Status Report Draft - Not an Official Record Website Tracked Projects

B809
Manager: Vinnie Hunt As Of 05/31/2011

Central Energy Plant Repairs and Capacity Expansion


Status In Design Budget: $9,070,000 $6,914,000 Completion Date (est.): 02/28/2012 Expended: $2,932,154 $2,771,221 Encumbered: $660,423 Estimate Given: 03/02/2011 Unobligated: $5,477,423

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget: Scope: Replace aging plant equipment and infrastructure to provide continuity of service to Police Headquarters, Fire Headquarters and the TCC Complex. Benefits: Critical pieces of existing equipment in the Central Plant are from 20 to 40 years old and must be replaced. Status: 06/06/2011 Phase I (condenser water system) is substantially complete. Phase II (boilers and heating system) has been submitted for permits. Phase III (chillers and chilled water system) has completed design review and will be submitted for permits in early June. Next Steps: 05/03/2011 Complete Phase I construction. Complete design and permitting for Phases II and III. Issues: 05/03/2011 Qualified energy efficiency bond funding may present compliance/reporting issues.

Friday, June 10, 2011

Page 1 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


K118
Manager: Chris Leighton As Of 05/31/2011

City Public Parking Garage at Plaza Centro


Status Under Construction Budget: $6,675,000 $6,675,000 Completion Date (est.): 08/31/2011 Expended: $4,441,364 $4,441,364 Encumbered: $1,738,067 Estimate Given: 12/02/2010 Unobligated: $495,569

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget: Scope: Design and construct City owned, Parkwise operated 400 stall public parking garage on city-owned land west of Union Pacific right of way, east of Toole, between Broadway and 4th. Benefits: Mayor and Council adopted resolution 21313 on June 9, 2009 approving and authorizing a development agreement between the City of Tucson and OT Kino, LLC for development of the Plaza Centro project on two currently city owned parcels on either side of Toole between Broadway and 4th/Congress. The agreement requires the City of Tucson to design and construct a public parking garage on the property as a precondition to the developer purchasing the land and starting his mixeduse, high density, pedestrian oriented development. The City garage will be integrated into the overall development, meeting public parking needs in the area, including those of the Plaza Centro development. Status: 12/02/2010 Under Construction, Scheduled to open by 8/31/11 Next Steps: 10/01/2010 Finalize private sector plans and financing. Issues: 10/01/2010 None

Friday, June 10, 2011

Page 2 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


S30N
Manager: Tom Fisher As Of 05/31/2011 Status In Design Budget: $84,674,000 $9,171,800

Downtown Links - Barraza-Aviation


Completion Date (est.): 12/30/2016 Expended: $9,760,726 $1,467,164 $84,664,100 Encumbered: $889,003 Estimate Given: 08/31/2010 Unobligated: $74,024,271

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget:

Scope: The project will be a modest, four-lane roadway north of the Union Pacific railroad tracks that will connect Barraza-Aviation Parkway to 22nd Street and I-10, offering an alternate access to Downtown, plus new underpass with the Union Pacific railroad. Benefits: The project will provide an additional transportation link to the existing arterial system that will allow alternate access and egress to Downtown Tucson. Additionally, the project removes an existing atgrade railroad crossing with the construction of a new underpass and provides safety improvement to three other crossings Status: 06/06/2011 TDOT has secured $9 million in RTA funds for the project which will go out to bid in May. The St. Mary's segment design is 99% complete. The project will go out to bid in late summer pending RTA funding. Phases 3 and 4 design for the rest of the corridor is at 30%. Further design is on hold due to RTA funding shortages. Next Steps: 06/06/2011 The 8th Street Drainage improvement project will go out to bid in June. The St Marys segment will go out to bid in August. Issues: 06/06/2011 Continued coordination of the 8th Street Drainage plans with the Modern Streetcar plans. Need to acquire portion of Corbett block property in order to begin construction after contract is amended. RTA funding deficiencies have caused a stop on further design of the middle segment of the corridor.

