ABOUT SINGRAULI

Singrauli is the 50th district of Madhya Pradesh State of Union Republic India. It was granted district status on 24th May 2008, with its headquarter at Waidhan to fullfill the aspirations of people of this place. It has been formed after dividing it from Sidhi district. Singrauli has three tehsils namely 1. Singrauli 2. Deosar 3. Chitarangi. It has three develovment blocks by the same name. Singrauli Town is a municipal corporation with a population of about 2 lakhs. The estimated population is about 11 lakhs. Singrauli is fast emerging as an energy hub of India , especially for electric power and coal and therefore locally it is also called Urjanchal ( a Hindi word which means land of energy ). The total installed capacity of all power plants at Singaruli is around 10% of total installed capacity of India. The area in the eastern part of the state of MP and the adjoining southern part of Sonebhadra Distt. in the state of UP is collectively known as Singrauli. Singrauli is emerging as India's Energy Capital, the place earlier known as Shringavali, named after the sage Shringi, was once upon a time covered with dense and unnavigable forests and inhabited by wild animals. The place was considered so treacherous that it was used by the Kings of Rewa State, who ruled the area till 1947, as an open air prison for detaining errant civilians and officers. Just two generations ago, small holders were tending their parcels of land here, and the original inhabitants were gathering honey and herbs in the forest. In the late fifties, a large scale dam banked up the water of the River Rihand. The dam known as Govind Vallabh Pant Sagar, was inaugurated by Pt. Jawahar Lal Nehru in 1962. Later, rich coal deposits spread over an area of 2200 km in the state of M.P. and U.P. (southern part of Sonebhadra Distt.) were discovered close to the artificial lake that could be used to generate electricity. In this district, Northern Coal Fields (NCL) is spread over a vast area with a production of about 15-20 percent of total coal in the country. There are 11 Open cast mines of the NCL which supplies coal to around 8-9 Power Projects spread in and around Singrauli both in Madhya Pradesh and Uttar Pradesh. Vindhya Nagar NTPC is the single largest Super Thermal Power Project of the country with a power production of 3260MW. NTPC Shaktinagar is adjoining this place with another 2000MW power capability. NTPC Rihand is nearby with another 2000MW capacity. Apart from these power projects there are at least 5 Power Projects of the State Government of UP with a combined capacity of about 4500MW. Singrauli is going to become the "Power capital" of the Country with new power projects being set up in near future. Apart from Power Projects 9 Open cast coal mines are also going to start production within 3 years. Land Acquisition for all these Power Projects are all most over and these power projects will get commissioned by 2011-12. Reliance, ESSAR, Hindalco, Jaypee and DB Power are establishing their power projects here. Hindalco is establishing its" Aluminium Smelter" Plant under the SEZ Act and this unit is going to be a total Export Oriented Unit. The Combined Investment of all these projects is going to be around 1 lakh Crores. Singrauli with its natural resourses and enabling environment by the State Government and District administration has become most suitable destination for investment. The Chief Minister of M.P. Shri Shivraj Singh Chauhan dreams to develop Singrauli on the lines of Singapore

De

tination

ingrauli
The brochure illustrates various projects that are taking shape in Singrauli

"I want to develop Singrauli into another Singapore."


- Shivraj Singh Chauhan
Chief Minister, Madhya Pradesh

District Collectorate, Singrauli

Destination Singrauli
Sasan Ultra Mega Power Project (S.P.L.) ReLI NCe
Company : Reliance (Anil Dhirubhai Ambani Group-ADAG)
1. Reliance Power Ltd. is executing 3960 MW Sasan Ultra Mega Power Project (UMPP) through its 100% wholly owned subsidiary Sasan Power Ltd. (SPL) at village Sasan, District Singrauli, Madhya Pradesh. 2. Sasan UMPP has been allotted 3 captive coal mines namely Moher, Moher-Amlohri extention and Chhattrasal. These are the largest mines in the country in terms of volume handled. Sasan UMPP is the biggest integrated coal mine cum power project in India. 3. Sasan UMPP is a project of national importance and would benefit 35 crore people in 7 states of India. State of Madhya Pradesh is the largest beneficiary with 1,500 MW (37.5% of total capacity) allocated to the state. 4. The project is based on environment friendly Super Critical Technology and has far less impact on environment than conventional coal based plants. The plant also has very high efficiency resulting in lower coal consumption thereby saving precious natural resource coal. 5. SPL has advanced commissioning schedule of Sasan UMPP from the schedule in PPA. 6. Project has achieved Financial Closure. This is the largest debt financing on project finance basis in India. Within an estimated investment of over Rs 19,500 crores, project would play a significant role in economic development and industrialization in Madhya Pradesh. The project would generate several direct and indirect employment opportunities resulting in social and economic upliftment of local community. 7. Environment clearance and final forest clearance for power plant and Moher & Moher Amlohri extention coal mines have been obtained. In compliance to stipulated conditions by MoEF, Environment Monitoring during construction phase is in progress. 8. Engineering works are complete. Internationally reputed consultants such as Black & Veatch, Toshiba, STUP, HOK etc. are working on the project. Main power plant equipment is being supplied by Shanghai Electric Corporation (SEC), one of the largest power plant equipment manufacturers in the world.
Anil Dhirubhai Ambani Group

Destination Singrauli
9. Construction at site is in full swing. Site enabling works have been completed. TG Column erection, permanent store have completed while boiler & bunker erection, Power House Building (PHB), TG Deck shuttering is in progress. BOP civil works are also in advanced stage. 10. SPL is committed towards the social & economic development of project affected & surrounding villages. As a part of its proactive approach towards welfare of local community, SPL started a mobile medical facility including an ambulance van to provide free medical services to the villagers, much before construction work had commenced at site. 11. To relocate affected families, SPL has developed a R&R village Surya Vihar, spread over an area of 368.97 acres, with all basic facilities such as School, Health Care Centre, Market Place, Panchayat Bhavan, Temple, roads, drinking water, sanitation and electrification, etc. The SPL R&R package provides benefits better than NRRP & MP Model R&R Policy and ensures sustainable development. 12. SPL has constructed ready to move-in houses on residential plots of 5400 sq feet. The house has basic amenities such as toilet, kitchen, smokeless chulha, electrification, etc. About 450 families have got their House/Plot allotment done. 13. School in R&R village Surya Vihar, run by DAV organization, is providing free education & stipend to the wards of displaced families. Presently, 765 students are studying in R&R village school. 14. Free medical treatment & medicines is being provided at the health care centre at Surya Vihar, having functional laboratory. More than 5000 patients have benefitted from the hospital. 15. Trainings for skill development such as CIDC training and tailoring for women have been organized. 12 Cooperative Societies have also been formed by the PAPs who are being allotted works by SPL and its agencies. The cumulative value of works allotted till date is more than Rs 3 Crores. 16. Monthly old age pension & destitute pension is being provided which is in addition to the old age pension given by Government. Presently, 200 persons are receiving old age pension from SPL. 17. Weekly Bazaar, is being organized at Surya Vihar in the open built up shops constructed for this purpose by SPL in which villagers from nearby places also participate.

Reliance Airport
Allotment of Govt. land for Reliance Airport ( Phase - I) has been done. Land Acquisition for Airport (Phase -II) is under progress. This airport will be fully owned by Reliance and will be ready for operation in near future.

