PROJECT MANAGEMENT

Construction of Pharmaceutical Company

Group Members
Ahmad Ali
Ali Akbar
Hamza Ahmad
Introduction of
Project
Overview of presentation
Critical Steps
related to our Name of project
Steps involved project Location
up to Authority
construction Plan Provision
Project Objectives
Technical Parameters
Cost Analysis Capital Cost Estimates
Recruitment
manpower Demand And Supply
Financial Plan
Project benefits
Implementation
Manpower
Introduction of Pharmaceutical Industry

Pharmaceutical
Pakistan has a
Industry meets
very vibrant and
around 70% of
forward looking
the country's
Pharma Industry
demand

Today Pakistan
has about 400
pharmaceutical
Companies
Site Selection

Minimum
The
Requirement
environment
of Ministry of
should be
Health
clean; there
Should be no
That is four
pollution
canals of area
Site Verification

This is one of our


critical path

The location will


be presented to
MOH for the
approval
This phase takes
almost 2-3
months for
approval
Layout & Approval

We will hire engineers to develop


a layout that would meet the
requirements of Ministry of
Health

Layout approval from This step will take


Ministry of health 5 months
Construction

This step would take almost 2 year of time


Construction should be according to the
approved layout
If there is any diversion from the
approved layout this will lead to inquiry
from MOH
Application for Licenses &
Registration
Inspection from
This step would ministry of
take almost 6 health for
months issuing license

Registration from
MOH takes almost 3
months
Procurement of Raw
material

This would Major Suppliers


depend on of Raw Material
products we are China and
will going to India
manufacture

3 Months
consume
Departments

 PRODUCTION
 QUALITY CONTROL
 ADMINISTRATION
HUMAN RESOURCE

QUALITY CONTROL
 Quality Control Manager 01
 Pharmacist 01
 Assistant 01
 Helper 01
Production Staff

PRODUCTION
 Plant Manager 01
 Pharmacist 01
 Operators 06
 Helpers (permanent staff) 20

3 Months
consume
Marketing Force

Availability in the market

Sales Strategies

Placement of Distributors
6 Months
consume
Financials

Activity Cost
Land Rs.15 million
Construction Rs. 10 million
License fee Rs. 50,000
Machinery Rs. 10 million
Per product Registration Rs. 8,000*40= 320,000
fee(40 products)
Raw material Rs. 10 million
Staffing Rs. 7 million

Total Rs. 52.32 million


Questions
&
Answers
Thanks