Ref No.- UGM/P&HM/SOMA-N1/ To M/s. Monnet Ispat & energy Ltd.

Village & Po- Naharpali, The: Kharsia, Raigarh(CG)- 496661, Ph.-+91 7762 391540.

Date:-13.10.2011

Kind Attn.- Mr. Amit Rastogi (07389940704) Sub- Offer for Supply of 25 Mtr. High Mast with light fitting & complete accessories Dear sir, With reference to the your E-mail Dtd 11th October , we have the pleasure of quoting our best prices are as per the following. Sl. Description No. (A) HIGH MAST STRUCTURE 1. Unit (Rs) Rate Nos. Total (Rs) Rate

Supply of 25Mtr. long Galvanized Polygonal High 1,90,000.00 Mast Tower with (As per Enclosed Drawing No. UG1349) Lantern carriage , Head frame and foundation accessories.

3 sets

5,70,000.00

(B) HIGH MAST ACCESSORIES 2. Supply of High Mast Accessories Consisting of Manual winch , 6mm dia 7/19 construction steel wire rope, 4x2.5sqmm trailing cable, lighting arrestor, wiring Cable Compensating disc and other hardware etc. 3 a) Supply of Flood Light Luminaries & Fittings : 2x400 watt integral flood light fitting complete with control gear and 400watt HPSV lamps 12 Nos. (Philips Make) b) Aviation Light with red colour dome with twin GLS lamps 01 No. 4 Feeder Pillar made out of 2mm CRCA Sheet duly acid treated and painted with I/C & O/G MCBs with timer (Rupees Twelve Lakhs Ninety Thousands only)

68,500.00

3 sets

2,05,500.00

1,29,000.00

3 sets

3,87,000.00

2,500.00 40,000.00

3 sets 3 sets

7,500.00 1,20,000.00 12,90,000.00

NB: Cable (16 Sqmm 4 Core ) supply with laying on GI Pipe will cost extra @ Rs. 475 /- per running Mtr length form feeder pillar to supply point.

PRICE- The above prices are of Ex-works, Kapursingh, Oranda. Cuttack, Orissa Exclusive of all taxes and duties. C. E. D. - will be charged extra @ 10.30% on basic price as per prevailing rate (For Item- A) CST- CST will be charged extra @ 2% on basic price & Central Excise duty thereon against form C for item A and @ 2% only on basic price for Item B. If form C is not produced then @ 13.5 % will be charged. Any change in Taxes & Duties will be borne by the Customer. FRIEGHT- Transportation charges will be charged extra as per actual. VALIDITY- Our Offer is valid for a period of 30 days from the date of this offer. PAYMENT 70% advance payment may please be released along with the technically / commercially clear purshase Order. Balance 30% amount with 100% taxes & duties may please be released before delivery of materials from factory. COMPLETION- Within 1 months from the date of receipt of technically / commercially clear work order & Advance Payment.

We will be happy to comply with any technical or commercial clarification you need. We would request you to kindly place your valued order in our favour.

Thanking you, Yours faithfully For Utkal Galvanizers Ltd.

(Er. Sourav Satapathy) (Manager Marketing) 09853425013