Destination Singrauli

Moher & Moher Amlohri Extension Coal Block


Company : Reliance (Anil Dhirubhai Ambani Group-ADAG)

ReLI NCe
Anil Dhirubhai Ambani Group

A BRIEF NOTE OF MOHER AND MOHER-AMLOHRI EXTENSTION COAL BLOCK (20 MTPA) INTRODUCTION Moher and Moher-Amlohri Extension coal blocks under the command area of Northern Coalfields Ltd have been allocated to Sasan Power Ltd by Ministry of Coal vide letter no. 13016/4/2006-CA-I dated 13th September 2006. In terms of the letter, the Govt. decided on the basis of competitive bidding about the developer of the Sasan UMPP and accordingly Sasan Power Limited along with the Moher and Moher-Amlohri Extension coal blocks were transferred to Reliance Power Limited on 7th August 2007. The coal produced from the above mines would be exclusively used for power generation by Sasan Power Limited (6X660 MW) as well as another Power Plants belonging to Reliance Power Limited. EXECUTIVE SUMMARY I) Name of the Mine ii) Target Capacity of Mine iii) Life of the Mine iv) Coalfield v) Location vi) Company vii) End use of Coal proposed viii) Grade of Coal ix) Geological Blocks & Reserves : : : : : : : Moher &Moher-Amlohri Extension Opencast Mine 20.00 Mtpa 29 years Singrauli Coalfield Singrauli District, M.P. Sasan Power Limited Proposed Sasan Ultra Mega Power Plant (3960 MW) and other power plants under RPL group : : a) Area : Total area- 15.39 sq.km. (Moher-10.70 sq.km. + Moher-Amlohri -4.69 sq.km.) b) Net Geological reserves : 575.00 MT : 470.43 Stripping Ratio (m3/t) : 4.03 : Coal 13 M m3 + OB 78 M m3 : a. Forest Land : 1198 Ha, b. Government Land : 213.204 Ha, c. Private Land : 776.744 Ha

x) Extractable Coal Reserves xi) Required Excavation Capaity

xii) Total Land Requirement: 2240 Ha

xiii) Manpower Requirement xiv) Major Equipments

: 1021 Persons : 1. Dragline (43-51m3 bucket capacity/ 100 m boom length) 2 nos. 2. Shovel : a) OB (36-38 m3) 5 nos. b) Coal (10 m3) 4 nos.

Destination Singrauli
c) Miscellaneous (2-3 m3) 2 nos. 3. Rear Dumpers: a) OB (240 T) 30 nos. b) Coal (100 T) 4. Drills: a) Dragline Benches (311 mm) 2 nos. b) Shovel Benches (250 mm) 7 nos. c) Coal (160 mm) 4 nos. 5. Dozers: a) 850 HP 5 nos. b) 560 HP 8 nos. c) 450 HP 2 nos. xv) Mining Operation The Mining Plan proposes to start South Pit first by developing a mine entry through the western side box-cut. The volume of OB in the box-cut has been estimated as 12.65 Mm3. The North Pit is proposed to be developed from the year-2 onward from the box-cut area located on the western side for which 22.81 Mm3 will be excavated. Coal production starts from year-2 from the South Pit and the same from North Pit starts from year-3. xvi) Mining Technology ? The most suitable mining technology for the proposed opencast mine will be using a combination of Draglines and shovel-dumper system considering the following geo-mining conditions: ? Gentle gradient of Turra Seam floor, viz. 2-3 in South Pit and 3-5 in North-East Pit ? Mining of multiple seams viz. Turra (12.30-19.30m) and Purewa (19.50-26.15 m) Overburden cover above Purewa Seam (84.70m to 198.47m) and Parting between Turra and Purewa ? Seams is in the range of 51.97m to 68.70m Large scope of work including 20.00 Mt. of ROM coal and 78.21 Mm3 (Peak) per annum of OBR. ? Shovel-dumper system for higher benches and draglines on the parting between Turra and Purewa Seams ? has been proposed in the Mining Plan as this is the most suitable technology under the present geomining condition.

Other Coal Blocks


(under exploration) ? Indraprastha Coal Block : Delhi Harayana Mineral Development Corporation

Andhra Pradesh Mineral Development Corporation Coal Block

Destination Singrauli

Chatrasal Coal Block


Company : Reliance ADA Group
A BRIEF NOTE OF CHHATRASAL COAL BLOCK (5 MTPA)

ReLI NCe
Anil Dhirubhai Ambani Group

INTRODUCTION Chhattrasal coal block has been allocated to Sasan Power Ltd by Ministry of Coal vide letter no. 13016/4/2006-CA-I dated 26 Oct'2006. In terms of the letter, the Govt. decided on the basis of competitive bidding about the developer of the Sasan UMPP and accordingly Sasan Power Limited along with the Chhattrasal coal block was transferred to Reliance Power Limited on 7th August 2007. The coal produced from the above mines would be exclusively used for power generation by Sasan Power Limited (6X660 MW) as well as another Power Plants belonging to Reliance Power Limited. LOCATION: Chhattrasal Block is located in between Amelia Block, on the north and Mahan Block, on the south, in the easternmost part of Main basin, Singrauli Coalfield. It falls in between latitudes 24o 2' 41'' & 24o 4' 26 North and longitudes 82o 22' 34'' & 82o 26' 15 East and is covered by Survey of India toposheet No. 63L/8 on RF 1:50,000 (2cm=1km). Administratively, it is under the jurisdiction of Singrauli (Waidhan) tehsil, District Sidhi of Madhya Pradesh State. MINING STATUS: The block is free from mining activity. Nearby OCPs are located about 20 Km north-west of the block in Moher subbasin. Total 10 coal seams, including splits section of Seam III & V namely Seam I, II, III Bottom, III Top, IV, V Bottom, V Top, VI, VII and VIII in ascending order exist in the block. ? Open Cast proposition are for seams VII and VIII ? Seam VII is the thickest and most potential seam of the block. Life of the Project is 21 Years. Rated Production achieved on 3rd year of production. Minable reserve: 94.80 Million Tones Salient Mining features and post mining Activities : 1. Backfilling starts from 3rd year of mining operations 2. Total 88.82 Mm3 (16%) is proposed to be dumped in external dump and balance 461.66 Mm3 (84%) in internal dump 3. About 5% of the total mine area will be left as mine void. 4. Maximum depth of water in the left out void is less than 40m. This water reservoir will improve the water balance chart of the area and used for irrigation purposes.

Destination Singrauli

Chitrangi Power Project


Company : Reliance (Anil Dhirubhai Ambani Group-ADAG)
Reliance Power is executing the Chitrangi Project on a fast track mode. The following progress has been made towards project Implementation. 1. Engineering/Other Studies : ! The Detailed Project Report (DPR) for the 6 660 MW Thermal Power Project has been finalized. All the major engineering/other studies have been completed. Sl. No. 1. 2. 3. 4. 5. 6. Study Topography Survey Preliminary Geotechnical Investigation Water Intake Study Preliminary Transportation Study Area Drainage Study Socio Economic Study Status Completed Completed Completed Completed Completed Completed

ReLI NCe
Anil Dhirubhai Ambani Group

Nishulk Medical Camp organized at Khokhwa Village on 27/12/2009

2. Memorandum of understanding (MoU)/ State Support Agreement (SSA) : ! A Memorandum of Understanding (MoU) was signed with the Government of Madhya Pradesh (GoMP) on 20TH Sept 2007 to set up the 3960 MW thermal Power Plant. ! A State Support Agreement (SSA) was also signed with GoMP on 26TH October 2007 to facilitate project implementation. ! Section 41 Agreement and detailed R & R Agreement (Over and above Model R & R Policy 2002) was signed on 10/08/2010. 3. Land : ! Possession of 1353 Ares of Government Land obtained. Advance Possession of 1159. Acres of Government land received from GoMP Dated 11/10/2010 ! Acquisition of 341.76 Acres of Pvt Land is in progress ! Section 9(1) Public Hearing for Khokhwa Village held on 25/11/2010. Gazette Notification of Section 6 of Villages Jhamtihewa, Badgad and Bagaiya done on 29/10/2010.

Inauguration of Ambulance Service 24/07/10 Daily Medical Camps/Ambulance service at Villages Khokhwa, Jhamtihewa, Badgad, Bagaiya & Kapurdehi.

Area Grading and Leveling for BTG Area in Khokhwa Village started in Dec 2010.

Destination Singrauli
4. Resettlement and Rehabilitation : ! Plotting of R & R Site started. Construction of Approach Road to R & R Village in Progress ! Public Information Centre (PIC) activated in Khokhwa for Dissemination of Information/Guidance to PAP's/PAF's regarding R & R Benefits 5. CSR : ! CIDC Training: Mason Training for villagers already in Progress at Khokhwa, Jhamtihewa & Kapurdehi. ! Site Office(in Porta Cabins) Functional at Khokhwa Village ! Construction of Helipad Completed at Khokhwa Site. 7. Environmental Clearance : ! Environmental Clearance obtained on 28/05/2010 for 3960 MW Power Generation Project ! Consent to Establish obtained from MPPCB on 30/09/2010 8. Water : ! In Principle Approval obtained from GoMP for allocation of 0.14 MAF of water in Jan 09 ! Water Allocation for the project from Gopad River has been approved by the district water Committee and the recommendation forwarded to the state level committee.