Friday, June 10, 2011

Page 3 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


JA03
Manager: Jessie Sanders As Of 01/31/2011 Status Pre-Development Budget: $20,422 $0

Gadsden Development
Completion Date (est.): 04/14/2014 Expended: $20,422 $0 Encumbered: Estimate Given: 11/02/2009 Unobligated:

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget: Scope: Planned development includes 125 room boutique hotel, 400 residential units (of which 17.5% will be offered to households at or below 80% of Area Medium Iincome (AMI) and 17.5% will be offered to households between 80% and 125% of AMI) Additional development include office space, market, restaurant, and other commercial uses. Benefits: This project brings new neighborhood approved development to the westside as a planned extension of Downtown. Status: 06/01/2011 The back-to-back closing on Block 3 (aka Block G) from City to Gadsden to Senior Housing was completed on May 13. Next Steps: 06/01/2011 Site work begins in early June on the 143 Unit Senior Housing Project. Issues: 06/01/2011 Need to amend the Development Agreement (DA) to remove any ambiguities and to determine when credits that are authorized in the DA, are earned.

Friday, June 10, 2011

Page 4 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


J050
Manager: Jessie Sanders As Of 01/31/2011 Status On Hold Budget: $2,117,430 $64,494

Mission San Agustn Garden


Completion Date (est.): Estimate Given:

Expended: $2,052,936 $0

Encumbered: $10,585

Unobligated: $53,909

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget:

$1,000,000

Scope: Design and construction of replica of historic Mission Gardens, with historically accurate sizing of adobe walls, and interior spaces designed to have plantings representing several eras of Tucson agriculture, from ancient to modern. Site infrastructure designed to include irrigation, electrical needs, and currently contains raised bed cedar planters in "modern" portion of the 4 acre area. Benefits: The Mission Garden is a reconstruction of the Spanish Colonial walled garden that was part of the historic San Agustn Mission. Rebuilt on its original site and located today in the heart of downtown Tucson, the Mission Garden will feature heirloom plants and living Timeline Gardens, interpreting 4000 years of Tucson agriculture. Status: 02/01/2011 The City is developing a Development and Management Plan for the Mission Garden prior to drafting a new IGA between the City and the County. Wells Fargo has offered to help with a Business Plan. The Tucson Parks Foundation has expressed an interest in helping support such things as irrigation costs. Next Steps: 02/01/2011 Keep working with the Friends of Tucsons Birthplace, Pima County, Wells Fargo, and the Tucson Parks Foundation to bring the Garden alive. Issues: 02/01/2011 The Garden wall was hit with major graffiti again.

Friday, June 10, 2011

Page 5 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


9640
Manager: Ann Vargas As Of 04/30/2011 Status Operational Budget: $23,238,004 $6,776,151

MLK Building
Completion Date (est.): 11/26/2010 Expended: $21,390,354 $3,891,044 Encumbered: $1,308,573 Estimate Given: 11/10/2010 Unobligated: $539,077

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget: Scope: A new 6-story public housing project consisting of 68 units for the elderly and/or people with disabilities. This is the new Martin Luther King building. Benefits: Replaces public housing in the downtown area and adds to the total housing offered in the immediate area to those created with the conversion of the old MLK building to market rate units which is now known as 1 N 5th. Status: 01/11/2011 Project is complete except for the installation of a back-up generator and a few punch list items monitored by the General Services Department. The building is occupied. The City has received HUD approval for a revised Revitalization Plan, and with that approval all the HOPE VI contract production goals have been met. Next Steps: 12/10/2010 Typical project close-down activities will be worked. Issues: 12/10/2010 None.

