APRIL 19, 2012 SOCOTECO II respectfully inform the public on New Load Curtailment Schedule for APRIL 19, 2012 due to total plant shut down of Pulangi IV Hydro Electric Plant: TIME 7:00 AM - 11:00 AM 11:01 AM - 3:00 PM 3:01 PM - 7:00 PM 7:01 PM - 11:00 PM GROUP GROUP D GROUP A GROUP B GROUP C FEEDER 6-2; 4-4; 9-2; 9-1; 11-2; 12-1; 9-3; 1-5; 7-2; 12-2 1-1; 13-1; 4-1; 12-5; 12-3; 3-1;14-3; 6-3; 9-4 ; 7-4 3-2; 14-1; 12-4; 13-3; 7-3; 3-3; 1-3; 15-1; 11-1; 7-1 6-1; 13-2; 1-4; 15-2; 14-2; 4-3; 14-4; 8-1; 8-2 ; 1-2; 4-2
NOTE: The schedule of interruption is highly dependent on the allowable dispatchable capacity from the NGCP which varies from time to time. Please bear with us. For inquiries on this matter, please call 553-5448 to 50 or text 09177205365.