Boundary wall work started in Nov 2010 in progress at Khokhwa Village

Construction of Cement Store/ Weigh Bridge in Progress at Site

9. Fuel Linkage : ! Permission granted by Ministry of Coal (MoC) on 13 May 2009 for use of coal from Moher, Moher Amlohri and Chatrasal Coal Blocks. 10. EPC Contractor : ! EPC Contractor has been selected. ! International Competitive Bidding (ICB) was conducted for selection of EPC Contractor. 11. Construction Power : ! Application has been filed for Construction Power to MPPKVVCL for Supply of 5 MVA on 33KV 12. Power Evacuation and Long Term Open Access : ! Application has been filed with Power Grid Corporation of India Ltd for power Evacuation and long term open access. 13. Sale of Power : ! Letter of Intent (LoI) obtained from Madhya Pradesh Power Trading Company Limited (MPPTCL) for 1241 MW power from the project in May 08. 14. Financing : The Information Memorandum for Financing Launched in Sept 2009 ! Rs 5000 Crore of Loan Syndication already tied up. 15. Organizational Setup : ! A Dedicated Team of 50 Professionals is at present posted at Site ! A team of more than 150 Professionals at Corporate Office Mumbai is working for the project. The Plot Plan has been finalized

Destination Singrauli
POWER

Mahan Super Thermal Power Project


Company : Essar Group
ESSAR GROUP The Essar Group is a multinational conglomerate and a leading player in the sectors of Steel, Energy, Power, Communications, Shipping Ports & Logistics, Construction, and Mining & Minerals. With operations in more than 20 countries across five continents, the Group employees 60,000 people, with revenues of about USD 15 billion in FY08-09. ESSAR POWER LTD Essar Power currently operates five power plants with a combined capacity of 1,200 MW in three locations across India which is being expanded to 6000MW.This includes two gas-based plants and one liquid fuel based plant in Hazira, a cogeneration plant in Vadinar and a coal-based plant in Visakhapatnam. Essar Power has an immaculate track record of safety, and has won several safety awards. The 515 MW Hazira plant is among the few power plants in India to receive the ISRS (International Safety Rating System) safety rating, which has also helped the company win the very elite Sword of Honour, the British Safety Council's highest award. Essar Power is committed to reducing emissions from its plants and earning carbon credits. The 500 MW combined cycle power plant at Hazira is eligible for Certified Emission Reductions (CERs) under the Kyoto Protocol's Clean Development Mechanism (CDM). Essar Power is today driven by a team of highly skilled technical experts who area amongst the best in the country. Essar has built a competent and experienced team to construct, manage and operate its state-of-the-art power plants. ESSAR POWER M.P. LTD As part of ambitious plans of expanding its Power Business, Company is setting up a 2000 MW coal based Thermal Power Plant at villages Karsualal, Bandhora, Khairahi & Nagwa Tehsil & District Singrauli M.P. MoU for 2000 MW has been signed between EPMPL & Govt. of M.P. on 17.01.2007. In the Ist phase ,ESSAR POWER M.P. LTD. (EPMPL) a part of ESSAR POWER is setting up Rs 4860 Crore ,1200 MW ( 2x 600 MW) pithead Coal based Thermal Power Plant at 4 Villages namely Karsualal, Bandhora, Khairahi & Nagwa in Singrauli Tehsil of Singrauli Distt. in Madhya Pradesh. Coal Linkage- Mahan Coal Block located at 4 Km distance from site allotted to Joint venture Company Mahan Coal Ltd formed between EPMPL & Hindalco. All statutory permits & clearances have been received for the project, construction activities are progressing according to schedule Target for completion is 2011.

10

Destination Singrauli
Essar has already placed orders for all the long lead items for all its projects with reputed vendors and the supply of plant and equipments has also begun. Evacuation of power will be through dedicated transmission facilities under implementation through Essar Power Transmission Limited for which the open access approval has been received.

LAND DETAILS & STATUS Total Land in the project area Private land Government land Govt. Forest land Pvt Revenue Forest (included in Pvt land) 705.14 Ha. 503.37 Ha 185.81 Ha 15.96 Ha 39.44 Acre 1742.40 Acre 1243.83 Acre 459.13 Acre 19.02 Ha 46.99 Acre

LAND STATUS Final Awards (LA) for all 4 villages namely Nagwa, Bandhoura, Khairahi and Karsualal Village are issued. Forest Clearance is available. Govt. Land Total land available with the company. CONFIGURATION OF POWER PLANT

Sr. No 1 2 3 4 5 6

Detail Project capacity (MW) Size of Steam Turbine (MW) Number of steam turbines Number of Boilers Boiler technology Condenser cooling

Features 1200 MW 600 2 2 Sub critical Circulating water cooled with IDCT

PLANT PROGRESS Financial Closure achieved in June, 2009. Basic Engineering 100% completed Detailed Engineering >90% completed. Balance is in progress. PROCUREMENT PROGRESS All equipments and materials ordered. Major consignments started arriving at site. Approx. 73000 MT of Materials received at site. CONSTRUCTION PROGRESS Entire project area levelled and graded. Boundary wall complted.

11

Destination Singrauli
Sufficient Concreting facility commissioned at site. Administration building completed. Open and Closed storage yards completed. Construction at al fronts is going on all full swing. Unit # 1 Boiler drum lifted on 20.06.10 .Generator placed on foundation. Unit # 2 Boiler drum lifting on 10.06.11. Other Construction activities going on at fast pace at all the fronts. As can be seen from annexed photographs.

SALIENTFEATURESANDACHIEVEMENTSOFR&RPOLICYAGREEDWITHSTATEGOVT. For the first time in the history of country, Essar has gone for providing Sustenance/ Livelihood Allowance (Monthly Bhatta) to each male member in the age group 18-50 yrs @ [Min Industrial wages + Rs 10] calculated for 30 days up to age of 58 years .Present rate is Rs 5190/- per month. Free education to children of PAP's up to Class -10. Development of Medical centre with well qualified Doctor & provision of Ambulance Services. Difference between Land rate payable as per Land Acquisition Act -1894 & Guidelines for land Rate for the Year - 2008-09 to all land losers. PAP's are being provided plots of size 90 X 60 ft= 5400 sq ft (502 sq. mtr) Priority to be given the PAP's in jobs based on their skills & qualification. Provision of reservation for PAP's in Allotment of shops in R&R colony. All PAP's at R & R colony are being provided Transit accommodation for the period of construction of their houses. Most of their construction materials are being transported by EPMPL from their existing house to their respective plots. Construction of infrastructure facilities in R & R colony - Roads, Sanitation, Sewage system, High School, Community centre / Panchayat hall, Cooperative Stores / Market, Religious Place, Health Centre, Grazing ground, Cattle sheds, Cremation & Burial ground. ACHIEVEMENTS UNDER R & R Summary of Sustenance and pension allowance under R & R Benefits has been described below-

DETAILS OF R & R BENEFITS GIVEN


PAPs Allowance Pension Widow Pension Total House Grant (Const) Transportation Grant Bandhora 213 19 4 236 260 255 Khairahi 92 5 1 98 48 30 Nagwa 138 15 0 153 152 135 Total 443 39 5 487 460 420

12

Destination Singrauli
722 children from PAFs communities are getting education in Essar aided Saraswati Shishu Mandir School at Nand Vihar Colony, Nagwa, and the school has been commenced since July 2010. 603 plots have been allotted to displaced PAFs. Under priority of project affected perosns' engagement through petty contractor, 476 persons are working in different construction activities of the plant. Roads-15 km of roads developed. Water - 60 no. of hand pumps install and 10 nos. are in progress. Sanitation - 15 km of drain developed. School - School building's construction is completed & started functioning from Ist July 2010 with strength of approx 700 students. Community centre / Panchayat hall - under construction. Cooperative stores / Market - under construction. Religious Place - under construction Health center- made available in Visthapit Colony and construction of hospital is in progress. Grazing ground -made available Cattle sheds - constructed. Cremation & Burial ground - under construction Separate community Bath Rooms & Toilets have been provided for Ladies & Gents. Entertainment Room provided with Colour TV & Dish TV connection. Cultural programs are being organised in Visthapit Colony. Electrification of Rehabilitation Nand Vihar Colony is almost completed.