Friday, June 10, 2011

Page 6 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


MRC3
Manager: Shellie Ginn As Of 05/31/2011 Status In Design Budget: $196,822,000 $31,546,800

Modern Streetcar
Completion Date (est.): 09/30/2012 Expended: $32,775,036 $16,613,813 Encumbered: $28,579,661 Estimate Given: 12/04/2009 Unobligated: $135,467,303

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget: Scope: A four-mile modern streetcar line that connects the University of Arizona to the 4th Avenue commercial district, downtown and the redevelopment area west of downtown. Benefits: The purpose of the Tucson Modern Streetcar Project is to address the need for improved connectivity between Tucson's major activity centers. The modern streetcar will serve as an urban transit circulator to address the transportation needs of the residents, workers, students, and visitors traveling in the corridor. The City of Tucson and other local decision-makers have been focused on addressing this need, as documented in previous transportation planning and development initiatives. More specifically, the proposed project is based on the need to connect major activity centers, create economic development, support population and employment growth, improve transit service, and mitigate parking constraints. Status: 06/06/2011 Design of the project is nearly 100% complete. The combination of all design segments will be submitted as one 100% submittal in June 2011 for final review. The maintenance facility, systems, and streetcar stop design will follow soon after. Private utility companies have begun utility relocations in advance of the project. Next Steps: 06/06/2011 Final review of design drawings; preparation of design plans for contract packages, and award contracts for special trackwork and traction power substations. Issues: 06/06/2011 No new issues. The previous item regarding the property being acquired by COT for the Downtown Links 8th Street/Tucson Arroyo box culvert is unresolved. The property acquisition has not been finalized yet; this needs to occur prior to the start of streetcar construction, before August 2011. Several downtown projects adjacent to the alignment also must consider streetcar construction during their project planning.

Friday, June 10, 2011

Page 7 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


R978
Manager: Rob Just As Of 04/30/2011

Reid Park Africa Expansion - Elephant Exhibit


Status Under Construction Budget: $9,611,000 $4,260,951 Completion Date (est.): 01/03/2012 Expended: $3,291,892 $2,548,492 $0 Encumbered: $5,850,394 Estimate Given: 06/06/2011 Unobligated: $468,714

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget:

Scope: Design and construct a 7-acre expansion of the Reid Park Zoo. This expansion will include connecting pathways from the current zoo footprint, restrooms, drinking fountains, and a 3-acre elephant exhibit and holding facility. This project is a joint effort between the City of Tucson and the Reid Park Zoological Society. Benefits: Expedition Tanzania will be providing important improvements for the nationwide lephant program. Additionally, it will provide guests with a dynamic educational exhibit to explore and enjoy. The community has been extremely supportive, and should be very proud of this achievement. Status: 06/06/2011 Construction is in progress and on schedule. Next Steps: Issues:

Friday, June 10, 2011

Page 8 of 9

Status Report Draft - Not an Official Record Website Tracked Projects


M611
Manager: Tom Fisher As Of 05/31/2011

Ronstadt Transit Center Improvements


Status In Design Budget: $2,797,458 $2,797,458 Completion Date (est.): 09/30/2011 Expended: $243,439 $101,027 $0 Encumbered: $16,896 Estimate Given: 03/07/2011 Unobligated: $2,537,123

TOTAL PROJECT Fiscal Year

** Project Cost Estimate IF DIFFERENT from Adopted Budget:

Scope: Design and construct safety, security, and comfort improvements as part of a comprehensive CPTED study. CPTED= Crime Prevention Through Environmental Design. Benefits: --rebuild the east median island to accommodate additional bus bays --upgrade lighting and video surveillance systems --upgrade cooling towers for passenger comfort --enclose arcade openings with decorative metal fencing --simplify and enhance directional and regulatory signage --replace broken pavers with concrete walkway Status: 06/06/2011 Design & construction Plans are 100% complete and approved by PDSD for permitting. Next Steps: 06/06/2011 Go out to bid in July. Issues: 06/06/2011 Work with Architecture and Engineering division to prepare bid package. Need to prepare specifications for the security camera upgrades.

Friday, June 10, 2011

Page 9 of 9