (inflows) Rs  PV Factor at 10%  PV of Cash flows (in flows) 


1  40,000  0.909  36,360 
2  50,000  0.826  41,300 
3  15,000  0.751  11,265 
4  30,000  0.683  20,490 
PV of cash in flows  1,09,415

Sikkim Manipal University  152 
Financial Management  Unit 9 

PV of Cash outflows  1,00,000 
NPV  9,415 

(b)  Using risk – adjusted discount rate 
Year  Cash in flows Rs  PV factor at 20%  PV of cash inflows 
1  40,000  0.833  33,320 
2  50,000  0.694  34,700 
3  15,000  0.579  8,685 
4  30,000  0.482  14,460 
PV of Cash in flows  91,165 
PV of Cash out flows  100,000 
NPV  (8,835) 

The project would be acceptable when no allowance is made for risk. 
But it will not be acceptable if risk premium is added to the risk free rate.  It moves from positive 
NPV to negative NPV. 
If the firm were to use the internal rate of return, then the project would be accepted when IRR is 
greater than the risk – adjusted discount rate. 
Evaluation of Risk – adjusted discount rate: 
Advantages: 
1.  It is simple and easy to understand. 
2.  Risk premium takes care of the risk element in future cash flows. 
3.  It satisfies the businessmen who are risk – averse. 

Limitations: 
1.  There  are  no  objective  bases of  arriving  at  the  risk  premium.    In  this  process  the  premium 
rates computed become arbitrary. 
2.  The assumption that investors are risk – averse may not be true in respect of certain investors 
who are willing to take risks.  To such investors, as the level of risk increases, the discount 
rate would be reduced. 
3.  Cash flows are not adapted to incorporate the risk adjustment for net cash in flows. 

Self Assessment Questions 2 

1. Risk premium is the __________________ that the investors require as compensation for

Sikkim Manipal University  153 
Financial Management  Unit 9 

assumption of additional risks of project. 
2. RADR is the sum of ______________ and ______________. 
3. Higher the risk __________________ the premium. 
4. Man by nature is risk­averse and tries to avoid risk. 

9.4  Certainty Equivalent: 
Under this method the risking uncertain, expected future cash flows are converted into cash flows 
with  certainty.    Here  we  multiply  uncertain  future  cash  flows  by  the  certainty  –  equivalent 
coefficient  to  convert  uncertain  cash  flows  into  certain  cash  flows.    The  certainty  equivalent 
coefficient  is  also  known  as  the  risk  –  adjustment  factor.    Risk  adjustment  factor  is  normally 
denoted by αt (Alpha).  It is the ratio of certain net cash flow to risky net cash flow 
= Certainty Equivalent = Certain Cash flow 
Risky Cash flow 

The discount factor to be used is the risk free rate of interest.  Certainty equivalent coefficient is 
between 0 and 1.  This risk – adjustment factor varies inversely with risk.  If risk is high a lower 
value is used for risk adjustment.  If risk is low a higher coefficient of certainty equivalent is used 

Illustration (Example) 
A project costs Rs 50,000.  It is expected to generate cash inflows as under 
Year  Cash in flows  Certainty Equivalent 
1  32,000  0.9 
2  27,000  0.6 
3  20,000  0.5 
4  10,000  0.3 

Risk – free discount rate is 10% compute NPV 
Answer: 
Year  Uncertain cash  C E  Certain cash  PV Factor at  PV of certain cash 
in flows  flows  10%  inflows 
1  32,000  0.9  28,800  0.909  26,179 
2  27,000  0.6  16,200  0.826  13,381 
3  20,000  0.5  10,000  0.751  7,510 
4  10,000  0.3  3,000  0.683  2,049

Sikkim Manipal University  154 
Financial Management  Unit 9 

PV of certain cash in  49,119 
flows 
Initial cash out lay  50,000 
NPV  (881) negative 

The project has a negative NPV. 
Therefore, it is rejected. 

If IRR is used the rate of discount at which NPV is equal to zero is computed and then compared 
with the minimum (required) risk free rate.  If IRR is greater than specified minimum risk free rate, 
the project is accepted, other wise rejected. 

