QSHE-2007/PMT/AA/W/001
RAPAT ENGINEERING
PROYEK Hari / Tgl Jam Tempat Dihadiri oleh
No Uraian Masalah
: FT-UNHAS GOWA : Sabtu, 19 October 2011 : 10:00 - selesai : R. Rapat Proyek : (terlampir sesuai absen)
No.Rec:../4.1/QSHE-2007/PMT/AA/W/001
Target Penyelesaian
Revisi Target
Penanggung Jawab
REVIEW
P.16 GAMBAR SUBKON - GRC P.23 Gedung COT 7-May 26-Nov IDUP open
1 Shop drawing
- Tangga utama COT (struktur) Meminta sub untuk membuat shop drawing 18-Jun 26-Nov Larso open
P.40 - Pengajuan seluruh material paket 3 Finishing d. Kusen aluminium & Kaca e. Waterproofing coating & membrane h. Tanaman g. Metal roof ME f. Lightning g. Blacksteel pipe h. GSP Pipe i. Pump k. Hydrant box n. Fan p. Lift Shop Drawing paket-3 - Naval Kolom P.42 Paket-1 Tangga utama COT Ismail Material - Ada perubahan material dari steel hollow ke aluminium (di area entrance Civil) TINDAK LANJUT RAPAT EXTEREN TGL 21 Partial standard drawing diminta diajukan oleh konsultan Konsultan menerbitkan EID teguran retak di shaft Gedung Classroom Pondasi fatique mesin belum selesai Segera diajukan - MEP drawing Mengajukan metode repair dengan membongkar dan membuatkan kolom praktis - Meminta detail design dari ITOCHU - Membuat shop drawing 29-Oct 29-Oct 29-Oct 29-Oct 26-Nov 19-Nov 26-Nov 26-Nov Ismail Aprit Galang Larso open closed open open 8-Oct 19-Nov Usep closed
ex Fosroc
ex. Indelec ex. PPI & Bakrie ex. Bakrie ex. Torishima & Ebara ex. Ozeki & Quick Fire ex. Fantech ex. Mitsubishi Sanghai
& Andre & Andre & Andre & Andre & Andre & Andre & Andre
22-Oct 22-Oct
26-Nov 19-Nov
Imam Ismail
open open
22-Oct
26-Nov
Imam
open
- plan naval 1st floor - revisi tangga pedestrian ST 6A (di T3) - T5A - T5B - T5D - T5A gider masih dikonsultan
AGENDA RAPAT TGL 5 Nov. Cab meminta tiap proyek memasang CCTV Cab meminta tiap proyek memberikan inovasi proyek (minimal 3) PMC minta metode waterproofing membrane untuk semua area PMC meminta dokumen IMB Paket-3 Menentukan posisi CCTV (2 spot) Email ke cab terdiri dari change bored pile to driven pile, safety card, Change asphalt to concrete Mensubmit metode Submit dokumen paket-3 12-Nov 12-Nov 12-Nov 12-Nov 26-Nov 26-Nov 19-Nov 26-Nov Galang Galang Danang Galang open open closed open
- GF - revisi 3rd floor - GF - 1st floor - 2nd floor - 3rd floor - GF (submitted) - 3rd floor (submitted)
closed open open open closed open closed closed closed open open open
- WO a. COT - Granite a. Library b. COT - Parquet pattern untuk lecture and theatre room Plafond detail
15-Nov 26-Nov
26-Nov
Miscellaneous Perhitungan struktur GRC Library dan COT Additional Cost RAPAT TGL 19 Nov Curtain wall Aluminium hollow di Library bagian belakang Surat pernyataan manufacture lift Shanghai PMC minta metode potong tiang pancang dan pekerjaan pile cap PIU minta CPM Meminta sample kaca es ke Tulus Sinage belum disetujui
Melengkapi revisi
19-Nov 19-Nov
26-Nov 26-Nov
Aprit Imam
open on going
Diskusi dengan PMC Membuat perhitungan biaya Membuat shop drawing Submit metode
Galang Alwindo Alwindo Adi Aprit Danang Imam Alki Putru Imam Galang
open open open open open open open open open open open
Doly system sudah disetujui namun harga belum disetujui Design catwalk belum diputuskan
Submit sinage plan sesuai contract drawing a. COT, Library, Architecture b. Civil & Classroom Bersurat ke konsultan mengenai harga doly system disertai analisa Mencari spek hose crane