You are on page 1of 9

006. N0. REV. N0.

DE-690-19-001





0E8|CN HEH0RAN0UH F0R ELEVAT0R8





0
ISSUED FOR OWNERS REVIEW AND
APPROVAL
TRM DJS VRR 03.11.2010
0A PRELIMINARY ISSUE SS / KGK DJS VRR 23.10.2010
REV. NO. DESCRIPTION PRED. BY CHKD. BY APPD BY DATE

PROJECT 2x300 MW, COAL BASED TPP
CHANDRAPUR

OWNER

DHARIWAL INFRASTRUCTURE PVT. LTD.
OWNER'S
CONSULTANT
TATA CONSULTING ENGINEERS LIMITED,
KOLKATTA


BOP CONTRACTOR PUNJ LLOYD LIMITED,

HYDERABAD


BOP
CONSULTANT
FICHTNER Consulting Engineers (India) Private Limited

Chennai




Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 2 of 9


TABLE OF CONTENTS

1.0 PREAMBLE............................................................................................................................. 3
2.0 REFERENCE DOCUMENTS.................................................................................................. 3
3.0 DESIGN CRITERIA ................................................................................................................ 3
4.0 DESIGN AND CONSTRUCTION ........................................................................................... 4
5.0 TECHNICAL PARAMETERS OF ELEVATORS..................................................................... 5



Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 3 of 9


1.0 PREAMBLE

Coal Based Thermal Power Station consisting of 2 x 300 MW generating units is being set
up at Chandrapur by Dhariwal infrastructures Pvt Ltd. In this power plant, Boilers, Technical
building, Chimney and other buildings which is having more than 2 Floor shall be provided
with Elevators. This document covers the Design basis for the Elevators of following
locations / buildings.
Two numbers passenger cum goods elevators for Boilers (one number in each Boiler)
Two numbers passenger elevators for Technical building
One number rack & pinion type elevator for the Chimney
One number passenger elevator for buildings higher than 2 storied (CHP Building)

2.0 REFERENCE DOCUMENTS
Tender Specification-LII-GEOE09043-00003-002.
IS: 14665 (part-1 to Part-5) Electric Traction Lifts

3.0 DESIGN CRITERIA

Service Passenger Elevator
Quantity 2 Nos. for Boilers (one number in each Boiler) - passenger cum
goods elevators
2 Nos. passenger elevators for Technical building
One number rack & pinion type elevator for the Chimney
1 No. passenger elevator for buildings higher than 2 storied
(CHP Building)
Location Boilers / Technical building / CHP
Design/Construction/ a. Latest edition of BS:5655 (All parts) installation codes and also
meeting any additional requirements of IS:4666, IS:1860 and
IS:3534
b. The safety code for elevators dump waiters & moving walks
shall be as per USA Std. Inst. Code No. A17.1
Load carrying capacity
a. 884 Kg for passenger elevator
b. 2000 Kg for goods elevator
c. 400 Kg for Chimney elevator
Rated speed
0.55 m/s for passenger lift
0.7 m/s for Chimney elevator
Number of floors Boiler elevator
Ten (10) - 0M, 7.2M, 12.6M, 19.6M, 23.2M, 29.8M, 36.4M, 44.2M,
52.6M, 60.7M, 66.4M

Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 4 of 9


Technical building
As per approved architectural drawing
Chimney
Ten (10) - 0M, 9M, 20M, 25M, 65M, 105M, 145M, 185M, 225M,
265M
CHP building
As per approved architectural drawing (to be provided by CHP
vendor)
Drive/Motor Worm geared traction machine driven by suitable motor or Two
speed motor with proven microprocessor based controls
Power Supply 415 V, 3 phase, 50 cycles, AC supply
Method of Control
Single Speed Servo drive control type with automatic level
adjustment
Type of doors Vertically split, Imperforated collapsible door of hollow metal
construction from 16 gauge thick steel sheet.
Machine room Machine room shall be located at top of Elevator. Machine shall be
Pressurized dust proof. Sound reducing material below machines
in machine room shall be provided
Operation of Elevator a. Selective duplex collective automotive operation with or without
attendant.
b. Provision for locking control in auto or attendant position.

4.0 DESIGN AND CONSTRUCTION

The Elevator shall be of industrial duty, rugged and suitable for the dusty power plant
environment. The drives and control shall have appropriate degree of protection. Metallic wire
mesh/screen in the area of lift travel shall be provided where car and the counter weight cross
each other. Elevator shaft shall be enclosed with 3.15 mm thick galvanized MS cladding sheet
from top of elevator pit upto machine room level.