Evaluation: 
It recognises risk.  Recognition of risk by risk – adjustment factor facilitates the conversion of risky 
cash flows into certain cash flows.  But there are chances of being inconsistent in the procedure 
employed from one project to another. 
When forecasts pass through many layers of management, original forecasts may become highly 
conservative. 
Because of high conservation in this process only good projects are likely to be cleared when this 
method is employed. 
Certainty –  equivalent approach is considered to be theoretically superior to the risk –  adjusted 
discount rate. 
Self Assessment Questions 3 
1. CE coefficient is the _______ . 
2. Discount factors to be used under CE approach is _____________. 
3. Because of high ______________ CE clears only good projects. 
4. ___________ is considered to be superior to RADR 
9.5  Sensitivity Analysis: 
There  are  many  variables  like  sales,  cost  of  sales,  investments,  tax  rates  etc  which  affect  the 
NPV  and  IRR  of a  project.    Analysing  the  change  in  the  project’s  NPV or  IRR  on  account  of a 
given change in one of the variables is called Sensitivity Analysis.  It is a technique that shows the 
change in NPV given a change in one of the variables that determine cash flows of a project.  It 
measures the sensitivity of NPV of a project in respect to a change in one of the input variables of 
NPV.

Sikkim Manipal University  155 
Financial Management  Unit 9 

The  reliability  of  the  NPV  depends  on  the  reliability  of  cash  flows.    If  fore  casts  go  wrong  on 
account  of  changes  in  assumed  economic  environments,  reliability  of  NPV  &  IRR  is  lost. 
Therefore, forecasts are made under different economic conditions viz pessimistic, expected and 
optimistic. NPV is arrived at for all the three assumptions. 
Following steps are involved in Sensitivity analysis: 
1.  Identification of variables that influence the NPV & IRR of the project. 
2.  Examining and defining the mathematical relationship between the variables. 
3.  Analysis of the effect of the change in each of the variables on the NPV of the project. 

Example:    A  company  has  two  mutually exclusive  projects  under  consideration viz  project  A  & 
project B. 
Each project requires an initial cash outlay of Rs 3,00,000 and has an effective life of 10 years. 
The  company’s  cost  of  capital  is  12%.    The  following  fore  cast  of  cash flows  are  made  by  the 
management. 

Economic  Project A  Project B 


Environment  Annual cash inflows  Annual cash in flows 
Pessimistic  65,000  25,000 
Expected  75,000  75,000 
Optimistic  90,000  1,00,000 

What is the NPV of the project? 
Which project should the management consider? 
Given PVIFA = 5.650 
Answer / Solutions 
NPV of project A 

Economic  Project  PVIFA  PV of cash in flows  NPV 


Environment  cash inflows  at  12%  10 
years 
Pessimistic  65,000  5.650  3,67,250  67,250 
Expected  75,000  5.650  4,23,750  1,23,750 
Optimistic  90,000  5.650  5,08,500  2,08,500

Sikkim Manipal University  156 
Financial Management  Unit 9 

NPV of Project B 
Pessimistic  25,000  5.650  1,41,250  (1,58,750) 
Expected  75,000  5.650  4,23,750  1,23,750 
Optimistic  1,00,000  5.650  5,65,000  2,65,000 

Decision 
1.  Under pessimistic conditions project A gives a positive NPV of Rs 67,250 and Project B has a 
negative NPV of Rs 1,58,750 Project A is accepted. 
2.  Under  expected  conditions, both  gave  some  positive  NPV  of Rs  1,23,000.  Any  one  of  two 
may be accepted. 
3.  Under optimistic conditions Project B has a higher NPV of Rs 2,65,000 compared to that  of 
A’s NPV of Rs 2,08,500. 
4.  Difference  between  optimistic  and  pessimistic  NPV  for  Project  A  is  Rs  1,41,250  and  for 
Project B the difference is Rs 4,23,750. 
5.  Project B is risky compared to Project A because the NPV range is of large differences. 
Statistical Techniques: 
Statistical techniques use analytical tools for assessing risks of investments. 

Self  Assessment Questions 4 

1. _____________ analysis the changes in the project NPV on account of a given change in one 
of the input variables of the project. 
2.  Examining  and  defining  the  mathematical  relation  between  the  variable  of  the  NPV  is 
_________________________. 
3. Forecasts under sensitivity analysis are made under __________. 

9.6  Probability Distribution Approach: 
When  we  incorporate the  chances  of occurrences  of various economic environments  computed 
NPV  becomes  more  reliable.    The  chances  of  occurrences  are  expressed  in  the  form  of 
probability.  Probability is the likelihood of occurrence of a particular economic environment.  After 
assigning probabilities to future cash flows expected net present value is computed. 

Illustration:    A  company  has  identified  a project  with  an  initial  cash  outlay  of  Rs  50,000.    The 
following distribution of cash flow is given below for the life of the project of 3 years.