CSR Initiatives by EPMPL Free education to children of PAP's up to Class -10. One building for junior section has completed & started functioning from Ist July 2010 with strength of approx 300 students. Now 722 students have admitted in junior classes and school operates in two shifts with additional teachers and school staff. Under Free Computer Training to Project affected youth, 240 students have benefitted so far. Free Medical facility by Site clinic and Ambulance facility for PAP's Under skill improvement of project affected communities 105 youths have got free ITI training. School Stationary , Bag & Water Bottle distribution (2500 nos.) to all school going children in the project areas Blanket distribution to every PAP on vacation of his residential accommodation. 2 schools' buildings have constructed in lieu of previous school buildings had acquired due to project area & simultaneously 1 Aganwadi is being constructed due to affected by project. All three buildings are situated in village Bandhoura. 6 plots had allotted to Ganiyari blast victims on the request of District Administration. As on date 13 cooperative societies of PAP's (324 nos.) have been registered & allotted work without tendering amounting to Rs. 90 lacs. 3 special camps have been organized for Khairahi & Nagwa village for taking care of Heat stroke patients.

13

Destination Singrauli

Mahan Coal Limited


Company : Joint venture of Essar & Hindalco
MAHAN COAL LIMITED

MAHAN COAL BLOCK Mahan Coal Limited (MCL), a joint venture company between Hindalco Industries Limited (HIL) and Essar Power M.P Limited (EPMPL), has been granted a captive coal block (Mahan Coal Block) in Singaruli District of Madhya Pradesh, which will mine coal for the two ventured companies. The total coal reserves are about 144 Million Tonnes with the grade of coal as E to F. The Mahan Coal Block is to produce 8.5 Million Tonnes of coal per annum by open cast mining system Location of Mahan Coal Block Mahan coal block is located on the plateau on the eastern fringe of the Main Basin in Singrauli Coalfield, Sidhi District, Madhya Pradesh. Almost entire ML area (1182.35 ha) falls under Mohanban Reserve Forest. Part of revenue land (17.65 ha) of Amelia and Budher villages of Waidhan block, Singrauli district falls under the Lease area. The block geographically extends from Longitude 82o 22' 30 to 82o 24' 49 E and Latitude 24o 00' 28" to 24o 02' 32" N and the entire lease area falls in Survey of India topo sheet-63-L/8. The block is about 35km from WAIDHAN , which is the district head quarter and is approachable from Rajmilan village and Parsona crossing. It is also approachable from Singrauli township and NCL (HQ) via Waidhan and Rajmilan by about 60km long fair weather road. A fair weather approach road from Rajmilan village passes through the northern part of the block and leads to Gajrabahra railway station, which is about 6-km from the western limits of the block. Nearest major town is Waidhan located about 35-km eastwards.
(JV of M/s. ESSAR Power Ltd. & M/s Hindalco Industries Ltd.)

Need of the Project The activities in both these Power Plants are in very advanced stage and the plants are scheduled to be commissioned in middle of the year 2010. The coal project is to be worked by State of Art Opencast Mining Technology to keep the mining costs to absolute minimum. The ultimate capacity of the mine is 8.5 Million Tonnes per annum, which is required to be achieved by October 2011. The corresponding Overburden (OB) removal shall be around 50 Million Cubic Meters per annum, which has to be achieved from the second year of operation. The Mahan Coal Mining Project is proposed to cater to requirement of the twoThermalPower Plants of M/s Essar Power Ltd. and M/S Hindalco Industries Ltd for almost 15 years. Hindalco Industries Limited is proposing to set-up a greenfield integrated aluminum complex under the name of Mahan Aluminium with a production capacity 3,25,000 TPA (primary aluminium metal) near Bargawan, Deosar tehsil in Sidhi district, Madhya Pradesh. To cater to the demand of electricity on continuous basis, a 650-MW coal based captive power plant is also proposed in the complex. The coal requirement for the project is about 3.5-MTPA. ESSAR group is proposing to set-up 1200-MW thermal power plant, agreenfield project, under the name of Essar Power (MP) Limited near Karsua village, Waidhan block, Singrauli district, Madhya Pradesh. The coal requirement for the project is about 5.0-MTPA.

14

Destination Singrauli
SMELTER AREA PHOTOS

MAHAN ALUMINIUM PROJECT Hindalco Greenfield Venture in M.P.


Company : Hindalco (Aditya Birla Group)
PROJECT SNAPSHOT : MOU signed with Government of Madhya Pradesh on 23rd May 2006
Facility Smelter Captive Power Plant Capacity (Phase-I) 3.25 LTPA 750 MW (6150 MW 5W+1S) Start Date 1st Metal by July 2011 1st Unit by May 2011

Location : Near Bargawan on NH-75E Raw Materials : Alumina : To be sourced from captive sources in Orissa / Uttar Pradesh Coal : 3.5 Mln Ton from Mahan Coal block & 0.5 Mln Ton from others Water : 4,500 cu m / hr from Gopad river Investment : Rs. 9,200 Cr Technology and Engineering : ! Smelter process technology licensor & basic engineering: Aluminum Pechiney, France. ! Detailed engineering Engineers India Limited PROGRESS : Statutory Clearances : ! All major clearances including environment related have been obtained. ! Approval for SEZ by Ministry of Commerce, Govt. of India. Project spending : Ordered Rs. 8200 Cr. / Spent Rs. 3200 Cr. Man Power and Vendors working at site : ! Around 10000 people working at site. ! Major Indian & international contractors like L&T, Rohan, BHEL, Solios MBE, Simplex, Alstom, Areva, Thermax are operational at site. Construction progress : ! Smelter : Pot line, Green Anode Plant, Gas Treatment Centre, Cast house are under progress . ! CPP : Unit 1, 2,3,4, Coal Handling Plant, Water treatment plant are under progress.

15

Destination Singrauli
CPP (Captive Power Plant) AREA PHOTOS :

R&R COLONY :
Total no. of houses planned: 1200 / 'ready for occupation'- 720 / Under construction - 200 / No. of PAFs residing at R&R: 300. Rain water harvesting : three check dams constructed at R&R colony Primary Health Centre, School & Anganawadi: Construction nearing completion. 11 KV HT power transmission line (17 KM) : Construction nearing completion. Other infrastructure planned : Community Hall, Shops & market place, temple etc.

16

Destination Singrauli

CSR INITIATIVES :
Key focus areas : Healthcare, education, skill development, capacity building & livelihood. Health care : General & mobile Health Camps ongoing at all four project affected villages as well as R&R colony. Sponsored Family Planning Camps organized jointly with Dist. Admin.

Hygiene & sanitation : Sanitation improvement in village schools Distribution of utensils to children for mid day meals

Skill enhancement training programs : Pump repairing workshop Diesel engine mechanic workshop Tailoring training workshops conducted regularly at R&R Colony 6 month long vocational training of PAPs at ITI have commenced in Oct'10. Formation of 30 Self Help Groups (SHG) exclusively for women & 12 Co-operative Societies & allocation of contract works - First Milk Co-operative formed in Singrauli District.

