B aefgjopu 7+30+9+7+13+18+7+8=99
C aefgjqu 7+30+9+7+13+8+8=82
D aefgjru 7+30+9+7+13+7+8=81
E aefnopu 7+30+9+7+18+7+8=86
F aefnqu 7+30+9+7+8+8=69
G aefnru 7+30+9+7+7+8=68
H aefsu 7+30+9+28+8=82
I bilopu 18+20+12+18+7+8=83
J bilru 18+20+12+7+8=65
K bilqu 18+20+2+8+8=56
L bhkqu 18+21+8+8+8=63
M bhkru 18+21+8+7+8=62
N bhkopu 18+21+8+18+7+8=80
O bfgjopu 18+9+7+13+18+7+8=80
P bfgjqu 18+9+7+13+8+8=63
Q bfgjru 18+9+7+13+7+8=62
R bfnopu 18+9+7+18+7+8=67
S bfnqu 18+9+7+8+8=50
T bfnru 18+9+7+7+8=49
U bfsu 18+9+28+8=63
V cfgjopu 11+9+7+13+18+7+8=73
W cfgjqu 11+9+7+13+8+8=56
X cfgjru 11+9+7+13+7+8=55
Y dfgjopu 22+9+7+13+18+7+8=84
Z dfgjqu 22+9+7+13+8+8=67
A1 dfgjru 22+9+7+13+7+8=66
C1 dfnqu 22+9+7+8+8=54
D1 dfnru 22+9+7+7+8=53
E1 dfsu 22+9+28+8=67
A 0 0 7 7 0
B 0 16 18 34 16
C 0 26 11 37 26
D 0 15 32 37 15
E 7 7 37 37 0
F 37 37 46 46 0
G 46 46 53 53 0
H 18 37 39 58 19
I 18 34 38 54 16
J 53 53 66 66 0
K 39 58 47 66 19
L 38 54 50 66 16
M 37 66 47 76 29
N 46 59 53 66 17
O 66 66 84 84 0
P 84 84 91 91 0
Q 66 83 74 91 17
R 66 84 73 91 18
S 46 63 74 91 17
T 47 76 62 91 29
U 91 91 99 99 0
= aefgjopu
=7+30+9+7+13+18+7+8
=99 days