Sikkim Manipal University  157 
Financial Management  Unit 9 

Year 1  Year 2  Year 3 


Cash in flow  Probability  Cash in flow  Probability  Cash in flow  Probability 
15,000  0.2  20,000  0.3  25,000  0.4 
18,000  0.1  15,000  0.2  20,000  0.3 
35,000  0.4  15,000  0.2  20,000  0.3 
32,000  0.3  30,000  0.2  45,000  0.1 

Discount rate is 10% 
Year 1 
= 15,000 x 0.2 + 18,000 x 0.1 + 35,000 x 0.4 + 32,000 x 0.300 
3,000 + 1,800 + 14,000 + 9,600 = 28,400 
Year 2 
20,000 x 0.3 + 15,000 x 0.2 + 30,000 x 0.3 + 30,000 x 0.2 
= 6,000 + 3,000 + 9,000 + 6,000 = 24,000 
Year 3 
25,000 x 0.4 + 20,000 x 0.3 + 40,000 x 0.2 + 5,000 x 0.1 = 
10,000 + 6,000 + 8,000 + 4,500 == 28,500 

PV of expected 
Year  Expected cash inflows  PV factor at 10% 
cash in flows 
1  28,400  0.909  25,816 
2  24,000  0.826  19,824 
3  28,500  0.751  21,403 
PV of expected cash in flows  67,043 
PV of initial cash out lay  50,000 
Expected NPV  17,043 
Variance: 
A  study  of  dispersion  of  cash  flows  of  projects  will  help  the  management  in  assessing  the  risk 
associated  with  the  investment  proposal.    Dispersion  is  computed  by  variance  or  standard 
deviation.    Variance  measures  the  deviation  of  each  possible  cash  flow  from  the  expected. 
Square root of variance is standard deviation. 

Example:  Following details are available in respect of a project which requires an initial cost of 
Rs 5,00,000.

Sikkim Manipal University  158 
Financial Management  Unit 9 

Year  Economic Conditions  Cash flows  Probability 


1  High growth  2,00,000  0.3 
Average growth  1,50,000  0.6 
No growth  40,000  0.1 
2  High growth  3,00,00  0.3 
Average growth  2,00,000  0.5 
No growth  5,00,000  0.2 
3  High growth  4,00,000  0.2 
Average growth  2,50,000  0.6 
No growth  30,000  0.2 

Discount rate is 10% 
Solution: 
Year 1 
Economic Condition  Cash in flow  Probability  Expected value of Cash in flow 
1  2  3 
High growth  2,00,000  0.3  60,000 
Average growth  1,50,000  0.6  90,000 
No growth  40,000  0.1  4,000 
Expected Value  1,54,000 

Year 2 
Economic Condition  Cash in flow  Probability  Expected value of Cash in flow 
High growth  3,00,000  0.3  90,000 
Average growth  2,00,000  0.5  1,00,000 
No growth  50,000  0.2  10,000 
Expected Value  2,00,000 

Year 3 
Economic Condition  Cash in flow  Probability  Expected value of Cash in flow 
High growth  4,00,000  0.2  80,000 
Average growth  2,50,000  0.6  1,50,000 
No growth  30,000  0.2  6,000

Sikkim Manipal University  159 
Financial Management  Unit 9 

Expected Value of  2,36,000 
Cash inflows 
1,54,000         2,00,000  2,36,000 
Expected NPV =  1.10               (1­10) 
+  2  +  (1.10) 3  ­ 5,00,000

= 1,40,000 + 1, 65, 289 + 1, 77, 310 – 5,00,000 = (17,401) negative NPV 

Standard Deviation for I year 

Cash in flow  Expected Value  (C – E) 2  (C – E) 2  x prob 


C  E 
2,00,000  1,54,000  (46,000) 2  (46,000) 2  x 0.3 = 634800  000 
1,50,000  1,54,000  (­ 4000) 2  (­ 4,000) 2  x 0.3 = 9600  000 
40,000  1,54,000  ( ­ 1,14,000) 2  (­ 1,14,000) 2  x 0.3 = 12996 00 000 
Total  1944  000 000 

Standard deviation of Cash flows for I year = 44091 
For 2 nd  year 
Cash in flow  Expected Value  (C – E) 2  (C – E) 2  x prob 
C  E 
3,00,000  2,00,000  (1,00,000) 2  (1,00,000) 2  x 0.3 = 3000 000  000 
2,00,000  2,00,000  (0) 2  (0) 2  x 0.5 = 0 
50,000  2,00,000  ( ­ 1,50,000) 2  (­ 1,50,000) 2  x 0.2 = 45 00 000 000 
Total  7500 00 000 