17

Destination Singrauli

heeJejefe[

Vindhyachal Pooling Sub-Station


Comapny : Power Grid Corporation of India Limited

765/400 KV Vindhyachal Pooling Sub-Station


POWERGRID, the Central Transmission Utility (CTU) of the country and a Navratna Company operating under Ministry of Power, is engaged in power transmission business with the mandate for planning, co-ordination, supervision and control over complete InterState transmission system and operation of National and Regional Power Grids. At present POWERGRID owns & operates a huge transmission network comprising 79556 Ckt Km transmission lines, 132 No Sub-Stations, 89170 MVA transformation capacity and 22400 MW Inter-State transmission capacity. POWERGRID, Vindhyachal office is looking after Operation & Maintenance of existing transmission lines of Vindhyachal Super Thermal Power Station viz 2 Nos 400 KV S/C Vindhyachal Korba Ckt-1 & Ckt-2 lines, 2 No D/C Vindhyachal - Jabalpur Ckt 1&2 and Ckt 3&4 lines, 2 Nos D/C Vindhyachal - Satna Ckt 1&2 and Ckt 3&4 transmission lines. Apart from this, we are also constructing the transmission lines for evacuation of power from Sasan UMPP (2 No 765 KV S/C Sasan - Satna Transmission lines) and Vindhyachal Stage-IV (400 KV D/C (Quad) Vindhyachal - Vindhyachal Pooling line). In future 2 No 765 KV S/C transmission lines shall be constructed from Vindhyachal Pooling to Satna Sub-Station. POWERGRID has to establish a 765/400 KV Pooling Sub-Station near Vindhyachal Generation Project for pooling of Power from Vindhyachal Stage-IV (1000 MW), Rihand Stage-III (1000 MW) as well as Aryan Coal Benefication Pvt Ltd (1200 MW) Generation Projects. For construction of Vindhyachal Pooling Sub-Station, land has been identified in Village Khamhariya and Parasdehi, Tehsil & District Singrauli (MP) and a proposal submitted for acquisition of 57.56 Hac Land comprising 25.50 Hac Private Land and 32.06 Hac MP Govt Land which also includes 10.76 Hac Revenue Forest . Regarding 25.50 Hac Private Land In-Principal approval has been obtained from Govt of MP, an amount of Rs 23678202.00 has been deposited to Land Acquisition Officer and Land has been notified under Section 4 (already published in MP Gazete dated 17.12.2010 and two local New papers Dainik Jagaran & Vindhya Jyoti dated 18.10.10. Regarding 18.05 Hac MP Govt Land, proposal for advance possession submitted to Principal Secretary (Rev), Bhopal on 04.12.2010 and for 10.76 Hac Revenue Forest, proposal has been submitted to DFO, Singrauli.

18

Destination Singrauli

AMELIA (NORTH) COAL BLOCK


Company : Jaypee Group
The Ministry of Coal, Govt. of India had allotted Amelia (North) Coal Block (located at Majhauli village, Distt. Singrauli, MP) to M.P. State Mining Corporation Ltd. and Jaiprakash Associates Ltd. had been selected as a Joint Venture partner (the new company formed being Madhya Pradesh Jaypee Minerals Ltd. on 27th January 2006) to develop and mine coal from the coal block which will be utilized for the 1320 MW (2660 MW) thermal power plant being set up by Jaiprakash Power Ventures Ltd. (a subsidiary of Jaiprakash Associates Ltd.) at Nigri village, Distt. Singrauli, MP. Amelia (North) Coal Block is located in Village Majhauli, Tehsil Deosar, Distt. Singrauli, (M.P.). Amelia (North) Coal Mine Project shall undertake coal mining activity at an annual capacity of 2.8 MTPA over a total lease area of 482 Ha. The entire lease area falls within forest land which forms part of Mohanban Reserve Forest.

Salient features of the coal mining project :


1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Mineable coal reserve (open cast) Production capacity (open cast) Stripping ratio Grade of coal Active mining area Expected mine life (open cast) Mining Plan Environmental clearance Forest Clearance Private land acquired through Land Acquisition 11. Govt. Land acquired through allocation 70 Million Tonnes. 2.8 MTPA. 1:8.4 mainly D & E type 482 Ha 27 years approved in Nov. 2006 approved in July 2007 under process

80.15 Ha 36.77 Ha

A railway siding is approved near the mining block where coal will be loaded into wagons. Coal shall be transported through Coal Handling plant (CHP)-2.8 Kms. Length from mine site on (ground level) up to loading point.

19

Destination Singrauli
Socio-Economic Activities :
Against land acquired though Land Acquisition Act approximately 300 persons (land oustees) have been employed. 30 persons from above have been given training for 1 month at our Jaypee Cement Factory Training Centre, Rewa for running and maintenance of excavators, dumpers, drilling machines as well as production of cement bricks. Dispensary was commissioned in February 2007 and providing free medical consultancy through certified Doctor as well as free medicine. So far over 90,000 patients have received treatment. As per R&R policy Pension has been distributed to elderly land oustees from October 2010. 3 handpumps have already been commissioned in Majhauli village and further 3 more shall be commissioned in January 2011. 1 water tanker is deployed for providing drinking water to nearby Govt. School and villagers. Permission for maintenance of PMGSY road from Behtadand to Ujjani (Approx . 8Km) has been received and contracts have been awarded to parties for strengthening the same. As per R&R policy, land is being identified for land oustees (approx. 60 persons). Drawing for construction of school has been finalised and construction for same shall commence in 2011. As per R&R policy, an amount of Rs. 5 Lacs has been contributed to Collector, Singrauli towards exemption of Stamp Duty and Land Registry Fees for those land oustees purchasing land elsewhere for their livelihood.

Dongri Tal II Phase I At a glance


Similar to the joint venture agreement between M/s Jaiprakash Associates Ltd. and M/s Madhya Pradesh State Mining Corporation for Amelia (North) Coal Block, a joint venture agreement was signed for Dongri Tal II Coal Block on 24th December 2008. Dongri Tal II Phase I is an opencast coal mining project consisting of 1392 Ha. Land with a production capacity of 2.8 MTPA which shall be consumed at Nigrie Thermal Power Plant having the installed capacity of 1320 MW. The geology of Dongri Tal II Phase I is Singrauli Main Basin with level topography. The mining lease lies in four villages viz. Dongri, Digwaha, Bhainsabuda and Bajaudi, Tehsil Singrauli, District Singrauli, M.P., with 1392 Ha. revenue land (Govt. land 968 Ha. and Private land 424 Ha). SPECIFIC FEATURES : 1. Mineable coal reserve 2. Coal seams 3. Production 4. Maximum depth of pit 5. Grade of coal 38 Million Tonnes. VII & VIII. 2.8 MTPA. 129 (Meters). B to E (Major grade C)

The mining methods that shall be adopted are drilling, blasting, loading & haulage/ transport. Mine shall be opened up from in crop, coal lying at a depth of 14 meters. The coal will be transported from mining site to Nigrie Thermal Power Plant by rail.

20

Destination Singrauli

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT, NIGRIE


Company : Jaypee Group
1. Rehabilitation & Resettlement. i. Total residential houses in the project 72 ii. Total project affected families under Rehabilitation & Resettlement 180 iii. Total permanent jobs given under land acquisition as well as under R &R 409 iv. Total temporary Majdoori jobs given under R&R 596 v. Total person over and above 60 years of age being given pension under R&R scheme since November,2009 19 vi. Total amount disbursed under R&R @ Rs.75,000/per person for construction of new house Rs. 87,75,000.00 vii. Total amount disbursed under R&R @ Rs.20,000/per person to families who did not take plots - Rs. 18,00000.00 viii. Total amount disbursed under R&R as Rehabilitation & Resettlement grant @ Rs.15,000/- per person Rs. 10,20,000.00 ix. Total amount disbursed under R&R @ Rs.1,000/- per person as transportation charges Rs. 68,000.00 x. Total nos of plots given to families under R&R for construction of new house - 28 xi. Total School going children of families coming under R&R who are being provided stipend under R&R scheme from July, 2010 66 so far xii. The company will be providing a school from July, 2011 for imparting a decent/good education to the children of families coming under R&R. 2. Health i. The company is already operating a 12 bedded hospital with all necessary/adequate equipment since 2008 for giving proper health care to villagers in the vicinity of the Project. Treatment as well as medicines are provided free of cost to the villagers. On an average, about 150 persons get treatment on a daily basis. ii. The company has also provided a medical van facility which goes to about 14 nearby villages and provides free treatment to the villagers. iii. The company also provides free ambulance services in emergency to all villagers in the vicinity of the project. 3. Social responsibility. i. The company has also provided about 10 Hand Pumps in Nigrie as well as nearby villages for benefit of local population. ii. In addition, as per requirement, the company also provides drinking water through tankers during marriage functions/in emergency in Nigrie/nearby villages. iii. The company also provides necessary financial help for common religious function /other community work which are organized by local population.

