RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN :
LOKASI :

HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME
(Rp)

I. PEK. PEDAHULUAN
1 Pembersihan Lokasi Ls 1.00 2,500,000.00
2 Direksi keet Ls 1.00 8,000,000.00
3 Pembuatan Pagar Proyek M1 90.00 180,000.00
4 Pas.Bowplank/Pengukuran M1 78.00 42,000.00
Jumlah I
II. PEKERJAAN PONDASI/SLOOF
1 Galian Tanah Pondasi Plat M3 19.20 37,500.00
2 Pondasi Beton Poor 0.25/1.00/1.00 M3 4.00 2,890,000.00
3 Beton Sloof 20/40 M3 8.00 4,760,000.00
4 Beto Kolom 30/30 M3 7.34 5,230,000.00
5 Beto Balok Latei 15/20 M3 1.50 4,610,000.00
6 Beto Ring Balok 20/30 M3 3.00 5,730,000.00
Jumlah II
III. PEKERJAAN KAP/ATAP
1 Pas.Kuda-kuda Rangka Atap M3 10.20 4,475,000.00
2 Pas Atap Seng BJLS 0,30 M2 281.60 110,000.00
3 Pas.Perabung Seng BJLS 0,30 M1 16.80 60,000.00
Jumlah III
IV. PEKERJAAN DINDING/PLESTERAN
1 Pas.Batu Bata 1:4 M2 260.00 92,000.00
3 Plesteran 1:4 M2 520.00 34,000.00
4 Afwerkink Beton M2 57.60 42,000.00
Jumlah IV
V. PEKERJAAN LANTAI
1 Urugan Bawah Lantai M3 75.00 156,000.00
2 Beton Bertulang Lantai M3 19.26 2,600,000.00
Jumlah V
VI. PEKERJAAN KONSEN PINTU DAN JENDELA
1 Pas.Pintu Folding Gate M2 9.00 900,000.00
2 Pas.Pintu Angin Besi Holow M2 4.00 670,000.00
3 Pas.Loster Beton Unit 24.00 85,000.00
Jumlah VI
VII. PEKERJAAN CAT
1 Cat.Dinding Dan Plafond M2 577.60 28,000.00

VII
VIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL
1 Pas.Stop Kontak Bh 4.00 225,000.00
2 Pas.Lampu TL Kap 2x40 Bh 4.00 235,000.00
3 Pas.Instalasi Lampu Titik 8.00 195,000.00
Jumlah VIII

REKAPITULASI

I. PEK. PEDAHULUAN
II. PEKERJAAN PONDASI/SLOOF
III. PEKERJAAN KAP/ATAP
IV. PEKERJAAN DINDING/PLESTERAN
V. PEKERJAAN LANTAI
VI. PEKERJAAN KONSEN PINTU DAN JENDELA
VII. PEKERJAAN CAT
VIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL

Terbilang: Tiga Ratus Sembilan Puluh Tiga- Sub Total


Juta Tujuh Ratus Tiga Ribu Rupiah PPN 10%
HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME
(Rp)
Jumlah Total
Dibulatkan
ANA ANGGARAN BIAYA (RAB)

JUMLAH HARGA
(Rp)

2,500,000.00
8,000,000.00
16,200,000.00
3,276,000.00
29,976,000.00

720,000.00
11,560,000.00
38,080,000.00
38,409,120.00
6,915,000.00
17,190,000.00
112,154,120.00

45,645,000.00
30,976,000.00
1,008,000.00
77,629,000.00

23,920,000.00
17,680,000.00
2,419,200.00
44,019,200.00

11,700,000.00
50,065,600.00
61,765,600.00

8,100,000.00
2,680,000.00
2,040,000.00
12,820,000.00

16,172,800.00

16,172,800.00

900,000.00
940,000.00
1,560,000.00
3,400,000.00

29,976,000.00
112,154,120.00
77,629,000.00
44,019,200.00
61,765,600.00
12,820,000.00
16,172,800.00
3,400,000.00