Variance of Cash flows for 2 nd  year = 7500 000 000 
Standard Deviation of cash flows for 2 nd  year = 8660 
For the third year 
Cash in flow  Expected Value  (C – E) 2  (C – E) 2  x prob 
C  E 
4,00,000  2,36,000  (1,64,000) 2  (1,64,000) 2  x 0.2 = 53792 00  000 
2,50,000  2,36,000  (14,000) 2  (14,000) 2  x 0.6 = 1176 00 000 
30,000  2,36,000  ( ­ 2,00,000) 2  (­ 2,00,000) 2  x 0.2 = 8000 000 000 
Total  13496800 000 

Sikkim Manipal University  160 
Financial Management  Unit 9 

Variance of Cash flows for 3 rd  year = 13496800 000 
Standard Deviation of cash flows for 3 rd  year = 116175 
Standard Deviation of NPV

Ö(44091) 2  (8660) 2  (116175) 2


sNPV  =  +  +
Ö(1.10) 2  (1.10) 4  (1.10) 6 
= Ö1606625026 + 51223004 + 7618496131 
= Ö9276344161 
= 96314 

Here the assumption is that there is no relationship between cash flows from one period to 
another. Under this assumption the standard deviation  of NPV  is Rs 96,314. 
On  the  other  hand,  if  cash  flows  are  perfectly  correlated,  cash  flows  of  all  years  have 
linear correlation to one another, then 

44091                8660                116175 
sNPV  =  +  (1.10) 2  + (1.10) 3 
1.10 
= 40083 + 7157 + 87284 = 134524 

The  standard  deviation  of  NPV  when  cash  flows  are  perfectly  correlated  will  be  higher 
than that under the situation of independent cash flows. 
Self Assessment Questions. 5 
1.  Probability  distribution  approach  incorporates  the  probability  of  occurrences  of  various 
economic environment, to make the NPV ________. 
2. _______ is likelihood of occurrence of a particular economic environment. 

9.7  Decision – tree approach: 
Many project decisions are complex investment decisions.  Such complex investment decisions 
involve a sequence of decisions over time.  Decisions tree can handle the sequential decisions of 
complex  investment  proposals.    The  decision  of  taking  up  an  investment  project  is  broken  into 
different stages.  At each stage the proposal is examined to decide whether to go ahead or not. 
The  multi  –  stages  approach  can  be  handled  effectively  with  the  help  of  decision  trees.    A 
decision tree presents graphically the relationship between a present decision and future events, 
future decisions and the consequences of such decisions.

Sikkim Manipal University  161 
Financial Management  Unit 9 

Example 
R & D section of a company has developed an electric moped.  The firm is ready for pilot 
production and test  marketing.    This  will  cost  Rs  20  million and  take  six  months.    Management 
believes that there is a 70% chance that the pilot production and test marketing will be successful. 
If successful the company can build a plant costing Rs 200 million. 
The plant will generate annual cash in flow of Rs 50 million for 20 years if the demand is high or 
an annual cash inflow or 20 million if the demand is low. 

High demand has a probability of 0.6 and low demand has a probability of 0.4.  Cost of capital is 
12%. 
Suggest  the  optimal  course  of  action  using  decision  tree  analysis  (Bangalore  University  MBA, 
adapted).  High Demand 
Probability 0.6 
C21 
D21  Investment  Annual Cash inflow 
Rs.200 million  Rs.50 million 
C2 
D11  Carry out pilot 
Production  C11  Success  Annual Cash inflow 
And Market  D2  Rs.20 million 
test (20 million) 
0.7 D22  Stop  C22  Low Demand 
C1  Probability  0.4 

D  D3 
C12  failure  D31  Stop 
Probability 0.3 

D12  Do Nothing 

Working Notes:  From right hand side of the decision tree 
I  step:    Computation of Expected  Monetary  Value at point  C2.    Here EMV  represents expected 
NPV. 

Cash in flow  Probability  Expected value of cash inflows 


50  0.6  30 
20  0.4  8 
EMV  38 

Present Value of EMV = Expected value of cash inflow x PVIFA (12% 20) 
38 x 7.469 = Rs 283.82 million 

Sikkim Manipal University  162 
Financial Management  Unit 9 

Step 2: 
Computation of EMV at decision point D2. 
Decision taken  Consequences  The resulting EMV at this level 
D2  Invest Rs 200 million  283.82 – 200 83.82 million 
D22  Stop  0 
Here the decision criterion is “select the EMV with the highest value”. 