21

Destination Singrauli
Jai Prakash Power Ventures Ltd.
Jaypee Nigrie Super Thermal Power Project, Nigrie, Singrauli, M.P Brief Project Status-Descriptive on 30.11.2010 .
S. No. Description of work/activities with quantity Name of Test 1. A. MAIN PLANT : Soil Testing Bore holes (BH) Electrical Resistivity test (ERT) Plate Load Test (PLT) Cross Hole Shear Wave test (CHST) Seismic Refraction Test (SRT) Cone Penetration Test (CPT) Menard Pressure Meter Test (MP) Permeability Test (PM) California Bearing Ratio Test (CBR) Testing Completion Schedule Dec. 2010 ! ! ! ! ! ! ! ! v. vi. Mill Area Unit-II ESP Unit-I ! ! ! ! ! ! Status as on date Total 37+4 10 11 5 2 22 4 4 7 Completed Balance 41 10 11 3 22 0 2 2 4 4 7

B. MAIN PLANT CIVIL WORK i. Boiler Unit-I ii. iii. iv. Mill Unit-II TG Hall Boiler Unit-II

vii. Chimney

Founding level is 334 mts. 33 nos. foundations completed. Back filling done and handed over to M/s. L&T. Mill area PCC work 1378 cum is completed. Mill area raft concreting completed. Total quantity 4923 m. 3 ABC rows excavation upto 335 m in progress. Quantity acheived 27000 m Batching Plant of M/s/ JMC erection completed and commissioned. The founding level of Boiler Unit-II is given by Engineering as 330M/ 328M as per site condition. Excavation upto 328M level is in progress 95% completed PCC/Plu concrete work in progress 11574 cum out of 14000 cum achieved. 70% excavation completed. Preparation of PCC at one location is in progress. Excavation upto 331 is completed in pass A PCC is planned from 01.12.2010 Excavation in pass E completed upto 324 m level. 3 Excavation completed. Quantity acheived is 20000 M Batching plant of M/s GDCL erection completed and commissioned. PCC in 3 progress 59 M completed. Total Area planned for Excavation Area Excavated till date Balance are to be Excavated

C. AREA GRADING i. Earthwork in cutting ii. Earthwork in filling D. CONSTRUCTION OF ROADS IN PROJECT AREA Total 24.88 Km i. 21 M wide 3905 RM ii. 10 M wide 5668 RM iii. 4.5 M wide 15312 RM

49.89 Lac Cum

21.03 Lac Cum

28.86 Lac Cum

! 65% earth work completed and WBM activity is in progress. ! 40% earth work completed. ! 4.5% earth work completed.

22

Destination Singrauli
S. No. Description of work/activities with quantity Total Length E. MAIN PLANT BOUNDARY WALL 9563.19 RM7000 RM Y Piece fixing Barbed wire3800 RM Fixing Concertina fixing F. WEIR / BARRAGE G. RAILWAY SIDING 2563.19 RM 4000 RM 5763.19 RM 3500 RM 5563.19 RM 6063.19 RM Status as on date Completed Balance

! Blasting work 8000 CuM completed and 5000 CuM rocks removed. ! Design of Weir is under revision Rock excavation work is under Hold ! Engineering scale plan for Railway siding of JNSTPP (2660 MW) has been approved by Railway vide DRM (W)s office, Jabalpur letter No. JBP/W/100/DB1/Genl/Pt.XVII(S-36) dated 15.03.2010 to RITES, Nagpur and the same was confirmed by RITES, Nagpur vide there Letter No. RITES/PO/NGP/JPVL/G62/Vol. I/No. 000905 dated 01.04.2010 to JPVL. ! To suit the availability of plant land MGR bulb has been modified by RITES by increasing the degree of curvature from 6 deg to 8 deg. the revised drawing of MGR bulb received from RITES on 09.04.2010 and same has been forwarded to DCPL to revise the plant layout. ! Completed and ready for charging ! 37 KM Completed. ! 6.2 km of 33 KV line in forest area all 89 poles erected and line stringing and tree cutting work is completed Expected date of commissioning is 14.12.2010

2.

CONSTRUCTION POWER i. 33/11 KV substation 25 MVA ii. 33 KV overhead Double Circuit Line 43 KM

iii. iv. v.

11 KV overhead lines (a) Phase 1 6 KM 11 KV/415 Volt transformer substation (a) Phase 1 8 Nos DG Sets

! 134/155 poles erected and 4.6 km of line completed out of 6 km. ! 5 No. 11 KV/415V transformer substation erected and ready for charging. ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! 2250 KVA DG Sets are functioning in Base Camp 2250 KVA DG Sets are functioning in APP & Batching Plant Area. 1160 KVA + 150 KVA DG Sets are functioning in main Plant Area. 21000 KVA DG Sets are building under construction. Expected date. 6 Nos lighting masks are installed in main plant area. 1 Nos lighting mask is installed in steel yard. 1 Nos lighting mask is installed in batching plant area. 4 Nos lighting mask are installed in base camp area. Preliminary survey completed. Detailed survey is completed. Tree counting in private area is completed Letter given to forest department for survey. Permission for survey in forest area of Sidhi District & Satna District is obtained. Sidhi District 7.2 KM out of 8.5 KM Tree counting completed Satna District 0.8 KM out of 0.8 KM Tree counting completed Rewa District 0.0 KM out of 2.0 KM

vi.

Area Illumination

3.

400 KV DOUBLE CIRCUIT TRANSMISSION LINE

23

Destination Singrauli
S. No. Description of work/activities with quantity Total Length Status as on date Completed Balance

4.

TOWNSHIP A. Boundary Wall B. Cement Grinding unit Boundary Wall C. Sardar Patel Uchttar Madhyamic Vidyalaya (SPUMV) This school to catter for children of families under R&R also Phase - 1

3288.50 RM 38.93.50 RM

32.82.50 RM 1491.50 RM

6 RM 2402.50 RM

! Contract awarded. The contractor has mobilized to site and started the work.

! Casting of plinth beam completed 81 No. of columns out of 81 Nos. are casted upto lintel level. Earth filling upto plinth level Block masonry work upto lintel level is in progress. ! Slab casting for 7 rooms in ground floor completed. ! Columns for 4 rooms in first floor completed. ! Block Masonry work in progress. ! Excavation, PCC, column footing and column upto lintel level 77 nos completed out of 94 Nos. ! Dhoka masonry work upto plinth beam bottom completed and plinth beam casting completed. Columns upto 2.5 M (lintel level) work in progress. ! Slab for 4 rooms in ground floor completed. ! RCC done for 4 rooms columns upto 1st floor completed ! Block Masonry work in progress. ! Column casting completed upto Roof Truss level. Concrete block masonry & paltering work completed. ! ! ! ! ! ! Excavation completed. PCC for all 128 footing completed. 128 footing are casted. 120 columns are completed upto plinth level Plinth Beam work in progress. Columns 40 Nos. completed upto lintel level 138.

Phase - 2

D. Guashala E. Power Lodge

F. Police Station G. 48 Nos. H-Type Houses

! Work upto lintel level completed. ! Shuttering work in progress for roof slab. ! Work started

24

Destination Singrauli

NTPC Vindhyanagar Stage - 4 Ash Dyke


Company : National Thermal Power Corporation (NTPC)
'VINDHYACHAL SUPER THERMAL POWER STATION'
The largest thermal power station of the NTPC and Nation is the serving the country with the installed capacity of 3260 MW. It has 6 units of 210MW each commissioned between 1987 to 1992 as stage-1 with Russian collaboration. In stage2 1000 MW (2x500MW) was added in 1999-2000. In 2006-07 2 more units of 500MW each was commissioned in stage-3 thus making the largest thermal power station of the country.This glorious power station is situated in the Singrauli District with daily coal consumption of 55000 MW. The coal linkage for this station is from the Nigahi Coal Mines of NCL. From there, the coal is transported by Merry Go Round (MGR) transportation system (22 Kms length with double track) owned and operated by NTPC. NTPC Vindhyachal has always shown an encouraging trend and the station has recorded more than 92% Plant load factor from last 4 years. During 2008-09 Vindhyachal has made a new record of 93.15% PLF. NTPC VINDHYACHAL was awarded IPMA AWARD FOR EXCELLENCE IN PROJECT EXECUTION OF STAGE-III in the year 2008. VSTPS has been awarded prestigious IEEMA award for Fast track project execution in Year 2009. NTPC VINDHYACHAL will retain its largest status with further capacity addition of 1000 MW (2 X500MW) in stage-4. The construction is in its full swing and units are expected to be commissioned in 11th Five Year Plan. For expansion only 500 Acres of land is being acquired at Baliyari Village for Ash Dyke . With the capacity addition NTPC Vindhyachal is dedicated towards environmental protection and Social care.