Appropriate sealing shall be provided for the cladding sheet to prevent dust/ water entry in the
shaft. Construction of the elevators shall have the following features:



Flooring of
Cabin
: Chequered plate flooring with heavy timber underlay over steel
sheeting and replaceable felt spreading, each 25 mm thick.
Design
Construction
: Car inside enclosure shall be scratch proof SS sheet.
Car entrance
and landing
doors
:
Type F doors of BS: 5655 (Part-I) fire resistant doors defined and
tested as per Appendix F of BS: 5655 (Part-I).
Landing doors shall have fire resistance of atleast one hour. These

Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 5 of 9


doors shall also be smoke tight as far as possible.
Car Door
Construction
:
Imperforated collapsible door of hollow metal construction from 16
gauge thick steel sheet.
Signals :
Car position indicator with directional arrows both audio and visual,
hall position indicator at all floors, tell lights at all floors, battery
operated alarm bell and emergency light with suitable battery,
charger & controls, fan and telephone
Type of
indicators
:
Standard indicators or alternatively luminous hall buttons and
luminous button in car operating panel and digital hall position
indicator on all floors. (All fixtures in stainless steel face plates)
Emergency
indicator
:
In case of Emergency hold-ups in between the floors, automatic
flashers should indicate its location of hold-up both audio & visually
as well.

Further, Elevators shall have provisions to meet following operational requirements as minimum.

(i) Selective collective, automatic operation with or without operator through illuminated push
button station located inside the lift car.
(ii) Power operated with automatic opening / closing car and landing doors.
(iii) Two push buttons, one for upward movement and the other for downward movement at each
intermediate landing, and one push button at each terminal landing shall be provided in order
to call the car.
(iv) Push buttons shall be fixed in the car for holding the doors open for any length of the time
required.
(v) All other safety / protection / operation interlocks as required by BS:5655 (Part-I)
(vi) Indication for position and call indication inside the car, and up/down travel direction
indication in car and at each landing.

5.0 TECHNICAL PARAMETERS OF ELEVATORS

5.1 Boiler & Building Elevator


Sl.
No.
Item Description Boiler Elevator
(Passenger cum Goods
Elevator)
Building Elevator (Passenger
Elevator)
a) No of Elevators Two (one number in each
boiler)
a) 2Nos. - Technical Building
b) 1No. - CHP Building

b) Type Floor Elevator System with Car Floor Elevator System with Car
c) Applicable standard IS: 14665 (Parts 1 to 5) IS: 14665 (Parts 1 to 5)
d) Rated Load 2000 kg 884 kg (6 8 persons)
e) Rated Speed 0.55 m / sec 0.55 m / sec
f) Total Rise 66.4 M
g) Number of floors Ten (10) including ground floor
Shall be furnished after the
finalisation of architectural
drawing

Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 6 of 9


Sl.
No.
Item Description Boiler Elevator
(Passenger cum Goods
Elevator)
Building Elevator (Passenger
Elevator)
served
h) Landing Levels
0M, 7.2M, 12.6M, 19.6M,
23.2M, 29.8M, 36.4M, 44.2M,
52.6M, 60.7M, 66.4M
i) Lift well Size Will be furnished during
engineering
Will be furnished during
engineering
j)
Leveling Zone
5 mm 5 mm
k)
Leveling Device
Two way automatic maintaining Two way automatic maintaining
l)
No. of door in car
One, Centre Opening Automatic
Horizontal sliding
One, Centre Opening Automatic
Horizontal sliding
m)
Type of control
AC Variable Voltage Variable
Frequency (ACVVVF) control
AC Variable Voltage Variable
Frequency (ACVVVF) control
n)
Operation
With / Automatic without
attendant
With / Automatic without
attendant
o)
Automatic Operation
type
Selective Duplex Collective Selective Duplex Collective
p)
Operating Devices
As listed clause 5.2 As listed clause 5.2
q)
Indicating Devices
As listed clause 5.2 As listed clause 5.2
r) Car enclosure Stainless Steel Stainless Steel
s) Accessories
Car Lighting (Fluorescent
Tube)
Car Ventilation fan with
manual / automatic through
selector switch
Inbuilt hand free Telephone
Hand rail
Emergency DC Light
Fire extinguisher
Over load device
Energy saving device
Emergency switch
Car Lighting (Fluorescent
Tube)
Car Ventilation fan with
manual / automatic through
selector switch
Inbuilt hand free Telephone
Hand rail
Emergency DC Light
Fire extinguisher
Over load device
Energy saving device
Emergency switch
t) Degree of protection
IP 55 & weather proof IP 55 & weather proof
u) Landing, operating
devices & indicating
devices
Weather proof and rain proof -
v) Car Door
Non contact type protective
device extending to the full
height, Electric contact &
mechanical interlock with
auxiliary closing device will be
provided
Non contact type protective
device extending to the full
height, Electric contact &
mechanical interlock with
auxiliary closing device will be
provided
w) Power supply
415V, 3 phase, 4 wire, 50Hz
supply
415V, 3 phase, 4 wire, 50Hz
supply
x) Power supply Main
Lockable as per requirements
of IS 1860
Lockable as per requirements of
IS 1860

Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 7 of 9


Sl.
No.
Item Description Boiler Elevator
(Passenger cum Goods
Elevator)
Building Elevator (Passenger
Elevator)
y) Maintenance Tool Kit
A maintenance tool kit will be
kept machine room
A maintenance tool kit will be
kept machine room

5.2 Chimney Elevator

Sl.
No.
Item Description Technical Parameters
a)
Type Rack & Pinion type
b)
Travel Length 9M to 268M (Chimney Height = 275M)
c)
Landing Levels 9 M, 20 M, 25 M, 65 M, 105 M, 145 M, 185 M,
225 M, 265 M
d)
Number of Landings Ten
e)
Type of Operation With attendant
f)
Minimum Carrying Capacity (Pay
load)
400 kg
g)
Speed 0.7 m /sec
h)
Controls Semi Automatic Control
i)
Car enclosure Aluminium sheet
j)
Landing entrance door Mild steel perforated sheet
k)
Operation of car door Manually operated
l)
Car floor MS Plates
m)
Controls & Indications Dead man type controls in the car, Push buttons
for up, down, stop next landing, stop &
emergency stop, cage light / key switch, fan
switch, hooter switch, thermal overload
indicating lamp.
n)
Safety Features Over travel protection.
Over speed governor
Emergency stop push button
o)
Essential Features a. Cage with frame guide rollers and
mechanical safety hooks.
b. Cage of welded steel structure with wire
mesh covered walls, with one door
electrically and mechanically interlocked.
c. Electrically and mechanically interlocked
trapped door in cage roof, safety railing on
top of cage and ladder inside cage.


Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 8 of 9


d. Semi-automatic control system for operation
of lift from inside the cage as well as on
landing with automatic stop equipment stop
next landing
e. Overspeed governor for controlling
excessive descending speed.
f. An external brake release mechanism
located inside the cage for descending cage
in case of power failure.
g. Progressive type positive action safety
device driven by a separate pinion engaged
in the rock (Alimak patented or equivalent)
h. Emergency alarm system

p)
Power Supply 415V , 3 phase, 4wire 50 Hz supply

5.3 Operating devices / Indicating devices

The following operating devices shall be provided in the car / on the landing / in the machine
room as indicated below:

Operating devices

In the car In the landing In the m/c room On top of the car
Up push button (PB)

Up PB Up PB Up
Down PB

Down PB Down PB Down
Number PB s for each
landing

Bell
Hand cranking
device
Stop
Bell PB, Phone

Lift PB Stop PB 240 V 1 receptacle
Non-stop PB

- -
Door open PB

- - -
Door close PB

- - -
Alarm PB

- - -
Emergency stop PB

- - -
Key operated selector
for attendant operation

- - -

Indicating devices

The following indicating devices shall be provided in the car / on the landing as indicated below:

In the Car

On the landing
Up direction of travel

Up direction of travel

Dhariwal Infrastructure Pvt. Ltd.
2 x 300 MW Coal based TPP
Design Memorandum for
Elevators


Doc. No. DE-690-19-001, Rev. 0 FICHTNER INDIA Page : 9 of 9


Down direction of travel

Down direction of travel
Floor position indicator

Car position indicator with direction
(Illuminated numeral for each landing)

(Illuminated numeral for each landing)
Landing car registering unit

Call registered Up indicator
Thermal Overload Indication Lamp Call registered Down indicator

You might also like