Stage 3: 
Therefore EMV with Rs 83.82 million will be considered therefore; we select the decision taken at 
D2, 
Stage 4: 
Computation of EMV at the point C, 
EMV  Probability  Expected Value 
83.82  0.7  58.67 
0  0.3  0 
EMV at this stage  58.67 

Step 5: 
Compute EMV at decisions point D, 
Decision taken  Consequences  The resulting Em at this 
level 
D11 carry out pilot  Invest  58.67 – 20 = Rs 38.67 Million 
production and market test  20 million 
D12 Do nothing  0  0 
EMV at this stage  38.67 Million 
(Apply the EMV criterion) i.e 
select the EMV with the 
highest value 

Therefore optimal strategy is 
1.  Carry out pilot production and market test. 
2.  If  the  result  of pilot production  and  market  test  is  successful,  go  ahead  with  the investment 
decision of Rs 200 million in establishing a plant. 
3.  If the result of pilot production and market test is future, stop.

Sikkim Manipal University  163 
Financial Management  Unit 9 

Evaluation of Decision tree approach: 
1.  It portrays inter – related, sequential  and critical multi dimensional elements of major project 
decisions. 
2.  Adequate attention is given to the critical aspects in an investment decision which spread over 
a time sequence. 
3.  Complex  projects  involve  huge  out  lay  and  hence  risky.    There  is  the  need  to  define  and 
evaluate  scientifically  the  complex  managerial  problems  arising  out  of  the  sequence  of 
interrelated decisions with consequential outcomes of high risk.  It is effectively answered by 
decision tree approach. 
4.  Structuring a  complex project  decision  with  many  sequential investment  decisions demands 
effective project risk management.  This is possible only with the help of an analytical tool like 
decision tree approach. 
5.  Able  to  eliminate unprofitable outcomes  and helps  in  arriving  at  optimum decision stages in 
time sequence. 

Self Assessment Questions 6 
1. Decision tree can handle the _____________ of complex investment proposals. 
2. _____ portrays inter­related, sequential and critical multi dimensional elements of major project 
decisions. 
3.  Adequate  attention  is  given  to  the  ______  in  an  investment  decision  under  decision  tree 
approach’s. 
4. ____________ are effectively handled by decision tree approach’s . 

9.8 Summary 
Risk in project evaluation arises on account of the inability of the firm to predict  the performance 
of the firm  with  certainty.  Risk in capital budgeting  decision  may  be  defined  as  the variability of 
actual  returns  from  the  expected.  There  are  many  factors  that  affect  forecasts  of  investment, 
costs and revenues of a project. It is possible to identify three type of risk in any project, viz stand­ 
alone risk, corporate risk and market risk. The sources of risks are: 
a.  Project 
b.  Competition 
c.  Industry 
d.  International factors and 
e.  Market

Sikkim Manipal University  164 
Financial Management  Unit 9 

The techniques for incorporation of risk factor in capital budgeting decision could be grouped into 
conventional techniques and statistical techniques. 

Terminal Questions 
1.  Define risk. Examine the need for assessing the risks in a project. 
2.  Examine the type and sources of risk in capital budgeting . 
3.  Examine  risk  adjusted  discount  rate  as  a  technique  of  incorporating  risk  factor  in  capital 
budgeting. 
4.  Examine the steps involved in sensitivity analysis. 
5.  Examine the features of Decision­tree approaches. 

Answer for Self Assessment Questions 
Self Assessment Questions 1 
1.  Stand­alone risk. 
2.  Beta 
3.  Diversify 
4.  International risk 

Self Assessment Question 2 
1.  Additional return 
2.  Risk free rate, risk premium. 
3.  Greater. 

Self Assessment Question 3 
1.  Risk­ adjustment factor 
2.  Risk free rate of interest. 
3.  Conservation. 
4.  CE 

Self Assessment Question 4 
1.  Sensitivity analysis 
2.  One of the steps of sensitivity analysis 
3.  Different economic conditions

Sikkim Manipal University  165 
Financial Management  Unit 9 

Self Assessment Question 5 
1.  More reliable 
2.  Probability 

Self Assessment Question 6 
1.  Sequential decisions 
2.  Decision tree. 
3.  Critical aspects 
4.  Complex projects. 

Answer for Terminal Questions 
1.  Refer to units 9.1 
2.  Refer to units 9. 2 
3.  Refer to units 9.3 
4.  Refer to unit 9.5 
5.  Refer to unit 9.7

Sikkim Manipal University  166 

You might also like