25

Destination Singrauli

M.P. Sanik Coal Mines Limited (Amelia Coal Block)


Company : Joint Venture of Sanik Aryan Group (49%) & Govt. of M.P. (51%)
BRIEF DESCRIPTION OF THE PROJECT M.P. Sainik Coal Mining Pvt. Ltd. is a Joint Venture Company of MIs. M.P.State Mining Corporation Ltd. (A Govt. of Madhya Pradesh Undertaking). Amelia Coal Block has been allotted in the name of M/s.M.P.State Mining Corporation Ltd. vide Govt. of India, Ministry of Coal, New Delhi letter No.13016/3/2003-CA/CA-1 dated 12.01.2006. Amelia Coal Block is located in Tehsil Singrauli Dist. Singrauli (M.P.) HIGHLIGHTS Amelia Opencast and Underground Coal Project is in Main Basin of Singrauli Coalfields, District Singrauli, Madhya Pradesh. PROJECT SITE INFORMATION ? Located in the North-Eastern Part of Main Basin-Singrauli Coalfields, Singrauli District of Madhya Pradesh. ? Block area 16.273 sq. km. of Mohan Ban Reserve Forest. ? Accessibility: Tehsil & District Singrauli, M.P. approximately at a distance of about 30 Kms from Waidhan. ? Katni-Singrauli-Chopan branch of West Central Railway - 5 Km. west of block.
? Nearest Railway Station

"DEORAGRAM" - for providing Railway siding for the block


? Topography

Undulating - Ground elevation varies between 381 m and 484m above MSL.
? Drainage

Controlled by Northerly flowing Kanchan Nadi.


? Numerous seasonal Nalas in the block leasehold which flows into Kanchan Nadi which ultimately joins Mahan

river.

26

Destination Singrauli
NEED OF THE PROJECT India has more than 250 Billion Tonnes of estimated coal reserves. In the growing Power shortage Scenario in the country power availability can be augmented by Thermal Generation using coal as the main fuel. The coal produced from Amelia Coal Block will be gainfully utilized by the State Govt. as follows:
? Major Portion of coal production is linked to Thermal Power Stations of M.P. Power Generation Corporation

Limited (MPPGCL)
? Basket Mine for nereby Thermal Power Stations to meet their coal Sortages. ? To Bridge the gap between Demand & Supply of Coal to other costumer like Cement, Steel, Power etc.

PROJECT COST : The tentative cost of the project is around 1200 crore. LAND USE DETAILS : 1. LOCATION 2. TYPE OF LAND Tenancy Land Govt. Land Forest Land Total Tehsil : Singrauli, District : Singrauli (Madhya Pradesh) 381.280 Ha 314.000 Ha 128.570 Ha 1978.850 Ha

LAND RECLAMATION PLAN 1. It is proposed to reclaim the land technically and biologically by backfilling the overburden and leveling by graders and dozers. 2. The land will be restored to economic utilization value. 3. Plantation over the backfilled areas will be carried out systematically. REHABILITATION PLAN 1. Due to the acquistion of land approx. 580 persons are likely to be affected. 2. The norms for rehabilitation of the project affected persons will be strictly in line with the approved Rehabilitation Scheme 2002 of Govt. of Madhya Pradesh. 3. P.A.Ps will be rehabilitated by way of offering them suitable jobs as per bnorms/Guidelines. 4. Site for rehabilitation will be developed and provided to Project Affected Persons (PAP).
BENEFITS TO GOVT. OF MADHYA PRADESH Social Benefits : ! Employment opportunities for 3000 workers ! Socio economic benefits to the local population due to development of area ! Some other ancilary Industries will come up tin the area generating more employment opportunities. General Benefits : ! Gap between demand and supply of coal bridged to the extent of 8.4 MTPA. ! More thermal generation will help industrialization of state of Madhya Pradesh.

27

Destination Singrauli

DB POWER (MADHYA PRADESH) LIMITED


Company : Dainik Bhaskar Group
Progress Report of Independent Power Projects Proposed in the state of Madhya Pradesh Name of the Company Proposed Capacity : : DB Power (Madhya Pradesh) Limited 1320 MW (2660 MW)

DB Power Ltd, an unlisted company belonging to media house Dainik Bhaskar Group, plans to set up three thermal power plants in Chhattisgarh and Madhya Pradesh. The unit in Singrauli district of Madhya Pradesh will have a total generation capacity of up to 2690 MW. The first two power plants will be set up in Chhattisgarh, having a capacity of 1,320 MW and 270 MW, respectively. The first plant is expected to be commissioned in 2011. DB Power has already been allotted coal mines in Chhattisgarh having 100 million tons reserves. The third plant will come up in Madhya Pradesh and will have a generation capacity of 2690 MW. A fourth 270 MW unit, based on coal washery rejects and middling coal, will come at Korba. The Madhya Pradesh plant is expected to be operational a year after the Chhattisgarh facility.

Progress as on date.
1. Milestone of the MOU : I. Date of MOU 15th February 2008, (Validity of MOU is extended till 14th February 2010 wide Agreement Dated 18th February 2009) II. Submission of implementation Submitted on 18th April 2008 schedule III. Submission of feasibility report / DPR Festibility Report submitted with GoMP on 7th June 2008 also, revised feasibility report submitted on 12th August 2008 DPR is under preparation, to be submitted shortly. IV. Signing of implementation agreement Implementation agreement will be signed after completion of land acquisition and obtaining other statutory clearances from concerned authorities. V. Offer of sale of power to MPEB 37.5% to MPEB as per MOU with GoMP VI. Power purchase agreement We are in the process of participanting in bid for sale of power to Northern and Western Grid (a) For supply of power to MPEBN 37.5% to MPEB as per MOU with GoMP. as per MOU (b) For supply of balance power 62.5% to Western and Norther Grid to other Project Related Activities Clearance : A. I. Feasibility report for Site Proposed Plant site in villages Gorgi-Papal-Mahuagaon identification and NOC from Chhamrachh in Deosar Tehsil of Singrauli District (Erstwhile Sidhi) energy department II. Submission of R&R Plan t Consultant has been appointed to conduct the survey and prepare State Revenue Department final report. Survey has been done and report preparation is in progress.

2.

28

Destination Singrauli
III. Application for land acquisition Application is Submitted in July 2008 Recommendation has been to state Revenue Department sent to District Collector from State Revenue Department of notification of land. Notification from Govt. of Sec. 4 for land acquisition is awaited. Total Land As on date 335.75 acres of private land has been acquired by the company out of total land area of 1500 Acres. Land allocation and confirmation towards availability of the same has been obtained from respective authorities. IV. Application for water allocation Water allocation for 1320 MW has already been obtained in August from WRD 2008 Total water requirement approved for peak capacity is 55 MCM PA (a) (b) (c) Water requirement Source of water Status of allocation of Water It has been approved by state govt. in August 200855 MCM pa for 1320 MW (2660 MW) Gopad River Allotment letters received for 55 MCM PA. We have submitted Conceptual plan and Pre-feasibility report for construction of anicut on river Gopad on to March 2009 approval awaited from WRD. Form-I & TOR (Term of Reference) is submitted in December 2008 And the same has been approved in the MOEF Meeting Dated 10th February 2009 Form-I is submitted in December 2008 TOR has been approved on 10 February 2009 TOR is already approved EIA report is being prepared and public hearing will be organized after submission of EIA report Application for coal linkage was submitted on 29th may 2008 Coal block

V.

MOE&F clearance status

(a) (b) (c) VI.