357,936,720.00
35,793,672.00
JUMLAH HARGA
(Rp)
393,730,392.00
393,730,000.00
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBUATAN GUDANG
LOKASI : PT PLN (PERSERO) WILAYAH RIAU

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOLUME
(Rp) (Rp)

I. PEK. PEDAHULUAN
1 Pembersihan Lokasi Ls 1.00 750,000.00 750,000.00
2 Pembuatan Pagar Proyek/Pengukuran M1 62.00 282,551.00 17,518,162.00
Jumlah I 18,268,162.00
II. PEKERJAAN PONDASI/SLOOF
1 Galian Tanah Pondasi Plat M3 19.20 37,500.00 720,000.00
2 Pondasi Beton Poor 0.25/1.00/1.00 M3 4.00 2,890,000.00 11,560,000.00
3 Beton Sloof 20/40 M3 8.00 4,760,000.00 38,080,000.00
4 Beton Kolom 30/30 M3 7.34 5,230,000.00 38,409,120.00
5 Beton Balok Lantai 15/20 M3 1.50 4,610,000.00 6,915,000.00
6 Beton Ring Balok 20/30 M3 3.00 5,730,000.00 17,190,000.00
Jumlah II 112,154,120.00
III. PEKERJAAN KAP/ATAP
1 Pas.Kuda-kuda Rangka Atap M3 10.20 4,475,000.00 45,645,000.00
2 Pas Atap Seng BJLS 0,30 M2 281.60 47,200.00 13,291,520.00
3 Pas.Perabung Seng BJLS 0,30 M1 16.80 60,000.00 1,008,000.00
Jumlah III 59,944,520.00
IV. PEKERJAAN DINDING/PLESTERAN
1 Pas.Batu Bata 1:4 M2 260.00 173,258.00 45,047,080.00
3 Plesteran 1:4 M2 520.00 27,154.00 14,120,080.00
4 Acian Beton M2 57.60 16,400.00 944,640.00
Jumlah IV 60,111,800.00
V. PEKERJAAN LANTAI
1 Urugan Bawah Lantai M3 75.00 137,150.00 10,286,250.00
2 Beton Bertulang Lantai Teb. 12 cm M3 18.00 2,600,000.00 46,800,000.00
Jumlah V 57,086,250.00
VI. PEKERJAAN PINTU
1 Pas.Pintu Folding Gate M2 12.00 950,000.00 11,400,000.00
2 Pas.Pintu Angin Besi Holow M2 4.00 670,000.00 2,680,000.00
Jumlah VI 14,080,000.00
VII. PEKERJAAN CAT
1 Cat.Dinding M2 414.00 28,000.00 11,592,000.00
VII 11,592,000.00
VIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL
1 Pas.Stop Kontak Bh 4.00 225,000.00 900,000.00
2 Pas.Lampu TL Kap 2x40 Bh 6.00 235,000.00 1,410,000.00
3 Pas.Instalasi Lampu Titik 8.00 195,000.00 1,560,000.00
Jumlah VIII 3,870,000.00

REKAPITULASI

I. PEK. PEDAHULUAN 18,268,162.00


II. PEKERJAAN PONDASI/SLOOF 112,154,120.00
III. PEKERJAAN KAP/ATAP 59,944,520.00
IV. PEKERJAAN DINDING/PLESTERAN 60,111,800.00
V. PEKERJAAN LANTAI 57,086,250.00
VI. PEKERJAAN PINTU 14,080,000.00
VII. PEKERJAAN CAT 11,592,000.00
VIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL 3,870,000.00

Terbilang: Tiga Ratus Tujuh Puluh Juta Delapan Sub Total 337,106,852.00
Ratus Tujuh Belas Ribu Rupiah PPN 10% 33,710,685.20
Jumlah Total 370,817,537.20
Dibulatkan 370,817,000.00