Application Date Status of TOR Status of public hearing

Submission of application for

(a) Coal requirement 7652 MT Coal linkage from Coal India Limited for 1320 MW (2660 MW) Application for coal linkage has been submitted on 29 May 2008. Also related queries are replied and further updates regarding land and water are provided alongwith plant order documents ot CEA in October-November 2008. Feedback awaited from state Govt. (b) Target for signing Fuel After allotment of Coal Linkage. Awaiting final approval of Coal supply Agreement Linkage from Standing Linkage Committee Ministry of Coal and New Delhi. Our case will be discussed in next SLC (Standing Linkage Committee) Meeting Application for Captive coal block is submitted on 4th June 2009 Consulting Agency is being finalized for conducting feasibility

(c) Rail Transport Clearance

29

Destination Singrauli
study on Railway siding as well as MGR for transporting coal from mining area loading siding to power plant site. VII. Status of other statutory clearance obtained (1) Land allocation approved by GOMP (2) Land Availability confirmed by Collector-Singrauli. (3) Coal Linkage application awaiting approval from SLC MOC (4) Agreement for water under Progress. (5) Application for Clearance of Chinney heigh will be submitted after land acquisition and fixing location of chimney. (6) Clearance from Defence Ministry will be taken up after acquisition of land (7) Any other clearance if rquired will be obrtained from timeto-time after complete acquisition of land. (8) Notification for section-4 awaited from state Govt. B.Construction Related Activities : I. Estimated cost of project Total Envisaged Investment Means of Finance Equity Debt Total II. Status of financial closure III. Construction power arrangement IV. Project construction commencement Yet to Apply Construction to egin after clearance from MOFE & R&R settlement date/status of preliminary as per final approved RAP construction at site First unit, within 36 months and second unit within 39 (Take oer) months from date of Notice to Proceed (NTP). Application is submitted to PGCIL for long term open access vide letter No. DBPL/MP/PGCIL/02042009 on dated 6th April 2009. 1782 4158 5940 30% 70% 100% Power Plant (2660 MW) Estimated Amount (In Rs. Cr.) 5940 (In %) 100%

Negotiations with Financial Institutions are under progress

V. VI

Unitwise commissioning schedule Power evacuation arrangement

30

Destination Singrauli

Singrauli Model of Land Acquisition and R&R


P.Narahari, IAS joined as Collector and District Magistrate on 2nd March 2009 and Anurag, IPS joined as SP around the same time in the month of January. The entire Land Acquisition and R&R were reviewed by the new team of administration and new methodologies were prepared to tackle the enormous amount of activity that is happening in the district. Land Acquisition cannot be done without effectively planning for the R&R and suitable packages need to be designed to cater to the demands of the Project Affected Peoples (PAPs). What rolled out in the next 2 years is a PAPs friendly administration which helped in the smoother eviction of people and R&R.

Mutually agreeable Time Line Schedule: Mutually agreeable Time Line Schedule (MATS) is a new concept that has been developed in Singrauli for Land Acquisition and R&R. Land acquisition officer (LAO) & Project Head of the Company prepare the MATS draft and it is approved in the weekly Projects' Review meeting after thorough discussion. Mutually agreeable Time Line Schedule (MATS) is the requirement of changing times. Generally the land acquisition takes its own time because a prescribed procedure has to be followed--- sec 4/6/9/Award! The companies for which Land acquisition takes place assert enormous pressure for quick land acquisition. Land acquisition follows eviction for which pressure is exerted. Our officers also need some time to resolve issues and do land acquisition following due procedure. Hence a mutually agreeable time line schedule takes care of both sides' time lines. Projects' Review Weekly meetings are organized for breaking schedule into smaller actionable units & execution and also to review the implementation of MATS. If any emergency crops up or new developing issues have to be resolved then these weekly meetings help to resolve them immediately. Entirely new method of Transition: About 100-125 Class-3/4 officers were selected from various departments of the district. They were grouped into teams, each team comprising of 4-5 persons. They were trained by the Collector himself. Each day they were picked up in vehicles at 7am from a fixed place and dropped back by 12pm. Again picked up at 4pm and dropped back by 7pm. Each group was given a sheet with a list of 20 PAFs (Project Affected Families). The team visits the house of PAFs and sits in their house and talks to them. The team explains to them about land acquisition, the need for eviction & shifting to R&R Colony. They write down all issues raised by the PAF and redress the issues there & then itself if possible. They visit the same PAFs several times till they are convinced. If the issues raised by PAFs are beyond their jurisdiction then they bring it to the notice of Tehsildar/SDM. Tehsildar/SDM would solve such issues immediately and if not possible then those issues reach ADM/DM who resolve them amicably using their descrition. During such team visits some of the oustees had problems pertaining to shifting to new places/R&R Colony. They wanted time to construct their own house. Such PAFs were provided with a) Temporary rental arrangement b) Transit accommodation. In 3 months all issues resolved and BTG/EW of Reliance & ESSAR cleared.

31

Destination Singrauli
District Administration organizes mega camps. These camps include: a) Lok Kalyan Shivirs b) Patta vitaran for PAFs shifted to R&R colony c) Rozgar Melas d) Redressal camps pertaining to R&R issues. Placement Based Skill Development Programmes: The set of activities include: (i) Free Industrial: At least one adult person of a displaced/affected family is being given free industrial training (ITI/CIDC). (ii) Free Computer training: Essar is giving computer training thru Aptech. (iii) Stipend: To encourage the PAPs to join such training programme a stipend of Rs 1000 per month is being provided. The stipend is being given on the basis of attendance and performance. (iv) Reliance has started a Women SHG which is into Stitching/embroidery etc. (v) Self employment: The District Administration is arranging for the loans from the banks for the displaced people, women, men, youth etc. of all ages to set up their own business. (vi) Employment opportunities at the R & R Colony are also being provided thru the training programmes under SGSY/CEDMAP to self-help groups. Organizing Rozgar Melas for the unemployed youth. (vii) Other Self-Employment opportunities were created thru the following organizations of the State Government: a) District Industries Center (DIC) b) Antyavsayi Corporation (SC Welfare) c) ST Welfare Corporation d) OBC Welfare Corporation

Grievance Redressal Mechanisms:


All applications & complaints received are feeded into software designed for R&R issues. Redressal of such applications is done in the same week. Pasting of redressed issues at the Admin building of the Dist Admin at the project sites. If necessary personally intimating the applicants about their applications. At least one officer of the Dist Admin sits daily at the Admin Building to listen to PAFs and redress their issues. This could be Tehsildar/SDM/ADM/DM. The Company people also sit at the Admin Building to resolve issues and problems on a dialy basis.

Revision of R&R Package:


R &R Package has been revised to suit to the needs of PAFs. A tripartite agreement is designed which is signed between district administration, company and the registered labour co-operatives to ensure that work is awarded to such societies without tendering. This agreement is first of its kind and is the most PAF friendly concept evolved in Singrauli district. Stamp Duty and Land Registry Exemption: As per the guidelines of MP R&R 2002 Section 29 (3) the Project Affected Families will be encouraged to buy agricultural land and the stamp duty and land registry charges for the quantum of land purchased will be exempted (equivalent to the quantum of land acquired). Started

32

implementing this provision. The objective is to encourage PAP's to fruitfully utilize the compensation paid under Land Acquisition process and also the restoration of livelihood for the farming community. A Standard Format was designed for easy application by the PAPs.

Employment action Plan:


1) The project authority submits a detailed employment action plan which entails a broader description of the skill and work wise man/women power deployment plan during construction phase as well as operation and maintenance phase. The dist administration is ensuring that mainly the PAPs get such work and only in case of non-availability of PAPs then outsiders to be allowed to work. The project authority ensures that each project affected family gets some source of livelihood in the long run either through direct employment in the company or as a member of the Labour Societies or shop allotment in the township and the R&R colony etc.

2)

School & Health:


Reliance started their school in the academic year 2009-10. More than 650 students are admitted. Their Hospital is also in place and is catering to the health needs of nearby villages. Essar has outsourced school for the children to Saraswati Shishu Mandir. About 700 children of PAPs are already admitted. Their hospital is functional since 2009. JP is staring their School from April 2011 but their hospital has earned goodwill in many nearby areas for the past few years. Hindalco has made adhoc arrangement made for School and is starting own school in April 2011. Hindalco renovated PHC Bargawan and started it from 15th Aug 2010. Regular Health Camps by all the companies. Hindalco is specially sponsoring for NSVT mega camps.

Other Major Initiatives:


Urjanchal Scholarship Society State of Art Training centre on the lines of L&T CSTI Chennai to be established in Singrauli. Construction of Anganwadis in the Project areas as well as nearby areas. Environmental Impact Assessment Study initiative. Creation of Singrauli Development Authority.

Umuntu ngumuntu ngabantu (Xhosa Language of South Africa) A person is a person because of other people. - Nelson Mandela

Designed & Developed by

P. Narahari, IAS
Collector & District Magistrate Singrauli (M.P.) Pin : 486 886 Tel : 07805 - 234541 (O), 244110(R), 234540(F) Email : dmsingrauli@mp.gov.in, p.narahari@yahoo.com Web : www.singraulidist.org

Printed by : Anand Printers, 9307765305 9455237323